1
Introduction Tung Chung East reclamation project pioneers the Deep Cement Mixing (DCM) technique to an Excavation and Lateral Support system. This novel approach in Hong Kong has successfully fast-tracked the construction of a box culvert with substantial savings in time and cost, provided a safer working environment and reduced the nuisance to the public. The DCM side walls act as a gravity retaining structure without struts. The design principle is based on well-established theories. The application of DCM in the context of retaining system is extended to resist lateral earth loading, which is a pioneer in Hong Kong. Using DCM as retaining walls to facilitate box culvert construction brings remarkable benefits to the project as a whole. STAGE 1: Installation of DCM STAGE 2: Excavation STAGE 3: Construction of Box Culvert STAGE 4: Backfilling with Construction and Demolition material Environmentally Friendly Less steelwork wastage Less vibration and noise Project Benefits 3-month savings in time 20% savings in cost Safety Safer working environment Simpler construction sequence Less high risk operations Outside the box innovation FORMATION LEVEL SIDE WALL-DCM ORIGINAL SEABED LEVEL (VARIES) PUBLIC FILL SAND BLANKET TRANSFER SLAB DCM FORMATION LEVEL SIDE WALL-DCM TOP LEVEL SIDE WALL-DCM TOELEVEL SIDE WALL-DCM ORIGINAL SEABED LEVEL (VARIES) PUBLIC FILL SAND BLANKET TRANSFER SLAB DCM FORMATION LEVEL SIDE WALL-DCM TOP LEVEL SIDE WALL-DCM TOELEVEL SIDE WALL-DCM ORIGINAL SEABED LEVEL (VARIES) PUBLIC FILL SAND BLANKET TRANSFER SLAB DCM BOX CULVERT FORMATION LEVEL SIDE WALL-DCM TOP LEVEL SIDE WALL-DCM TOE LEVEL SIDE WALL-DCM ORIGINAL SEABED LEVEL (VARIES) PUBLIC FILL SAND BLANKET TRANSFER SLAB DCM BOX CULVERT

facilitate box culvert construction brings remarkable

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: facilitate box culvert construction brings remarkable

IntroductionTung Chung East reclamation project pioneers the Deep Cement Mixing (DCM) technique to an Excavation and Lateral Support system. This novel approach in Hong Kong has successfully fast-tracked the construction of a box culvert with substantial savings in time and cost, provided a safer working environment and reduced the nuisance to the public.

The DCM side walls act as a gravity retaining structure without struts. The design principle is based on well-established theories.

The application of DCM in the context of retaining system is extended to resist lateral earth loading, which is a pioneer in Hong Kong.

Using DCM as retaining walls to facilitate box culvert construction brings remarkable benefits to the project as a whole.

STAGE 1: Installation of DCM

STAGE 2: Excavation

STAGE 3: Construction of Box Culvert

STAGE 4: Backfilling with Construction and Demolition material

Environmentally Friendly • Less steelwork wastage• Less vibration and noise

Project Benefits• 3-month savings in time• 20% savings in cost

Safety• Safer working environment• Simpler construction sequence• Less high risk operations

Outside the box innovation FORMATION LEVEL

SIDE WALL-DCM

ORIGINAL SEABED LEVEL (VARIES)

PUBLIC FILL

SAND BLANKET

TRANSFER SLAB DCM

FORMATION LEVEL

SIDE WALL-DCM TOP LEVEL

SIDE WALL-DCM TOE LEVEL

SIDE WALL-DCM

ORIGINAL SEABED LEVEL (VARIES)

PUBLIC FILL

SAND BLANKET

TRANSFER SLAB DCM

FORMATION LEVEL

SIDE WALL-DCM TOP LEVEL

SIDE WALL-DCM TOE LEVEL

SIDE WALL-DCM

ORIGINAL SEABED LEVEL (VARIES)

PUBLIC FILL

SAND BLANKET

TRANSFER SLAB DCM

BOX CULVERT

FORMATION LEVEL

SIDE WALL-DCM TOP LEVEL

SIDE WALL-DCM TOE LEVEL

SIDE WALL-DCM

ORIGINAL SEABED LEVEL (VARIES)

PUBLIC FILL

SAND BLANKET

TRANSFER SLAB DCM

BOX CULVERT