Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
Daniel Fielder
Design Engineer
FAST INTERVENTION TOOL
Webtool hydraulic cutters and systems
Tangye hydraulic jacks and lifting equipment
Millingford sub-surface sucker rod pumps
Kopp speed Variators
Blake Hydram self powered pump
Webtool specialist projects
Pontoon Bridge decommissioning tool
Cable retrieval tool TALOS energy emergency winch cutter
IWOCS emergency disconnection tool
Sellafield pond decommissioning
Portable Electro-Hydraulic power pack
FIT (Fast Intervention Tool)
Rigid Flowline
Offshore wells and Fields
• In the UK alone there are over 12,000 offshore wells.
• The global network of oil fields is in excess of 65,000.
• The largest oil field producing in excess of 30 billion barrels
• Pipes ranging from 3” to 16” in diameter and many kilometres long.
• Usually made of carbon steel or high specification alloys with corrosion resistant coatings.
Imag
e co
urt
esy
of
OG
A a
s o
f 2
01
8
https://www.ogauthority.co.uk/data-centre/interactive-maps-and-tools/
Decommissioning a Growing Industry
Forecast from Oil & Gas UK
• Oil fields are being abandoned at an increasing rate. Thus the demand for products that aid the decommissioning process will rise.
• Different regions have varying regulations on the abandonment and decommissioning of the fields Image courtesy of OGA as of 2018
https://oilandgasuk.cld.bz/Decommissioning-Insight-2018/26/#zoom=z
Decommissioning Expenditure
Offshore expenditure in the future
The estimated expenditure for removing subsea pipes and infrastructure accounts to around 12% of the total cost decommissioning.
State of Pipe Once Abandoned
Decommissioning the Pipe
Hazardous live product, residue and scale are the remaining contaminants left inside the pipe once it has been shut off.
Decommissioning Preparation
Pigging
This process consists of scraping the insides of the pipe using a billet/ “pig”. To do this the pig is loaded in one end of the pipeline, then the pipe is sealed to create a vacuum.
A suitable gas is pumped in behind the pig to project it down the pipeline and scrape away the residue.
https://www.e-education.psu.edu/marcellus/node/684
Current Removal Method
Image courtesy of Chevron
Webtool Fast Intervention Tool
Injector
Diver Handles
Crimper
Deployment Shackles
Spiker
Cutter
Crimper
Lifter
Lifter
Accumulator
How Does it Seal the Pipe?
The stages for the FIT are as follows:- • The pipe is lifted from the sea bed • The crimps squeeze the pipe closed to create a cavity • The spike pierces the pipe between the crimps • The injector fills the cavity with the sealant • The cutter splits the pipe, thus creating another crimped point
Crimp Crimp Cut Injection
Sealant Sealant
FIT Benefits
A single tool
Easy positioning
No leakage
Quick and easy
Multiple uses
The sealant is non toxic
Different pipe materials
Modular design
Current stage
10/5/19 Sea trails
14/2/19 Ready for
further testing
12/2/19 System
integration test
Complete to final testing
iteration
15/12/18 Test and
Chevron Visit
13/12/18 Complete
manufacture for testing purposes
27/8/18 Design
approval
Testing
A leak test has been performed up to 75 bar. This is to see if any water could be forced past the sealant (to resemble sub sea pressure). The test was a success as there wasn’t a single drop of water that passed through.
Future for the FIT
The FIT prototype has been designed to accommodate the X65 - 4.5” pipe. Once all tests have been approved work will begin on:- • Design and manufacture on the final iteration • Acceptance of varying sizes of pipe • Separating the modules to for other uses • Optimisation of the size of the assembly and weight • Automated control system • Other features • Deeper achievable depths
Offshore trials Q2 2019. Prototype project completion date, June 2019
Summary slide
Daniel Fielder, Design Engineer, Allspeeds Ltd (Webtool)
Email: [email protected]
www.allspeeds.co.uk
Any questions?
Thanks for listening Come and visit us at Stand 124