Upload
syed-umair-hashmi
View
262
Download
6
Embed Size (px)
Citation preview
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
1/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
2/43
SINOHYDRO GROUP LIMITED
Doha Expressway
Package 6
East Industrial Road Interchanges at Intersection with Street 10 and Street 23
Contract No. C2011/085
DohaState of Qatar Tel: +974-44606109 Fax: +974-44606107 www.sinohydro.com
Submittal Information
1. Document NumberEXW-P006-0000-CD-SHC-MT-00093
2. DescriptionMethod Statement for Waterproofing System (Cross Laminated Self
Adhesive Waterproofing Membrane)
3. Page43
4. RevisionRev.1
5. Reference NumberNil
6. Country of OriginQatar
7. Specification Ref.
QCS 2010, Section 5, Part 14 Clause 14.3Project Specification Section 328. Drawing Ref.
EXW-P006-0000-SR-SHC-DG-00007-003 Rev.3
EXW-P006-0000-SR-SHC-DG-00007-004 Rev.3
EXW-P006-0000-CD-SHC-DG-00022 Rev.1
EXW-P006-0000-CD-SHC-DG-00029-015 Rev.1
EXW-P006-0000-SR-SHC-DG-00035 Rev.2
EXW-P006-0000-SR-SHC-DG-00054 Rev.1
EXW-P006-0000-CD-SHC-DG-00055 Rev.1
EXW-P006-0000-CD-SHC-DG-00157-004 Rev.0
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
3/43
SINOHYDRO GROUP LIMITED
Doha Expressway
Package 6
East Industrial Road Interchanges at Intersection with Street 10 and Street 23
Contract No. C2011/085
DohaState of Qatar Tel: +974-44606109 Fax: +974-44606107 www.sinohydro.com
Index
1. SCOPE
2. REFERENCE DOCUMENTS
2.1 Qatar Construction Specification 2010
2.1.1 Section 5 Part 14 Clause 14.32.1.2 Project Specification Section 32
2.2 Health, Safety and Environmental Plan
2.3 Project Quality Plan
3. DRAWINGS
4. INSPECTION & TESTING
5. RESPONSIBILITY
6. RESOURCES
6.1 Manpower
6.2 Equipment and Tools
6.3 Materials
7. CONSTRUCTION METHODOLOGY
7.1 Work Permits
7.2 Site Planning & Preparation
7.3 Site Preparation
7.4 Self-Adhering Sheet Waterproofing Application of Primer
7.5 Self-Adhering Sheet Waterproofing Installation of Membrane
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
4/43
SINOHYDRO GROUP LIMITED
Doha Expressway
Package 6
East Industrial Road Interchanges at Intersection with Street 10 and Street 23
Contract No. C2011/085
DohaState of Qatar Tel: +974-44606109 Fax: +974-44606107 www.sinohydro.com
7.6 Cleaning and Protection
8. PARTICULAR SAFETY PRECAUTIONS
9. PARTICULAR ENVIRONMENTAL PROTECTION MEASURES
10. HSE PROCEDURES
11. QUALITY CONTOL
12. APPENDICES
12.1 Job Safety Analysis
12.2 Hazard & Risk Assessment
12.3 Technical Data Sheet Copy of POLYPRIME SB
12.4 Technical Data Sheet Copy of BITUSTICK XL
12.5 Technical Data Sheet Copy of BITUBOARD
12.6 Technical Data Sheet Copy of BITUTAPE TS
12.7 Technical Data Sheet Copy of Low Pressure Water Jet Cleaner
12.8 Storage Location
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
5/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 1 of 11
1. SCOPE
This method statement describes the construction methodology and safety measures for
Waterproofing System. The works related to the Construction of Doha Expressway Package 6
- East Industrial Road Interchanges At Intersections with Street 10 and Street 23.
2. REFERENCE DOCUMENTS
2.1 Qatar Construction Specifications 2010
o Section 5 Part 14 Clause 14.3
o Project SpecificationSection 32
2.2 HSE Plan EXW-P006-0000-HS-SHC-PL-00001 Rev 1
2.3 Project Quality Plan EXW-P006-0000-QM-SHC-PL-00003 Rev 1
3. DRAWINGS
- EXW-P006-0000-SR-SHC-DG-00007-003 Rev.3
- EXW-P006-0000-SR-SHC-DG-00007-004 Rev.3
- EXW-P006-0000-CD-SHC-DG-00022 Rev.1
- EXW-P006-0000-CD-SHC-DG-00029-015 Rev.1
- EXW-P006-0000-SR-SHC-DG-00035 Rev.2
- EXW-P006-0000-SR-SHC-DG-00054 Rev.1
- EXW-P006-0000-CD-SHC-DG-00055 Rev.1
- EXW-P006-0000-CD-SHC-DG-00157-004 Rev.0
4. INSPECTION & TESTING
- All material must be approved prior to utilization at site.
- Before commencing the work, the whole site shall be inspected to make sure of any
obstruction to the work.
5. RESPONSIBILITIES
Project Manager is responsible for ensuring that the work is performed in accordance with
the specifications and within the time and cost constraints. Control and monitor overall
project activities, including financial, technical, commercial, logistics, mechanical & electrical,
quality, safety & health and environmental management functions.
Construction Manageris responsible for ensuring that the waterproofing works are carried
out in accordance with the contract drawings/approved shop drawings, project specification,
equipment and workmanship requirements in a safer environment. He is also responsible for
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
6/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 2 of 11
ensuring that Site Engineer / Supervisor and workforce are informed and comply with Project
Quality Plan and HSE Plan requirements for earthworks.
Site Engineeris responsible for the physical execution of waterproofing works in the correct
location and in a safe and efficient manner in accordance with the contract requirements.
They are to ensure that the necessary QA/QC documents are completed in a timely manner.
They are to ensure that the employees for whom they are responsible carry out the work in
accordance with this method statement.
Safety Engineer ensures that all operations are carried out in a safe manner and in
accordance with the minimum requirements set out in HSE Safety Regulations for
Contractors, and the Site Specific Safety Plan. It is the responsibility of the Safety Engineer
to ensure that a Permit to Work covers all operations, and he reports directly to the Project
Manager.
QA/QC Engineer ensures that all materials, testing and procedure are carried out strictly in
accordance with the Contract Documents and Project Quality Plan. He liaises directly with
the Supervision Consultant authorized site representative to arrange and witness inspections
and testing. He reports directly to the Project Manager and he should be reporting to the
corporate Quality Manager.
Site Surveyoris responsible for setting out, monitoring and as built survey data. He is also
responsible for computations, physical work and selection of survey equipment necessary for
the earthworks in the correct locations on the project.
Foremandirectly supervises the work activity on the site and has full control over the use of
the labor, plant and equipment. He ensures that the work is carried out in full compliance
with the specification, and in a manner that conforms to the safety requirements. He reports
to the Site Engineer when the work is complete and ready for inspection.
6. RESOURCES
6.1 Manpower
The estimated manpower is outlined below, which will subject to adjustment according to the
actual requirement during implementations.
Project Manager1
Construction Manager - 1
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
7/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 3 of 11
HSE Engineer2
Site Engineer2
QA/QC Inspector2
Site Surveyor1
Safety Officer2
Site Foreman2
Skilled worker/trained installerTBD
Unskilled worker - TBD
6.2 Equipment and Tools
6.2.1 The following is a list of mechanical equipment to utilize in these operations.
- Electrical Grinder- Assorted Hand Tools
- Measuring tape
- Tower Light
- Cutting knife
- Cotton cleaning cloths
- Scissors
- Press roller & lap rollers
- Paint roller / paint brush
- Face mask
- Hand gloves and safety goggles.
6.3 Materials
6.3.1 All procured materials shall comply with approved material submittals (reference
material submittal). The following material shall be used:
POLYPRIME SBis a quick drying solvent based low viscosity bitumen primer. It is used as
a primer coat onmasonry and concrete substrates to improve the adhesion of bitumen
based membranes and coatings. See Appendix 12.3
BITUSTICK XLis a self-adhesive waterproofing membrane based on a tropical grade of
polymer modifiedbitumen. See Appendix 12.4
BITUBOARD is a multi-layer, asphaltic protection board. It is manufactured by thermallybonding polymer modified bitumen with selected additives which is then sandwiched
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
8/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 4 of 11
between a layer of saturated fibre-glass on one side and anti-polyethylene liner on the other.
See Appendix 12.5
BITUTAPE TSis a 50mm width twin side adhesive tape which comprises of polymerized
bitumen protection protected with a silicon release sheet on either side. See Appendix 12.6
7. CONSTRUCTION METHODOLOGY
7.1 Work Permits
- All necessary Work permits shall be obtained prior to the commencement of any activityon the site, and shall remain valid throughout the entire duration of the operation.
- Hot / Cold Permit to Work
- Confined Space Permit to Work
- Road Closure (if applicable)
- All interfacing activities shall be fully coordinated with Supervision Consultant.
7.2 Site Planning
- All relevant materials, drawings and ITP shall be approved for construction.
- Communication out of hearing distance on site will be via talkie or mobile phone.
- Ensure that sufficient tools, materials and manpower are available before
commencement of any work.
- All appropriate and authorized personnel shall be notified when commencing work.
- Secure work area and set up a perimeter with signs and approved barriers.
- Deliver to site the required quantities of installation material for the day.
- Provide approved and dedicated area for storage and disposal of waste materials.
- Storage location in Appendix 8
7.3 Site Preparation
- Identify access route and storage areas for materials and construction plants.
- Handle and store related materials to prevent deterioration or damage due to moisture,
temperature changes, contaminants, and other causes. Safe and adequate storage to
be prepared at the site to store materials. Protect materials from direct sunlight.
- Store liquid materials in their original packages in a clean, dry, protected location and
within temperature range required by approved waterproofing manufacturer.
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
9/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 5 of 11
- Ensure all equipment is in prime working condition. Plants and equipments shall be
checked on a daily basis and the checklist shall be made available on site.
- Ensure all workers are equipped with approved PPE relevant to the nature of work
being carried out. Provide signages and barricade at work location.
- Once the work area is handed over, place signages and securely barricades the area.
Only authorized personnel related to the work shall be allowed to access the working
area.
- Any specialized signage are required will be advice the Supervision Consultant.
- Permit to work shall be obtained prior to commencing work.
7.4 Self Adhering Sheet Waterproofing Application of Primer
- If any part of the surface is contaminated by oil, grease or fuel, the contamination shall
be removed before other forms of preparation are undertaken.
- Cleaning works, first try water and scrub with soft, non-metallic brush to see if this
removed the surface dirt.
- Low pressure water, a low pressure water cleaning shall be used where dirt has not
been ground into the surface (if required)
- Water jet cleaning equipment shall be used to remove the dirt on concrete surface
instead of cleaning agents.
- Before starting of the application of primer, ensure that all materials and tools are on
hand to allow completion of the work. The surface is dry and dust free.
- Remove grease, oil, bitumen, form-release agents, paints, curing compound, and other
penetrating contaminants or film-forming coatings from concrete.
- Prepare, fill, prime, and treat joints and cracks in substrate. Remove dust and dirt from
joints and cracks according to ASTM D 4258Paint and Related Coating Standards,
(Surface cleaning; used to prepare concrete surfaces for applying coatings intended for
light-duty services). Install sheet strips and center over treated construction and
contraction joints and cracks exceeding a width of 1.6mm.- Thoroughly stir POLYPRIME SB before application.
- Apply primer to cure 1 hour to 2 hours ; depending on weather conditions at the time of
application. On curing, any patches of discoloration should be treated again.
- Only the area that can be covered by membrane in one working day shall be primed.
- Area left exposed for more than 24 hours shall be given a further coat of POLYPRIME
SB.
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
10/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 6 of 11
7.5 Self Adhering Sheet Waterproofing Installation of Membrane
- Remove the release film of the membrane, BITUSTICK XL by peeling back not more
than 30cms at a time.
- Start to unroll the membrane keeping the adhesive side to face down on the primed
surface.
- Press down the membrane, working from the center to the outer edges to expel all trap
air, ensuring good adhesion to the primed substrate that membrane is being applied to.
- Membranes are produced with a selvage to facilitate forming lap joints, while ensuring
continuity of the membrane.
- Once the first roll has been applied to the substrate, place the next roll alongside same
overlapping the selvage, rolling out and aligning properly.
- Roll back the membrane without changing the give orientation. Then peel back the
selvage release strip from the first roll no more than a meter at a time.
- Peel back the release film on the second roll using the same method above.
- Press overlaps firmly down using a light roller.
- End laps should be formed using a minimum end lap of 15cms. Press end laps firmly
down or rolled if possible.
- Provide necessary labor, material, equipments, engineering and other services as
required to perform the work in accordance with the plans and specification.
7.6 Cleaning and Protection
- Do not permit foot or vehicular traffic on unprotected membrane.
- Protect waterproofing from damage and wear during remaining of construction period.
- Cleaning works, first try water and scrub with soft, non-metallic brush to see if this
removed the surface dirt.
- Low pressure water, a low pressure water cleaning shall be used where dirt has not
been ground into the surface (if required)
8. PARTICULAR SAFETY PRECAUTIONS
- All requirements related to safety including work permits are included in the Project
HSE Plan EXW-P006-0000-HS-SHC-PL-00001 Rev. 1
- All key personnel on this section of works are to be experienced in waterproofing works
and shall be inducted into this method statement. Records of attendance at the toolbox
meeting shall be kept and filed on site.
- Work procedures shall be in accordance to this method statement and manufacturers
recommendations while maintaining safety.
- Works procedures shall be in accordance with the HSE risk assessments.
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
11/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 7 of 11
- These shall be presented at toolbox meetings prior to commencement of these works
and then on regular intervals.
- Before commencing any work the safe operation of the related equipment as well as
safe work method shall be explained to all personnel that are involved at a toolbox
meeting by the Supervisor / Safety responsible for that area. Any new employee shall
also be inducted into the operating procedures of that area.
- All plant and equipment are to be inspected and approved as required by the contract
documents.
9. PARTICULAR ENVIRONMENTAL PROTECTION MEASURES
- The environmental protection measures relating to waterproofing works will be as
defined in the Health, Safety and Environmental Plan.
- Other particular environmental protection (Please refer to the material safety data sheet
Appendix 3 to 6).
10. HSE PROCEDURES
10.1 In the event of an emergency, the Supervisor in Charge shall act as the Rescue Team
Leader and the following shall be activated:
10.2 In the event of an accident occurrence:
- Warm / inform all site personnel about the accident.
- Stop all site activities surrounding the incident place.
- First aid may be provided to the victim by trained personnel provided consent given by
victim.
- Do not attempt to move an injured person unless it is absolutely necessary to preventfurther injury.
- Do not allow patient to walk to car or clinic, always have medic / male nurse to patient,
this action may safe life.
- Calmly assure the injured person that assistance / help is on the way.
- If patient has stopped breathing it will be necessary to start CPR, remember S.R.A.B.C
1) S.R.A.B.C
2) SSafety (yours and that of the patient)
3) R Response (shout at the patient, or shake, to ascertain level of
consciousness.
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
12/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 8 of 11
4) AAirway (does the patient have airway of yes fine, if no-open airway)
5) BBreathing (is the patient breathing, if yes fine. If NO, start mouth to mouth
resuscitation)
6) C Circulation does the patients have a pulse (circulation) if yes fine, if NO,
start external Cardiac compression (CPR)
- Assist emergency personnel in locating the victim and investigating the incident.
- Provide reasonable assistance to those in need.
- Refer to the Appendix 3 to 6 for material safety data sheet.
10.3 In the event of fire emergency procedures:
- Warn / inform all site personnel about the fire.
- Evacuate them to assembly point and await further instructions.
- If it is safe to do so, attempt to put out a fire with potable fire extinguisher. Attempt to
extinguish only small fires and make sure there is a clear escape path.
- If fire is extinguished and further action is required, then cleaning work can be carried
out.
- If the fire is out of control, call up the Fire Department at 999.
- Provide the following important details:
1) Location of fire / smoke.
2) Type of fire (if known).
3) When the incident occurred.
4) Name of caller, location of caller and phone number.
- Provide reasonable assistance to those in need.
- Seek medical assistance for all types of burns and injuries.
- Refer to the Appendix 3 to 6 for material safety data sheet.
10.4 In the event of a hazardous material emergency:- All chemical spills on site must be reported immediately.
- A hazardous material emergency exists when:
o Clean-up of a spill of a hazardous material is beyond the level knowledge,
training or ability of the staff in the immediately dangerous to the lives and health
of persons in the area of facility.
- Remove all persons in immediate danger.
- Evacuate them to assembly point and await further instructions.
- Use eyewash or safety showers as needed to wash off spilled chemicals. Flush the
affected area with copious amounts of water at least 15 minutes.
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
13/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 9 of 11
- Provide reasonable assistance to those in need. Seek medical assistance as required.
- Isolate contaminated persons and do not allow them to leave or spread the
contamination.
- Refer to the Appendix 3 to 6 for material safety data sheet.
10.5 Report of Accident / Incident / Occupational Disease
- All accidents, dangerous incidents and occupational disease, however minor, must be
reported at once using Safety accident reporting form.
- The immediate supervisor or supervisors delegate should complete the form and
forward it to Supervision Consultants HSE Department within 24 hours of the incident.
- When a victim is involved, the person completing the form should obtain the victims
signature if possible. When no injuries have been sustained, substitute the name of
victim with the name of the persons most closely involved with the incident.
- If assistance in completing the form is required, consult Supervision Consultant HSE
Department.
- Where serious injuries or property damage are involved care must be taken to leave
everything as it is (unless this creates an unsafe situation by doing so) so that:
o The cause of the accident and the extent of the damage incurred may be
investigated and
o Damaged of defective equipment / machinery can be retained for inspection by
insurance adjustors.
o On being notified that an incident has occurs, the Department head will take
whatever action is necessary to:
1) Remove any hazards still present and assist the person(s) involved to
prevent the incident leading to further injury.
2) Meet personnel in the immediate victim to any dangers, which are still
present.
3) Call for medical assistance.4) Notify the HSE Manager.
5) Arrange to take statements from all witness, including the injured person
if practical.
6) Where necessary arrange for relevant documentation to be collected.
7) Complete the Injury report form in conjunction with the injured persons.
- Preliminary Reporting of Injury
The following incidents shall be reported immediately to the Project Manager and HSE
Manager (regardless of time of accidents):
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
14/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 10 of 11
1) Fatality
2) Injuries to people comprising of:
a) Serious bodying injury including;
Fracture of skull, spine, pelvis, arm, forearm, tight or leg.
Dislocation of shoulder, elbow, hip, knee or spine.
Amputation of any limb, or part of limb.
Loss of sight of an eye.
Should any incident arise which is not clearly defined in document, the HSE
Manager should be contacted for advice.
- He shall inform the emergency controller (Project Manager) of the accident, Project
Managers name is Xian Shijun, and mobile number is 66969753.
- In the absence of the Project Manager, the Construction Manager shall act as the
Emergency Controller.
- The emergency controller shall alert the emergency response team, comprising of first
aiders to attend the accident when required.
- The emergency controller shall alert the firefighting team should there be a fire.
- The rescue team leader shall alert the emergency controller for additional assistance
from other rescue team leaders
- The emergency controller shall arrange for transportation to send the injured person tothe clinic or hospital if required
- The accident area shall be barricaded and nothing shall be removed from the area.
- A watchman shall be engaged to protect the area from unauthorized entry
- The emergency controller shall call for a post mortem meeting after the emergency with
the people involved in the emergency.
- The S&H representative shall organize the safety committee to perform a full accident
investigation. HSE Manager Mr. Fang Xinchang and mobile number is 5388562.
- All information leading to the accident including information, description, photos, time,
location, sources, witness statements, police and medical reports shall be prepared
and submitted by the Project Manager.
Contact Numbers involvedin the Work: Name
Designation Mobile #
Sun Jinhui Project Director 55854510
Xian Shijun Project Manager 66969753
Fang Xinchang HSE Manager 55388562Zhang Hong Construction Manager (Bridge) 66122363
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
15/43
Sinohydro Group Limited Method Statement for Waterproofing SystemDoha Expressway (Package6) (Cross Laminated Self Adhesive Waterproofing Membrane)
EXW-P006-0000-CD-SHC-MT-00093 Rev 1 24 Nov 2012 Page 11 of 11
Tong Jianhua Construction Manager (Roads) 33141887
Yang Chun Sheng Construction Supervisor 33589831
Abas QC Engineer 55059403
Cao Xilai QC Inspector 66492613
Kamal Imad Safety Manager 66879957
Fasasi HSE Engineer 55137219
11. QUALITY CONTROL
- Quality control for the works shall be operated and recorded with Project Quality Plan
EXW-P006-0000-QM-SHC-PL-00003 Rev 1
12. APPENDICES
12.1 Job Safety Analysis
12.2 Hazard & Risk Assessment
12.3 Technical Data Sheet Copy of POLYPRIME SB
12.4 Technical Data Sheet Copy of BITUSTICK XL
12.5 Technical Data Sheet Copy of BITUBOARD
12.6 Technical Data Sheet Copy of BITUTAPE TS
12.7 Technical Data Sheet Copy of Low Pressure Water Jet Cleaner
12.8 Storage Location
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
16/43
APPENDIX 1
Job Safety Analysis
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
17/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
18/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
19/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
20/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
21/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
22/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
23/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
24/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
25/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
26/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
27/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
28/43
APPENDIX 3
Technical Data Sheet Copy of POLYPRIME SB
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
29/43
Solvent ased itumen Primer
P
OLYPRIME
SB is a quick drying solvent based low viscosity bitumen primer. It is used as a primer coat onmasonry and concrete substrates to improve the adhesion of bitumen based membranes and coatings.POLYPRIME
SB is low in viscosity, which allows it to penetrate into the concrete pores and improve the ad-hesion between the membrane and the concrete surface. In addition to that, the primer also acts as abinder for the dust particles which gets accumulated on the concrete surface even after cleaning.
CHARACTERISTICS
Improves the adhesion between bitumen based
sheet membranes and coatings.
Cold applied, does not require heating.
Binder for dust particles.
As a curing compound on freshly cast concrete.
Excellent barrier against chloride and sulphate
ion ingress and carbon dioxide diffusion.
Anti corrosive.
Conforms to the following standards:
ASTM D 41 - Asphalt primer for roofing, damp
proofing and waterproofing
BS 3416, Type A Class C - Bitumen based
coatings for cold application, suitable for use in
contact with potable water.
FIELDS OF APPLICATION
P
OLYPRIME
SB is used as a primer and sealer coatprior to the application of bitumen based water-proofing membranes and coatings. This can alsobe used as a curing compound on freshly cast con-crete.
APPLICATION INSTRUCTIONS
The application temperature should be between4C to 45C. Application procedures may varyslightly depending upon site conditions. The gen-eral recommended guidelines for the applicationof the primer is as follows:
Surface preparation
The surface shall be cleaned thoroughly of allcontaminants like dust, traces of curing compound,oil and grease. All surface imperfections, nail head
protrusions, structurally unsound and friable con-crete shall be removed and repaired with a suit-able POLYCRETE* concrete repair mortar. The surfacemust be dry before priming with POLYPRIME SB.
ApplicationMix the contents of the pail or drum for a few min-utes to remove any sediments. Apply the primer@4-6 m/lt. to a clean smooth and dry surface bybrush, roller or airless spray. Allow the primer to dryprior to the application of the membrane. Forhighly porous surfaces application of a secondcoat is recommended.
COVERAGE
The coverage is 4-6 m/lt./coat. However, the
coverage will depend on the porosity of the sub-strate. In order to ascertain the exact coverage, atrial application is carried out at site.
STORAGE & SHELF LIFE
The pails and drums must be stored in a covered,dry and shaded area, away from direct sunlight,UV and other sources of heat and protected fromextreme temperatures. The shelf life of the productis up to 12 months if stored as per the recom-mendations. Excessive exposure to sunlight and UVwill result in the deterioration of the quality of the
product and reduce its shelf life.
HEALTH & SAFETY
P
OLYPRIME
SB contains volatile solvent with a lowflash point (38C). It should be kept far away fromnaked flame. Avoid inhalation of vapors and en-sure there is adequate ventilation in the work place.Gloves, protective masks and goggles should beworn during application. If swallowed seek medicalattention immediately.
TDS_
Polyprime-SB_
GCC_
1209
1
P
OLYPRIMELYPRIMESBS
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
30/43
2
Apart from the information given here it is also important to observe the relevant guidelines and regulations of various organisations and trade associations as wellas the respective standards. The aforementioned characteristics are based on practical experience and applied testing. Warranted properties and possible uses whichgo beyond those warranted in this information sheet require our written confirmation. All data given was obtained at an ambient and material temperature of+23C and 50 % relative air humidity unless specified otherwise. Please note that under other climatic conditions hardening can be accelerated or delayed.
The information contained herein, particularly recommendations for the handling and use of our products, is based on our professional experience. As materialsand conditions may vary with each intended application, and thus are beyond our sphere of influence, we strongly recommend that in each case sufficient tests areconducted to check the suitability of our products for their intended use. Legal liability cannot be accepted on the basis of the contents of this data sheet or any ver-bal advice given, unless there is a case of wilful misconduct or gross negligence on our part. This technical data sheet supersedes all previous editions relevant tothis product.
Quality for Professionals
Manufactured in G.C.C.
Henkel Polybit Industries Ltd. Henkel Polybit Industries Ltd. Branch)P.O. Box 48539, Sharjah, United Arab Emirates P.O. Box 2230, Al Khobar 31952, K.S.ASales Tel:+971 6 572 2282, Fax:+971 6 572 2289 Tel:+9663 8894110, Fax:+9663 8995313
Factory Tel:+971 6 767 0777, Fax:+971 6 767 1669
Internet: www.henkelpolybit.com E-mail: [email protected]
All values given are subject to 5-10% variation
* Refer to website for TDS
TECHNICAL SPECIFICATION SUPPLY
PROPERTIES VALUES TEST
STANDARDS
Density, [g/cc] 0.85-0.88 ASTM D 1475
Solid content, 40+2 ASTM D 1644[% by wt]
Viscosity @25C, 25-125 ASTM D 88[secs] Saybolt furolviscometer
Tack freetime 4 BS 3900@30C, [hrs]
Distillation, Vol [%] ASTM D 402Up to 225C 35 (min)Up to 360C 65 (max)
Tests on residuefrom distillation:Penetration @25C, 20-50 ASTM D 5[0.1 mm]
Solubility inTrichloroethylene > 99 ASTM D 2042
Water content, 0.5 (max) ASTM D 95Vol [%]
Flexibility No crack BS 3416
Effect on potable Pass BS 6920water
POLYPRIME SB 20 lt pail & 200 lt drum
POLYCRETE 25 kg bag
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
31/43
APPENDIX 4Technical Data Sheet Copy of BITUSTICK XL
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
32/43
TDS_
Bitustick-XL_
GCC_
1209
1
Cross Laminated Self dhesive Waterproofing Membrane
B
ITUSTICK
XL is a self adhesive waterproofing membrane based on a tropical grade of polymer modifiedbitumen. The bitumen compound is laminated onto an impervious, non-perforated, cross laminated HDPEfilm. The membrane is protected on the self adhesive side with a silicone coated release film. BITUSTICKXL conforms to the requirements of BS 8102.
1
2
3
4
5
6
7
8
9
10
11
CHARACTERISTICS
Specially formulated for tropical climate grade.
Provides protection against water and vapor.
Self adhesive. Requires just peeling off the sili-
cone film and sticking to the surface.
Excellent adhesion to vertical and horizontal
surfaces.
Excellent resistance to chlorides, sulphates, al-
kalis and acids.
Good tear and puncture resistance.
Excellent tensile strength.
FIELDS OF APPLICATIONBITUSTICK XL is used as waterproofing and dampproofing membrane intended for concrete protec-tion. It may be used for horizontal and vertical ap-plication for tanking below ground structures, sub-ways and retaining walls.
APPLICATION INSTRUCTIONS
The application temperature should be between4C to 45C. Application procedures may varyslightly depending upon site conditions. The generalrecommended guidelines for the application of theself adhesive waterproofing system is as follows:
Surface preparation
The surface shall be cleaned thoroughly of allcontaminants like dust, traces of curing compound,oil and grease. All surface imperfections, protru-sions, structurally unsound and friable concretemust be removed and repaired with a suitableP
OLYCRETE* concrete repair mortar.
Priming
Apply POLYPRIME SB* (Solvent based primer) @ 4-6 m/lt. as per ASTM D 41 to a clean smooth and
dry surface by brush, roller or spray. Allow theprimer to dry prior to the application of the mem-brane. As the viscosity of the primer is low, it easilypenetrates into the concrete pores which promotesthe adhesion between the membrane and the con-crete surface. In addition to that the primer also acts
as a binder for the dust which gets accumulated on
the concrete surface even after cleaning.Alignment
Start the installation of all membrane plies from thelow point or drains, so that the flow of water is overor parallel to the plies, but never against the laps.All overlaps at the membrane seams shall be in-stalled so as to have "up" slope laps over "down"slope laps. Begin membrane application by un-rolling the roll of BITUSTICK XL membrane and align-ing the side laps.
Application
Peel off the release film from the self adhesive side
and start unrolling the membrane and press it tothe surface. Smoothen the membrane from thecenter to the edges with a wooden press in orderto remove entrapped air. Furthermore, an ironroller shall be used for rolling on top of the appliedmembrane to ensure a proper and strong adhesionof the bitumen compound with the base surface.
For illustration Purpose only
Plain Cement Concrete (PCC)
Pile
POLYPRIME SB
Reinforcement strips
B
ITUSTICK
XL
BITUBOARD
Raft Slab
Basement Wall
BITUMASTIC/
Polyseal PS
Protection Screed
ITUSTICKTUSTICKXLXL
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
33/43
2
Apart from the information given here it is also important to observe the relevant guidelines and regulations of various organisations and trade associations as wellas the respective standards. The aforementioned characteristics are based on practical experience and applied testing. Warranted properties and possible uses whichgo beyond those warranted in this information sheet require our written confirmation. All data given was obtained at an ambient and material temperature of+23C and 50 % relative air humidity unless specified otherwise. Please note that under other climatic conditions hardening can be accelerated or delayed.
The information contained herein, particularly recommendations for the handling and use of our products, is based on our professional experience. As materialsand conditions may vary with each intended application, and thus are beyond our sphere of influence, we strongly recommend that in each case sufficient tests areconducted to check the suitability of our products for their intended use. Legal liability cannot be accepted on the basis of the contents of this data sheet or any ver-bal advice given, unless there is a case of wilful misconduct or gross negligence on our part. This technical data sheet supersedes all previous editions relevant tothis product.
Quality for Professionals
Manufactured in G.C.C.
Henkel Polybit Industries Ltd. Henkel Polybit Industries Ltd. Branch)P.O. Box 48539, Sharjah, United Arab Emirates P.O. Box 2230, Al Khobar 31952, K.S.ASales Tel:+971 6 572 2282, Fax:+971 6 572 2289 Tel:+9663 8894110, Fax:+9663 8995313
Factory Tel:+971 6 767 0777, Fax:+971 6 767 1669
Internet: www.henkelpolybit.com E-mail: [email protected]
TECHNICAL SPECIFICATION
SUPPLY
* Refer to website for TDS
All values given are subject to 5-10% variation
Side overlaps shall be a minimum of 50mm on theselvedge and end overlaps 100mm.
Protection
The membrane shall be protected immediately af-ter application from damage, due to ongoing siteactivities or from sharp aggregates during back-filling by a tough, weather, warp and rot proof as-phaltic protection board (BITUBOARD)*. Alternatively,on horizontal areas the membrane can also beprotected by laying a cement sand screed (50mm).BITUBOARD can be fixed with a double sided adhe-sive bitumen tape (BITUTAPE TS)*.
HANDLING
B
ITUSTICK
XL membranes are packed in loose cor-rugated boxes to avoid any damage during tran-sit or during storage at sites. Care should be takenwhen storing the membranes at sites and shouldnot be kept within close proximity of any sharp orprotruding edges to avoid puncturing or damag-ing the membrane.
STORAGE & SHELF LIFE
B
ITUSTICK
XL membranes must be stored in a shadedarea on wooden pallets neatly covered by a thickfabric and tied securely in a manner that will min-imize exposure to sunlight & UV. The membraneshall be protected from all sources of heat. Theshelf life is 12 months if stored as per recommen-dations. Excessive exposure to sunlight, UV andother sources of heat will result in considerable de-terioration of the product and reduce its shelf life.
DISPOSALB
ITUSTICK
XL is nonhazardous, non-flammableand therefore can be disposed off in any regulardisposal area. BITUSTICK XL should be disposed offonly after wrapping with paper, plastic or cloth asthe bitumen compound has a tendency to softenunder heat and pressure, which would make fur-ther handling very difficult.
HEALTH & SAFETY
B
ITUSTICK
XL contains a tacky bitumen compoundand during application can adhere to human skin.
Bitumen stains can be removed by using aclothdipped ina solvent. In case the affected areais a sensitive one, seek medical assistance imme-diately.
PROPERTIES VALUES TEST
STANDARDS
Thickness, [mm] 1.6 2.1 DIN EN 1849-1
Mass per unit 1.6 2.1 DIN EN 1849-1area, [kg/m]
Top surfacing Cross
laminated -HDPE Film
Softening point >105 ASTM D 36(R&B), [ C ]
Tensile strength, Long 42 ASTM D 882[N/mm2] Trans 48
Elongation (Film), Long 230 ASTM D 882[%] Trans 180
Tear strength (Film), Long 34 ASTM D 1004[N] Trans 31
Adhesion strength, ASTM D 1000
Primed substrate [N/mm] 2.0Self [N/mm] 2.2
Puncture resistance,[N] 220 ASTM E 154
Hydrostatic pressure >50m(5bar) BS EN 12390
Water absorption, [%] 0.14 @24hrs ASTM D 570
Moisture vapor trans 0.06 ASTM E 96mission, [g/m2/24 hrs]
Chemical resistance pH 2.5 -11.5 ASTM D 543
Low temp flexibility, -15C ASTM D 1970
Crack bridging ability, >1.5 mm ASTM C 836
BITUSTICKXL 1.6 mm 1m x 20m, wt 32 kg2.1 mm 1m x 15m, wt 31 kg
POLYPRIME SB 20 lt pail & 200 lt drum
BITUBOARD 3.2 mm 2m x 0.95m, wt 6.65 kg6.0 mm 2m x 1m, wt 7.25 kg
BITUTAPE TS 50mm x10mm, wt 0.6kg
Wooden Press 14mm x 210mm
Iron Roller Head Dia 38mm, wt 1.5kg(recommended Width 100mmspecification) Length 350mm
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
34/43
APPENDIX 5Technical Data Sheet Copy of BITUBOARD
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
35/43
Fibre impregnated asphaltic protection board
B
ITUBOARD is a multi layer, asphaltic protection board. It is manufactured by thermally bonding polymermodified bitumen with selected additives which is then sandwiched between a layer of saturated fibre-glass on one side and anti-stick polyethylene liner on the other.
CHARACTERISTICS
Non bio-degradable
Weather, warp and rot proof
Tough and durable
Excellent resistance to chemicals
Improved puncture resistance
Compatible with most waterproofing systems
FIELDS OF APPLICATION
B
ITUBOARD has been designed for use as a perma-nent protection to most waterproofing and dampproofing systems, especially the bitumen basedsheet membrane and coating systems indicated inBS 8102. BITUBOARD will absorb the impact of ag-gregate shock, normal site foot traffic and protectthe waterproofing membrane from penetration bythe sharp edges of reinforced steel and aggregateduring the backfill process and late settlement.
APPLICATION INSTRUCTIONS
The application of BITUBOARD should be carriedout when the ambient temperature is between 4C
and 45C and should avoided in case of extremeweather conditions such as sand storms, rain, etc.B
ITUBOARD can be fixed on top of the waterproofingmembrane by using a double sided adhesive tape(BITUTAPE TS)* or even by torching (for fixing overtorch applied membranes). Once the protectionboard is fixed in place, supports/props have to beused to keep the boards in place till the adhesiveis strong enough to hold the board. Subsequentboards shall be laid continuously by butt fitting theedges. For irregular profiles, the board shall be cutto fit all intersections and protrusions.The butt jointscan be sealed with 50mm HDPE bitumen adhesivestrip to prevent any backfill material entering andcausing damage to the underlying waterproofingmembrane.
HANDLING
B
ITUBOARD is shrink-wrapped and loaded on palletsfor easy handling. The pallets should be loaded or
offloaded with the help of a crane or forklift to pre-vent damage to the protection boards. If theboards are unloaded individually, it is to be en-sured that they are stacked back on a pallet or ona flat surface.
STORAGE & SHELF LIFE
B
ITUBOARD should be covered and stored in a dryand shaded area away from sunlight, UV andsources of heat. Do not stack one pallet on top ofthe other. It is recommended not to open the shrinkwrap till the time of application. The boards, looseor on pallets, must be stored on flat surface. Theshelf life is 24 months when stored as per the rec-
BITUBO RD
B
ITUSTICK
XL
Primer For illustration Purpose only
TDS_
Bituboard_
GCC_
0910
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
36/43
Apart from the information given here it is also important to observe the relevant guidelines and regulations of various organisations and trade associations as wellas the respective standards. The aforementioned characteristics are based on practical experience and applied testing. Warranted properties and possible uses whichgo beyond those warranted in this information sheet require our written confirmation. All data given was obtained at an ambient and material temperature of+23C and 50 % relative air humidity unless specified otherwise. Please note that under other climatic conditions hardening can be accelerated or delayed.
The information contained herein, particularly recommendations for the handling and use of our products, is based on our professional experience. As materialsand conditions may vary with each intended application, and thus are beyond our sphere of influence, we strongly recommend that in each case sufficient tests areconducted to check the suitability of our products for their intended use. Legal liability cannot be accepted on the basis of the contents of this data sheet or any ver-bal advice given, unless there is a case of wilful misconduct or gross negligence on our part. This technical data sheet supersedes all previous editions relevant tothis product.
Quality for Professionals
Manufactured in G.C.C.
Henkel Polybit Industries Ltd. Henkel Polybit Industries Ltd. Branch)P.O. Box 48539, Sharjah, United Arab Emirates P.O. Box 2230, Al Khobar 31952, K.S.ASales Tel:+971 6 572 2282, Fax:+971 6 572 2289 Tel:+9663 8894110, Fax:+9663 8995313
Factory Tel:+971 6 767 0777, Fax:+971 6 767 1669
Internet: www.henkelpolybit.com E-mail: [email protected]
2
ommendations. Excessive exposure to sunlight andUV will result in the deterioration of the quality ofthe product and reduce its shelf life.
HEALTH & SAFETY
B
ITUBOARD might leave bitumen stains on the skinand hands during application. The stains can beremoved by using a suitable cleaner. Care should
be taken when using tools to cut the boards.
TECHNICAL SPECIFICATION
SUPPLY
PROPERTIES VALUES TEST STANDARDS
Thickness, [mm] 3.2 3.5 4.0 6.0 DIN EN 1849-1
Density, [g/cc] 1.1-1.2
Mass per unit area 3.5-3.7 3.8-4.0 4.4-4.6 6.2-6.4 DIN EN 1849-1[kg/m2]
Softening point (R&B), > 105 > 105 > 105 > 125 ASTM D 36/DIN EN 1427[C]
Penetration, [0.1mm] 5-15 ASTM D 5/DIN EN 1426
Asphalt content, [%] > 65 ASTM D 545
Chisel puncture Pass In house test method
Resistance to static load L10 DIN EN 12730
Heat resistance @80C No Flow DIN EN 52 123
Hydrostatic pressure No leakage BS EN 12390 (Part 8)@5 bar (50 m)
Chemical resistance [pH] 2.5-11.5 ASTM D 543
All values given are subject to 5-10% tolerance
BITUBOARD 3.2 mm 2m x 0.95m, wt 6.65 kg#
3.5 mm 2m x 0.95m, wt 7.25 kg#
4.0 mm 2m x 0.95m, wt 8.50 kg#
6.0 mm 2m x 1m, wt 12.5 kg#
BITUTAPE TS 50mm x 10m, wt 0.60kg#
*Refer to website for TDS#
Approximate weight
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
37/43
APPENDIX 6Technical Data Sheet Copy of BITUTAPE TS
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
38/43
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
39/43
APPENDIX 7Technical Data Sheet Copy of Low Pressure Water
Jet Cleaner
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
40/43
Low Pressure Water Jet Cleaner
Specifications
Meier eletric low pressure washer/cleanerTypes of move: Wheel drag-styleInjection pressure: 150Mpa
Range: 10 m
Meier eletric low pressure washer/cleaner is your assistant for cleaning and watering.For plane/car/motorcycle/bike ect cleaningFor housework cleaning:such as cleaning window,floor,road/street and so on.For watering garden:such as watering tree,flower,vegetable and so on.
Model:HB6/15C
Types of move: Wheel drag-style
Temperature of water:cold water
Injection pressure: 150Mpa
Range: 10 mI,Overview:Vertical Compact cold water low pressure cleaner, external cleaning agents, theframework by the integration of high-strength plastic, small compact design.
2, The standard spare parts:1) high-pressure pipe :10 m2) 850 mm stainless steel rod gun3)Low pressure grips with the barrel4)Pressure control switch5)0 / liquid absorption / conversion of 40 degrees with three-hole nozzle
6)Anti-winding design of high-pressure pipe3, the technical parameters:
1)Power supply: Single-phase power/230 Volt, 50 Hz2)Water flow rate (can be adjusted): 230 ~ 560 l / h3)Pressure (can be adjusted):150/15 bar / MPa4)Maximum temperature of water: 60 degrees Celsius5)Supporting the load :3.1 kw6)Net Weight:30.5 kg
7)Size (L x W x H):375 x 360 x 925 mm
4, the product features and applications:
1)Vertical design, compact size, light weight
2)Widely used in hotels, professional cleaning company ect.3)Big wheel design, move easily
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
41/43
Low Pressure Water Jet Cleaner
Specifications
Meier electric low pressure washer/cleanerTypes of move: Wheel drag-styleInjection pressure: 150Mpa
Range: 10m
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
42/43
APPENDIX 8Storage Location
8/10/2019 EXW-P006-0000-CD-SHC-MT-00093 Method Statement for Waterproofing System Rev 1
43/43