STATUS INDICATION
Parameters Status Indicator
Cost
Schedule
Scope
CriteriaCost / Schedule / Scope is not satisfiedFacing some problem / Delay in scheduleAll parameters are satisfied
OVERALL STATUS• Cost Overrun of the project by CAD 180,220• Reasons behind cost overrun : -
- Change in project plan during execution phase. 33,698 CAD- Modified control phase of project, by implementing risk assessment and control
40,128 CAD
- Replaced all general workers by skilled construction workers.
26,570 CAD
- Increase number of manpower to speed up the activities.
68,236 CAD
- Minor expenses that includes daily expenses, transportation costs, material costs etc.
Around 16,000 to 18,000 CAD