Facilities Construction NORTHSIDE INDEPENDENT SCHOOL DISTRICT Leroy San Miguel ASST. SUPERINTENDENT FOR FACILITIES & OPERATIONS Henry Acosta EXECUTIVE DIRECTOR OF CONSTRUCTION & ENGINEERING Jim Berg AIA DIRECTOR OF FACILITIES CONSTRUCTION September 2018 1

Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 2: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

NEW SCHOOLS

2

Page 3: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

DR. LINDA G. MORA ELEMENTARY SCHOOL

Front Rendering

Architect – Noonan Rittimann Architects, LLC Project Architect – John Rittimann

NISD Project Manager – Chris Parker

Contract Amount - $22,465,000 Construction Period – March 2017 – August 2018 Construction Status – 100% Project Scope – New 800 Student Elementary School

(Prototype of Boldt ES and Cole ES)

Contractor – DL Bandy Constructors, Inc.

3

Page 4: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

DR. LINDA G. MORA ELEMENTARY SCHOOL

4

Page 5: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

DR. LINDA G. MORA ELEMENTARY SCHOOL

Front Entrance

Story Telling Mural Library Area

5

Page 6: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

DR. LINDA G. MORA ELEMENTARY SCHOOL

Front Entry

Serving Line Cafeteria Area

6

Page 7: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

ADDITIONS AND RENOVATION

PROJECTS IN CONSTRUCTION

7

Page 8: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

NORTHSIDE ACTIVITY CENTER RENOVATIONS

Architect – Richard Sanchez Architects, Inc. Project Architect – Richard Sanchez NISD Project Manager – Thomas Curiel Contractor – O’Haver Contractors Co. Contract Amount - $5,319,485 Construction Period – February 2017 – August 2018 Construction Status – 100% Project Scope – Addition of the New Building is complete and in use.

New Addition Main Entrance

8

Page 9: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

NORTHSIDE ACTIVITY CENTER RENOVATIONS

NAC Renovated Meeting Room

NAC Addition Corridor

NAC New Meeting Room 9

Page 10: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

JOHN GLENN ELEMENTARY School Building Replacements / Security Lobby

Architect – LPA, Inc. Project Architect – Mark Oppelt / Lowell Tacker NISD Project Manager – Thomas Curiel Contractor – Suburban Construction Contract Amount - $7,034,840 Construction Period – June 2017 – August 2018 Construction Status – 100% Project Scope – Replacement of Administration/Classroom Building

Building is in Final Punch.

Rendering of Building Replacement 10

Page 11: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

JOHN GLENN ELEMENTARY School Building Replacements / Security Lobby

Front Entrance Front Entrance

11

Page 12: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

JOHN GLENN ELEMENTARY School Building Replacements / Security Lobby

Lobby Entrance Front Entrance

12

Page 13: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Thomas Curiel Contractor – Bartlett Cocke Contract Amount - $32,014,460 Construction Period – June 2017 – December 2018 Construction Status – 74% Package 2 (Building) Project Scope – Fine Arts Building Replacement

Outdoor stairs and canopies underway. Flooring on lower level ongoing. Face brick area A West, Tile & Ceiling grid in B/A West cloud framing and sheetrock in Auditorium. Mezzanine piping, ductwork, roofing on flyloft, gutters and sheet metal.

Rendering of New Auditorium 13

Page 14: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM

14

Page 15: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM

Exterior Construction

Exterior Construction

15

Page 16: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

OLIVER WENDELL HOLMES HS - FINE ARTS NEW AUDITORIUM

Interior Construction

Exterior Construction

16

Page 17: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

MURRAY E. BOONE ELEMENTARY SCHOOL

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – James Evans Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018 Construction Status – 95% Project Scope – New Administration Area, New Bus/Student Walkway Canopy,

Landscaping in progress.

Rendering of New Administration Entrance 17

Page 18: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

Exterior Construction

Exterior Construction Bike Rack near Entry

MURRAY E. BOONE ELEMENTARY SCHOOL

Student Canopy

18

Page 19: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

DOLORES B. LINTON ELEMENTARY SCHOOL Additional Student Canopy

Architect – Munoz & Company Architects Project Architect – Randy Hohlaus NISD Project Manager – Chris Parker Contractor – Pronto Sandblasting Contract Amount - $375,900 Tentative Construction Period – March 2018 – August 2018 Construction Status – 100% Project Scope – Additional Student Canopy

19

Page 20: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

DOLORES B. LINTON ELEMENTARY SCHOOL Additional Student Canopy

Rendering of Additional Student Canopy

20

Page 21: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

DOLORES B. LINTON ELEMENTARY SCHOOL Additional Student Canopy

Student Canopy Student Canopy

Student Canopy

21

Page 22: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

SAM RAYBURN MIDDLE SCHOOL Building Replacement

Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – James Evans Contractor – Turner Construction Contract Budget - $12,500,000 GMP Amount – Phase I - $3,051,018 GMP Amount - Phase II

Tentative Construction Period - June 2018 - August 2019 Construction Status - 25%

Site utilities in progress.ALE - Building renovation in progress, demolition is complete. Phase I in progress - Foundation Piers site Phase II in progress - Structural frame

Project Scope - Building Replacement (D & F)

GMP Amount - Phase III - Currently being Bid

22

Page 23: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

SAM RAYBURN MIDDLE SCHOOL Building Replacement

Existing Campus Aerial View

23

Page 24: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

SAM RAYBURN MIDDLE SCHOOL Building Replacement

Canopy between Building “F” & "A" Excavation - Foundation

Building “J” - ALE

24

Page 25: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

SAM RAYBURN MIDDLE SCHOOL Building Replacement

New Library Location

New Gym and Boys Lockers LocationBand Hall Addition Former Location of Gym, Boys Locker Room and Band Hall

25

Page 26: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy

Architect – Chesney Morales Partners, Inc. Project Architect – Richard Morales NISD Project Manager – James Evans Contractor – Breda Construction, Inc. Contract Amount - $468,095 Construction Period – June 2018 – October 2018 Construction Status – 65% Project Scope – Additional Student Canopy

Foundation work and site utilities in progress.Weather delays ongoing.

26

Page 27: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy

27

Page 28: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

F.R. SCOBEE ELEMENTARY SCHOOL Additional Student Canopy

Existing Canopy

Excavation - Sidewalk

Entrance

28

Page 29: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

MARY HULL ELEMENTARY SCHOOL Bus Canopy Renovation

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Thomas Curiel Contractor – Henock Construction Contract Amount - $400,000 Construction Period – June 2018 – September 2018 Construction Status – 99% Project Scope – Bus Canopy Renovation

Canopy roof completion in progress.

Front Entrance 29

Page 30: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

MARY HULL ELEMENTARY SCHOOL Bus Canopy Renovation

Proposed Bus Canopy

30

Page 31: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

MARY HULL ELEMENTARY SCHOOL Bus Canopy Renovation

Canopy Structure

Canopy Structure

31

Page 32: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

BRAUN STATION ELEMENTARY Cafeteria/Kitchen Renovations & Window Upgrades

Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Thomas Curiel Contractor – WR Griggs Construction Co. Contract Amount - $2,671,000 Construction Period – June 2018 – December 2018 Construction Status – 60% Project Scope – Cafeteria/Kitchen Renovations and Window Upgrades

Concrete, caulking windows, electrical rough-ins, HVAC ductwork at Kitchen in progress. Temporary serving lines are complete.

Braun Station ES Braun Station ES 32

Page 33: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

BRAUN STATION ELEMENTARY Cafeteria/Kitchen Renovations & Window Upgrades

Cafeteria Interior Restroom Upgrade Kitchen Interior

33

Page 34: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

BRAUN STATION ELEMENTARY Cafeteria/Kitchen Renovations & Window Upgrades

Cafeteria Interior Temporary Serving Lines

34

Page 35: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

CHRISTIAN EVERS ES & JOHN JAY HIGH SCHOOL Flooring Project

Architect – CWS Architects Project Architect – Robert Watts NISD Project Manager – Chris Parker Contractor – San Antonio Floor Finishers, Inc. Contract Amount - $178,645 Construction Period – June 2018 – August 2018 Construction Status – 100% Project Scope – VCT and Carpet Flooring Replacement

35

Page 36: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

CHRISTIAN EVERS ES & JOHN JAY HIGH SCHOOL Flooring Project

Evers Elementary John Jay High School John Jay High School

36

Page 37: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

JOHN MARSHALL HIGH SCHOOL Courtyard Renovations

Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – RCO Construction Contract Amount - $336,525 Construction Period – June 2018 – August 2018 Construction Status – 100% Project Scope – Courtyard Renovations

37

Page 38: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

JOHN MARSHALL HIGH SCHOOL Courtyard Renovations

Exterior Courtyard

Exterior Courtyard 38

Page 39: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation

Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – CGC General Contractors, Inc. Contract Amount - $4,249,000 Construction Period – June 2018 – August 2019 Construction Status – 25% Project Scope – Cafeteria / Kitchen Renovation

Temporary serving lines are complete. Kitchen renovation work in progress.

39

Page 40: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen / Courtyard Renovations

Aerial of Site

NEW KITCHEN ADDITION

RENOVATED

CAFETERIA

40

Page 41: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

Kitchen Demolition

JOHN MARSHALL HIGH SCHOOL Cafeteria / Kitchen Renovation

Cafeteria Work Kitchen Demolition

41

Page 42: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

E. M. PEASE MIDDLE SCHOOL Fine Arts & Canopy Addition

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Thomas Curiel Contractor – Webber Commercial Construction Co. Contract Amount - $2,784,000 Construction Period – June 2018 – December 2018 Construction Status – 29% Project Scope – Fine Arts Addition, Bus Canopy & Drainage Upgrades

Canopy foundations complete.Fine Arts Classrooms renovation and addition in progress.

42

Page 43: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades

Aerial Vi ew of Campus 43

Page 44: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades

Existing Front Entrance and Fine Arts Classrooms

Rendering of Band Room Addition at Fine Arts Classrooms

44

Page 45: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

E.M. PEASE MIDDLE SCHOOL Fine Arts Addition, Drainage Improvement & Canopy Upgrades

Fine Arts Addition

Fine Arts Addition

Fine Arts Addition

Fine Arts Addition

45

Page 46: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

TOM C. CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation

Architect – Garza Architects Project Architect – Jesse Garza NISD Project Manager – Chris Parker Contractor – Central Builders, Inc. Contract Amount - $3,892,000 Construction Period – June 2018 – February 2019 Construction Status – 40% Project Scope – Cafeteria / Kitchen Renovation

Kitchen renovation framing/MEP rough-in in progress.Temporary serving lines are complete.

Renovated Cafeteria 46

Page 47: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

TOM C. CLARK HIGH SCHOOL Cafeteria / Kitchen Renovation

Existing Exterior of Cafeteria

Exterior of Cafeteria Addition

47

Page 48: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

HELOTES ELEMENTARY & POWELL ELEMENTARY Window Upgrades / ADA Work

Architect – Shawn Kaarlsen & Associates Project Architect – Shawn Kaarlsen NISD Project Manager – James Evans Contractor – Central Builders Contract Amount - $2,977,000 Construction Period – June 2018 – September 2018 Construction Status – 100% Project Scope – Window Upgrades, ADA Work

48

Page 49: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

HELOTES ELEMENTARY & POWELL ELEMENTARY Window Upgrades / ADA Work

POWELL ELEMENTARY SCHOOL 49

e006572
Rectangle
e006572
Rectangle
e006288
Rectangle
e006288
Rectangle
Page 50: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

HELOTES ELEMENTARY & POWELL ELEMENTARY Window Upgrades / ADA Work

HELOTES ELEMENTARY SCHOOL

50

Page 51: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

HELOTES ELEMENTARY & POWELL ELEMENTARY Window Upgrades / ADA Work

Helotes ES - Classroom Window Before Helotes ES - Classroom Window After

Powell ES - Window Upgrades After 51

e006572
Rectangle
Page 52: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation

Architect – Pfluger Architects Project Architect – Carr Hornbuckle NISD Project Manager – Chris Parker Contractor – WR Griggs Construction Contract Amount - $6,141,000 Tentative Construction Period – May 2018 – August 2019 Construction Status – 40% Project Scope – Science Classroom, Library Renovation and Classroom Addition

Demolition complete. Wall framing in progress. Plumbing, HVAC and Electrical rough-in in progress.

52

Page 53: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation

53Site Plan

Page 54: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation

Rendering of New Library

54

Page 55: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

Library - Interior Science Classroom - Renovation

KATHERINE STINSON MIDDLE SCHOOL Science Classroom & Library Renovation

Science Classroom - Addition55

Page 56: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

COLBY GLASS ELEMENTARY Window Upgrades / ADA Work

Architect – Marmon Mok Project Architect – Monty Howard NISD Project Manager – Chris Parker Contractor – CGC General Contractors, Inc. Contract Amount - $874,900 Construction Period – June 2018 – September 2018 Construction Status – 90% Project Scope – Window Upgrades and ADA Work

Punch list in progress.

56

Page 57: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

COLBY GLASS ELEMENTARY Window Upgrades / ADA Work

Existi ng Site Plan

57

Page 58: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

COLBY GLASS ELEMENTARY Window Upgrades / ADA Work

Window Replacement

58

e006288
Text Box
Window Replacement
e006288
Line
e006288
Text Box
Window Refurbishment
e006288
Line
e006288
Text Box
Window Replacement and Accessibility Upgrades
e006288
Text Box
Existing Restrooms
e006288
Line
e006288
Line
e006288
Text Box
Restroom Upgrades
Page 59: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

COLBY GLASS ELEMENTARY Window Upgrades / ADA Work

Before - Window Upgrades After - Window Upgrades

59

Page 60: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

2014 BOND PROJECTS

IN

BID/DESIGN PHASE

SUMMER 2018

60

Page 61: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

KALLISON RANCH AREA MIDDLE SCHOOL New Middle School

Architect – Alamo Architects Project Architect – Jerry Lammers NISD Project Manager – Thomas Curiel Contractor – TBD Construction Amount - $39,000,000 Construction Period – July 2019 – May 2021 Status - In Design Project Scope – New Middle School

Schematic Design is scheduled.

61

Page 62: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

RANCHO DEL LAGO AREA ELEMENTARY SCHOOL New Elementary School

Architect – Garza Bomberger Project Architect – Roy Lewis NISD Project Manager – Marilyn Sevedge Contractor – TBD Construction Budget - $23,000,000 Construction Period – March 2019 – May 2020 Status - In Design Project Scope – New Elementary School

Construction drawings 30%.

62

Page 63: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

RANCHO DEL LAGO AREA ELEMENTARY SCHOOL New Elementary School

Rendering of Rancho Del Lago Elementary School

63

Page 64: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

NORTHSIDE NATATORIUM Pool Replacement

Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – James Evans Contractor – TBD Construction Budget - $1,200,000 Construction Period – March 2019 – August 2019 Status – In Design Project Scope – Pool Replacement

Construction drawings 95%.

64

Page 65: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

NORTHSIDE SPORTS GYM PLAZA OF INFLUENCE PYLONS

Architect – Marmon MokProject Architect – Monty HowardNISD Project Manager – Thomas CurielContractor – TBDConstruction Budget – $350,000Construction Period – February 2019 – April 2019Project Scope – Plaza Pylons

Schematic Design in progress.

Flanking Steel Pylons 65

Page 66: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

NORTHSIDE SPORTS GYM PLAZA OF INFLUENCE PYLONS

Plaza of Influence Commemoration Marker

66

Page 67: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

2014 BOND PROJECTS

IN

BID/DESIGN PHASE

SUMMER 2019

67

Page 68: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

JOHN MARSHALL HIGH SCHOOL Library Upgrades

Architect – Garza Bomberger & Associates Project Architect – Roy Lewis NISD Project Manager – James Evans Contractor – TBD Construction Budget - $3,000,000 Construction Period – April 2019 – February 2020 Project Scope – Library Addition & Renovation

Schematic Design in progress.

68

Page 69: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

2018 BOND PROJECTS

ADDITIONS/RENOVATIONS

IN DESIGN

69

Page 70: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

GLENOAKS ELEMENTARY SCHOOL Library and Classroom Building

Architect – Nextgen Architects Project Architect – Joel Hernandez NISD Project Manager – Marilyn Sevedge Contractor – TBD Contract Amount - $4,000,000 Construction Period – June 2019 – July 2020 Project Scope – Library and Classroom Building

Schematic Design in progress.

70

Page 71: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

PROJECT LISTING - 2018 BOND PROJECTS

Galm Road Area High School

2019 Security Lobbies for 21 CampusesNorthwest Crossing Elementary School Cafeteria/Kitchen RenovationsPat Neff Middle School Cafeteria UpgradesMeadow Village Elementary School Special Education ALE UpgradesWilliam P. Hobby Middle School Bus/Student Covered WalkwayO'Connor High School Flooring ReplacementPaint Booth Replacement at Oliver Wendell Holmes High School and John Jay High School 2019 Door Hardware Project at Various CampusesIntegrated Security Management System Upgrades at Various Campuses - Phase 1O'Connor High School Agriculture Facility Upgrade

Additions and Renovations Projects in Design & Scheduled

New Construction Projects in Design

71

Page 72: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

ROOFING PROJECTS

72

Page 73: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

2016 Hail Damage Roofing Projects

Phase IV - Bidding

Phase I - Complete

Beard Elementary School

Carnahan Elementary School

Clark High School

Stevenson Middle School

Carlos Coon Elementary School

Elrod Elementary School

Phase II – In Construction

Esparza Elementary School

Nichols Elementary School Connally Middle School

Howsman Elementary School (2014 Bond) Leon Valley Elementary School

Scarborough Elementary School

Alternative ES & MS - North

Burke Elementary School

Brauchle Elementary School

Leon Springs Elementary School

Raba Elementary School

Phase III – In Construction

Burke Elementary School

Clark High School

Helotes Elementary School

O’Connor High School Rhodes Elementary School

Sul Ross Middle School

Steubing Elementary School

Portable Roofs – Phase II (102)

Vale Middle School

Zachry Middle School

Driggers Elementary School

Briscoe Middle School

Colonies North Elementary School Hoffmann Elementary School Scobee Elementary School Alternative MS - South

Northwest Crossing Elementary

Henderson Elementary School Knowlton Elementary School

Maintenance Building (2014 Bond)

LIST OF SC HOOLS

73

Portable Roofs - Phase I (40)

Page 74: Facilities Construction - Northside Independent School ... · Contractor – Central Builders, Inc. Contract Amount - $5,562,000 Construction Period – June 2017 – August 2018

2016 Hail Damage Roofing Projects

Phase V - Design

O'Connor High School

Brandeis High School

Stinson Middle School

Kuentz Elementary School

John Jay High School

Hobby Middle School

Phase VI – Future

Support Services Center

Oak Hills Terrace Elementary School Kelly Smith Technology Center

Taft High School Northside Activity Center

North Transportation Station

Pease Middle School

Health Careers High School

Northside Tennis Center

Jefferson Middle School

John Glenn Elementary School

Mireles Elementary

Brennan High School Holmes High School

Rhodes Transportation Center Ward Elementary School

McDermott Elementary School

Mead Elementary School

Myers Elementary School