38
Fabric & Finishes Gordon Farquharson July 2017

Fabric & Finishes

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Fabric & Finishes

Gordon Farquharson

July 2017

Slide 2 © PharmOut 2017

Every Cleanroom is a “Prototype” !!

• Process & Product has unique features

• The building and its environment are unique

• The equipment configuration is unique

• The project team is unique

BUT

All cleanrooms use common components and techniques

Slide 3 © PharmOut 2017

Cleanrooms are very different!

Cleanroom technology

applied to API manufacture

Slide 4 © PharmOut 2017

Cleanrooms are very different !

Formulation equipment

Slide 5 © PharmOut 2017

Role of the Cleanroom 1

1. Exclusion of the external environment.

2. To create the class of cleanliness required for the process by dilution or displacement of the contamination generated.

• To maintain ISO cleanliness Classes (1-9), or GMP Grades (A-D).

3. Containment of hazards arising from the process.

4. Control of Process-to-Process cross-contamination. A Pharma GMP issue.

5. Control and management of Personnel flow and procedures by way of planning and layout of the suite.

Way IN ==> Way Out.

Slide 6 © PharmOut 2017

Role of the Cleanroom 2

Role Control and management of Material flow by way of planning and layout of the suite.

To create optimum conditions for the process, including special requirements such as Low %RH; special illumination conditions; etc.

To accommodate the process equipment in a safe and effective way.

To allow effective monitoring of the controlled environment created in the cleanroom suite.

Slide 7 © PharmOut 2017

Configuration of clean rooms

Slide 8 © PharmOut 2017

Design layout

The expectation however, is quite clear. The layout and planning should ensure the following:

1. Effective segregation between the external environment and the classified space.

2. Well managed materials and personnel flow.

3. Segregation spaces of different grade or class.

Planning and layout requirements are not defined in GMPs.

Slide 9 © PharmOut 2017

Don’t underestimate the impact of the process equipment

Slide 10 © PharmOut 2017

vacuum

heatingcooling

CIP/SIP

classified area

uncontrolled area

uncontrolled area

The potential of closed process equipment

Slide 11 © PharmOut 2017

Designing for adaptability

Loose fit - enables changes with minimum disruption

Consider modular design

Clean construction protocol ISO 14644-4

External access for maintenance

Service chases

Slide 12 © PharmOut 2017

Loose Fit Design Concepts Service Zone Concept Plan

Process

Area“B”

Unclassified Technical Support Area

Process Corridor “B”

Slide 13 © PharmOut 2017

Loose Fit Design Concepts Service Chase Concept Plan - Microelectronics

Unclassified Technical Support Area

Process

Area“B”

Process Corridor “B”

Slide 14 © PharmOut 2017

Corridors and working spaces

Slide 15 © PharmOut 2017

Remember maintenance of technical systems

Slide 16 © PharmOut 2017

Some images from MRC Systems & Clestra

Construction of clean rooms

Slide 17 © PharmOut 2017

Basic construction methods

Finish options:

• Sheet PVC

• Sprayed elastomeric paint

• Epoxy paint

Masonry + gypsum applied plaster +

applied finish

Finish options:

• Sheet PVC

• Sprayed elastomeric paint

• Epoxy paint

Gypsum or calcium silicate board +

closing of joints + applied finish

• Mild steel painted

• Stainless steel

• GRP – Glass reinforced polyester

• Phenolic sheet

Options

GMP doesn’t mandate any specific approach.

1. “Stick-built”. In-situ construction

2. Pre-fabricated, pre-finished cleanroom wall & ceiling systems

Slide 18 © PharmOut 2017

Choosing the preferred option

• Shouldn’t always be at the top of the list.

• Remember you should be considering >20 years life.

Cost

• Materials

• Labour to install

• Technical support

Local sourcing

• Clean/dirty - Dry/wet

Construction environment

• Have to make decisions early for pre-fabricated

• Have longer to cogitate for stick-built

Project lead times and decision making

• Is the systems compatible with development and evolution of the business operations?

Modification and relocation requirements

• In house / Local resources

• Vendor dependent

Repair

Slide 19 © PharmOut 2017

Other attributes of the construction system

Ceiling:• Suspended• Bridging on walls• Walk-on

Low level return air ducts:• In wall construction• Double wall required• Plant on surface

Services in walls:• In wall thickness• In a service pod on wall• In a service chase

Slide 20 © PharmOut 2017

Masonry System

Slide 21 © PharmOut 2017

• Masonry walls

• Concrete ceiling

• Hard plaster (gypsum)

• Door frames set into

the wall structure

• Applied epoxy paint to

walls

• Thin epoxy floor finish

Slide 22 © PharmOut 2017

Gypsum Board and Frame System

• Metal frame

• Calcium silicate or Gypsum board attached

• Joints taped

• Finish applied – this case a glass reinforced polyester resin.

Slide 23 © PharmOut 2017

GRP Cleanroom System

Slide 24 © PharmOut 2017

Slide 25 © PharmOut 2017

Typical metal panel system

Slide 26 © PharmOut 2017

Floor channels...

Slide 27 © PharmOut 2017

Ceiling channels...

Slide 28 © PharmOut 2017

Single or double glazing…

Slide 29 © PharmOut 2017

Doors Swing Slide Powered…

Slide 30 © PharmOut 2017

Door attributes

1. Swing doors should close with air pressure.

2. Often need to work with electromechanical interlock systems

3. Doors should be self closing (soft close to avoid pressure shocks).

4. Hygienic design. Avoid cavities and ledges.

5. Powered doors

• Becoming more common

• Ensures optimum open/close rate

• Can help avoid hand contact

6. Sliding doors

• OK

• Ensure cleanroom style

• Avoid floor tracks

• Ensure top track cleanable

Slide 31 © PharmOut 2017

FLUSH with the panel

Integration of process and services…

Slide 32 © PharmOut 2017

Walk-on ceiling…

Slide 33 © PharmOut 2017

Cleanroom flooring (1)

• PVC sheet (lowest cost)

– Adhered to floor.

– Seams welded

– Cove former to walls

• Tacky mats

– Permanent

– Peel-off

Sheet materials adhered to floor:

Slide 34 © PharmOut 2017

Cleanroom flooring (2)

1. Epoxy (thin self levelling)

• Available in ESD/static dissipative and conductive versions.

2. Polyurethane (thin self levelling)

• Some uses the natural power of silver to fight bacteria, and

• Available in ESD/static dissipative and conductive versions.

3. Epoxy terrazzo (thick)

• recycled granular material.

4. Tiles

• Ceramic (chemical plants)

• Epoxy

• Terrazzo

Applied screeds

Slide 35 © PharmOut 2017

Cleanroom flooring (3)

1. Classified cleanrooms

• Surface swabbing with mops and controlled disinfectant materials.

• Routine hygiene and cleanliness monitoring

2. Non-sterile manufacturing

• Machine cleaning preferred

• Periodic housekeeping controls.

Cleaning

Slide 36 © PharmOut 2017

Equipment integration

Slide 37 © PharmOut 2017

Equipment integration

Slide 38 © PharmOut 2017

Thank you for your time.Questions?

Gordon Farquharson

[email protected]

www.pharmout.net

Executive Consultant