Upload
vinesh-krishna
View
216
Download
0
Embed Size (px)
Citation preview
8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi
1/9
Exploring the links between task-level automation usage
and project satisfaction
Li-Ren Yang
Department of Business Administration, Tamkang Uni versity, Tamsui, Taipei, 251, Taiwan
Accepted 7 August 2007
Abstract
The purpose of this study was to identify project satisfaction-leveraging tasks and common characteristics associated with these critical tasks.
To address the primary aim, a survey was conducted to determine correlations between task-level automation adoption and project satisfaction
from the perspectives of various types of project stakeholders. Identification of project satisfaction-leveraging tasks is employed as a way to gain
greater understanding of the connections. Also, this study explores the links between automation utilization and project satisfaction in further
detail. Task characteristics are investigated as an additional basis for gaining deeper insights into how automation technology usage may impact
project satisfaction. A second survey was used to collect needed data from industry professionals. The analyses suggest that degrees of automation
used in executing the project satisfaction-leveraging tasks may be positively related to project stakeholder satisfaction. The results also indicate
that information and data intensive and management-related characteristics may be associated with overall project stakeholder satisfaction.
2007 Elsevier B.V. All rights reserved.
Keywords: Automation; Technology; Project; Stakeholder satisfaction; Task
1. Introduction
Many studies have shown that the construction industry is
reluctant to apply new technologies and employs lower levels of
technology than other industries. A national-wide survey
conducted by the Civil Engineering Research Foundation
indicated that the design and construction industry spends
only 0.5% of its total revenues on research and development[1].
In recent years, however, there has been a growing trend
towards increased technology utilization levels on Architect/
Engineering/Construction (A/E/C) capital facility projects.According to a 1995 study, four drivers for adoption of new
technologies were identified: 1) competitive advantage, 2)
external requirements, 3) priority problems avoid losses
from reduced performance, and 4) technological opportunity to
improve operations [2]. Some construction firms adopt
automation in the attempt to reduce the cost and schedule of a
project. These companies are also examining their operations
for ways to improve stakeholder satisfaction. However, since
the benefits of innovation can be rather intangible, this has
slowed or prevented the adoption of new automation technol-
ogy. Accordingly the impact of automation on project
performance has been one of the major issues for both industry
and academic fields. In order to understand the benefits, there is
a need for quantification of the benefits derived from
automation application. Simmons [3] suggested that methods
used to evaluate the impact of technology on performance
measures may be the problem in connecting investment in
technology to improvements in business performance. Researchon automation utilization at the task level and its associations
with project success should offer tangible evidence of
advantages from using technologies.
While many studies have promoted technology as a means to
enhance project performance [47], very few published
empirical studies in construction have explored the direct
effects of automation on project performance from the
perspectives of various types of stakeholders. None of the
previous research attempts to explain the links between
automation usage and project performance. In addition, there
has been no comprehensive study on the impacts of automation
Automation in Construction 17 (2008) 450458
www.elsevier.com/locate/autcon
Tel.: +886 2 26215656; fax: +886 2 26209742.
E-mail address:[email protected].
0926-5805/$ - see front matter 2007 Elsevier B.V. All rights reserved.doi:10.1016/j.autcon.2007.08.001
mailto:[email protected]://dx.doi.org/10.1016/j.autcon.2007.08.001http://dx.doi.org/10.1016/j.autcon.2007.08.001mailto:[email protected]8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi
2/9
usage on overall project stakeholder satisfaction. Empirical
evidence that supports the link between automation usage at the
task level and project stakeholder satisfaction is lacking. Thus,
developing such support will illustrate the benefits of
automation adoption. This study attempts to fill this void of
empirical evidence by identifying project satisfaction-leverag-
ing tasks and common characteristics associated with thesecritical tasks. This paper addresses associations between task-
level automation technology usage and project success. The
links between automation utilization and project satisfaction are
explored in detail. For the purposes of this research, automation
is defined as the use of an electronic or mechanized tool by a
human being to manipulate data or produce a product[8]. The
purpose of this research is three-fold. The first objective of this
study was to identify project clusters formed on the basis of the
perceptions of stakeholder satisfaction. The second objective
was to determine project satisfaction-leveraging tasks. The third
objective was to investigate the characteristics associated with
these project satisfaction-leveraging tasks to gain deeperinsights into how automation usage may impact project success.
The analyses of automation usage and relationships with
project satisfaction are based on an industry-wide survey per-
formed between October 2004 and June 2005. A data collection
tool was developed to assess automation use levels in the
Taiwanese industry. A total of 98 project responses were collected
through personal interviews. Automation usage metrics are based
on 61 common project tasks. In order to measure the degree of
automation used on projects and its impacts on project outcomes,
the data collection tool was used on all types of projects in the
building, industrial, and infrastructure sectors. The data analyzed
in this study are project-specific, meaning the data are repre-
sentative of the levels of automation used on projects. In addition,the analyses of characterization of the project satisfaction-
leveraging tasks are based on a second survey conducted between
February 2006 and February 2007. The data collection effort
involved characterization of the project satisfaction-leveraging
tasks. This paper explains the links between automation
utilization and project success. Automation usage metrics
analyzed include those at the task level. Project success parameter
analyzed is project stakeholder satisfaction.
2. Literature review
A considerable body of research has been conducted on theadoption and use of technology in the A/E/C industry. Much of
the project/construction management literature relevant to this
research is associated with the adoption of technology, factors
influencing the implementation of technology, and the expected
benefits associated with the use of technology. Concerning
technology usage, O'Connor et al.[9]investigated the extent to
which technologies are being used in executing projects in the
construction industry. Webb et al.[10]explored the potential of
4D CAD as a tool for construction management. Abduh and
Skibniewski[11]presented an assessment model to measure the
utility of Electronic Networking Technologies (ENT) services
in construction project activities. Tse and Choy[12]carried out
an in-depth interview for studying the scope of use of IT in
Hong Kong's construction industry. Peansupap and Walker
[13] addressed the critical issue of how best to adopt and
diffuse information and communication technology (ICT) into
organizations.
While the above authors promoted the adoption of technol-
ogy, other researchers have also been active in identifying the
factors influencing the adoption of technology. Goodrum andGangwar [14] examined the relationship between changes in
equipment technology and changes in construction wages with
the help of five factors of equipment technology change: control,
energy, ergonomics, functionality and information processing.
Mitropoulos and Tatum[15]argued that uncertain competitive
advantage from using new technologies and lack of information
regarding technologies and benefits may be the reasons for
reluctance to adopt technology. There has been also much work
conducted on the benefits from technology in the construction
industry. Earlier studies supported the notion that technology
adoption is beneficial. Several researchers have investigated the
impacts of different technology on project performance. Some ofthe project performance indicators they examined include cost,
schedule, and safety success, which are of course major concerns
to project stakeholders. Fergusson [16]investigated the relation-
ships between facility integration and quality. Back and Bell [17]
identified the impacts of use of electronic data interchange (EDI)
in bulk materials management. Griffis et al. [18] studied the
impacts of using 3-D computer models on cost, schedule
duration, and rework metrics. Back et al.[19]undertook a study
to determine the impact of information management on project
schedule and cost. Tan[20]studied the impact and linkage of
information technology and competitive advantage.
Additionally, Hampson and Tatum[4]stated that technology
strategy can positively influence competitive performance.Johnson and Clayton[5]contended that information technology
can improve productivity of teams and management procedures.
Back and Moreau [6] suggested that improving internal
information exchange and integrating project-based information
across organizational boundaries may result in project cost and
schedule reductions. Thomas et al.[7] evaluated the impacts of
design/information technologies by connecting their use to
project performance in terms of cost growth, schedule growth,
and safety success. Whyte et al. [21] explored processes by
which emerging technologies can be introduced into construc-
tion organizations. Goodrum and Haas [22] investigated the
impact of different types of equipment technologies on con-struction productivity. De Lapp et al.[23]examined the impacts
of computed aided design (CAD) on design realization. Sexton
and Barrett [24] performed in-depth case study to understand
the role of technology transfer in innovation within small con-
struction firms. Lee et al.[25]examined the relative impacts of
selected practices on project cost and schedule. Above prior
studies indicated that technology is playing an important
enabling role in construction. While the diverse benefits of
technology have received substantial attention, the number of
studies dealing with technology's impact on the performance in
terms of stakeholder satisfaction is rather scarce.
A reviewof the literature suggests that the use of technologyas
a means to enhance project performance has been widely
451L.-R. Yang / Automation in Construction 17 (2008) 450458
8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi
3/9
supported. Generally, many researchers have suggested that
technology provides significant benefits to capital facility
projects. The literature review provides background for devel-
oping an understanding of the issues related to the adoption and
use of technology, factors influencing the adoption of technology,
and the benefits to be derived from technology. Issues discussed
include the use of technologies for specific project tasks,technology strategy, information technology, and the application
of integration. Project performance measurements commonly
used in the previous studies include cost, schedule, degree of
attainment, return on investment, and safety. The literature review
suggests that most performance measurements currently being
used are quantitative or hard measures of cost and schedule. Soft
measures such as leadership, employee satisfaction, and team-
work are now being measured using qualitative or subjective
measurement techniques[26]. In light of the previous research, it
is evident that additional work is justified. While research has
centered on the project performance in terms of cost and schedule
success, relatively less has approached the associations betweenautomation utilization and overall project satisfaction from the
perspectives of various types of stakeholders. Also, few articles
are known about the explanation of the links between automation
utilization and project success. Additionally, most studies in
construction seeking to provide insights into technology usage
have not developed specific measures for automation implemen-
tation and stakeholder satisfaction levels.
In summary, there has been much research conducted on the
use of technology and the benefits derived from technology
application, although there is little work with quantifiable
information on how automation affects overall project stake-
holder satisfaction. Additionally, few studies have empirically
tested the relationships between technology usage at the tasklevel and project performance in terms of stakeholder
satisfaction. Thus, it will be useful to develop quantitative
measures of automation utilization and stakeholder satisfaction.
Also, there is a need for more comprehensive empirical evi-
dence that evaluates the benefits associated with automation
and, more specifically, its impact on project performance in
terms of stakeholder satisfaction.
This research adds to the literature in two valuable ways. First,
it provides evidence of performance implications of automation
implementation at the task level. Second, it offers important
results on the identification of project satisfaction-leveraging
tasks and their common characteristics from the perspectives ofmajor stakeholders involved in projects, including the Owner,
Architect/Engineering (A/E), and General Contractor (GC)
groups. Research on automation utilization at the task level
should provide construction firms with information on whether to
adopt automationtechnologies. In addition, the assessment of task
characteristics that can leverage the benefits of automation should
also be beneficial. To address this gap in the literature, the
following research hypotheses were developed:
Levels of automation utilization for certain tasks are positively
related to projects' levels of stakeholder satisfaction
Task characteristics can explain the links between automa-
tion utilization and project stakeholder satisfaction.
3. Determining project satisfaction-leveraging tasks
3.1. Data collection tool
The first phase of research included identifying project
satisfaction-leveraging tasks. A survey instrument was used to
measure the degree of automation usage on capital facilityprojects and its associations with project outcomes. The data
collection toll was developed based on variables used in pre-
vious studies and understanding gained from interviews
conducted with executives in the construction industry. The
survey was composed of two sections: project/company
information and degree of automation use for tasks. The first
section of the survey obtains information concerning the project,
project type, and final performance of the project in terms of
stakeholder satisfaction. The second section assesses level of
automation used in executing the project. For the purpose of this
study, a project's life cycle is structured in five phases: Front
End (which includes scoping, feasibility, and preliminary designactivities), Design, Procurement, Construction Management,
and Construction Execution[9]. To provide a basis for assessing
automation usage, it is necessary to determine the common tasks
performed on projects. Based on brainstorming and the litera-
ture search [9,27], a total of 61 common project tasks were
developed. Study participants were first asked to identify a
recent project that they were familiar with for assessment. For
the subject project, the survey then asks participants to assess the
degree of automation used in executing each task for that project.
3.2. Sample selection and data collection
An industry-wide survey of automation use levels on capitalfacility projects was conducted in Taiwan between October
2004 and June 2005. A data collection tool was developed to
collect project-based data. A total of 98 project responses were
collected through personal interviews. Individuals interested in
participating in the study were identified by a search from
various industry associations. In order to obtain a truly repre-
sentative sample, not only was the geographic mix of projects
intentionally diverse, but a diverse mix of participation was
sought with respect to sector of industry. Additionally, a
specified mix of project size was targeted in order to obtain a
representative sample of the industry. More than 100 projects
were investigated and some were not included in the analysisbecause they contained insufficient information. In addition, the
projects were examined to ensure that no duplicate project
information was collected. Ultimately, 98 survey responses
were used in the analysis.
3.3. Measurement: automation usage metrics
In assessing the degree of automation used in executing each
task, respondents could choose from four levels [9,27,28]:
Level 1, where no electronic or mechanized tools are used.
Execution of task is labor intensive and involves little
mechanization. Level 2, where there are a few uncommon
electronic or mechanized tools involved but human workers
452 L.-R. Yang / Automation in Construction 17 (2008) 450458
8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi
4/9
dominate the process. Execution of task involves some
mechanization. Level 3, where there are several specialized
electronic or mechanized tools involved. Execution of task
involves more mechanization. Level 4, where fully- or nearly
fully-automated systems dominate execution of the task.
Execution of task involves mechanization linked with external
information. Levels 1, 2, 3, and 4 are associated respectivelywith the lowest, medium low, medium high, and highest levels
of automation utilization in executing tasks. The characteristics
of four levels provide quantitative measures of automation
usage for each task. In addition, Not Applicableand Don't
Knowresponses were also available for each item.
Automation index was developed to measure the use of
automation technologies for common project tasks across the
industry. For any given task, the level of automation employed
is the task score. The sum of these scores was then divided by
the total number of responses to yield the automation index for
that task. The automation index for each task is computed as
follows:
AI X
TS=NTS; 1
where AI is the Automation Index, TS is the task score, and
NTS is the number of responses with 1, 2, 3, or 4.
3.4. Measurement: project satisfaction metrics
The surveyed participants are at the project level. All major
stakeholders (including the Owner, Architect/Engineering, and
General Contractor) involved in the subject project were
interviewed to evaluate overall project satisfaction. In other
words, overall project satisfaction was measured from theperspectives of the Owner, A/E, and GC groups. The variables
of interest were assessed through the respondents' perceptual
evaluations. Items regarding project satisfaction used a five-
point scale to determine the respondents' perception of satis-
faction, where 1 represented strongly dissatisfy, 2 represented
inclined to dissatisfy, 3 represented neither satisfy nor dissatisfy,
4 represented inclined to satisfy, and 5 represented strongly
satisfy. In addition, Not Applicable and Don't Know res-
ponses were also available.
3.5. Dealing with incomplete data, reliability and validity
In order to determine if the response data associated with a
particular project were adequate to be representative, a minimum
response rate of 70% of all tasks associated with a project was
established as the criterion for acceptance. If a particular project
did not meet the 70% rate criterion, then it was not included in
the analysis. This approach helped ensure that sufficient
information was obtained about the entire project in order to
be truly representative of the actual project.
Cronbach's coefficient () was computed to test the
reliability and internal consistency of the responses. For the
items assessed in this research, the values are found to be
more than 0.90 with an average value of 0.98, which indicate a
high degree of internal consistency in the responses. Addition-
ally, two main types of validity, content and construct validity,
were tested.
The content validity of the survey used in this study was
tested through a literature review and interviews with practi-
tioners. In other words, the survey items were based on previous
studies and discussions with these construction executives. The
industry interviews encompassed a number of executives fromthe Owner, A/E, and GC groups. The refined assessment items
were included in the final survey. Finally, copies of a draft
survey were sent to several industry professions to pre-test for
the clarity of questions. Their insights were also incorporated
into the final version of the survey.
The construct validity was tested by factor analysis. Factors
were extracted using varimax rotation. As suggested by Hair
et al.[29], an item is considered to load on a given factor if the
factor loading from the rotated factor pattern is 0.40 or more for
that factor. The factor loadings for the items used in the study
are more than 0.40 with an average value of 0.71.
4. Characterizing project satisfaction-leveraging tasks
4.1. Survey instrument and process
Once project satisfaction-leveraging tasks were identified,
steps were attempted to better understand how automation
utilization affects project success. Phase 2 of the research
entailed explaining the links between automation utilization and
project satisfaction. The value of task characteristics in further
explaining the links was investigated. Task characteristics were
used to characterize the project satisfaction-leveraging tasks.
Task characteristic analysis of these critical tasks can reveal
features that leverage project performance. This approach pro-vides deeper insights into how automation usage impacts
project success.
The data collection effort involved characterization of the
project satisfaction-leveraging tasks via task characteristics. A
second data collection tool was used to assess how strongly
certain characteristics are related to a given task. Based on
brainstorming and the literature review[30], six categories of
task characteristics were developed to classify tasks by their
attributes and as a way to study differences between tasks
relative to automation usage: 1) nature of task procedures, 2)
time/space/cost factors, 3) information and data aspects, 4) task
management, 5) nature of task product, and 6) nature of humanresource.
For each subject task, the survey asks participants to assess
the extent to which individual characteristic apply to that task.
This survey offers respondents five optional responses: Strongly
Agree, Agree, Neutral, Disagree, or Don't Know. The survey of
characteristic applicability was conducted between February
2006 and February 2007.
4.2. Dealing with incomplete data, reliability and validity
In order to determine if the response data associated with a
particular task were adequate to be representative, a minimum
response rate of 70% of all characteristics associated with a task
453L.-R. Yang / Automation in Construction 17 (2008) 450458
8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi
5/9
was established as the criterion for acceptance. If responses
associated with a particular task did not meet the 70% rate
criterion, then they were not used in the analysis. This approach
helped ensure that sufficient knowledge was obtained about the
task.
In the process of determining the survey items, it is crucial to
ensure the validity of their content, which is an important
measure of a survey instrument's accuracy. A content validity
was tested through a theoretical review and interviews with
industry practitioners. Based on previous studies and discus-sions with a number of construction experts, the survey items
were accepted as possessing content validity. The draft version
of the data collection instrument was then sent to several
construction professionals to pre-test for the clarity of questions.
Their insights were incorporated into the final version of the
survey.
Based on the personal interviews conducted prior to the
survey, the targeted respondents were identified as the senior
individuals who were responsible for the project tasks. Potential
respondents to the survey were identified by these practitioners.
The respondents included presidents, vice presidents, design
managers, project managers, project engineers, and projectplanners. A specified mix of expertise, group involvement, and
industry sector participation was targeted in order to acquire a
comprehensive knowledge from different perspectives. The
data were collected from 54 industry professionals through
personal interviews. These professionals averaged 18 years of
experience. Detailed information regarding the respondents is
presented inTable 1.
4.3. Analysis of responses
For any given characteristic, the assessed degree to which a
task relates to that characteristic was established as the
Characteristic Score. In order to perform quantitative analysis,
responses were converted to Characteristic Scores as follows:
Strongly Agree = 4, Agree = 3, Neutral = 2, and Disagree = 1.
The Characteristic Applicability Index was computed as
follows:
CAI X
CS=NR; 2
where CAI is the Characteristic Applicability Index, CS is the
Characteristic Score for a task, and NR is the number of
responses with Strongly Agree, Agree, Neutral, or Disagree.
The mean Characteristic Applicability Index was then
calculated to identify the characteristics with high applicability
to the project satisfaction-leveraging tasks. A Characteristic
Applicability Index score of zero indicates not applicable.A
value of 3.00 or greater indicates highly applicable(an index
value of 3.00 is associated with Agree response). If a
characteristic has high applicability to the project satisfaction-
leveraging tasks, it indicates that this characteristic may explain
project satisfaction-leveraging. The mean Characteristic Appli-cability Index was calculated as follows:
MAI X
CAI=NST; 3
where MAI is the Mean Applicability Index, CAI is the
Characteristic Applicability Index value for a satisfaction-
leveraging task, and NST is the total number of satisfaction-
leveraging tasks assessed.
5. Results and analysis
5.1. Identification of project clusters with the same perceptions
of stakeholder satisfaction
Cluster analysis was used in an exploratory mode to develop
an objective classification of projects. This research was
exploratory; therefore, different sets of clusters consisting of
two, three, four, and five groups were examined. In order to
identify homogeneous projects clusters with the same kinds of
perceptions of stakeholder satisfaction, a K-means cluster
analysis was performed on the basis of the three dimensions
of satisfaction (Owner, A/E, and GC satisfaction). To validate
the results of the cluster analysis, a discriminant analysis was
conducted. The discriminant analysis presented in Table 2
classified 98.9% of the projects as the cluster analysis did,indicating extremely good differentiation and a correct
classification. These results suggest that the two clusters are
distinctive.
Table 1
Information regarding respondents to survey of characteristic applicability
Characteristic Classes N
Title President 06
Title Vice president 05
Title Project manager 09
Title Design manager 08Title Project engineer 19
Title Project planner 07
Expertise Need analysis 09
Expertise Budget estimate 09
Expertise Scheduling 09
Expertise Structure design 09
Expertise Electrical design 09
Expertise Project management 09
Years of experience 510 06
Years of experience 1120 28
Years of experience 2130 20
Group involvement Owner 27
Group involvement A/E 27
Industry sector involvement Building 22
Industry sector involvement Industrial 16Industry sector involvement Infrastructure 16
Table 2
Discriminant analysis
Number/percentage Group Predicted group
membership
Total
1 2
Number 1 70 1 71
2 0 18 18
Percentage 1 98.6 1.4 100.0
2 0.0 100.0 100.0
454 L.-R. Yang / Automation in Construction 17 (2008) 450458
8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi
6/9
The cluster analysis has identified two clusters, with the
cluster mean values of discriminating variables given inTable 3.
In addition, independent-samples t tests were undertaken to
assess the internal validity of the cluster results. The results of
thettests show that statistically significant differences do exist
between the two clusters. The independent-samples t tests
shown in Table 3 confirm that the three variables of Owner
satisfaction, A/E satisfaction, and GC satisfaction do signifi-cantly differentiate across the two clusters. Combining these
results with those of the discriminant analyses, the analysis
ended with a two-cluster solution. The study reveals two project
satisfaction segments, including high project satisfaction cluster
(Cluster 1) and low project satisfaction cluster (Cluster 2). The
levels of project satisfaction by stakeholder type are shown in
Table 3. The analyses indicate that Cluster 1 has, on average,
higher levels of stakeholder satisfaction than Cluster 2 for all
satisfaction metrics analyzed. In most cases, there are only
slight differences in perception of satisfaction among the project
stakeholders. Finally, an independent-samples t test was
conducted to determine whether the data provide evidence for
significant differences in performance outcomes being associ-ated with differences in automation usage for each task. This
discussion is presented in the subsequent section.
5.2. Identification of project satisfaction-leveraging tasks
The tasks with a significant difference in automation usage
between projects with stakeholder satisfaction and dissatisfac-
tion are defined as project satisfaction-leveraging tasks. Table 4
presents the comparisons of task-level automation usage
between projects with stakeholder satisfaction and dissatisfac-
tion. The test results indicate that levels of automation usage for
these tasks may be positively associated with projects' levels ofstakeholder satisfaction.
Table 5shows the levels of automation usage for the project
satisfaction-leveraging tasks. Among the 6 critical tasks,
automation technology levels appear highest for design
structure systems and design electrical systems. Computer
Aided Design (CAD) software is commonly used to create two-
dimensional (2-D) drawings or three-dimensional (3-D) models
in the industry. CAD software can be used to generate precision
drawings or technical illustrations and refine the design at low
cost. Many organizations adopt CAD software in these designtasks. Advancements in design tasks may tend to precede the
other tasks because the limited scope aspect of design should
make related advancements more easily achievable. Also,
information- and data-intensive tasks appear to be more easily
automated than other task types. The lowest levels of automation
utilization are associated with track design progress. Data
management software may be a solution that automates the task.
A data management tool provides a means to monitor and track
design progress. It may also help design teams organize design
data. Track design progressmay lag in technology usage as a
result of inadequate automation devices driven by lack of R&D
investment. In addition, this task lags in automation usage
perhaps due to its frequent communication characteristic forwhich automation systems are difficult to accomplish. Prepare
milestone schedule and develop budget estimate are
associated with the greatest overall variability in level of
automation technology employed. While many scheduling and
cost estimating software systems exist, many of these are either
expensive or complex relative to user skills. Levels of auto-
mation utilization are the most uniform for design electrical
systems. Many organizations are making significant techno-
logical advances in the task.
Preproject planning is the project phase encompassing all the
tasks between project initial to detailed design [31]. Prior
studies have shown the importance of preproject planning onprojects and its influence on project performance [3235].
Table 3
Cluster means of discriminating variables
Variable Projects
with
satisfaction
Projects
with
dis-
satisfaction
t-statistic p-value
N Mean N MeanOwner satisfaction 76 3.67 19 2.21 10.035 0.000
A/E satisfaction 74 3.58 18 2.28 08.113 0.000
GC satisfaction 74 3.55 19 2.21 09.513 0.000
Table 4
t-Test for project satisfaction-leveraging tasks
Task Projects with stakeholder
satisfaction
Projects with stakeholder
dissatisfaction
Mean difference t-statistic Significance
N Mean Standard deviation N Mean Standard deviation
Conduct need analysis for a new facility 45 2.31 1.02 16 1.94 1.12 0.37 1.223 0.056
Develop budget estimate 67 2.45 0.99 18 2.11 1.08 0.34 1.258 0.053
Prepare milestone schedule 67 2.49 1.05 19 2.16 1.07 0.33 1.222 0.056
Design structure systems 58 2.53 0.92 18 2.28 0.89 0.25 1.039 0.076
Design electrical systems 54 2.50 0.86 17 2.29 0.77 0.21 0.878 0.096
Track design progress 60 2.07 0.88 18 1.89 0.90 0.18 0.748 0.098
Table 5
Levels of automation usage for project satisfaction-leveraging tasks
Task N Mean Standard deviation
Conduct need analysis for a new facility 62 2.21 1.01
Develop budget estimate 85 2.38 1.04
Prepare milestone schedule 86 2.42 1.06
Design structure systems 77 2.48 0.91Design electrical systems 72 2.46 0.84
Track design progress 78 2.03 0.88
455L.-R. Yang / Automation in Construction 17 (2008) 450458
8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi
7/9
Previous research indicated that greater project planning efforts
may contribute to project performance in terms of cost,
schedule, and stakeholder success. The project satisfaction-leveraging tasks identified in this study are associated with
preproject planning process, during which success in the
following phases is highly dependent on the level of effort
expended. This may be a reason why employing automation
technology in these leveragingtasks may be associated with
project stakeholder satisfaction.
5.3. Explaining the links between automation utilization and
project stakeholder satisfaction
The preliminary results from this research indicate that a total
of 6 tasks are associated with project satisfaction-leveraging
tasks. These project satisfaction-leveraging tasks are associated
with the FrontEnd and Design phases. In order to identify
characteristics associated with the project satisfaction-leverag-
ing tasks, these critical tasks were analyzed using task charac-
teristics. The data collection effort involved characterization of
these identified tasks. Task characteristics that may explain
project satisfaction-leveraging were identified to further explainthe links between automation utilization and project satisfac-
tion. Characteristic data associated with these tasks were used to
help identify common characteristic trends for project satisfac-
tion-leveraging tasks.
The critical tasks identified include: 1) conduct need analysis
for a new facility, 2) develop budget estimate, 3) prepare
milestone schedule, 4) design structure systems, 5) design
electrical systems, and 6) track design progress. The first three
are associated with the FrontEnd phase and the last three
pertain to the Design phase. Task characteristic analysis of these
critical tasks reveals features common to a specific task group.
Comparing to the Design tasks, the critical tasks associated withthe FrontEnd phase involves uncertainty or probabilistic
information. On the other hand, the critical design tasks require
frequent communication between individuals and, compared to
the FrontEnd tasks, involve more different types of organiza-
tions. Additionally, data accuracy is crucial to successful task
performance for these critical Design tasks.
The complete information of all task characteristics is
provided inTables 6 and 7.Table 6presents high applicability
characteristics for the project satisfaction-leveraging tasks.
Table 7 presents low applicability characteristics for these
tasks. These tables show the overall image of how the selected
characteristics perform. Six characteristics that may explain
Table 6
High applicability characteristics for project satisfaction-leveraging tasks
Category Task characteristics Mean
applicability
index value
Information and data Task involves uncertainty or
probabilistic information
3.60
Information and data Historical data from previous
projects are required for execution
3.11
Information and data Data accuracy is crucial to
successful task performance
3.56
Management Many different types of
organizations are involved
3.17
Management Responsible individual must
communicate frequently with others
3.58
Work procedure Task involves iterations and revisions 3.30
Table 7
Low applicability characteristics for project satisfaction-leveraging tasks
Category Task characteristics Mean applicability index value
Human resource Many individuals are involved to perform task 2.42
Human resource Task involves many individuals with different skills and specialties
Human resource User s, worker's or operator's experience is critical to performance
WF product Performance of many subsequent tasks relies heavily on this task
WF product Task product is physically large and bulky
WF product Errors are difficult to fix or require a large amount of resources to f ix
Time/space/cost Task is a critical path activity in most cases
Time/space/cost Task requires spatial coordination 2.69
Time/space/cost Task involves relatively high uncertainty in cost, schedule, quality, or safety
Time/space/cost Task management operates in close proximity to workers 2.75Time/space/cost Task involves environmental hazard
Time/space/cost Task is costly to execute
Information and data Task relies on industry technical standards 2.52
Information and data Task data are in many different formats 2.44
Information and data Security of related data is very important
Information and data Task involves significant amount of data updating
Management A specialty organization is involved in most cases 2.72
Management Primary performance driver of the task is quality, safety, cost, or schedule 1.75
Management Task involves high probability of change 2.69
Work procedure Task is error prone 2.49
Work procedure Task procedures are driven by regulations
Work procedure Task involves repetit ive activity
Work procedure Some task resources are often idle
Work procedure Task procedures are very complex
Work procedure Task relies on or requires physical output products of many previous task
456 L.-R. Yang / Automation in Construction 17 (2008) 450458
8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi
8/9
leveraging were identified in the analysis. These characteristics
show a strong association with the project satisfaction-
leveraging tasks. Most of the characteristics that may explain
leveraging fall in the following two categories: 1) information
and data and 2) management. This indicates that information/
data-intensive and management-related characteristics may be
associated with project stakeholder satisfaction.Characteristics that may explain project satisfaction-leverag-
ing were identified in order to explore project stakeholder
satisfaction determinants. The analyses suggest that tasks in-
volving iterations, revisions, and many different types of orga-
nizations may deserve the execution with high automation
approaches. Tasks that require frequent communication between
individuals may be associated with project stakeholder satisfac-
tion. In addition, degrees of automation used in executing the
tasks that involve uncertainty or probabilistic information may
be positively related to the stakeholder satisfaction of a project.
The priority for automation implementation may also pertain to
the tasks for which data accuracy is critical to performance andhistorical data from previous projects are required for execution.
One of the low applicability characteristics (Primary
performance driver of the task is cost, schedule, quality, or
safety) was further analyzed to explain the links between
automation utilization and project satisfaction. Regarding
primary performance driver of the satisfaction-leveraging
tasks, the applicability index values for cost, schedule, quality,
and safety are 1.50, 2.25, 2.25, and 1.00 respectively (with a
mean of 1.75). The relatively high levels of applicability are
associated with schedule and quality. The analyses suggest that
primary performance driver of the leveraging tasks may be
more closely associated with schedule and quality than are cost
and safety.
6. Conclusions and recommendations
The lack of information regarding automation benefits along
with uncertain competitive advantage from new technology
have resulted in industry reluctance to implement new
automation technologies. Thus, a study of the relationship
between automation utilization and project stakeholder satis-
faction is necessary. The purpose of this study was to identify
project satisfaction-leveraging tasks and common characteris-
tics associated with these critical tasks. Metrics were developed
to determine automation usage at the task level and perceivedstakeholder satisfaction. The projects are examined by cluster-
ing them on the basis of differences in perceptions of the
proposed satisfaction dimensions. In other words, cluster
analysis was used as a means to group similar properties on
the basis of stakeholder satisfaction. Independent-samples t
tests were undertaken to assess the internal validity of the
cluster results. Combining these results with those of the
discriminant analyses, a two-cluster solution was identified. The
study reveals two project satisfaction segments, including high
project satisfaction cluster and low project satisfaction cluster.
Furthermore, hypothesis testing was performed to identify
relationships between task-level automation utilization and
project satisfaction. For each of the tasks, levels of automation
usage were analyzed to identify project satisfaction-leveraging
tasks. The tasks with a significant difference in automation
usage between projects with stakeholder satisfaction and
dissatisfaction are associated with project satisfaction-leverag-
ing tasks. In other words, the project satisfaction-leveraging
tasks have significant differences in automation usage for
projects with stakeholder satisfaction as opposed to projectswith stakeholder dissatisfaction. These project satisfaction-
leveraging tasks are associated with the FrontEnd and Design
phases. The critical tasks identified in this study include: 1)
conduct need analysis for a new facility, 2) develop budget
estimate, 3) prepare milestone schedule, 4) design structure
systems, 5) design electrical systems, and 6) track design
progress.
This paper also explores the links between project
satisfaction and automation utilization in detail. The technique
used for analyzing the associations is analysis of task
characteristics. The project satisfaction-leveraging tasks were
further analyzed using characteristic analysis to explain thelinks between automation utilization and project success. In
other words, task characteristics were used to better understand
project satisfaction-leveraging tasks through analysis of their
attributes. In summary, task characteristics analyses of project
satisfaction-leveraging tasks are employed as a way to gain
greater understanding of the connection between automation
usage and project satisfaction. The characteristic analysis
reveals attributes common to the project satisfaction-leveraging
tasks. These analyses suggest that data/information-intensive
and management-related task characteristics may be associated
with project stakeholder satisfaction. Degrees of automation
used in executing the tasks that require frequent personnel
communications may be positively related to the stakeholdersatisfaction of a project. Consideration should be also given to
employing higher levels of automation usage for the tasks that
involve many different types of organizations. Furthermore, the
priority for automation implementation may also pertain to the
tasks for which data accuracy is critical to performance and
historical data from previous projects are required for execution.
In addition, tasks that involve iterations, revisions, uncertainty,
or probabilistic information may deserve the high automation
approaches.
The research provides empirical evidence that supports the
expectation of gaining significant benefits with higher levels of
automation implementation. This paper reports on the findingsof empirical research on the adoption of automation technology
at the task level, identifies the benefit of adopting automation
technology, and provides recommendations for the implemen-
tation of automation technology on projects. The results of this
study indicate that automation is critical to assist in the exe-
cution of project tasks and may contribute significantly to
project performance in terms of stakeholder satisfaction.
Findings from this study provide direction for the decision
making of automation investment and are helpful to managers
in deciding whether to apply automation to tasks with certain
characteristics on capital facility projects.
One limitation of the research is that qualitative factors are
excluded from the analysis. The qualitative issues may be
457L.-R. Yang / Automation in Construction 17 (2008) 450458
8/14/2019 Exploring the links between task-level automation usage.pdfAbstract Hybrid assembly systems consist of an automatic assembly section that feeds a manual fi
9/9
significant in helping explain the associations between
automation utilization and project performance. In spite of the
limitation of acquisition of qualitative information, character-
istic applicability analysis is a logical approach for exploring the
links. However, it would be worthwhile to examine the quali-
tative factors in future studies.
Acknowledgments
The author would like to thank the anonymous referees for
their extremely helpful comments on this paper. The work
described in this article was supported by grant from the
National Science Council of Taiwan (93-2211-E-032-024 and
94-2211-E-032-021).
References
[1] CERF, Commercializing infrastructure technologies, CERF Report #97-
5028, Civil Engineering Research Foundation, Reston, VA, 1997.
[2] P. Mitropulos, C.B. Tatum, Process and criteria for technology adoption
decisions, Proceedings of Construction Congress, San Diego, CA, 1995,
pp. 1724.
[3] P. Simmons, Measurement and the evaluation of I.T. investments,
Proceedings of IEEE 2nd International Software Metrics Symposium,
London, England, 1994, pp. 7483.
[4] K. Hampson, C.B. Tatum, Technology strategy and competitive
performance in bridge construction, Journal of Construction Engineering
and Management 123 (2) (1997) 153161.
[5] R.E. Johnson, M.J. Clayton, The impact of information technology in
design and construction: the owner's perspective, Automation in
Construction 8 (1) (1998) 314.
[6] W.E. Back, K.A. Moreau, Cost and schedule impacts of information
management on EPC process, Journal of Management in Engineering 16
(2) (2000) 5970.
[7] S.R. Thomas, C.L. Macken, S.H. Lee, Impacts of Design/Information
Technology on Building and Industrial Projects, BMM2001-10, Construc-
tion Industry Institute (CII), Austin, TX, 2001.
[8] J.T. O'Connor, L. Yang, Project performance vs. use of technologies at the
project- and phase-levels, Journal of Construction Engineering and
Management 130 (3) (2004) 322329.
[9] J.T. O'Connor, M.E. Kumashiro, K.A. Welch, S.P. Hadeed, K.E. Braden,
M.J. Deogaonkar, Project- and Phase-Level Technology use Metrics for
Capital Facility Projects, Report, vol. 16, Center for Construction Industry
Studies, Austin, TX, 2000.
[10] R.M. Webb, J. Smallwood, T.C. Haupt, The potential of 4D CAD as a tool
for construction management, Journal of Construction Research 5 (1)
(2004) 4360.
[11] M. Abduh, M.J. Skibniewski, Electronic networking technologies in
construction, Journal of Construction Research 5 (1) (2004) 1742.
[12] R.Y. Tse, L. Choy, Is IT training in construction industry useful, Journal of
Construction Research 6 (1) (2005) 113.
[13] V. Peansupap, D. Walker, Factors affecting ICT diffusion: a case study of
three large Australian construction contractors, Engineering, Construction
and Architectural Management 12 (1) (2005) 2137.
[14] P.M. Goodrum, M. Gangwar, The relationship between changes in
equipment technology and wages in the US construction industry,
Construction Management and Economics 22 (3) (2004) 291301.
[15] P. Mitropoulos, C. Tatum, Factors driving adoption of new information
technologies, Journal of Construction Engineering and Management 126
(5) (2000) 340348.
[16] K.J. Fergusson, Impact of integration on industrial facility quality, PhD
Thesis, Stanford University, 1993.
[17] W.E. Back, L.C. Bell, Quantifying Benefits of Electronic Technology
Applied to Bulk Materials Management, The Construction Industry Action
Group, Houston, TX, 1994.[18] F.H. Griffis, D.B. Hogan, W. Li, An analysis of the impacts of using three
dimensional computer models in the management of construction,
Research Report 106-11, Construction Industry Institute (CII), Austin,
TX, 1995.
[19] W.E. Back, K.A. Moreau, J. Toon, Determining the impact of information
management on project schedule and cost, Research Report 125-11,
Construction Industry Institute (CII), Austin, TX, 1996.
[20] R.R. Tan, Information technology and perceived competitive advantage:
an empirical study of engineering consulting firms in Taiwan, Construction
Management and Economics 14 (3) (1996) 227240.
[21] J. Whyte, D. Bouchlaghem, T. Thorpe, IT implementation in the
construction organization, Engineering, Construction and Architectural
Management 9 (56) (2002) 371377.
[22] P.M. Goodrum, C.T. Haas, Partial factor productivity and equipment
technology change at activity level in U.S. construction industry, Journal ofConstruction Engineering and Management 128 (6) (2002) 463472.
[23] J.A. De Lapp, D.N. Ford, J.A. Bryant, J. Horlen, Impacts of CAD on
design realization, Engineering, Construction and Architectural Manage-
ment 11 (4) (2004) 284291.
[24] M. Sexton, P. Barrett, The role of technology transfer in innovation within
small construction firms, Engineering, Construction and Architectural
Management 11 (5) (2004) 342348.
[25] S. Lee, S.R. Thomas, R.L. Tucker, The relative impacts of selected
practices on project cost and schedule, Construction Management and
Economics 23 (5) (2005) 545553.
[26] J.D. Stevens, C. Glagola, W.B. Ledbetter, Quality-measurement matrix,
Journal of Management in Engineering 10 (6) (1994) 3035.
[27] K.A. Welch, Development of a tool for assessing the degree of automation
and integration on capital projects, MS Thesis, The University of Texas at
Austin, 1998.[28] M.E. Kumashiro, Measuring automation and integration in the construc-
tion industry, MS Thesis, The University of Texas at Austin, 1999.
[29] J.F. Hair, R.E. Anderson, R.L. Tatham, W.C. Black, Data Analysis with
Readings, 4th ed.Prentice-Hall, Englewood Cliffs, NJ, 1995.
[30] S. Won, A model for work function-based prioritization of technologies for
capital projects, PhD Thesis, The University of Texas at Austin, 2002.
[31] C.S. Cho, G.E. Gibson, Building project scope definition using project
definition rating index, Journal of Architectural Engineering 7 (4) (2001)
115125.
[32] L. Yang, J.T. O'Connor, C. Huang, Comparison of technology utilization
and benefits in Taiwanese and U.S. industries, Journal of Management in
Engineering 23 (3) (2007) 147155.
[33] L. Yang, J.T. O'Connor, J. Chen, Assessment of automation and
integration technology's impact on project stakeholder success, Automa-
tion in Construction 16 (6) (2007) 725733.[34] A.F. Griffith, G.E. Gibson, Alignment during preproject planning, Journal
of Management in Engineering 17 (2) (2001) 6976.
[35] A.F. Griffith, G.E. Gibson, M.R. Hamilton, A.L. Tortora, C.T. Wilson,
Project success index for capital facility construction projects, Journal of
Performance of Constructed Facilities 13 (1) (1999) 3945.
458 L.-R. Yang / Automation in Construction 17 (2008) 450458