FANSHAWE WALKWAY By Project Revolutions

• Sameer B.

• Michael W. Mandeep

K.• Bhushan C. • Zohaib M.

Work Breakdown Structure

PROJECT OVERVIEW REPORT

PENDING WORK

STATUS INDICATION

Parameters Status Indicator

Cost

Schedule

Scope

CriteriaCost / Schedule / Scope is not satisfiedFacing some problem / Delay in scheduleAll parameters are satisfied

OVERALL STATUS• Cost Overrun of the project by CAD 180,220• Reasons behind cost overrun : -

- Change in project plan during execution phase. 33,698 CAD- Modified control phase of project, by implementing risk assessment and control

40,128 CAD

- Replaced all general workers by skilled construction workers.

26,570 CAD

- Increase number of manpower to speed up the activities.

68,236 CAD

- Minor expenses that includes daily expenses, transportation costs, material costs etc.

Around 16,000 to 18,000 CAD