Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
2012
P0443-01
DateSignature
Group/Facility manager
(or nominated, suitably qualified and
experienced deputy)
National Grid Reference (6E, 6 N) 0738N 5223E
A description of the activities/processes at
the site for the reporting year. This should
include information such as production
increases or decreases on site, any
infrastructural changes, environmental
performance which was measured during
the reporting year and an overview of
compliance with your licence listing all
exceedances of licence limits (where
applicable) and what they relate to e.g. air,
water, noise.
Bulmers Clonmel is part of C & C group plc. There are 194 employees on site - 128 of which work within the
manufacturing section. The installed capacity on site is 500 million litres. Total production 2012/ 13 was 146
million litres , total production forecasted for 13/14 is 155million litres. approximately 4 millon litres of this is
attributed to contract bottling. Beer bottling commenced on site April 2012 - acting as a contingency for sister
company Tennents Glasgow. Relocation of line 4 bottling line off site is scheduled to take place in May 2013.
Aquisition of Gleesons Bottling & Warehousing took place in March 2013.
Declaration:All the data and information presented in this report has been checked and certified as being accurate. The
quality of the information is assured to meet licence requirements.
NACE Code
Class/Classes of Activity Class 7.3.1 & 7.8
Suzanne Shine 31/03/2013
Facility Information Summary
Licence Register Number
Name of site Bulmers Clonmel - C & C group plc
Site Location Annerville, Clonmel, Co tipperary
AER Reporting Year
2
AIR-summary template Lic No: P0443-01 Year 2012
Answer all questions and complete all tables where relevant
2
Yes
3Basic air
monitoring
checklist AGN2 Yes
Table A1: Licensed Mass Emissions/Ambient data-periodic monitoring (non-continuous)
Emission
reference no: Parameter/ Substance
Frequency of
Monitoring
ELV in licence
or any revision
therof Licence Compliance criteria Measured value
Unit of
measurement
Compliant with
licence limit Method of analysis
Annual mass
load (kg)
Comments -reason for change
in % mass load from previous
year if applicable
SELECT annually n/a SELECT SELECT SELECT SELECTSELECT SELECT SELECT SELECT SELECTSELECT SELECT SELECT SELECT SELECT
SELECT SELECT SELECT SELECT SELECT
Note 1: Volumetric flow shall be included as a reportable parameter
1
Does your site have licensed air emissions? If yes please complete table A1 and A2 below for the
current reporting year and answer further questions. If you do not have licenced emissions and do not
complete a solvent management plan (table A4 and A5) you do not need to complete the tables
Yes
Licence states that no monitoring of emissions is required other than that stated in 7.5.
There are emissions from boilers & fermentation vessels. All CO2 from fermentation
process is recovered. Bulmers is almost 100% self sufficient in CO2. Plant is operated so
that 100 % of CO2 is recovered. 2.29 kg / HL CO2 used during last financial year (
2012/13). All boilers are tested as part of annual servicing. See report attached
outlining results of boiler testing.
Periodic/Non-Continuous Monitoring
Was all monitoring carried out in accordance with EPA
guidance note AG2 and using the basic air monitoring
checklist?
Additional information
Are there any results in breach of licence requirements? If yes please provide brief details in the comment
section of TableA1 below
Licence states that no monitoring of emissions is required other than that stated in 7.5.
Biogas that is not recovered for use in boilers is flared. Total volume flared is measured.
Almost 95 % of the biogas generated is reused.
3
AIR-summary template Lic No: P0443-01 Year 2012
4No
5No
6No
7 No
Table A2: Summary of average emissions -continuous monitoring
Emission
reference no:
Parameter/ Substance
ELV in licence or
any revision
therof
Averaging
Period
Compliance Criteria Units of
measurement
Annual Emission Annual maximum Monitoring Equipment downtime (hours) Number of ELV
exceedences in
current
reporting year
Comments
SELECT SELECT SELECT
SELECT SELECT
SELECT SELECT
SELECT SELECT
SELECT SELECT
note 1: Volumetric flow shall be included as a reportable parameter.
Table A3: Abatement system bypass reporting table Bypass protocol
Date* Duration** (hours) Location
Did your site experience any abatement system bypasses? If yes please detail them in table 4 below
Continuous Monitoring
Does your site carry out continuous air emissions monitoring? Emissions monitoring are scheduled as part of the 2013/ 14 financial year.
If yes please review your continuous monitoring data and report the required fields below in Table 3 and
compare it to its relevant Emission Limit Value (ELV)
Did continuous monitoring equipment experience downtime? If yes please record downtime in table 3 below
Do you have a proactive service agreement for each piece of continuous monitoring equipment?
* this should include all dates that an abatement system bypass occurred
** an accurate record of time bypass beginning and end should be logged on site and maintained for future
Agency inspections please refer to bypass protocol link
Reason for bypass Corrective actionImpact magnitude
4
AIR-summary template Lic No: P0443-01 Year 2012
8 Do you have a total Emission Limit Value of direct and fugitive emissions on site? if yes please fill out tables A4 and A5
SELECT
Solvent
regulations
Reporting year Total solvent input on
site (kg)
Total VOC
emissions to Air
from entire site
(direct and
Total VOC
emissions as
%of solvent
input
Total Emission Limit Value
(ELV) in licence or any revision
therof
Compliance
SELECT
SELECT
(I) Inputs (kg)
Solvent (I) Inputs (kg)
Organic solvent
emission in
waste gases(kg)
Solvents lost
in water (kg)
Collected waste solvent (kg) Fugitive Organic
Solvent (kg)
Solvent released
in other ways e.g.
by-passes (kg)
Solvents destroyed
onsite through
physical reaction
Total emission of Solvent to air (kg)
Total
(O) Outputs (kg)
Table A4: Solvent Management Plan Summary
Total VOC Emission limit value
Table A5: Solvent Mass Balance summary
Please refer to linked solvent regulations to
complete table 5 and 6
Solvent use and management on site
5
AER Monitoring returns summary template-WATER/WASTEWATER(SEWER) Lic No: P0443-01 Year 2012
2
Yes
Location
Reference Date of inspection Source of
contamination
SW2.
7th December 2013. Issue
in discussion with Agency
as per correspondence
CI000134
site
3Yes
4
External /Internal
Lab Quality
checklist
Assessment of
results checklist Yes
Table W3: Licensed Emissions to water and /or wastewater (sewer)-periodic monitoring (non-continuous)
Emission
reference no: Emission released toParameter/
SubstanceNote 1
Frequency of
monitoring Averaging period
ELV or trigger
values in licence or
any revision
therofNote 2 Licence Compliance criteria Measured value
Unit of
measurement
Compliant with
licence Method of analysis
Procedural
reference source
Procedural
reference
standard numberAnnual mass load
(kg)
CS1 Wastewater/Sewer Ammonia (as N) composite Daily 24 hour 10mg/Litre All results < 1.2 times ELV, plus 8
from ten results must be < ELV13 mg/L
no (if no please
enter details in Spectrophotometry (Colorimetry)
APHA / AWWA
"Standard 4500 37078
CS1 Wastewater/Sewer Ammonia (as N) composite Daily 24 hour 10mg/Litre All results < 1.2 times ELV, plus 8
from ten results must be < ELV12.2 mg/L
no (if no please
enter details in Spectrophotometry (Colorimetry)
APHA / AWWA
"Standard 4500 34797
CS1 Wastewater/Sewer Ammonia (as N) composite Daily 24 hour 10mg/Litre All results < 1.2 times ELV, plus 8
from ten results must be < ELV10.6 mg/L
no (if no please
enter details in Spectrophotometry (Colorimetry)
APHA / AWWA
"Standard 4500 30233
CS1 Wastewater/Sewer Ammonia (as N) composite Daily 24 hour 10mg/Litre All results < 1.2 times ELV, plus 8
from ten results must be < ELV10.2 mg/L
no (if no please
enter details in Spectrophotometry (Colorimetry)
APHA / AWWA
"Standard 4500 29092
Note 1: Volumetric flow shall be included as a reportable parameter
2852185
Additional information
1
Does your site have licensed emissions direct to surface water or direct to sewer? If yes please
complete table W2 and W3 below for the current reporting year and answer further questions. If you
do not have licenced emissions you only need to complete table W1 and or W2 for surface water
analysis and visual inspectionsYes
Licence requires that there be no emissions to water of Environmental
significance. Storm water emissions require to be monitored weekly as per C3.1
Licenced emissions direct to sewer must be monitored as per C4.1 & 4.2.
Was it a requirement of your licence to carry out visual inspections on any surface water discharges or
watercourses on or near your site? If yes please complete table W2 below summarising only any
evidence of contamination noted during visual inspectionsSee above. All storm water emissions are held in attenuation ponds and treated
via the WWTP ( Anaerobic WWTP ). Ponds are monitored daily to ensure
sufficient capacity to maintain firewater retention capacity and rainfall.
Table W2 Visual inspections-Please only enter details where contamination was observed.
Comments
Holding ponds on site which collect all surface water from the site - SW2 and
sampng chamber no 2 feed into the ponds.
Sump cleaned out and attenuation pond cleaned.
Procedures being reviewed with all site personnel to ensure
spill kit use for all spillages.
Contaminated water was not
discharged to river Suir but was
redirected to WWTP via the
attenuation pond system.
Description of contamination Corrective action
Licensed Emissions to water and /or wastewater(sewer)-periodic monitoring (non-continuous)
Was there any result in breach of licence requirements? If yes please provide brief details in the comment
section of Table W3 below Breach of licence limit in relation to ammonia emissions to sewer.
Was all monitoring carried out in accordance with EPA guidance and
checklists for Quality of Aqueous Monitoring Data Reported to the EPA? If
no please detail what areas require improvement in additional
information box Laboratory used is accredited with INAB.
Note 2: Where Emission Limit Values (ELV) do not apply to your licence please compare results against EQS for Surface water or relevant receptor quality standards
6
AER Monitoring returns summary template-WATER/WASTEWATER(SEWER) Lic No: P0443-01 Year 2012
Additional information
5 Yes
6
Yes
7Yes Service contract in place with Hanleys & Endress & Hauser
8No
Table W4: Summary of average emissions -continuous monitoring
Emission
reference no: Emission released to Parameter/ Substance
ELV or trigger
values in licence
or any revision
thereof
Averaging
Period
Compliance
Criteria
Units of
measurement
Annual Emission for current
reporting year (kg)
% change +/- from
previous reporting yearMonitoring
Equipment
downtime (hours)
Number of ELV
exceedences in
reporting year
CS1 Wastewater/Sewer pH PH 4 - 10 24 hour
No pH value shall
deviate from the
specified range .
pH unitsno exceedence on ELV - just
downtime on equipment n/a
26th - 30th
November 20120
note 1: Volumetric flow shall be included as a reportable parameter.
Table W5: Abatement system bypass reporting tableDate Duration (hours) Location Resultant
emissions
Reason for
bypass
Corrective
action*
Was a report
submitted to the
EPA?
When was this report submitted?
*Measures taken or proposed to reduce or limit bypass frequency
If yes please summarise your continuous monitoring data below in Table W4 and compare it to its relevant
Emission Limit Value (ELV)
Continuous monitoring Additional Information
Does your site carry out continuous emissions to water/sewer monitoring?
Continuous monitoring on flow, temp and ph on wastewater emissions
Did continuous monitoring equipment experience downtime? If yes please record downtime in table W4 below Loss of communication link only from Scada system to local ph meter. Local ph
meter continued to function but no automatic log could be maintained of ph
due to communication failure. Issue reported to EPA as a licence notification
Do you have a proactive service contract for each piece of continuous monitoring equipment on site?
Did abatement system bypass occur during the reporting year? If yes please complete table W5 below
Comments
No exceedences on ph - ph is neutralised as part of anaerobic treatment process to allow treatment
to continue.
7
Comments
Feb-12
Jun-12
Jun-12
Jun-12
9
Bund/Pipeline testing template Lic No: P0443-01 Year 2012
Bund testing Additional information
1 Yes
2 Please provide integrity testing frequency period 3 years
3 Yes
Bund inspection check is completed
weekly in both WWTP and on main
site.
4 How many bunds are on site? 20 bunds
One of these bunds is used by Grants
and is monitired as part of Grants
EMS. All plastic bunds / containment
pallets are located in effluent
drainage areas and any leaks are
detected and reported. . Bund
replaced out if damaged etc
5 How many of these bunds have been tested witin the required test schedule?
Plastic bund containment pallets not
inspected as per 3 year integrity
testing schedule but are monitored
weekly. Concrete bund structures are
tesed every 3 years - due in 2013.
6 How many mobile bunds are on site? 10 Containment pallets
7 Are the mobile bunds included in the bund test schedule? No
8 How many of these mobile bunds have been tested witin the required test schedule?
9 7 sumps / tanks
These sumps are pumping statiions
and are inspected by Cantwells every
six months - servivce completed
March 2013. Maintenance work
generated actioned via Pragma.
10 4 sumps Others due in 2013.
Please list any sump integrity failures in table B1
11 No
5 of them have high level alarms -
Factory, apple crushing sump,
warehousing sump and inlet sump
overflow sump in WWTP have high
level alarms
12 Yes
Maintenance programme in place
with Cantwell electrical
Bund/Containment structure ID Type Specify Other type Product containment Actual capacity Capacity required* Type of integrity test Other test type Test date Integrity reports maintained on site? Results of test
Integrity test failure
explanation <50 words Corrective action taken
Scheduled date
for retest
Results of
retest(if in
current
reporting year)
B1 - Outside process room general purpose concrete/masonryCombined bund type Citric acid 30.197 33.216 Hydraulic test n/a 2009 Yes Pass N/A Repaired crack FY 2013 N/A
B2 - Chemical Compound reinforced concrete Remote Brilatol caustic 48 52.8 Hydraulic test n/a 2009 Yes Pass N/A SELECT FY 2013 N/A
B3 - NMU general purpose concrete/masonryCombined bund type Sodium hydroxide 25 50.5 Hydraulic test n/a 2012 Yes Pass N/A SELECT FY 2013 N/A
B4 - CIP station - nmu general purpose concrete/masonryCombined bund type 68 54.8 Hydraulic test n/a 2009 Yes Pass N/A SELECT FY 2013 N/A
Grants - B5 general purpose concrete/masonryCombined bund type whiskey 130 61 Hydraulic test n/a 2012 Yes Pass N/A SELECT FY 2015 N/A
SELECT* Capacity required should comply with 25% or 110% containment rule as detailed in your licence Commentary
14 bunding and storage guidelines Yes
15 Are channels/transfer systems to remote containment systems tested? No all transfer lines overhead - spills / leaks evident
16 Are channels/transfer systems compliant in both integrity and available volume? Yes
1 Yes
2 Please provide integrity testing frequency period 3 years
Structure ID Type system Material of construction:
Does this structure have
Secondary containment?
Type of secondary
containment
Type integrity testing
Integrity reports
maintained on site? Results of test
Integrity test failure
explanation <50 words Corrective action taken
Scheduled date
for retest
Results of retest(if in current
reporting year)
Existing tank farm - zone 5 & zone 6 ( North Tank Farm ) Process pvc Yes
Pipe in channel
CCTV yes Pass N/A
All drains cleaned and surveyed -July 2011.
Remedial work completed on drains around
CIP room and yeast and nutrient room June
2012. Water pooling in area. 2014
Current financial year starts
March 2013
Existing tank farm - zone 3 ( South tank Farm ) Process pvc Yes Pipe in channel CCTV yes Pass N/A Part tested in 2007 on installation 2013
Existing tank farm - zone 5 ( West tank Farm ) Storm water drainage pvc Yes Pipe in channel CCTV yes Pass N/A tested on installation in 2007 2014
process area - Zone 7 Process pvc Yes
Pipe in channel
CCTV yes Pass Report available
Drains rebuild and integrity tested in area in
2006 - rerouting of drains etc completed by
USSR. 2014 SELECT
OMU bottlng hall areas - line 1 ( Zone 7 ) Process pvc Yes
Pipe in channel
CCTV yes Pass N/A
Drain repair work completed by Mulcahy
construction 2012 2014
dropdown menu click to see options
Are you required by your licence to undertake integrity testing on bunds and containment structures ? if yes please fill out table B1 below listing all new bunds and containment structures on site, in addition to all
bunds which failed the integrity test-all bunding structures which failed including mobile bunds must be listed in the table below
Are you required by your licence to undertake integrity testing on underground structures e.g. pipelines or sumps etc ? if yes please fill out table 2 below listing all underground structures and pipelines on site which
failed the integrity test
How many sumps on site are included in the integrity test schedule?
How many of these sumps are integrity tested within the test schedule?
Table B1: Summary details of bund /containment structure integrity test
Does the site maintain a register of bunds, underground pipelines (including stormwater and foul), Tanks, sumps and containers? (containers refers to "Chemstore" type units and mobile bunds)
Has integrity testing been carried out in accordance with licence requirements and are all structures tested in line with BS8007/EPA Guidance?
Do all sumps and chambers have high level liquid alarms?
If yes to Q11 are these failsafe systems included in a maintenance and testing programme?
Pipeline/underground structure testing
Table B2: Summary details of pipeline/underground structures integrity test
10
Bund/Pipeline testing template Lic No: P0443-01 Year 2012
Keg line drainage ( Zone 7) Process pvc Yes
Pipe in channel
CCTV No FAIL
Fail - drains rebuilt as
no outlet flow from
line due to blockage -
water pooling in area Drains rebuilt over xmas period 2012/13. 2015 Pass
Empty can warehouse area and Line 2 Process pvc Yes
Pipe in channel
CCTV No N/A N/A N/A Jun-13 N/A
warehouse area ( zone 4 ) Storm water drainage pvc Yes Pipe in channel CCTV yes Pass Completed 2009 2013 SELECT
water room / co2 recovery / chemical stores ( zone 4 ) Storm water drainage pvc Yes Pipe in channel CCTV yes Pass Completed 2009 2013 SELECT
NMU area despatch Process pvc Yes Pipe in channel CCTV yes Pass New area installed 2007 2013 SELECT
nmu area Process pvc Yes Pipe in channel CCTV yes Pass New area installed 2007 2013 SELECT
Factory sump and apple crush effluent lines to WWTP Process pvc Yes Pipe in channel CCTV yes Pass 2013 SELECT
Exiisting old plant and Grant Process pvc Yes Pipe in channel CCTV yes Pass completed 2010 2014 SELECT
Effluent route via can line line 2 and empty can warehouse Process pvc Yes Pipe in channel CCTV yes Pass 2013 SELECT
drainage area at front of offces Storm water drainage pvc Yes Pipe in channel CCTV no N/A NOT COMPLETED 2014
Please use commentary for additional details not answered by tables/ questions above
11
Groundwater/Soil monitoring template Lic No: P0443-01 Year 2012
Comments
1
yes
As per condition C7 of licence.
Monitoring is also completed in line
with spring water directive , potable
water standards . Sample collected at
bore hole.
2no
Only as part of Landspreading NMP
submission
3
yes
two aquifers on site - 3 wells in use.
Total usage for 2012 was 4747120hl
4
yes
Contaminated groundwater that ius
no longer used. Two wells were
decommissioned since 2002 due to
odour issue from water and biomass
growth on walls of well
5
yes
Historic and due to well itself - reason
for contamination never detected.
6
7 N/A
8 N/A ELRA completed 2009.
9 no
10 no
11 no
12 no
Table 1: Upgradient Groundwater monitoring results
Date of sampling
Sample
location
reference
Parameter/
Substance Methodology Monitoring frequency
Maximum
Concentration++
Average
Concentration+ unit GTV's* IGV
% change in
average
concentration
previous year +/-
Upward trend in
pollutant
concentration over last
5 years of monitoring
data
07/04/2012 PW3 PH
Method based on “Standard
Methods for the Examination of
Water and Wastewater”, Method
4500, 21st Edition, APHA, 2005.
Daily
7.7
7.6 units 6.5 - 9.5
6.9 - 8.1 lower
limit 6.8.
Extremely high
or low values
may be an
indication of
pollution 0% no
DWD Analysis -
March 2012 PW3 COD
Method based on Standard
Methods for the Examination of
Water and Wastewater”, APHA
5220 - D, 21st Edition, APHA, 2005
Quarterly
2
1 mg/l no extreme variations no abnormal change 0% no
Has a Conceptual Site Model been developed for the site?
Are you required to carry out groundwater monitoring as part of your licence requirements?
Are you required to carry out soil monitoring as part of your licence requirements?
Do you extract groundwater for use on site? If yes please specify use in comment section
Is there contaminated land and /or groundwater on site? If yes please answer q's 5-12
Is the contamination related to operations at the facility (either current and/or historic)
Have actions been taken to address contamination issues?If yes please summarise remediation strategies
proposed/undertaken for the site no
Contamination is due to rock type -
opinion of hydrogeologist at the time
of the investigation into odour.
Please specify the proposed time frame for the remediation strategy
Is there a licence condition to carry out/update ELRA for the site?
Has any type of risk assesment been carried out for the site?
Have potential receptors been identified on and off site?
Is there evidence that contamination is migrating offsite?
12
Groundwater/Soil monitoring template Lic No: P0443-01 Year 2012
Public analysts lab
report PW3 Nitrate Quarterly
6.7
6.6 mg/l
background range <.0023
- 16.4, interim guideline :
5.65mg/l potable water
directive 50 5.65 0% no
PW3
Total
ammonia Biannually
0.03
0.02 mg/l 0.3 0.116mg/l 0% no
PW3 nitrite
“Standard Methods for the
Examination of Water and Waste
Water (21st edition, 2005) APHA
AWWA WEF Method 4500 – NO2- B Quarterly
0.06
0.05 mg/l 0.5 0.3 0% no
PW3 conductivity
Method is derived from Method
based on Method 2510, 21st Edition,
APHA, 2005.
Daily
602
599 us/cm 1000
Upper Limit
999. Elevated
concentrations
may indicate
saline
Intrusion and
increases with
contamination
generally 0% no
PW3 Chloride Quarterly
18
14.4 mg/l 250 0% no
PW3 fluoride Quarterly
0.09
0.07 mh/LF 0.8 0% no
PW3
Organohalog
ens EN ISO 6468, US EPA 8081, DIN 38407-
2 Biannually
n/a
0.3 ug/l no extreme variations no abnormal change 0% no
SELECT
.+ where average indicates arithmetic mean
.++ maximum concentration indicates the maximum measured concentration from all monitoring results produced during the reporting year
Date of sampling
Sample
location
reference
Parameter/
Substance Methodology Monitoring frequency
Maximum
Concentration++
Average
Concentration+ unit GTV's* SELECT**
% change in
average
concentration
previous year +/-
Upward trend in
pollutant
concentration over last
5 years of monitoring
data
Method as detailed in “Standard
Methods for the Examination of
Water and Waste Water (21st
edition, 2005) APHA AWWA WEF
Method 4500 – Cl E“.Method as
detailed in HACH Manual
13
Groundwater/Soil monitoring template Lic No: P0443-01 Year 2012
rw3 PH
Method based on “Standard
Methods for the Examination of
Water and Wastewater”, Method
4500, 21st Edition, APHA, 2005.
Daily
7.8
7.7 units 6.5 - 9.5
6.9 - 8.1 lower
limit 6.8.
Extremely high
or low values
may be an
indication of
pollution 0 SELECT
rw3 COD
Method based on Standard
Methods for the Examination of
Water and Wastewater”, APHA
5220 - D, 21st Edition, APHA, 2005
Quarterly
1
1 mg/l no extreme variations no abnormal change 0
rw3 Nitrate Quarterly
12.86
7.6 mg/l
background range <.0023
- 16.4, interim guideline :
5.65mg/l potable water
directive 50 5.65 0
rw3
Total
ammonia
(nh3 - n ) Biannually
0.04
0.02 mg/l 0.3 0.116mg/l 0
rw3 nitrite no2
“Standard Methods for the
Examination of Water and Waste
Water (21st edition, 2005) APHA Quarterly
0.06
0.05 mg/l 0.5 0.3 0
rw3 conductivity
Method is derived from Method
based on Method 2510, 21st Edition,
APHA, 2005.Daily
655
651 us/cm 1000
Upper Limit
999. Elevated
concentrations
may indicate 0
rw3 Chloride Quarterly 21.2 19.3 mg/l 250 0rw3 fluoride Quarterly 0.07 0.06 mh/LF 0.8 0
rw3
Organohalog
ens EN ISO 6468, US EPA 8081, DIN 38407-
2 Biannually
0.4
0.3 ug/l no extreme variations no abnormal change
SELECT SELECT
Date of sampling
Sample
location
reference
Parameter/
Substance Methodology Monitoring frequency
Maximum
Concentration++
Average
Concentration+ unit GTV's* SELECT**
% change in
average
concentration
previous year +/-
Upward trend in
pollutant
concentration over last
5 years of monitoring
data
RW4 PH
Method based on “Standard
Methods for the Examination of
Water and Wastewater”, Method
4500, 21st Edition, APHA, 2005.
Daily 7.6 7.5 units 6.5 - 9.5
6.9 - 8.1 lower
limit 6.8.
Extremely high
or low values
may be an
indication of
pollution 0 SELECT
RW4 COD
Method based on Standard
Methods for the Examination of
Water and Wastewater”, APHA
5220 - D, 21st Edition, APHA, 2005
Quarterly 3 2 mg/l no extreme variations no abnormal change 0
RW4 Nitrate Quarterly 16 15.14 mg/l
background range <.0023
- 16.4, interim guideline :
5.65mg/l potable water
directive 50 5.65 0
Total Oxidised Nitrogen is the sum
of Nitrate and Nitrite Nitrogen.
Nitrate Nitrogen is calculated by
subtracting the Nitrite Nitrogen
from the Total Oxidised
Nitrogen.Documented in-house
method adapted from “Standard
Total Oxidised Nitrogen is the sum
of Nitrate and Nitrite Nitrogen.
Nitrate Nitrogen is calculated by
subtracting the Nitrite Nitrogen
from the Total Oxidised
Nitrogen.Documented in-house
method adapted from “Standard
Methods for the Examination of
Method as detailed in “Standard
Methods for the Examination of
14
Groundwater/Soil monitoring template Lic No: P0443-01 Year 2012
RW4
Total
ammonia Biannually 0.04 0.02 mg/l 0.3 0.116mg/l 0
RW4 nitrite “Standard Methods for the
Examination of Water and Waste Quarterly 0.06 0.05 mg/l 0.5 0.3 0
RW4 conductivity
Method is derived from Method
based on Method 2510, 21st Edition,
APHA, 2005.
Daily 654 622 us/cm 1000
Upper Limit
999. Elevated
concentrations
may indicate
saline
Intrusion and
increases with
contamination
generally 0
RW4 Chloride Quarterly 21.2 19 mg/l 250 0RW4 fluoride Quarterly 0.16 0.15 mh/LF 0.8 0
RW4
Organohalog
ens EN ISO 6468, US EPA 8081, DIN 38407-
2 Biannually 0.4 0.3 ug/l no extreme variations no abnormal change 0
Table 2: Downgradient Groundwater monitoring results
Date of sampling
Sample
location
reference
Parameter/
Substance Methodology Monitoring frequency
Maximum
Concentration
Average
Concentration unit GTV's* SELECT**
% change in
average
concentration
previous year +/-
Upward trend in yearly
average pollutant
concentration over last
5 years of monitoring
data
N/A SELECT SELECT
SELECT SELECT
Surface water EQS
Groundwater
regulations
GTV's
Drinking water
(private supply)
standards
Drinking water (public
supply) standards
Table 3: Soil results
Date of sampling
Sample
location
reference
Parameter/
Substance Methodology Monitoring frequency
Maximum
Concentration
Average
Concentration unit
N/A SELECT
SELECT
* please note exceedance of a relevant Groundwater threshold value (GTV) at a representative monitoring point does not indicate non compliance, an exceedance triggers further investigation to confirm whether the criteria for poor groundwater chemical
**Depending on location of the site and proximity to other sensitive receptors alternative Receptor based Water Quality standards should be used in addition to the GTV e.g. if the site is close to surface water
compare to Surface Water Environmental Quality Standards (SWEQS), If the site is close to a drinking water supply compare results to the Drinking Water Standards (DWS)
Where additional detail is required please enter it here in 200 words or less
Total Oxidised Nitrogen is the sum
of Nitrate and Nitrite Nitrogen.
Nitrate Nitrogen is calculated by
subtracting the Nitrite Nitrogen
from the Total Oxidised
Nitrogen.Documented in-house
method adapted from “Standard
Method as detailed in “Standard
Methods for the Examination of
15
Environmental Liabilities template Lic No: P0443-01 Year 2012
Commentary
1
Submitted and not agreed by EPA;
Residual management
plan rev 1 submitted
to EPA in 2009. Report
revised.
2 Review required and completed Not submitted to EPA
3 cash in bank
4 Submitted and not agreed by EPA;
5 N/A
6 cash in bank
7 Review required
8 Required but not submitted
9 Review required and not completed
10 Submitted and not agreed by EPA;
11 383513
12 cash in bank
13 N/A
Click here to access EPA guidance on Environmental Liabilities and Financial
provision
Financial provision for ELRA expiry date
Closure plan initial agreement status
Closure plan review status
Financial Provision for Closure status
Financial provision for Closure expiry date
Financial Provision for Closure - type
ELRA initial agreement status
ELRA review status
Amount of Financial Provision cover required as determined by the latest ELRA
Financial Provision for ELRA status
Financial Provision for ELRA - amount of cover
Financial Provision for ELRA - type
Financial Provision for Closure - amount of cover
16
Environmental Management Programme/Continuous Improvement Programme template Lic No: P0443-01 Year 2012
Additional Information
1Yes
2 Yes
3 Yes
4 Yes
Environmental Management Programme (EMP) reportObjective Category Target Status (% completed) How target was progressed Responsibility Intermediate outcomes
Energy Efficiency/Utility
conservation - lighting
not confirmed. Each
project was justified
payback 77
Site lighting project review energy
usage trends to identify the link
between changes and
consumption. Astranomical timers
fitted , induction lighting fitted in
keg yard and on keg line. K type
fittings installed in full goods
warehouse. Switches in canteen
relocated so easy to Facilities area engineer Reduced emissions
Energy Efficiency/Utility
conservation - office area
optimisation project
not confirmed. Each
project was justified
payback 61
Create an open office procurement
and managers, Installed 7 day
timers on the all domestic boilers,
Fitted thermostatic valves on old
installs Facilities area engineer Reduced emissions
Energy Efficiency/Utility
conservation - Line 1 conveyor
projects & CO2 flowmeter
installation not confirmed. Each
project was justified
payback 100
Modify the control sequence to the
filler and then labeller can be
cleaned without having the
conveyors running
Payback - €2k / year.
CO2 flow meters installation link
up to Energy track system OMU area engineer and Energy repsReduced emissions
Highlighted cells contain dropdown menu click to view
Does the EMS reference the most significant environmental aspects and associated
impacts on-site
Does the EMS maintain an Environmental Management Programme (EMP) as required in
accordance with the licence requirements
Do you maintain an Environmental Mangement System (EMS) for the site. If yes, please
detail in additional information IS014001
Public information file available at security via Q - pulse system
Do you maintain an environmental documentation/communication system to inform the
public on environmental performance of the facility, as required by the licence
17
Environmental Management Programme/Continuous Improvement Programme template Lic No: P0443-01 Year 2012
Highlighted cells contain dropdown menu click to view
Energy Efficiency/Utility
conservation - CO2 recovery
optimisation Project
not confirmed. Each
project was justified
payback 100
install Fresh water flow meters and
link to chem track, validate the
cooling tower performance against
manufacturers recommendations,
complete optimisation study on
line 1 Pasteuriser OMU area engineer and Energy repsReduced emissions
Energy Efficiency/Utility
conservation - OMU area
not confirmed. Each
project was justified
payback 100
Coaching techs to understand and
use A3 problem solving to deal
with CO2 losses. Analyse the data
colection sheet s and determin
what target levels need to be set
for the percentage of co2 recovery
expected per
fermentation.Orgainise training
with Haffmans on Co2 Collection OMU area engineer and Energy repsReduced emissions
Energy Efficiency/Utility
conservation - WWTP -
optimisation of WWTP process to
reduce energy and sludge
generation
not confirmed. Each
project was justified
payback 100
Reduced usage of aerobic plant -
operation of aerobic only when
beer bottling taking place or when
monitoring dicates requirement . WWTP operator & SHE manager Reduced emissions
Waste reduction/Raw material
usage efficiency
not confirmed. Each
project was justified
payback 100
reduced glass , glue , raw materials
by increased monitoring and loss
reporting Line managers Reduced emissions
18
Lic No: P0443-01 Year 2012
1 Yes
2
Noise
Guidance
note NG4
Yes
3 No
4 n/a
5 No
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive
noise was identified
was 5dB penalty
applied?
Comments (ex. main noise sources on site, & extraneous noise ex. road
traffic)
Is site compliant with
noise limits
(day/evening/night)?
4/12/2012 - 9.18 66 58 68
No no
4/12/2012 - 12.23 64 56 66 No No no
4/12/2012 - 15.35 67 59 71No No no
Arithmetic Mean 66 58 68
*Please ensure that a tonal analysis has been carried out as per guidance note NG4. These records must be maintained onsite for future inspection
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive
noise was identified
was 5dB penalty
applied?
Comments (ex. main noise sources on site, & extraneous noise ex. road
traffic)
Is site compliant with
noise limits
(day/evening/night)?
4/12/2012 - 11.11 53 51 55 No No yes
4/12/2012 - 14.12 53 50 55 No No yes
4/12/2012 - 17:32 52 49 53 No No yes
Arithmetic Mean 53 50 54
yes
*Please ensure that a tonal analysis has been carried out as per guidance note NG4. These records must be maintained onsite for future inspection
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive
noise was identified
was 5dB penalty
applied?
Comments (ex. main noise sources on site, & extraneous noise ex. road
traffic)
Is site compliant with
noise limits
(day/evening/night)?
4/12/2012 - 11.47 64 59 67 No No no
4/12/2012 - 14.50 65 61 68 No No no
4/12/2012 - 18.06 64 58 67 No No no
Arithmetic Mean 64 59 67
no
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive
noise was identified
was 5dB penalty
applied?
Comments (ex. main noise sources on site, & extraneous noise ex. road
traffic)
Is site compliant with
noise limits
(day/evening/night)?
4/12/2012 - 11.11 53 51 55 No No Yes
4/12/2012 - 14.12 53 50 55 No No Yes
4/12/2012 - 17:32 52 49 53 No No Yes
Arithmetic Mean 53 50 54
Yes
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive
noise was identified
was 5dB penalty
applied?
Comments (ex. main noise sources on site, & extraneous noise ex. road
traffic)
Is site compliant with
noise limits
(day/evening/night)?
4/12/2012 - 9.55 61` 54 62
No No
The primary noise audible from on-site activity was from
HGVs entering, exiting, and stalling/reversing at security
barriers (approximately 10 vehicles passed by
during each monitoring period). No noise was
audible from this point of any other operations on-site. Noise was
detected from birds singing in the orchard opposite
the monitoring point. The other noise audible
was the constant passing of traffic on the N24.
no
4/12/2012 - 13.00 62 56 63 No No no
4/12/2012 - 16.21 63 57 63 No No no
Arithmetic Mean 62 56 63 no
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive
noise was identified
was 5dB penalty
applied?
Comments (ex. main noise sources on site, & extraneous noise ex. road
traffic)
Is site compliant with
noise limits
(day/evening/night)?
4/12/2012 - 23.00 56 40 59 No No no
4/12/2012 - 01:54 57 39 58 No No no
noThe main source of noise was traffic (approx. 50 vehicles during each
monitoring period) passing on the Ferryhouse Roundabout on the N24
which was wet at the time and this elevated noise. Other noise audible
included the constant noise from the stacks at Medite facility, north of
Bulmer’s facility, rustling of trees. Noise generated on the Bulmer’s
facility was beeping from reversing HGVs, faint noise from ventilation
from site buildings and the engine from Waste WaterTreatment Plant
Main source of noise from the site at this location included noise
generated by the hum from a pump at the Waste Water Treatment
plant,employees talking on-site, plastic piping
being dragged along loose gravel. Tractor entered site & parked during 1
survey period.Noise was audible from vehicles pulling out of main site
entrance. Low noise audible from HGVs movement on occasion from the
main facility. Primary noise audible from the monitoring point was the
constant traffic on the
N24 road.
Table N1: Noise monitoring summary
12/04/2012 Day - NML05
The main source of noise during monitoring at this location was
activities from the premises north of the Bulmer’s facility
and noise audible included humming noise from 2 stack units operating
constantly,HGVs and plant activity moving material, scraping noise off
metal and beeping siren from reversing vehicles. On-site noise involved
HGVs movement around thetrailer park,reversing sirens, clanking noise
when trailers were opened/closed,horns blowing,
trees rustling. An occasional car passed by during the monitoring at this
location.
Table N1: Noise monitoring summary
12/04/2012 Day - NML03
Main noise source on-site was from the loading yard
across from the monitoring point and involved 2 electric forklifts
lifting, reversing & loading crates onto HGV trailers, horn & beeping
noise from HGVs reversing and HGVs pulling in/out of yard, clanking
noise of trailers opening/closing and people talking. No other activity on-
site was audible from this location. The offsite noise generated was the
constant movement of traffic on the N24 road, birds chirping, leaves
rustling.
there was no audible noise at this location generated from
on-site activity at Bulmer’s Showerings. The primary source
of noise was from vehicles passing through the N24 Ferryhouse
roundabout creating noise such as the screeching of brakes, revving of
engines and tyres squelching on the wet road
surface. On average during 30 minutes of monitoring at
this location approximately 270 cars and 50 HGVs passed
the monitoring location. Other noise sources audible were
trees rustling in the wind & crows cawing and a horse
passed by with noise generated from the horse shoes on the
road during the final monitoring daytime period.NML01 Day - 12:2312/04/2012
Table N1: Noise monitoring summary
Was noise monitoring a licence requirement for the AER period?
If yes please fill in table N1 noise summary below
Was noise monitoring carried out using the EPA Guidance note including completion of the "Checklist for
noise measurement report" included in the guidance note as table 6?
Does your site have a noise reduction plan
Table N1: Noise monitoring summary
12/04/2012 Day - NML04
Table N1: Noise monitoring summary
12/04/2012 night time NML01
When was the noise reduction plan last updated?
Noise monitoring summary report
Have there been changes relevant to site noise emissions (e.g. plant or operational changes) since the last noise survey?
Table N1: Noise monitoring summary
12/04/2012 Day NML02
19
Arithmetic Mean 57 40 59
no
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive
noise was identified
was 5dB penalty
applied?
Comments (ex. main noise sources on site, & extraneous noise ex. road
traffic)
Is site compliant with
noise limits
(day/evening/night)?
5/12/2012 - 00:45 46 45 47 No No no
5/12/2012 - 03:38 49 48 48 No No no
no
Arithmetic Mean 48 47 49no
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive
noise was identified
was 5dB penalty
applied?
Comments (ex. main noise sources on site, & extraneous noise ex. road
traffic)
Is site compliant with
noise limits
(day/evening/night)?
5/12/2012 - 01:19 57 42 61 No No no
5/12/2012 - 04:11 53 41 56 No No no
no
Arithmetic Mean 55 59 42
no
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive
noise was identified
was 5dB penalty
applied?
Comments (ex. main noise sources on site, & extraneous noise ex. road
traffic)
Is site compliant with
noise limits
(day/evening/night)?
5/12/2012 - 00:19 54 45 58 No No no
5/12/2012 - 03:03 52 46 53 No No no
no
Arithmetic Mean 53 46 56
Date of
monitoring Time period
Noise location
(on site)
Noise sensitive
location -NSL (if
applicable) LAeq LA90 LA10 LAmax
Tonal or Impulsive
noise* (Y/N)
If tonal /impulsive
noise was identified
was 5dB penalty
applied?
Comments (ex. main noise sources on site, & extraneous noise ex. road
traffic)
Is site compliant with
noise limits
(day/evening/night)?
5/12/2012 - 23:34 51 38 54 No No SELECT
5/12/2012 - 02:28 54 36 52 No No
Arithmetic Mean 53 37 53
Nothing
No
Noise audible from this monitoring location was
generated by traffic on the N24 road,constant low
humming noise from the stacks at Medite facility, 3 HGVs
entering and exiting the Bulmer’s site during each
monitoring period and idling at security barriers. The security
van also pulled up by the monitoring location during the
first round of monitoring and engine was left idling
Conclusions
The EPA IPPC Licence P0443-02 states in Condition 8.1 that noise emissions from the site shall not exceed LAeq of 55 dB(A) during the daytime, and LAeq of 45 dB(A) during the night-time. Furthermore, Schedule B.4. states “There shall be
no clearly audible impulsive component in the noise emission from the activity at any noise sensitive location.”Average daytime L(A)eq measurements at monitoring location NML01 measured 66 dB(A),mainly influenced by the frequent
road traffic along the N24 Limerick/Waterford Rd and not to noise generated by the Bulmer's facility. Average daytime L(A)eq measurements at monitoring location NML02 measured 53 dB(A),mainly influenced by Medite Europe Ltd north
of the monitoring location. Average daytime L(A)eq measurements at monitoring location NML03 measured 64 dB(A), mainly influenced by the frequent road traffic along the N24 Limerick/Waterford Rd and activity on-site in the loading
yard across from the monitoring point. Average daytime L(A)eq measurements at monitoring location NML04 measured 63 dB(A),
mainly influenced by the frequent road traffic along the N24 Limerick/Waterford Rd and on-site loading activity across from the monitoring point. Average daytime L(A)eq measurements at monitoring location NML05 measured 62
dB(A),mainly influenced by the frequent road traffic along the N24 Limerick/Waterford Road frequent passage of vehicles along the HGV on-site road entering and exiting the facility.With respect to the above, noise levels at almost all
boundary locations at the facility were significantly influenced by surrounding traffic noise and not from noise generated on-site at the Bulmer’s Showerings facility. This is evident from the LAF10, T values determined at these monitoring
locations.The EPA Noise Guidance (NG4) states that for some noise surveys, the LAF90,T index may be used to give a good indication of the actual noise output from the site, where the noise emissions on site are relatively steady and
extraneous noises may unduly influence the
measured LAeq, T. Assessment of the LAF90 values for daytime measurements at monitoring locations NML01, NML03, NML04 and NML05 indicate that the average noise level is above the 55 dB(A) daytime limit while monitoring location
NML02 is below the 55 dB(A)daytime limit. NML02 monitoring location was the only monitoring point not influenced by noise from the traffic on the N24 road so it can be concluded that the daytime limit breached at NML01, NML03,
NML04 and NML05, locations that are significantly influenced by noise generated during frequent passage of traffic on the N24, is caused by off-site noise attributing to the excess daytime noise above the maximum limit set. Average night-
time L(A)eq measurements at monitoring location NML01 measured 57 dB(A), mainly influenced by the frequent road traffic along the N24 Limerick/Waterford Rd. Average night-time L(A)eq measurements at monitoring location NML02
measured 48 dB(A), mainly influenced by Medite Europe Ltd north of the monitoring location. Average night-time L(A)eq measurements at monitoring location NML03 measured 55 dB(A), mainly influenced by the frequent road traffic
along the N24 Limerick/Waterford Rd and activity on-site in the loading yard across from the monitoring point. Average night-time L(A)eq measurements at monitoring location NML04 measured 53 dB(A), mainly influenced by the
frequent road traffic along the N24 Limerick/Waterford Rd
and HGV on-site loading activity across from the monitoring point. Average night-time L(A)eq measurements at monitoring location NML05 measured 53 dB(A), mainly influenced by the frequent road traffic along the N24
Limerick/Waterford Road frequent passage of vehicles along the HGV on-site road entering and exiting the facility. Night-time L(A)eq noise limits were exceeded at monitoring locations NML01, NML02,
NML03, NML04 and NML05. Again, considering that the LAF90,T index may be used to give a good indication of the actual noise output from the site, where the noise emissions on site are relatively steady
and extraneous noises may unduly influence the measured LAeq, T, the assessment of LAF90 values for night-time measurements at monitoring locations NML01, NML03 & NML05 indicate that the average noise level attributable to the
site is below the 45 dB(A) nighttime limit at these locations. The LAF90 for NML02 and NML04 was above the 45 dB(A) night-time limit but this is due to the low constant sound of engines operating from Medite Europe Ltd influencing
NML02, and engine/ventilation from the Waste Water Treatment facility influencing NML04, during night-time surveys. No tonal or impulsive noise components were detected at any of the noise sensitive locations.
Table N1: Noise monitoring summary
12/04/2012 night time NML04
Traffic from the N24 was the most audible noise. Noise
generated from the Waste Water Treatment facility
included once off hissing of vapour, andventilation/engine
running constantly creating a low humming noise from behind the
monitoring location, the Treatment plant’s main gates creaking opening
and closing when the security van entered the area and drove around
the site across gravel for 3 mins during the second round of night time
monitoring at this site. Noise audible from the Bulmer’s main facility
involved occasional movement of HGVs and beeping noise when HGVs
reversing, a constant low hum from ventilation, and a boiler starting up
creating a hissing noise as air was released.
The main source of noise was traffic (approx. 50 vehicles during each
monitoring period) passing on the Ferryhouse Roundabout on the N24
which was wet at the time and this elevated noise. Other noise audible
included the constant noise from the stacks at Medite facility, north of
Bulmer’s facility, rustling of trees. Noise generated on the Bulmer’s
facility was beeping from reversing HGVs, faint noise from ventilation
from site buildings and the engine from Waste WaterTreatment Plant
Table N1: Noise monitoring summary
Table N1: Noise monitoring summary
NML02
The dominating noise was from the woodchip mill, Medite Europe Ltd,
operating 2 stacks constantly. Noise on-site included
low sound from ventilation, HGVs moving around the trailer park on
occasion collecting and dropping off trailers. Other noises
included trees rustling, clanking noise from trailers
opening/closing, crows cawing.
Table N1: Noise monitoring summary
12/04/2012 night time NML03
High noise from this location was largely due to the traffic on the N24. A
low humming sound was audible coming from the Waste Water
Treatment Plant across the road from Bulmer’s main site, discreet
warning alarms went off when the main gate of the facility was opening
and closing which rarely occurred, distant noise of occasional HGV
movements could be heard on-site.
Fitz Scientific Bulmers Showerings (C&C)Report
12/04/2012 night time NML01
12/04/2012 night time
If noise limits exceeded as a result of noise attributed to site activities, please choose the corrective action from the following options?
12/04/2012 night time
NML05
20
Resource Usage/Energy efficiency summary Lic No: P0443-01 Year 2012
Additional information
1 Yes - March 2012
2
SEAI - Large
Industry Energy
Network (LIEN) yes
Member of SEAI. Site
also accredited to IS
50001
3 n/a Nil
Energy Use Previous year Current year
Production +/- %
compared to
previous reporting
year**
Energy
Consumption +/- %
vs overall site
production* Comments
Total Energy Used (MWHrs) 27648 26302 minus 3.76 4.9
Total Energy Generated (MWHrs) 0 0 N/A N/A
Total Renewable Energy Generated (MWHrs) 0 0 N/A N/A
Electricity Consumption (MWHrs) 11137 9890 3.76 11.2
Fossil Fuels Consumption: 0 0 N/A N/A
Heavy Fuel Oil (m3) 139 N/A N/A
Light Fuel Oil (m3) 0 0 N/A
Natural gas (CMN) 16510 16411 3.76 0.6
Coal/Solid fuel (metric tonnes) 0 0 N/A N/A
Peat (metric tonnes) 0 0 N/A N/A
Renewable Biomass 0 0 N/A N/A
Renewable energy generated on
site 0 0 N/A N/A
* where consumption of energy can be compared to overall site production please enter this information as percentage increase or decrease compared to the previous reporting year.
** where site production information is available please enter percentage increase or decrease compared to previous year
Water Emissions Water Consumption
Water use Water extracted Previous year m3/yr. Water extracted Current year m3/yr.
Production +/- %
compared to
previous reporting
year**
Energy
Consumption +/- %
vs overall site
production*
Volume Discharged back to
environment(m3yr):
Volume used i.e not
discharged to
environment e.g.
released as steam
m3/yr Unaccounted for Water:
Groundwater 443508 486327 3.76 increase of 9.6% 285218 201109
Reduced water
consumption to 3.31
hectolitres of water used
per hectolitre (hl/hl ) of
product produced ,
significantly below the
recognised global brewing
benchmark of 4hl/hl
Surface water 0 0 N/A N/A
Not measured - not a
requirement of licence
Public supply 6358 8797 3.76 38%
approximately 80% of the water is used in
canteens & toilets
Town water used for
canteens, welfare facilities ,
Fire protection systems -
safety showers , sprinkler
systems , hydrants. Based
on financial year data ,
achieved a Town water
usage reduced by 14 % .
Leak detection and weekly
monitoring.
7599m3 used in 2012 v
8862m3 in 2011
Recycled water n/a n/a n/a n/a
Total 449866 495124
* where consumption of water can be compared to overall site production please enter this information as percentage increase or decrease compared to the previous reporting year.
** where site production information is available please enter percentage increase or decrease compared to previous year
When did the site carry out the most recent energy efficiency audit? Please list the recommendations in table 3 below
Is the site a member of any accredited programmes for reducing energy usage/water conservation such as the SEAI programme linked to the right? If yes please list them in
additional information
Where Fuel Oil is used in boilers on site is the sulphur content compliant with licence conditions? Please state percentage in additional information
Table R1 Energy usage on site
The reductions here are based on data
from calender year , site energy
performance is reviewed based on
financial year data ( march to fEB ) which
shows the following ; Gas – total gas
increased by 1.6% mainly due to increased
production volume / introduction of beer
bottling, reviewing KWHRS per HL, usage
increased by 3%.
• Total Electricity usage decreased by
9.5%. kwhrs / HL decrease of 8% on FY
11/12.☺
• .
• CO2 usage ( kg /hl ) reduced by 16%.
Table R2 Water usage on site
21
Resource Usage/Energy efficiency summary Lic No: P0443-01 Year 2012
Total Landfill Incineration Recycled Other comments
Hazardous (Tonnes)
Non-Hazardous (Tonnes) 1809.35 0 0 1809.35
It was all either
recycled or sent for
recovery (waste-to-
energy facilities).
Date of audit Recommendations Description of Measures proposed Origin of measures
Predicted energy
savings % Implementation date Responsibility Completion date
Status and
comments
10/11th May 2012
There are some issues with the Integrated
manual e.g. ;
a) Energy planning is not specifically
addressed.
b) Base line is not addressed.
c) Clause 4.4.5 EnPi’s is not specifically
addressed.
d) Section 4.2 does not reference clause 4.5.2
Competence awareness and training.
e) Design and procurement clauses are not
addressed.
There are some issues with the Integrated
Integrated manual reviewed in terms of recommendations in
column d
accredited
programme N/A Completed SHE manager completed closed
10/11th May 2012 Alert/alarm levels have not been set for EnPi’s recommendation included in Energy strategy for 2013
accredited
programme
indirectly - cannot
be measured Jun-13 area engineer 2013 open
10/11th May 2012
A measurement plan for significant users -
boilers , air compressors etc has not been
formalised recommendation included in Energy strategy for 2013
accredited
programme
indirectly - cannot
be measured Jun-13 area engineer 2013 open
10/11th May 2012
Overall verification/calibration of meters on
significant users has not been formalised. recommendation included in Energy strategy for 2014
accredited
programme N/A Jul-13 area engineer 2013 open
10/11th May 2012
The system element of the Internal EnMS
auditing process is not robust at present e.g.
Management representative is doing all the
audits. Energy Auditing now included in housekeeping audits completed by Quality.
accredited
programme N/A Completed SHE manager closed
10/11th May 2012
Procurement procedures do not specifically
address Energy and are in ‘Draft’ only.
Reference made to Energy and procedure approved
accredited
programme N/A Completed SHE manager closed
10/11th May 2013
How energy performance evaluation is taken
into account at the design stage of new,
modified and renovated facilities,
equipment, systems and processes that can
have a significant impact on Energy use, has
not been addressed. Change control process on Q pulse ensures an evaluation is completed
accredited
programme N/A Completed SHE manager closed
Table R5: Power Generation: Where power is generated onsite (e.g. power generation facilities/food and drink industry)please complete the following information
Unit ID Unit ID Unit ID Unit ID Station Total
Technology n/a n/a n/a n/a n/a
Primary Fuel n/a n/a n/a n/a n/a
Thermal Efficiency n/a n/a n/a n/a n/a
Unit Date of Commission n/a n/a n/a n/a n/a
Total Starts for year n/a n/a n/a n/a n/a
Total Running Time n/a n/a n/a n/a n/a
Total Electricity Generated (GWH) n/a n/a n/a n/a n/a
House Load (GWH) n/a n/a n/a n/a n/a
KWH per Litre of Process Water n/a n/a n/a n/a n/a
KWH per Litre of Total Water used on Siten/a n/a n/a n/a n/a
Table R3 Waste Stream Summary
Table R4: Energy Audit finding recommendations
22
Complaints and Incidents summary template Lic No: P0443-01 Year 2012
Additional information
No
Date Category
Other type (please
specify)
Brief description of
complaint (Free txt
<20 words)
Corrective action< 20
words
Resolution
status Resolution date
Further
information
SELECT SELECT
SELECT SELECT
SELECT SELECT
SELECT SELECT
SELECT SELECT
Total complaints
open at start of
reporting year 0Total new
complaints
received during
reporting year 0Total complaints
closed during
reporting year 0Balance of
complaints end of
reporting year 0
Additional information
No
What is an incident
Table 2 Incidents summary
Date of
occurrence Incident nature Location of occurrence
Incident
category*please refer
to guidance Receptor
Cause of
incident
Other
cause(please
specify)
Activity in
progress at time
of incident Communication Occurrence
Corrective
action<20 words
Preventative
action <20
words
Resolution
status
Resolution
date
Liklihood of
reoccurence
SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT
SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT
SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT
SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT
SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECT SELECTTotal number of
incidents current
year 0Total number of
incidents
previous year 0% reduction/
increase 0
*For information on how to report and what
constitutes an incident
Complaints
Have you received any environmental complaints in the current reporting year? If yes please complete
summary details of complaints received on site in table 1 below
Table 1 Complaints summary
Incidents
Have any incidents occurred on site in the current reporting year? Please list all incidents for current
reporting year in Table 2 below
23
WASTE SUMMARY Lic No: P0443-01 Year 2012
PRTR facility logon
Additional Information
1 No
2 No
3 No
Table 1 Details of waste accepted onto your site for recovery, disposal or treatment (do not include wastes generated at your site, as these will have been reported in your PRTR workbook)EWC code Description of waste
accepted
Please enter an
accurate and detailed
description - which
Quantity of waste
accepted in current
reporting year (tonnes)
Reason for
reduction/increase
from previous
reporting year
Packaging Content (%)-
only applies if the
waste has a packaging
component
European Waste Catalogue EWC
codes
European Waste
Catalogue EWC codes
4 SELECT
SELECT
5 SELECT
6 SELECT
7 Do you have an odour management system in place for your facility? If no why? SELECT
8 Do you maintain a sludge register on site? SELECT
Table 2 Waste type and tonnage-landfill only
Waste types permitted
for disposal
Authorised/licenced annual intake
for disposal (tpa)
Actual intake for disposal in
reporting year (tpa)
Remaining licensed
capacity at end of
reporting year (m3) Comments
Table 3 General information-Landfill only
Total disposal
area occupied by
waste
Lined disposal
area occupied by
waste
Unlined area
SELECT UNIT SELECT UNIT SELECT UNIT
Cell 8
Accepted asbestos in reporting
year
Comments on
liner type
Private or Public
OperatedInert or non-hazardous
Predicted date
to cease
landfilling
Licence permits
asbestos
Is there a separate cell
for asbestos?
SECTION D-TO BE COMPLETED BY LANDFILL SITES ONLY
Area ID Date landfilling commenced Date landfilling ceased Currently landfilling
Does your facility have relevant nuisance controls in place?
SECTION C-TO BE COMPLETED BY ALL WASTE FACILITIES (waste transfer stations, Composters, Material recovery facilities etc) EXCEPT LANDFILL SITES
Is all waste processing infrastructure as required by your licence and approved by the Agency in place? If no please list waste processing infrastructure required onsite
Is all waste storage infrastructure as required by your licence and approved by the Agency in place? If no please list waste storage infrastructure required on site
Reduction/Incr
ease over
previous year
+/ - %
Disposal/Recovery or
treatment operation carried out
at your site and the description
of this operation
Quantity of
waste
remaining on
site at the end
of reporting
year (tonnes)
Comments -
If yes please enter details in table 1 below
Did your site have any rejected consignments of waste in the current reporting year? If yes please give a brief explanation in the additional information
Was waste accepted onto your site that was generated outside the Republic of Ireland? If yes please state the quantity in tonnes in additional information
Licenced annual
tonnage limit for your
site (total
tonnes/annum)
Source of waste accepted Quantity of waste accepted in
previous reporting year (tonnes)
SECTION A-PRTR ON SITE WASTE TREATMENT AND WASTE TRANSFERS TAB- TO BE COMPLETED BY ALL IPPC AND WASTE FACILITIES dropdown list click to see options
SECTION B- WASTE ACCEPTED ONTO SITE-TO BE COMPLETED BY ALL IPPC AND WASTE FACILITIES
Were any wastes accepted onto your site for recovery or disposal or treatment prior to recovery or disposal within the boundaries of your facility ?; (waste generated within your
boundaries is to be captured through PRTR reporting)
24
WASTE SUMMARY Lic No: P0443-01 Year 2012
SECTION A-PRTR ON SITE WASTE TREATMENT AND WASTE TRANSFERS TAB- TO BE COMPLETED BY ALL IPPC AND WASTE FACILITIES dropdown list click to see optionsTable 4 Environmental monitoring-landfill onlyLandfill Manual-Monitoring Standards
Was meterological
monitoring in
compliance with
Landfill Directive (LD)
standard in reporting
year +
Was leachate monitored in
compliance with LD standard in
reporting year
Was Landfill Gas monitored in
compliance with LD standard in
reporting year
Was SW monitored in
compliance with LD
standard in reporting
year
Have GW trigger levels
been established
Were emission limit values agreed with
the Agency (ELVs)
Was
topography of
the site
surveyed in
reporting year
Has the statement
under S53(A)(5) of
WMA been
submitted in
reporting year Comments
.+ please refer to Landfill Manual linked above for relevant Landfill Directive monitoring standards
Table 5 Capping-Landfill only
Area uncapped* Area with temporary cap
SELECT UNIT SELECT UNIT
*please note this includes daily cover area
Table 6 Leachate-Landfill only9 Is leachate from your site treated in a Waste Water Treatment Plant? SELECT
10 Is leachate released to surface water? If yes please complete leachate mass load information below SELECT
Volume of leachate in
reporting year(m3)
Leachate (BOD) mass load
(kg/annum)
Leachate (COD) mass load
(kg/annum)
Leachate (NH4) mass
load (kg/annum)
Leachate (Chloride)
mass load kg/annum Leachate treatment on-site
Specify type of
leachate
treatment Comments
Table 7 Landfill Gas-Landfill only
Gas Captured&Treated
by LFG System m3 Power generated (MW / KWh) Used on-site or to national grid
Was surface emissions
monitoring performed
during the reporting
year? Comments
SELECT
Please ensure that all information reported in the landfill gas section is consistent with the Landfill Gas Survey submitted in conjunction with PRTR returns
Area with final cap to LD
Standard m2 ha, a Area capped other
Area with waste that
should be permanently
capped to date under
licence What materials are used in the cap Comments
Sheet : Facility ID Activities AER Returns Workbook 9/12/2014 16:5
| PRTR# : P0443 | Facility Name : Bulmers Limited | Filename : AER summary
TEMPLATES-v1 xls 2013 xls rev0.xlsm | Return Year : 2013 | 3102 09/12/2014 16:08
Guidance to completing the PRTR workbook
Version 1.1.18
REFERENCE YEAR 2013
1. FACILITY IDENTIFICATION
Parent Company Name Bulmers Limited
Facility Name Bulmers Limited
PRTR Identification Number P0443
Licence Number P0443-02
Waste or IPPC Classes of Activity
No. class_name
7.3.1
Brewing (including cider and perry production) in installations where
the production capacity exceeds 25 million litres per year, not
included in paragraph 7.8.
7.8(b)
vegetable raw materials with a finished product production capacity
greater than 300 tonnes per day (average value on a quarterly basis).
Address 1 Annerville
Address 2 Clonmel
Address 3 County Tipperary
Address 4
Tipperary
Country Ireland
Coordinates of Location -7.64725 52.3606
River Basin District IESE
NACE Code 1103
Main Economic Activity Manufacture of cider and other fruit wines
AER Returns Contact Name Suzanne Shine
AER Returns Contact Email Address [email protected]
AER Returns Contact Position SHE manager
AER Returns Contact Telephone Number 086 8160693
AER Returns Contact Mobile Phone Number 087 8160693
AER Returns Contact Fax Number 0526172280
Production Volume 1447351.0
Production Volume Units hectolitres
Number of Installations 1
Number of Operating Hours in Year 3760
Number of Employees 160
User Feedback/Comments
Web Address
2. PRTR CLASS ACTIVITIES
Activity Number Activity Name
50.1 General
8(b)(ii) Vegetable raw materials
3. SOLVENTS REGULATIONS (S.I. No. 543 of 2002)
Is it applicable? No
Have you been granted an exemption ? No
If applicable which activity class applies (as per
Schedule 2 of the regulations) ?
Is the reduction scheme compliance route being
used ?
4. WASTE IMPORTED/ACCEPTED ONTO SITE Guidance on waste imported/accepted onto site
Do you import/accept waste onto your site for on-
site treatment (either recovery or disposal
activities) ? No
This question is only applicable if you are an IPPC or Quarry site
AER Returns Workbook
| PRTR# : P0443 | Facility Name : Bulmers Limited | Filename : P0443_2013.xlsm | Return Year : 2013 | Page 1 of 10
4.1 RELEASES TO AIR Link to previous years emissions data | PRTR# : P0443 | Facility Name : Bulmers Limited | Filename : AER summary TEMPLATES-v1 xls 2013 xls rev0.xlsm | Return Year : 2013 | 09/12/2014 16:08
8 10 18 18 26 26 6 6 6 6 6 6 8
SECTION A : SECTOR SPECIFIC PRTR POLLUTANTS
Please enter all quantities in this section in KGs
QUANTITY
No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
11 Sulphur oxides (SOx/SO2) M EN 14791:2005 3512.0 3512.0 0.0 0.0
08 Nitrogen oxides (NOx/NO2) M EN 14792:2005 83974.0 83974.0 0.0 0.0
02 Carbon monoxide (CO) M EN 15058:2004 1405.3 1405.3 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
SECTION B : REMAINING PRTR POLLUTANTS
Please enter all quantities in this section in KGs
QUANTITY
No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
SECTION C : REMAINING POLLUTANT EMISSIONS (As required in your Licence)
Please enter all quantities in this section in KGs
QUANTITY
Pollutant No. Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
Additional Data Requested from Landfill operators
Landfill: Bulmers LimitedPlease enter summary data on the
quantities of methane flared and / or
utilised
additional_pollutant_no T (Total) kg/Year M/C/E Method Code
Designation or
Description
Facility Total Capacity
m3 per hour
Total estimated methane generation (as per
site model) 0.0 N/A
Methane flared 0.0 0.0 (Total Flaring Capacity)
Methane utilised in engine/s 0.0 0.0 (Total Utilising Capacity)
Net methane emission (as reported in Section
A above) 0.0 N/A
Method Used
For the purposes of the National Inventory on Greenhouse Gases, landfill operators are requested to provide summary data on landfill gas (Methane)
flared or utilised on their facilities to accompany the figures for total methane generated. Operators should only report their Net methane (CH4) emission
to the environment under T(total) KG/yr for Section A: Sector specific PRTR pollutants above. Please complete the table below:
Method Used
Method Used
RELEASES TO AIR
POLLUTANT METHOD
Method Used
POLLUTANT
RELEASES TO AIR
RELEASES TO AIR
METHOD
POLLUTANT METHOD
4.3 RELEASES TO WASTEWATER OR SEWER Link to previous years emissions data | PRTR# : P0443 | Facility Name : Bulmers Limited | Filename : AER summary TEMPLATES-v1 xls 2013 xls rev0.xlsm | Return Year : 2013 |09/12/2014 16:08
8 8 16 23 6 6 6 6 0
SECTION A : PRTR POLLUTANTS
Please enter all quantities in this section in KGs
QUANTITY
No. Annex II Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
0.0 0.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
SECTION B : REMAINING POLLUTANT EMISSIONS (as required in your Licence)
Please enter all quantities in this section in KGs
QUANTITY
Pollutant No. Name M/C/E Method Code Designation or Description Emission Point 1 T (Total) KG/Year A (Accidental) KG/Year F (Fugitive) KG/Year
240 Suspended Solids M MAB 60866.0 60866.0 0.0 0.0
303 BOD M CRM 61549.0 61549.0 0.0 0.0
238 Ammonia (as N) M CRM 1788.0 1788.0 0.0 0.0
308 Detergents (as MBAS) M CRM 71.69 71.69 0.0 0.0
314 Fats, Oils and Greases M CRM 3788.0 3788.0 0.0 0.0
343 Sulphate M CRM 3565.0 3565.0 0.0 0.0
347 Total heavy metals M CRM 1.72 1.72 0.0 0.0
387 Ortho-phosphate (as P) M CRM 336.0 336.0 0.0 0.0
* Select a row by double-clicking on the Pollutant Name (Column B) then click the delete button
OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER
OFFSITE TRANSFER OF POLLUTANTS DESTINED FOR WASTE-WATER TREATMENT OR SEWER
Method Used
Method Used
POLLUTANT METHOD
POLLUTANT METHOD
5. ONSITE TREATMENT & OFFSITE TRANSFERS OF WASTE | PRTR# : P0443 | Facility Name : Bulmers Limited | Filename : AER summary TEMPLATES-v1 xls 2013 xls rev0.xlsm | Return Year : 2013 | 09/12/2014 16:08
5 29 Please enter all quantities on this sheet in Tonnes 29
Quantity
(Tonnes per
Year)
Haz Waste : Name and
Licence/Permit No of Next
Destination Facility Non
Haz Waste: Name and
Licence/Permit No of
Recover/Disposer
Haz Waste : Address of Next
Destination Facility
Non Haz Waste: Address of
Recover/Disposer
Name and License / Permit No. and
Address of Final Recoverer /
Disposer (HAZARDOUS WASTE
ONLY)
Actual Address of Final Destination
i.e. Final Recovery / Disposal Site
(HAZARDOUS WASTE ONLY)
Transfer Destination
European Waste
Code Hazardous Quanti ty T/Year Description of Waste
Waste
Treatment
Operation M/C/E Method Used
Location of
Treatment Nam e and L ic enc e / Perm i t No. o f Rec ov erer / Dis pos er / Brok er Addres s of Rec ov erer / Dis pos er / Brok er Nam e and Addres s of Fina l Des tination i .e . Fina l Rec ov ery / Dis pos al Si te (HAZARDOUS WASTE ONLY) Lic enc e / Perm i t No. o f Fina l Des tination i .e . Fina l Rec ov ery / Dis pos al Si te (HAZARDOUS WASTE ONLY)
Within the Country 02 03 01 No 14.92
sludges from washing, cleaning, peeling,
centrifuging and separation R10 M Weighed Offsite in Ireland
KCD Farm Relief ,WCP
/KK/10/438/02 BNM 198 -
1
Cillin Hill / Bord Na Mona
PLc ,Dublin Road / Kilberry
,Kilkenny,Kilkenny,Ireland
Within the Country 02 07 05 No 451.72 sludges from on-site effluent treatment R10 M Weighed Offsite in Ireland
KCD Farm Relief ,WCP
/KK/10/438/02 BNM 198 -
1
Cillin Hill / Bord Na Mona
PLc ,Dublin Road / Kilberry
,Kilkenny,Kilkenny,Ireland
Within the Country 13 02 06 Yes 1.905 synthetic engine, gear and lubricating oils R9 M Weighed Offsite in Ireland
Enva Ireland ,WCP DC 08
1116 01
Clonminam Industrial Estate
,Port laoise ,Co Laois ,Co
Laois ,Ireland
Enva Ireland Ltd ,Licence
WO184 1 Collection Permit
WCP dc 1116 01 ,Clonm
inam Industtrial Estate
,Clonm inam Industtrial
Estate ,portlaoise ,portlaoise
,Ireland
Clonm inam Industtrial
Estate ,Clonm inam
Industtrial Estate ,portlaoise
,portlaoise ,Ireland
Within the Country 15 01 01 No 117.92 paper and cardboard packaging R12 M Weighed Offsite in Ireland
Clonmel waste Disposal
,WFP - TS - 11 -0001 -01
Clonmel ,Co Tipperary ,Co
Tipperary ,Co Tipperary ,Co
Tipperary
Within the Country 15 01 07 No 791.62 glass packaging R12 M Weighed Offsite in Ireland
Clonmel waste Disposal
,WFP - TS - 11 -0001 -01
Clonmel ,Co Tipperary ,Co
Tipperary ,Co Tipperary ,Co
Tipperary
To Other Countries 15 01 10 Yes 0.03
packaging containing residues of or
contaminated by dangerous substances D10 M Weighed Abroad
Enva Ireland ,WCP DC 08
1116 01
Clonminam Industrial Estate
,Port laoise ,Co Laois ,Co
Laois ,Ireland
Lindenschmidt KG
Umweltservice,04 714
98089,Krombacher
Strabe,42 - 46
,57223,Kreuztal,Germany
Krombacher Strabe,42 -
46,57223,Kreuztal,Germany
Within the Country 16 06 04 No 0.025 alkaline batteries (except 16 06 03) R8 M Weighed Offsite in Ireland
Rilta Environmental ,WCP
DC 12 1192 01
block 402 Grants Drive
,Grenogue Business Park
,Rathcoole ,Dublin ,Ireland
HJ Enthoven & Sons
,BL5598,South Darley
Matlock ,South Darley
Matlock ,Derbeyshire ,GB
DE 4 2LP ,United Kingdom
South Darley Matlock
,South Darley Matlock
,Derbeyshire ,GB DE 4 2LP
,United Kingdom
Within the Country 17 02 01 No 14.5 wood R3 M Weighed Offsite in Ireland
Clonmel waste Disposal
,WFP - TS - 11 -0001 -01
Clonmel ,Co Tipperary ,Co
Tipperary ,Co Tipperary ,Co
Tipperary
Within the Country 17 04 07 No 145.9 mixed metals R4 M Weighed Offsite in Ireland
Clonmel waste Disposal
,WFP - TS - 11 -0001 -01
Clonmel ,Co Tipperary ,Co
Tipperary ,Co Tipperary ,Co
Tipperary
Within the Country 20 01 08 No 14.15 biodegradable kitchen and canteen waste R1 M Weighed Offsite in Ireland
Clonmel waste Disposal
,WFP - TS - 11 -0001 -01
Clonmel ,Co Tipperary ,Co
Tipperary ,Co Tipperary ,Co
Tipperary
Within the Country 20 01 21 Yes 0.87
fluorescent tubes and other mercury-
containing waste R9 M Weighed Offsite in Ireland
Irish Lamp Recycling ,WCP
DC 08 1115 01 Facility
permit WCP : KE 08 0348 01
Woodstock Industrial Estate
,Kilkenny Road ,Athy
,Kildare ,Ireland
Irish Lamps Recycling and
Recovery Services Ltd,WFP-
KE-08-0348-01,Woodstock
Industrial Estate,Athy
,Co.Kildare,.,Ireland
Woodstock Industrial
Estate,Athy
,Co.Kildare,.,Ireland
Within the Country 20 01 35 Yes 2.467
discarded electrical and electronic
equipment other than those mentioned in
20 01 21 and and 20 01 23 containing
hazardous components R12 M Weighed Offsite in Ireland
Rehab Enterprises Limited
T/A Rehab Recycle ,Rehab
Group Mutli - Region Waste
Collection Permit – WCP-DC-
10-1257-01
Rehab Cork Waste
Management Permit –
03/10a
Roslyn Park
,Sandymount,Dublin
4,Dublin 4,Ireland
KMK Metals Recycling
Limited ,113 - 2 ,Cappincur
Industrial Estate ,Daingean
Road ,Tullamore ,Co Offaly
,Ireland
Cappincur Industrial Estate
,Daingean Road ,Tullamore
,Co Offaly ,ireland
Within the Country 20 01 38 No 0.0 wood other than that mentioned in 20 01 37 R3 M Weighed Offsite in Ireland
Clonmel waste Disposal
,WFP - TS - 11 -0001 -01
Clonmel ,Co Tipperary ,Co
Tipperary ,Co Tipperary ,Co
Tipperary
Within the Country 20 01 39 No 97.49 plastics R3 M Weighed Offsite in Ireland
Clonmel waste Disposal
,WFP - TS - 11 -0001 -01
Clonmel ,Co Tipperary ,Co
Tipperary ,Co Tipperary ,Co
Tipperary
Within the Country 20 01 40 No 0.0 metals R4 M Weighed Offsite in Ireland
Clonmel waste Disposal
,WFP - TS - 11 -0001 -01
Clonmel ,Co Tipperary ,Co
Tipperary ,Co Tipperary ,Co
Tipperary
Within the Country 20 03 01 No 156.22 mixed municipal waste D1 M Weighed Offsite in Ireland
Clonmel waste Disposal
,WFP - TS - 11 -0001 -01
Clonmel ,Co Tipperary ,Co
Tipperary ,Co Tipperary ,Co
Tipperary
To Other Countries 08 03 12 Yes 6.0 waste ink containing dangerous substances R1 M Weighed Abroad
Enva Ireland Ltd ,WTF
Number : TS000839
Smithstown Industrial Estate
,Shannon ,Co Clare ,Co
Clare ,Ireland
Lindenschmidt KG
Umweltservice,04 714
98089,Krombacher
Strabe,42 - 46
,57223,Kreuztal,Germany
Krombacher Strabe,42 -
46,57223,Kreuztal,Germany
To Other Countries 13 02 08 Yes 161.0 other engine, gear and lubricating oils R1 M Weighed Abroad
Enva Ireland Ltd ,WTF
Number : TS000839
Smithstown Industrial Estate
,Shannon ,Co Clare ,Co
Clare ,Ireland
Lindenschmidt KG
Umweltservice,04 714
98089,Krombacher
Strabe,42 - 46
,57223,Kreuztal,Germany
Krombacher Strabe,42 -
46,57223,Kreuztal,Germany
To Other Countries 13 07 01 Yes 7.0 fuel oil and diesel R1 M Weighed Abroad
Enva Ireland Ltd ,WTF
Number : TS000839
Smithstown Industrial Estate
,Shannon ,Co Clare ,Co
Clare ,Ireland
Lindenschmidt KG
Umweltservice,04 714
98089,Krombacher
Strabe,42 - 46
,57223,Kreuztal,Germany
Krombacher Strabe,42 -
46,57223,Kreuztal,Germany
To Other Countries 15 01 10 Yes 0.03
packaging containing residues of or
contaminated by dangerous substances R1 M Weighed Abroad
Enva Ireland Ltd ,WTF
Number : TS000839
Smithstown Industrial Estate
,Shannon ,Co Clare ,Co
Clare ,Ireland
Lindenschmidt KG
Umweltservice,04 714
98089,Krombacher
Strabe,42 - 46
,57223,Kreuztal,Germany
Krombacher Strabe,42 -
46,57223,Kreuztal,Germany
To Other Countries 16 05 06 Yes 0.115
laboratory chemicals, consisting of or
containing dangerous substances,
including mixtures of laboratory chemicals R1 M Weighed Abroad
Enva Ireland Ltd ,WTF
Number : TS000839
Smithstown Industrial Estate
,Shannon ,Co Clare ,Co
Clare ,Ireland
Lindenschmidt KG
Umweltservice,04 714
98089,Krombacher
Strabe,42 - 46
,57223,Kreuztal,Germany
Krombacher Strabe,42 -
46,57223,Kreuztal,Germany
Within the Country 15 01 05 No 99.0 composite packaging R12 M Weighed Offsite in Ireland
Freight team Ireland ,wcp
001
Promenade Road ,Dublin
Port ,Dublin ,Dublin ,ireland
Within the Country 20 01 25 No 0.465 edible oil and fat R1 M Weighed Offsite in Ireland
Frylite Cork GB Business
park Little Island Cork
,WFP - CK -11 - 0092 -01 LN
11/63
fRylite Headoffice ,Orchard
Road Ind Est ,Strabane ,Co
Tyrone ,Ireland
* Select a row by double-clicking the Description of Waste then click the delete button
Link to previous years waste data
Link to previous years waste summary data & percentage change
Link to Waste Guidance
Method Used