  EXERCISE 20 A Project Overview Three ingredients (city water, ingredient QR and ingredient KM) are added in specified amounts by weight to the Mixing Tank. After all the ingredients have been added to the Mixing Tank, the mixture is blended by running the agitator for a given time. When the blending time is complete, the finished product is pumped to the Filling Lines for bottling and final packaging. Detailed Sequence of Operations To begin a new batch, the operator will verify that the “SYSTEM READY” pilot light is on and that the Mixing Tank is ready to receive ingredients.The operator will then press the “START BATCH”  pushbutton to begin the batch ing process. No f urther operator input is re quired.The “SYSTEM READY” pilot light will turn off.Automatic valve AV-CW will open. The “ADDING WATER” pilot light will illuminate.The state of AV-CW will be verified by limit switch LS-CW2. If LS-CW2 is not made within 2 seconds after the valve was told to open, a fault will be generated and the system will shut down. The pilot light “SYSTEM FAULT” PL2 will illuminate indicating that a fault has occurred.  

Exercise 20 A

Embed Size (px)

Citation preview

7/21/2019 Exercise 20 A

http://slidepdf.com/reader/full/exercise-20-a 1/1

EXERCISE 20 A

Project Overview Three ingredients (city water, ingredient QR and ingredient KM) are added in specified amounts byweight to the Mixing Tank. After all the ingredients have been added to the Mixing Tank, the

mixture is blended by running the agitator for a given time. When the blending time is complete, thefinished product is pumped to the Filling Lines for bottling and final packaging. Detailed Sequenceof Operations To begin a new batch, the operator will verify that the “SYSTEM READY” pilot light is on and thatthe Mixin g Tank is ready to receive ingredients.The operator will then press the “START BATCH”

pushbutton to begin the batching process. No further operator input is required.The “SYSTEMREADY” pilot light will turn off.Automatic valve AV -CW will open. The “ADDING WATER” pilotlight will illuminate.The state of AV-CW will be verified by limit switch LS-CW2. If LS-CW2 is notmade within 2 seconds after the valve was told to open, a fault will be generated and the system willshut down. The pilot light “SYSTEM FAULT” PL2 will illuminate indicating that a fault has

occurred.