Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual finishing line. They are competitive

Embed Size (px)

Citation preview

  • 8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi

    1/9

    Exploring the links between task-level automation usage

    and project satisfaction

    Li-Ren Yang

    Department of Business Administration, Tamkang Uni versity, Tamsui, Taipei, 251, Taiwan

    Accepted 7 August 2007

    Abstract

    The purpose of this study was to identify project satisfaction-leveraging tasks and common characteristics associated with these critical tasks.

    To address the primary aim, a survey was conducted to determine correlations between task-level automation adoption and project satisfaction

    from the perspectives of various types of project stakeholders. Identification of project satisfaction-leveraging tasks is employed as a way to gain

    greater understanding of the connections. Also, this study explores the links between automation utilization and project satisfaction in further

    detail. Task characteristics are investigated as an additional basis for gaining deeper insights into how automation technology usage may impact

    project satisfaction. A second survey was used to collect needed data from industry professionals. The analyses suggest that degrees of automation

    used in executing the project satisfaction-leveraging tasks may be positively related to project stakeholder satisfaction. The results also indicate

    that information and data intensive and management-related characteristics may be associated with overall project stakeholder satisfaction.

    2007 Elsevier B.V. All rights reserved.

    Keywords: Automation; Technology; Project; Stakeholder satisfaction; Task

    1. Introduction

    Many studies have shown that the construction industry is

    reluctant to apply new technologies and employs lower levels of

    technology than other industries. A national-wide survey

    conducted by the Civil Engineering Research Foundation

    indicated that the design and construction industry spends

    only 0.5% of its total revenues on research and development[1].

    In recent years, however, there has been a growing trend

    towards increased technology utilization levels on Architect/

    Engineering/Construction (A/E/C) capital facility projects.According to a 1995 study, four drivers for adoption of new

    technologies were identified: 1) competitive advantage, 2)

    external requirements, 3) priority problems avoid losses

    from reduced performance, and 4) technological opportunity to

    improve operations [2]. Some construction firms adopt

    automation in the attempt to reduce the cost and schedule of a

    project. These companies are also examining their operations

    for ways to improve stakeholder satisfaction. However, since

    the benefits of innovation can be rather intangible, this has

    slowed or prevented the adoption of new automation technol-

    ogy. Accordingly the impact of automation on project

    performance has been one of the major issues for both industry

    and academic fields. In order to understand the benefits, there is

    a need for quantification of the benefits derived from

    automation application. Simmons [3] suggested that methods

    used to evaluate the impact of technology on performance

    measures may be the problem in connecting investment in

    technology to improvements in business performance. Researchon automation utilization at the task level and its associations

    with project success should offer tangible evidence of

    advantages from using technologies.

    While many studies have promoted technology as a means to

    enhance project performance [47], very few published

    empirical studies in construction have explored the direct

    effects of automation on project performance from the

    perspectives of various types of stakeholders. None of the

    previous research attempts to explain the links between

    automation usage and project performance. In addition, there

    has been no comprehensive study on the impacts of automation

    Automation in Construction 17 (2008) 450458

    www.elsevier.com/locate/autcon

    Tel.: +886 2 26215656; fax: +886 2 26209742.

    E-mail address:[email protected].

    0926-5805/$ - see front matter 2007 Elsevier B.V. All rights reserved.doi:10.1016/j.autcon.2007.08.001

    mailto:[email protected]://dx.doi.org/10.1016/j.autcon.2007.08.001http://dx.doi.org/10.1016/j.autcon.2007.08.001mailto:[email protected]
  • 8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi

    2/9

    usage on overall project stakeholder satisfaction. Empirical

    evidence that supports the link between automation usage at the

    task level and project stakeholder satisfaction is lacking. Thus,

    developing such support will illustrate the benefits of

    automation adoption. This study attempts to fill this void of

    empirical evidence by identifying project satisfaction-leverag-

    ing tasks and common characteristics associated with thesecritical tasks. This paper addresses associations between task-

    level automation technology usage and project success. The

    links between automation utilization and project satisfaction are

    explored in detail. For the purposes of this research, automation

    is defined as the use of an electronic or mechanized tool by a

    human being to manipulate data or produce a product[8]. The

    purpose of this research is three-fold. The first objective of this

    study was to identify project clusters formed on the basis of the

    perceptions of stakeholder satisfaction. The second objective

    was to determine project satisfaction-leveraging tasks. The third

    objective was to investigate the characteristics associated with

    these project satisfaction-leveraging tasks to gain deeperinsights into how automation usage may impact project success.

    The analyses of automation usage and relationships with

    project satisfaction are based on an industry-wide survey per-

    formed between October 2004 and June 2005. A data collection

    tool was developed to assess automation use levels in the

    Taiwanese industry. A total of 98 project responses were collected

    through personal interviews. Automation usage metrics are based

    on 61 common project tasks. In order to measure the degree of

    automation used on projects and its impacts on project outcomes,

    the data collection tool was used on all types of projects in the

    building, industrial, and infrastructure sectors. The data analyzed

    in this study are project-specific, meaning the data are repre-

    sentative of the levels of automation used on projects. In addition,the analyses of characterization of the project satisfaction-

    leveraging tasks are based on a second survey conducted between

    February 2006 and February 2007. The data collection effort

    involved characterization of the project satisfaction-leveraging

    tasks. This paper explains the links between automation

    utilization and project success. Automation usage metrics

    analyzed include those at the task level. Project success parameter

    analyzed is project stakeholder satisfaction.

    2. Literature review

    A considerable body of research has been conducted on theadoption and use of technology in the A/E/C industry. Much of

    the project/construction management literature relevant to this

    research is associated with the adoption of technology, factors

    influencing the implementation of technology, and the expected

    benefits associated with the use of technology. Concerning

    technology usage, O'Connor et al.[9]investigated the extent to

    which technologies are being used in executing projects in the

    construction industry. Webb et al.[10]explored the potential of

    4D CAD as a tool for construction management. Abduh and

    Skibniewski[11]presented an assessment model to measure the

    utility of Electronic Networking Technologies (ENT) services

    in construction project activities. Tse and Choy[12]carried out

    an in-depth interview for studying the scope of use of IT in

    Hong Kong's construction industry. Peansupap and Walker

    [13] addressed the critical issue of how best to adopt and

    diffuse information and communication technology (ICT) into

    organizations.

    While the above authors promoted the adoption of technol-

    ogy, other researchers have also been active in identifying the

    factors influencing the adoption of technology. Goodrum andGangwar [14] examined the relationship between changes in

    equipment technology and changes in construction wages with

    the help of five factors of equipment technology change: control,

    energy, ergonomics, functionality and information processing.

    Mitropoulos and Tatum[15]argued that uncertain competitive

    advantage from using new technologies and lack of information

    regarding technologies and benefits may be the reasons for

    reluctance to adopt technology. There has been also much work

    conducted on the benefits from technology in the construction

    industry. Earlier studies supported the notion that technology

    adoption is beneficial. Several researchers have investigated the

    impacts of different technology on project performance. Some ofthe project performance indicators they examined include cost,

    schedule, and safety success, which are of course major concerns

    to project stakeholders. Fergusson [16]investigated the relation-

    ships between facility integration and quality. Back and Bell [17]

    identified the impacts of use of electronic data interchange (EDI)

    in bulk materials management. Griffis et al. [18] studied the

    impacts of using 3-D computer models on cost, schedule

    duration, and rework metrics. Back et al.[19]undertook a study

    to determine the impact of information management on project

    schedule and cost. Tan[20]studied the impact and linkage of

    information technology and competitive advantage.

    Additionally, Hampson and Tatum[4]stated that technology

    strategy can positively influence competitive performance.Johnson and Clayton[5]contended that information technology

    can improve productivity of teams and management procedures.

    Back and Moreau [6] suggested that improving internal

    information exchange and integrating project-based information

    across organizational boundaries may result in project cost and

    schedule reductions. Thomas et al.[7] evaluated the impacts of

    design/information technologies by connecting their use to

    project performance in terms of cost growth, schedule growth,

    and safety success. Whyte et al. [21] explored processes by

    which emerging technologies can be introduced into construc-

    tion organizations. Goodrum and Haas [22] investigated the

    impact of different types of equipment technologies on con-struction productivity. De Lapp et al.[23]examined the impacts

    of computed aided design (CAD) on design realization. Sexton

    and Barrett [24] performed in-depth case study to understand

    the role of technology transfer in innovation within small con-

    struction firms. Lee et al.[25]examined the relative impacts of

    selected practices on project cost and schedule. Above prior

    studies indicated that technology is playing an important

    enabling role in construction. While the diverse benefits of

    technology have received substantial attention, the number of

    studies dealing with technology's impact on the performance in

    terms of stakeholder satisfaction is rather scarce.

    A reviewof the literature suggests that the use of technologyas

    a means to enhance project performance has been widely

    451L.-R. Yang / Automation in Construction 17 (2008) 450458

  • 8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi

    3/9

    supported. Generally, many researchers have suggested that

    technology provides significant benefits to capital facility

    projects. The literature review provides background for devel-

    oping an understanding of the issues related to the adoption and

    use of technology, factors influencing the adoption of technology,

    and the benefits to be derived from technology. Issues discussed

    include the use of technologies for specific project tasks,technology strategy, information technology, and the application

    of integration. Project performance measurements commonly

    used in the previous studies include cost, schedule, degree of

    attainment, return on investment, and safety. The literature review

    suggests that most performance measurements currently being

    used are quantitative or hard measures of cost and schedule. Soft

    measures such as leadership, employee satisfaction, and team-

    work are now being measured using qualitative or subjective

    measurement techniques[26]. In light of the previous research, it

    is evident that additional work is justified. While research has

    centered on the project performance in terms of cost and schedule

    success, relatively less has approached the associations betweenautomation utilization and overall project satisfaction from the

    perspectives of various types of stakeholders. Also, few articles

    are known about the explanation of the links between automation

    utilization and project success. Additionally, most studies in

    construction seeking to provide insights into technology usage

    have not developed specific measures for automation implemen-

    tation and stakeholder satisfaction levels.

    In summary, there has been much research conducted on the

    use of technology and the benefits derived from technology

    application, although there is little work with quantifiable

    information on how automation affects overall project stake-

    holder satisfaction. Additionally, few studies have empirically

    tested the relationships between technology usage at the tasklevel and project performance in terms of stakeholder

    satisfaction. Thus, it will be useful to develop quantitative

    measures of automation utilization and stakeholder satisfaction.

    Also, there is a need for more comprehensive empirical evi-

    dence that evaluates the benefits associated with automation

    and, more specifically, its impact on project performance in

    terms of stakeholder satisfaction.

    This research adds to the literature in two valuable ways. First,

    it provides evidence of performance implications of automation

    implementation at the task level. Second, it offers important

    results on the identification of project satisfaction-leveraging

    tasks and their common characteristics from the perspectives ofmajor stakeholders involved in projects, including the Owner,

    Architect/Engineering (A/E), and General Contractor (GC)

    groups. Research on automation utilization at the task level

    should provide construction firms with information on whether to

    adopt automationtechnologies. In addition, the assessment of task

    characteristics that can leverage the benefits of automation should

    also be beneficial. To address this gap in the literature, the

    following research hypotheses were developed:

    Levels of automation utilization for certain tasks are positively

    related to projects' levels of stakeholder satisfaction

    Task characteristics can explain the links between automa-

    tion utilization and project stakeholder satisfaction.

    3. Determining project satisfaction-leveraging tasks

    3.1. Data collection tool

    The first phase of research included identifying project

    satisfaction-leveraging tasks. A survey instrument was used to

    measure the degree of automation usage on capital facilityprojects and its associations with project outcomes. The data

    collection toll was developed based on variables used in pre-

    vious studies and understanding gained from interviews

    conducted with executives in the construction industry. The

    survey was composed of two sections: project/company

    information and degree of automation use for tasks. The first

    section of the survey obtains information concerning the project,

    project type, and final performance of the project in terms of

    stakeholder satisfaction. The second section assesses level of

    automation used in executing the project. For the purpose of this

    study, a project's life cycle is structured in five phases: Front

    End (which includes scoping, feasibility, and preliminary designactivities), Design, Procurement, Construction Management,

    and Construction Execution[9]. To provide a basis for assessing

    automation usage, it is necessary to determine the common tasks

    performed on projects. Based on brainstorming and the litera-

    ture search [9,27], a total of 61 common project tasks were

    developed. Study participants were first asked to identify a

    recent project that they were familiar with for assessment. For

    the subject project, the survey then asks participants to assess the

    degree of automation used in executing each task for that project.

    3.2. Sample selection and data collection

    An industry-wide survey of automation use levels on capitalfacility projects was conducted in Taiwan between October

    2004 and June 2005. A data collection tool was developed to

    collect project-based data. A total of 98 project responses were

    collected through personal interviews. Individuals interested in

    participating in the study were identified by a search from

    various industry associations. In order to obtain a truly repre-

    sentative sample, not only was the geographic mix of projects

    intentionally diverse, but a diverse mix of participation was

    sought with respect to sector of industry. Additionally, a

    specified mix of project size was targeted in order to obtain a

    representative sample of the industry. More than 100 projects

    were investigated and some were not included in the analysisbecause they contained insufficient information. In addition, the

    projects were examined to ensure that no duplicate project

    information was collected. Ultimately, 98 survey responses

    were used in the analysis.

    3.3. Measurement: automation usage metrics

    In assessing the degree of automation used in executing each

    task, respondents could choose from four levels [9,27,28]:

    Level 1, where no electronic or mechanized tools are used.

    Execution of task is labor intensive and involves little

    mechanization. Level 2, where there are a few uncommon

    electronic or mechanized tools involved but human workers

    452 L.-R. Yang / Automation in Construction 17 (2008) 450458

  • 8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi

    4/9

    dominate the process. Execution of task involves some

    mechanization. Level 3, where there are several specialized

    electronic or mechanized tools involved. Execution of task

    involves more mechanization. Level 4, where fully- or nearly

    fully-automated systems dominate execution of the task.

    Execution of task involves mechanization linked with external

    information. Levels 1, 2, 3, and 4 are associated respectivelywith the lowest, medium low, medium high, and highest levels

    of automation utilization in executing tasks. The characteristics

    of four levels provide quantitative measures of automation

    usage for each task. In addition, Not Applicableand Don't

    Knowresponses were also available for each item.

    Automation index was developed to measure the use of

    automation technologies for common project tasks across the

    industry. For any given task, the level of automation employed

    is the task score. The sum of these scores was then divided by

    the total number of responses to yield the automation index for

    that task. The automation index for each task is computed as

    follows:

    AI X

    TS=NTS; 1

    where AI is the Automation Index, TS is the task score, and

    NTS is the number of responses with 1, 2, 3, or 4.

    3.4. Measurement: project satisfaction metrics

    The surveyed participants are at the project level. All major

    stakeholders (including the Owner, Architect/Engineering, and

    General Contractor) involved in the subject project were

    interviewed to evaluate overall project satisfaction. In other

    words, overall project satisfaction was measured from theperspectives of the Owner, A/E, and GC groups. The variables

    of interest were assessed through the respondents' perceptual

    evaluations. Items regarding project satisfaction used a five-

    point scale to determine the respondents' perception of satis-

    faction, where 1 represented strongly dissatisfy, 2 represented

    inclined to dissatisfy, 3 represented neither satisfy nor dissatisfy,

    4 represented inclined to satisfy, and 5 represented strongly

    satisfy. In addition, Not Applicable and Don't Know res-

    ponses were also available.

    3.5. Dealing with incomplete data, reliability and validity

    In order to determine if the response data associated with a

    particular project were adequate to be representative, a minimum

    response rate of 70% of all tasks associated with a project was

    established as the criterion for acceptance. If a particular project

    did not meet the 70% rate criterion, then it was not included in

    the analysis. This approach helped ensure that sufficient

    information was obtained about the entire project in order to

    be truly representative of the actual project.

    Cronbach's coefficient () was computed to test the

    reliability and internal consistency of the responses. For the

    items assessed in this research, the values are found to be

    more than 0.90 with an average value of 0.98, which indicate a

    high degree of internal consistency in the responses. Addition-

    ally, two main types of validity, content and construct validity,

    were tested.

    The content validity of the survey used in this study was

    tested through a literature review and interviews with practi-

    tioners. In other words, the survey items were based on previous

    studies and discussions with these construction executives. The

    industry interviews encompassed a number of executives fromthe Owner, A/E, and GC groups. The refined assessment items

    were included in the final survey. Finally, copies of a draft

    survey were sent to several industry professions to pre-test for

    the clarity of questions. Their insights were also incorporated

    into the final version of the survey.

    The construct validity was tested by factor analysis. Factors

    were extracted using varimax rotation. As suggested by Hair

    et al.[29], an item is considered to load on a given factor if the

    factor loading from the rotated factor pattern is 0.40 or more for

    that factor. The factor loadings for the items used in the study

    are more than 0.40 with an average value of 0.71.

    4. Characterizing project satisfaction-leveraging tasks

    4.1. Survey instrument and process

    Once project satisfaction-leveraging tasks were identified,

    steps were attempted to better understand how automation

    utilization affects project success. Phase 2 of the research

    entailed explaining the links between automation utilization and

    project satisfaction. The value of task characteristics in further

    explaining the links was investigated. Task characteristics were

    used to characterize the project satisfaction-leveraging tasks.

    Task characteristic analysis of these critical tasks can reveal

    features that leverage project performance. This approach pro-vides deeper insights into how automation usage impacts

    project success.

    The data collection effort involved characterization of the

    project satisfaction-leveraging tasks via task characteristics. A

    second data collection tool was used to assess how strongly

    certain characteristics are related to a given task. Based on

    brainstorming and the literature review[30], six categories of

    task characteristics were developed to classify tasks by their

    attributes and as a way to study differences between tasks

    relative to automation usage: 1) nature of task procedures, 2)

    time/space/cost factors, 3) information and data aspects, 4) task

    management, 5) nature of task product, and 6) nature of humanresource.

    For each subject task, the survey asks participants to assess

    the extent to which individual characteristic apply to that task.

    This survey offers respondents five optional responses: Strongly

    Agree, Agree, Neutral, Disagree, or Don't Know. The survey of

    characteristic applicability was conducted between February

    2006 and February 2007.

    4.2. Dealing with incomplete data, reliability and validity

    In order to determine if the response data associated with a

    particular task were adequate to be representative, a minimum

    response rate of 70% of all characteristics associated with a task

    453L.-R. Yang / Automation in Construction 17 (2008) 450458

  • 8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi

    5/9

    was established as the criterion for acceptance. If responses

    associated with a particular task did not meet the 70% rate

    criterion, then they were not used in the analysis. This approach

    helped ensure that sufficient knowledge was obtained about the

    task.

    In the process of determining the survey items, it is crucial to

    ensure the validity of their content, which is an important

    measure of a survey instrument's accuracy. A content validity

    was tested through a theoretical review and interviews with

    industry practitioners. Based on previous studies and discus-sions with a number of construction experts, the survey items

    were accepted as possessing content validity. The draft version

    of the data collection instrument was then sent to several

    construction professionals to pre-test for the clarity of questions.

    Their insights were incorporated into the final version of the

    survey.

    Based on the personal interviews conducted prior to the

    survey, the targeted respondents were identified as the senior

    individuals who were responsible for the project tasks. Potential

    respondents to the survey were identified by these practitioners.

    The respondents included presidents, vice presidents, design

    managers, project managers, project engineers, and projectplanners. A specified mix of expertise, group involvement, and

    industry sector participation was targeted in order to acquire a

    comprehensive knowledge from different perspectives. The

    data were collected from 54 industry professionals through

    personal interviews. These professionals averaged 18 years of

    experience. Detailed information regarding the respondents is

    presented inTable 1.

    4.3. Analysis of responses

    For any given characteristic, the assessed degree to which a

    task relates to that characteristic was established as the

    Characteristic Score. In order to perform quantitative analysis,

    responses were converted to Characteristic Scores as follows:

    Strongly Agree = 4, Agree = 3, Neutral = 2, and Disagree = 1.

    The Characteristic Applicability Index was computed as

    follows:

    CAI X

    CS=NR; 2

    where CAI is the Characteristic Applicability Index, CS is the

    Characteristic Score for a task, and NR is the number of

    responses with Strongly Agree, Agree, Neutral, or Disagree.

    The mean Characteristic Applicability Index was then

    calculated to identify the characteristics with high applicability

    to the project satisfaction-leveraging tasks. A Characteristic

    Applicability Index score of zero indicates not applicable.A

    value of 3.00 or greater indicates highly applicable(an index

    value of 3.00 is associated with Agree response). If a

    characteristic has high applicability to the project satisfaction-

    leveraging tasks, it indicates that this characteristic may explain

    project satisfaction-leveraging. The mean Characteristic Appli-cability Index was calculated as follows:

    MAI X

    CAI=NST; 3

    where MAI is the Mean Applicability Index, CAI is the

    Characteristic Applicability Index value for a satisfaction-

    leveraging task, and NST is the total number of satisfaction-

    leveraging tasks assessed.

    5. Results and analysis

    5.1. Identification of project clusters with the same perceptions

    of stakeholder satisfaction

    Cluster analysis was used in an exploratory mode to develop

    an objective classification of projects. This research was

    exploratory; therefore, different sets of clusters consisting of

    two, three, four, and five groups were examined. In order to

    identify homogeneous projects clusters with the same kinds of

    perceptions of stakeholder satisfaction, a K-means cluster

    analysis was performed on the basis of the three dimensions

    of satisfaction (Owner, A/E, and GC satisfaction). To validate

    the results of the cluster analysis, a discriminant analysis was

    conducted. The discriminant analysis presented in Table 2

    classified 98.9% of the projects as the cluster analysis did,indicating extremely good differentiation and a correct

    classification. These results suggest that the two clusters are

    distinctive.

    Table 1

    Information regarding respondents to survey of characteristic applicability

    Characteristic Classes N

    Title President 06

    Title Vice president 05

    Title Project manager 09

    Title Design manager 08Title Project engineer 19

    Title Project planner 07

    Expertise Need analysis 09

    Expertise Budget estimate 09

    Expertise Scheduling 09

    Expertise Structure design 09

    Expertise Electrical design 09

    Expertise Project management 09

    Years of experience 510 06

    Years of experience 1120 28

    Years of experience 2130 20

    Group involvement Owner 27

    Group involvement A/E 27

    Industry sector involvement Building 22

    Industry sector involvement Industrial 16Industry sector involvement Infrastructure 16

    Table 2

    Discriminant analysis

    Number/percentage Group Predicted group

    membership

    Total

    1 2

    Number 1 70 1 71

    2 0 18 18

    Percentage 1 98.6 1.4 100.0

    2 0.0 100.0 100.0

    454 L.-R. Yang / Automation in Construction 17 (2008) 450458

  • 8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi

    6/9

    The cluster analysis has identified two clusters, with the

    cluster mean values of discriminating variables given inTable 3.

    In addition, independent-samples t tests were undertaken to

    assess the internal validity of the cluster results. The results of

    thettests show that statistically significant differences do exist

    between the two clusters. The independent-samples t tests

    shown in Table 3 confirm that the three variables of Owner

    satisfaction, A/E satisfaction, and GC satisfaction do signifi-cantly differentiate across the two clusters. Combining these

    results with those of the discriminant analyses, the analysis

    ended with a two-cluster solution. The study reveals two project

    satisfaction segments, including high project satisfaction cluster

    (Cluster 1) and low project satisfaction cluster (Cluster 2). The

    levels of project satisfaction by stakeholder type are shown in

    Table 3. The analyses indicate that Cluster 1 has, on average,

    higher levels of stakeholder satisfaction than Cluster 2 for all

    satisfaction metrics analyzed. In most cases, there are only

    slight differences in perception of satisfaction among the project

    stakeholders. Finally, an independent-samples t test was

    conducted to determine whether the data provide evidence for

    significant differences in performance outcomes being associ-ated with differences in automation usage for each task. This

    discussion is presented in the subsequent section.

    5.2. Identification of project satisfaction-leveraging tasks

    The tasks with a significant difference in automation usage

    between projects with stakeholder satisfaction and dissatisfac-

    tion are defined as project satisfaction-leveraging tasks. Table 4

    presents the comparisons of task-level automation usage

    between projects with stakeholder satisfaction and dissatisfac-

    tion. The test results indicate that levels of automation usage for

    these tasks may be positively associated with projects' levels ofstakeholder satisfaction.

    Table 5shows the levels of automation usage for the project

    satisfaction-leveraging tasks. Among the 6 critical tasks,

    automation technology levels appear highest for design

    structure systems and design electrical systems. Computer

    Aided Design (CAD) software is commonly used to create two-

    dimensional (2-D) drawings or three-dimensional (3-D) models

    in the industry. CAD software can be used to generate precision

    drawings or technical illustrations and refine the design at low

    cost. Many organizations adopt CAD software in these designtasks. Advancements in design tasks may tend to precede the

    other tasks because the limited scope aspect of design should

    make related advancements more easily achievable. Also,

    information- and data-intensive tasks appear to be more easily

    automated than other task types. The lowest levels of automation

    utilization are associated with track design progress. Data

    management software may be a solution that automates the task.

    A data management tool provides a means to monitor and track

    design progress. It may also help design teams organize design

    data. Track design progressmay lag in technology usage as a

    result of inadequate automation devices driven by lack of R&D

    investment. In addition, this task lags in automation usage

    perhaps due to its frequent communication characteristic forwhich automation systems are difficult to accomplish. Prepare

    milestone schedule and develop budget estimate are

    associated with the greatest overall variability in level of

    automation technology employed. While many scheduling and

    cost estimating software systems exist, many of these are either

    expensive or complex relative to user skills. Levels of auto-

    mation utilization are the most uniform for design electrical

    systems. Many organizations are making significant techno-

    logical advances in the task.

    Preproject planning is the project phase encompassing all the

    tasks between project initial to detailed design [31]. Prior

    studies have shown the importance of preproject planning onprojects and its influence on project performance [3235].

    Table 3

    Cluster means of discriminating variables

    Variable Projects

    with

    satisfaction

    Projects

    with

    dis-

    satisfaction

    t-statistic p-value

    N Mean N MeanOwner satisfaction 76 3.67 19 2.21 10.035 0.000

    A/E satisfaction 74 3.58 18 2.28 08.113 0.000

    GC satisfaction 74 3.55 19 2.21 09.513 0.000

    Table 4

    t-Test for project satisfaction-leveraging tasks

    Task Projects with stakeholder

    satisfaction

    Projects with stakeholder

    dissatisfaction

    Mean difference t-statistic Significance

    N Mean Standard deviation N Mean Standard deviation

    Conduct need analysis for a new facility 45 2.31 1.02 16 1.94 1.12 0.37 1.223 0.056

    Develop budget estimate 67 2.45 0.99 18 2.11 1.08 0.34 1.258 0.053

    Prepare milestone schedule 67 2.49 1.05 19 2.16 1.07 0.33 1.222 0.056

    Design structure systems 58 2.53 0.92 18 2.28 0.89 0.25 1.039 0.076

    Design electrical systems 54 2.50 0.86 17 2.29 0.77 0.21 0.878 0.096

    Track design progress 60 2.07 0.88 18 1.89 0.90 0.18 0.748 0.098

    Table 5

    Levels of automation usage for project satisfaction-leveraging tasks

    Task N Mean Standard deviation

    Conduct need analysis for a new facility 62 2.21 1.01

    Develop budget estimate 85 2.38 1.04

    Prepare milestone schedule 86 2.42 1.06

    Design structure systems 77 2.48 0.91Design electrical systems 72 2.46 0.84

    Track design progress 78 2.03 0.88

    455L.-R. Yang / Automation in Construction 17 (2008) 450458

  • 8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi

    7/9

    Previous research indicated that greater project planning efforts

    may contribute to project performance in terms of cost,

    schedule, and stakeholder success. The project satisfaction-leveraging tasks identified in this study are associated with

    preproject planning process, during which success in the

    following phases is highly dependent on the level of effort

    expended. This may be a reason why employing automation

    technology in these leveragingtasks may be associated with

    project stakeholder satisfaction.

    5.3. Explaining the links between automation utilization and

    project stakeholder satisfaction

    The preliminary results from this research indicate that a total

    of 6 tasks are associated with project satisfaction-leveraging

    tasks. These project satisfaction-leveraging tasks are associated

    with the FrontEnd and Design phases. In order to identify

    characteristics associated with the project satisfaction-leverag-

    ing tasks, these critical tasks were analyzed using task charac-

    teristics. The data collection effort involved characterization of

    these identified tasks. Task characteristics that may explain

    project satisfaction-leveraging were identified to further explainthe links between automation utilization and project satisfac-

    tion. Characteristic data associated with these tasks were used to

    help identify common characteristic trends for project satisfac-

    tion-leveraging tasks.

    The critical tasks identified include: 1) conduct need analysis

    for a new facility, 2) develop budget estimate, 3) prepare

    milestone schedule, 4) design structure systems, 5) design

    electrical systems, and 6) track design progress. The first three

    are associated with the FrontEnd phase and the last three

    pertain to the Design phase. Task characteristic analysis of these

    critical tasks reveals features common to a specific task group.

    Comparing to the Design tasks, the critical tasks associated withthe FrontEnd phase involves uncertainty or probabilistic

    information. On the other hand, the critical design tasks require

    frequent communication between individuals and, compared to

    the FrontEnd tasks, involve more different types of organiza-

    tions. Additionally, data accuracy is crucial to successful task

    performance for these critical Design tasks.

    The complete information of all task characteristics is

    provided inTables 6 and 7.Table 6presents high applicability

    characteristics for the project satisfaction-leveraging tasks.

    Table 7 presents low applicability characteristics for these

    tasks. These tables show the overall image of how the selected

    characteristics perform. Six characteristics that may explain

    Table 6

    High applicability characteristics for project satisfaction-leveraging tasks

    Category Task characteristics Mean

    applicability

    index value

    Information and data Task involves uncertainty or

    probabilistic information

    3.60

    Information and data Historical data from previous

    projects are required for execution

    3.11

    Information and data Data accuracy is crucial to

    successful task performance

    3.56

    Management Many different types of

    organizations are involved

    3.17

    Management Responsible individual must

    communicate frequently with others

    3.58

    Work procedure Task involves iterations and revisions 3.30

    Table 7

    Low applicability characteristics for project satisfaction-leveraging tasks

    Category Task characteristics Mean applicability index value

    Human resource Many individuals are involved to perform task 2.42

    Human resource Task involves many individuals with different skills and specialties

    Human resource User s, worker's or operator's experience is critical to performance

    WF product Performance of many subsequent tasks relies heavily on this task

    WF product Task product is physically large and bulky

    WF product Errors are difficult to fix or require a large amount of resources to f ix

    Time/space/cost Task is a critical path activity in most cases

    Time/space/cost Task requires spatial coordination 2.69

    Time/space/cost Task involves relatively high uncertainty in cost, schedule, quality, or safety

    Time/space/cost Task management operates in close proximity to workers 2.75Time/space/cost Task involves environmental hazard

    Time/space/cost Task is costly to execute

    Information and data Task relies on industry technical standards 2.52

    Information and data Task data are in many different formats 2.44

    Information and data Security of related data is very important

    Information and data Task involves significant amount of data updating

    Management A specialty organization is involved in most cases 2.72

    Management Primary performance driver of the task is quality, safety, cost, or schedule 1.75

    Management Task involves high probability of change 2.69

    Work procedure Task is error prone 2.49

    Work procedure Task procedures are driven by regulations

    Work procedure Task involves repetit ive activity

    Work procedure Some task resources are often idle

    Work procedure Task procedures are very complex

    Work procedure Task relies on or requires physical output products of many previous task

    456 L.-R. Yang / Automation in Construction 17 (2008) 450458

  • 8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi

    8/9

    leveraging were identified in the analysis. These characteristics

    show a strong association with the project satisfaction-

    leveraging tasks. Most of the characteristics that may explain

    leveraging fall in the following two categories: 1) information

    and data and 2) management. This indicates that information/

    data-intensive and management-related characteristics may be

    associated with project stakeholder satisfaction.Characteristics that may explain project satisfaction-leverag-

    ing were identified in order to explore project stakeholder

    satisfaction determinants. The analyses suggest that tasks in-

    volving iterations, revisions, and many different types of orga-

    nizations may deserve the execution with high automation

    approaches. Tasks that require frequent communication between

    individuals may be associated with project stakeholder satisfac-

    tion. In addition, degrees of automation used in executing the

    tasks that involve uncertainty or probabilistic information may

    be positively related to the stakeholder satisfaction of a project.

    The priority for automation implementation may also pertain to

    the tasks for which data accuracy is critical to performance andhistorical data from previous projects are required for execution.

    One of the low applicability characteristics (Primary

    performance driver of the task is cost, schedule, quality, or

    safety) was further analyzed to explain the links between

    automation utilization and project satisfaction. Regarding

    primary performance driver of the satisfaction-leveraging

    tasks, the applicability index values for cost, schedule, quality,

    and safety are 1.50, 2.25, 2.25, and 1.00 respectively (with a

    mean of 1.75). The relatively high levels of applicability are

    associated with schedule and quality. The analyses suggest that

    primary performance driver of the leveraging tasks may be

    more closely associated with schedule and quality than are cost

    and safety.

    6. Conclusions and recommendations

    The lack of information regarding automation benefits along

    with uncertain competitive advantage from new technology

    have resulted in industry reluctance to implement new

    automation technologies. Thus, a study of the relationship

    between automation utilization and project stakeholder satis-

    faction is necessary. The purpose of this study was to identify

    project satisfaction-leveraging tasks and common characteris-

    tics associated with these critical tasks. Metrics were developed

    to determine automation usage at the task level and perceivedstakeholder satisfaction. The projects are examined by cluster-

    ing them on the basis of differences in perceptions of the

    proposed satisfaction dimensions. In other words, cluster

    analysis was used as a means to group similar properties on

    the basis of stakeholder satisfaction. Independent-samples t

    tests were undertaken to assess the internal validity of the

    cluster results. Combining these results with those of the

    discriminant analyses, a two-cluster solution was identified. The

    study reveals two project satisfaction segments, including high

    project satisfaction cluster and low project satisfaction cluster.

    Furthermore, hypothesis testing was performed to identify

    relationships between task-level automation utilization and

    project satisfaction. For each of the tasks, levels of automation

    usage were analyzed to identify project satisfaction-leveraging

    tasks. The tasks with a significant difference in automation

    usage between projects with stakeholder satisfaction and

    dissatisfaction are associated with project satisfaction-leverag-

    ing tasks. In other words, the project satisfaction-leveraging

    tasks have significant differences in automation usage for

    projects with stakeholder satisfaction as opposed to projectswith stakeholder dissatisfaction. These project satisfaction-

    leveraging tasks are associated with the FrontEnd and Design

    phases. The critical tasks identified in this study include: 1)

    conduct need analysis for a new facility, 2) develop budget

    estimate, 3) prepare milestone schedule, 4) design structure

    systems, 5) design electrical systems, and 6) track design

    progress.

    This paper also explores the links between project

    satisfaction and automation utilization in detail. The technique

    used for analyzing the associations is analysis of task

    characteristics. The project satisfaction-leveraging tasks were

    further analyzed using characteristic analysis to explain thelinks between automation utilization and project success. In

    other words, task characteristics were used to better understand

    project satisfaction-leveraging tasks through analysis of their

    attributes. In summary, task characteristics analyses of project

    satisfaction-leveraging tasks are employed as a way to gain

    greater understanding of the connection between automation

    usage and project satisfaction. The characteristic analysis

    reveals attributes common to the project satisfaction-leveraging

    tasks. These analyses suggest that data/information-intensive

    and management-related task characteristics may be associated

    with project stakeholder satisfaction. Degrees of automation

    used in executing the tasks that require frequent personnel

    communications may be positively related to the stakeholdersatisfaction of a project. Consideration should be also given to

    employing higher levels of automation usage for the tasks that

    involve many different types of organizations. Furthermore, the

    priority for automation implementation may also pertain to the

    tasks for which data accuracy is critical to performance and

    historical data from previous projects are required for execution.

    In addition, tasks that involve iterations, revisions, uncertainty,

    or probabilistic information may deserve the high automation

    approaches.

    The research provides empirical evidence that supports the

    expectation of gaining significant benefits with higher levels of

    automation implementation. This paper reports on the findingsof empirical research on the adoption of automation technology

    at the task level, identifies the benefit of adopting automation

    technology, and provides recommendations for the implemen-

    tation of automation technology on projects. The results of this

    study indicate that automation is critical to assist in the exe-

    cution of project tasks and may contribute significantly to

    project performance in terms of stakeholder satisfaction.

    Findings from this study provide direction for the decision

    making of automation investment and are helpful to managers

    in deciding whether to apply automation to tasks with certain

    characteristics on capital facility projects.

    One limitation of the research is that qualitative factors are

    excluded from the analysis. The qualitative issues may be

    457L.-R. Yang / Automation in Construction 17 (2008) 450458

  • 8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi

    9/9

    significant in helping explain the associations between

    automation utilization and project performance. In spite of the

    limitation of acquisition of qualitative information, character-

    istic applicability analysis is a logical approach for exploring the

    links. However, it would be worthwhile to examine the quali-

    tative factors in future studies.

    Acknowledgments

    The author would like to thank the anonymous referees for

    their extremely helpful comments on this paper. The work

    described in this article was supported by grant from the

    National Science Council of Taiwan (93-2211-E-032-024 and

    94-2211-E-032-021).

    References

    [1] CERF, Commercializing infrastructure technologies, CERF Report #97-

    5028, Civil Engineering Research Foundation, Reston, VA, 1997.

    [2] P. Mitropulos, C.B. Tatum, Process and criteria for technology adoption

    decisions, Proceedings of Construction Congress, San Diego, CA, 1995,

    pp. 1724.

    [3] P. Simmons, Measurement and the evaluation of I.T. investments,

    Proceedings of IEEE 2nd International Software Metrics Symposium,

    London, England, 1994, pp. 7483.

    [4] K. Hampson, C.B. Tatum, Technology strategy and competitive

    performance in bridge construction, Journal of Construction Engineering

    and Management 123 (2) (1997) 153161.

    [5] R.E. Johnson, M.J. Clayton, The impact of information technology in

    design and construction: the owner's perspective, Automation in

    Construction 8 (1) (1998) 314.

    [6] W.E. Back, K.A. Moreau, Cost and schedule impacts of information

    management on EPC process, Journal of Management in Engineering 16

    (2) (2000) 5970.

    [7] S.R. Thomas, C.L. Macken, S.H. Lee, Impacts of Design/Information

    Technology on Building and Industrial Projects, BMM2001-10, Construc-

    tion Industry Institute (CII), Austin, TX, 2001.

    [8] J.T. O'Connor, L. Yang, Project performance vs. use of technologies at the

    project- and phase-levels, Journal of Construction Engineering and

    Management 130 (3) (2004) 322329.

    [9] J.T. O'Connor, M.E. Kumashiro, K.A. Welch, S.P. Hadeed, K.E. Braden,

    M.J. Deogaonkar, Project- and Phase-Level Technology use Metrics for

    Capital Facility Projects, Report, vol. 16, Center for Construction Industry

    Studies, Austin, TX, 2000.

    [10] R.M. Webb, J. Smallwood, T.C. Haupt, The potential of 4D CAD as a tool

    for construction management, Journal of Construction Research 5 (1)

    (2004) 4360.

    [11] M. Abduh, M.J. Skibniewski, Electronic networking technologies in

    construction, Journal of Construction Research 5 (1) (2004) 1742.

    [12] R.Y. Tse, L. Choy, Is IT training in construction industry useful, Journal of

    Construction Research 6 (1) (2005) 113.

    [13] V. Peansupap, D. Walker, Factors affecting ICT diffusion: a case study of

    three large Australian construction contractors, Engineering, Construction

    and Architectural Management 12 (1) (2005) 2137.

    [14] P.M. Goodrum, M. Gangwar, The relationship between changes in

    equipment technology and wages in the US construction industry,

    Construction Management and Economics 22 (3) (2004) 291301.

    [15] P. Mitropoulos, C. Tatum, Factors driving adoption of new information

    technologies, Journal of Construction Engineering and Management 126

    (5) (2000) 340348.

    [16] K.J. Fergusson, Impact of integration on industrial facility quality, PhD

    Thesis, Stanford University, 1993.

    [17] W.E. Back, L.C. Bell, Quantifying Benefits of Electronic Technology

    Applied to Bulk Materials Management, The Construction Industry Action

    Group, Houston, TX, 1994.[18] F.H. Griffis, D.B. Hogan, W. Li, An analysis of the impacts of using three

    dimensional computer models in the management of construction,

    Research Report 106-11, Construction Industry Institute (CII), Austin,

    TX, 1995.

    [19] W.E. Back, K.A. Moreau, J. Toon, Determining the impact of information

    management on project schedule and cost, Research Report 125-11,

    Construction Industry Institute (CII), Austin, TX, 1996.

    [20] R.R. Tan, Information technology and perceived competitive advantage:

    an empirical study of engineering consulting firms in Taiwan, Construction

    Management and Economics 14 (3) (1996) 227240.

    [21] J. Whyte, D. Bouchlaghem, T. Thorpe, IT implementation in the

    construction organization, Engineering, Construction and Architectural

    Management 9 (56) (2002) 371377.

    [22] P.M. Goodrum, C.T. Haas, Partial factor productivity and equipment

    technology change at activity level in U.S. construction industry, Journal ofConstruction Engineering and Management 128 (6) (2002) 463472.

    [23] J.A. De Lapp, D.N. Ford, J.A. Bryant, J. Horlen, Impacts of CAD on

    design realization, Engineering, Construction and Architectural Manage-

    ment 11 (4) (2004) 284291.

    [24] M. Sexton, P. Barrett, The role of technology transfer in innovation within

    small construction firms, Engineering, Construction and Architectural

    Management 11 (5) (2004) 342348.

    [25] S. Lee, S.R. Thomas, R.L. Tucker, The relative impacts of selected

    practices on project cost and schedule, Construction Management and

    Economics 23 (5) (2005) 545553.

    [26] J.D. Stevens, C. Glagola, W.B. Ledbetter, Quality-measurement matrix,

    Journal of Management in Engineering 10 (6) (1994) 3035.

    [27] K.A. Welch, Development of a tool for assessing the degree of automation

    and integration on capital projects, MS Thesis, The University of Texas at

    Austin, 1998.[28] M.E. Kumashiro, Measuring automation and integration in the construc-

    tion industry, MS Thesis, The University of Texas at Austin, 1999.

    [29] J.F. Hair, R.E. Anderson, R.L. Tatham, W.C. Black, Data Analysis with

    Readings, 4th ed.Prentice-Hall, Englewood Cliffs, NJ, 1995.

    [30] S. Won, A model for work function-based prioritization of technologies for

    capital projects, PhD Thesis, The University of Texas at Austin, 2002.

    [31] C.S. Cho, G.E. Gibson, Building project scope definition using project

    definition rating index, Journal of Architectural Engineering 7 (4) (2001)

    115125.

    [32] L. Yang, J.T. O'Connor, C. Huang, Comparison of technology utilization

    and benefits in Taiwanese and U.S. industries, Journal of Management in

    Engineering 23 (3) (2007) 147155.

    [33] L. Yang, J.T. O'Connor, J. Chen, Assessment of automation and

    integration technology's impact on project stakeholder success, Automa-

    tion in Construction 16 (6) (2007) 725733.[34] A.F. Griffith, G.E. Gibson, Alignment during preproject planning, Journal

    of Management in Engineering 17 (2) (2001) 6976.

    [35] A.F. Griffith, G.E. Gibson, M.R. Hamilton, A.L. Tortora, C.T. Wilson,

    Project success index for capital facility construction projects, Journal of

    Performance of Constructed Facilities 13 (1) (1999) 3945.

    458 L.-R. Yang / Automation in Construction 17 (2008) 450458