Feb 2011 AIM FRB Feb 2011 AIM FRB Action Item ReviewAction Item Review
23 Aug 11
Jake Aplanalp, AIM Pgm Mgr
AI ID POC Issue Action Status
166Roy Hoyt/
Leslie Desenburg
FRB assigned to review FEA/BCA white papers on initial requirements for CPM implementation
Ensure 137 and other NETC policy/process documents available to SYSCOMs (e.g., SPAWAR) for review and comment
CLOSED: verified at 18 May briefing.
167 Jake/AIM teamFRB placed high priority on implementation of LP/TG portion marking for AIM II/I
Provide a ROM to Roy Hoyt for implementation of LP/TG portion marking, including basic implementation for print / PDF output products and option for full database implementation for XML data output
CLOSED: included in first software modification Task Order under new AIMEREON support contract
168 Jake/AIM teamMike Clifford concerned that new AIM II Chg Pkg function may not produce a List of Effective Elements (LOEE)
Verify that LOEE is included in the new AIM II change pkg
CLOSED: included in AIM II/LO Module Rel 5.0.
169 Ron/AIM teamFRB members recommended a thorough review and prioritization of ACRs presented at this week's mtg
Clean up list of ACRs and issue to FRB for review, comment, and potentially voting after this meeting
CLOSED: Jake distributed Ron's final listing to FRB on 8 Mar.
170Angel Strong/
IPT
Re-invigorate AIM-to-CeTARS IPT to wring out detailed functional reqts and develop recommendation for AIM and CeTARS teams to program
Chair working group to analyze additional AIM-to-CeTARS CMS interface functionality as well as other data exchange possibilities if time permits and report to NETC N74 - Kim Blalock, Roy Wilde (CSF), SLC, Dave Donnelly (CSFE)
CLOSED: included in first software modification Task Order under new AIMEREON support contract
171Jake/
AIM teamBased on FRB review of ACRs at 15-17 Feb meeting
Generate ROM CMS intra-day period sequencing (ACR 156) and inform FRB for review and prioritization
CLOSED: Will be addressed as part of CMS enhancement ACR to be funded under new contract in Aug 11.
172Jake/
AIM teamSupport FRB review of FEA/BCA design documents distributed at FRB meeting
Distribute draft NETC 20-category Likert scale model document to FRB to support their review of FEA white paper
CLOSED: Jake/Ron distributed to FRB..
173 FRBFRB to review white papers distributed at the meeting
Review FEA/BCA white papers per FRB discussion and provide comments to AIM team and NETC N74
CLOSED: FEA prototype in final development for NETC N7 and user community review.
174Rick Bly(CPPD)
Need to incorporate some user-proven functions in AIM I/II into CPM/LO Module
Develop white paper on the convergence of AIM II functionality into CPM/LO Module; e.g., reuse whole learning site data pkg (CMS and RRL) and tailor that copy vs. having to manually re-enter the subordinate data
OPEN.
175Ron Zinnato/
AIM teamCNE has been experiencing data corruption problems with current configuration
Talk to CNE staff about implementing SQL Server database
CLOSED: CNE scheduled for AIM II Central Site instance at NETPDTC.
176Jake/
AIM team
SWS team needs several additional functions carried forward from AIM I to LO Module to support MT Continuum
Develop a ROM for implementation of No-change Change and Link to Later IETM functions in LO Module
OPEN: on ACR list for prioritization at Aug meeting; not yet funded.
177Jake/Ron
NAVMED indicated strong interest in having a NETPDTC-hosted Central Site AIM II instance
Coordinate with Leo Grassi (NAVMED), Lisa Wade (NAVRES), Karen Pohl (NSWC), and Peg David (NETPDTC) about non-NETC Central Site hosting
OPEN: Jake and Ron to discuss with NAVMED team at Aug meeting.
178Jake/
AIM teamNeed better method of routing ACRs for FRB review, comment, and prioritization
Socialize Serena functionality for document routing/comment/approval with Leslie Desenburg
OPEN: Ron Zinnato to discuss ACR distro/statusing at Aug meeting.
179Jerry Benzel/Ron Zinnato
Submarine community has a unique requirement for hosting their AIM content and supporting documents
Lead working group on centralized hosting of NOFORN data, develop implementation options, and report to AIM PM and NETC N74
OPEN: RIS developed and submitted to NETPDTC. Still in review; to be discussed at Aug meeting.
180Denise Green/Jerry Marino
CPM needs to integrate other job-task analysis model data into current JDTA tab
Lead working group to explore migration of MTL, SPAWAR JTA, and other job-task data into CPM JDTA, develop implementation options, and report to AIM PM and NETC N74
OPEN: Jamie Stewart coordinating discussion / prototyping with SPAWAR and CNATT.
181Jake/Ron/
Tiffany
FRB is very interested in getting more frequent status information about pending ACRs
Define mechanism and frequency for communicating ACR status to the FRB and determine resolution of NMCI-related issues with Bugzilla
OPEN: Ron Zinnato to discuss ACR distro/statusing at Aug meeting.
182Jake/
AIM team
Implementation of FEA/BCA support in CPM is an urgent requirement for NETC N74
Develop a ROM for implementation of FEA/BCA functions in CPM, based on NETC N7-approved functional requirements with FRB feedback
OPEN: FEA prototype ready shortly for NETC N7 and community review.