2
(construction and fit out) (2018 exc. GST both buildings) Litecrete precast concrete cladding panels, Litecrete precast concrete planters, prestressed flooring ribs, timber pre-nail wall frames & trusses by PlaceMakers (PrefabNZ Member) PROJECT CHALLENGES Real Living Group is the owner-operator of The Oaks Retirement Village in Warkworth. The clients desired a robust cladding system that would give the two Oaks buildings a sense of permanence. The external building envelope was required to be attractive, safe, weathertight, durable and low maintenance. The primary criteria for success was to develop a robust, buildable structure that complied with the New Zealand Building Code. The basement of the project was almost the full footprint of the site and limited large vehicle access. Heavy trucks were also restricted on site due to the stringent controls on ground-movement that concerned the proximity of neighbouring buildings. As a result, one loading bay was established on Neville Street, the only other site accessible Street, that took up eight car parks and was managed by a gateman. The basement level of the design sat below the site’s very high water table and high water inflows. A top-down construction methodology was used to overcome this issue. This meant the ground floor and foundation piles were constructed before the excavation for the basement. Cut-off piles were used to form perimeter basement walls to stabilise the site and support the neighbouring buildings. To reduce the overall construction time, work commenced on the superstructure as excavation for the basement proceeded. The very weak soil and high water table meant the structures weight was limited. The cladding, therefore, needed to be light-weight as well as meeting the design requirements of the project. Precast Litecrete panels met these factors and were the predominant cladding material. The panels are manufactured from local pumice aggregate which is 40% lighter than standard precast concrete. This reduced the beam and foundation loads which allowed for considerable savings in both buildings’ weight and cost. The Litecrete panel thickness was designed for insulation, fire-rating and durability requirements of the New Zealand Building Code (NZBC). The panels allowed for quick installation and enclosing of both buildings. This meant internal fit-outs could proceed quickly and assist in meeting the timeframe. Client: Real Living Group Kalmar Construction Ltd Morconsult Ltd Kalmar Construction / Harbour Construction Litecrete / Wilco Brown Day Group 8000m² both buildings Component + Panel Contractor: Architect: Floor Area: Prefab Type: Prefab Materials Used: Structural Engineer: Builder: Supplier: Completed September 2018 Status: February 2019 HOW to Prefab 2018 Queen Street Warkworth Auckland The Oaks Retirement village The Oaks Project expresses the benefits of lightweight precast concrete panels when building on a site with a high water table and low weight restriction. Litecrete offers the appearance of traditional concrete but allows for a lighter structure and a safer build. PROJECT INTENT COST (NZD) 40M 30M 50M 60M 18m 20m 22m 24m 26m TIME (months) The Oaks Retirement Village

February 2019 HOW to Prefab The Oaks Retirement village · 2019. 3. 25. · The Oaks is the largest retirement village that has used precast concrete panels in Warkworth. On completion,

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • (construction and fit out)(2018 exc. GST both buildings)

    Litecrete precast concrete cladding panels, Litecrete precast concrete planters, prestressed flooring ribs, timber pre-nail wall frames & trusses by PlaceMakers (PrefabNZ Member)

    PROJECT CHALLENGES

    Real Living Group is the owner-operator of The Oaks Retirement Village in Warkworth. The clients desired a robust cladding system that would give the two Oaks buildings a sense of permanence. The external building envelope was required to be attractive, safe, weathertight, durable and low maintenance. The primary criteria for success was to develop a robust, buildable structure that complied with the New Zealand Building Code.

    The basement of the project was almost the full footprint of the site and limited large vehicle access. Heavy trucks were also restricted on site due to the stringent controls on ground-movement that concerned the proximity of neighbouring buildings. As a result, one loading bay was established on Neville Street, the only other site accessible Street, that took up eight car parks and was managed by a gateman.

    The basement level of the design sat below the site’s very high water table and high water inflows. A top-down construction methodology was used to overcome this issue.

    This meant the ground floor and foundation piles were constructed before the excavation for the basement. Cut-off piles were used to form perimeter basement walls to stabilise the site and support the neighbouring buildings. To reduce the overall construction time, work commenced on the superstructure as excavation for the basement proceeded.

    The very weak soil and high water table meant the structures weight was limited. The cladding, therefore, needed to be light-weight as well as meeting the design requirements of the project. Precast Litecrete panels met these factors and were the predominant cladding material. The panels are manufactured from local pumice aggregate which is 40% lighter than standard precast concrete. This reduced the beam and foundation loads which allowed for considerable savings in both buildings’ weight and cost.

    The Litecrete panel thickness was designed for insulation, fire-rating and durability requirements of the New Zealand Building Code (NZBC). The panels allowed for quick installation and enclosing of both buildings. This meant internal fit-outs could proceed quickly and assist in meeting the timeframe.

    Client: Real Living Group

    Kalmar Construction Ltd

    Morconsult Ltd

    Kalmar Construction / Harbour Construction

    Litecrete / Wilco

    Brown Day Group

    8000m² both buildings

    Component + Panel

    Contractor:

    Architect:

    Floor Area:

    Prefab Type:

    Prefab Materials Used:

    Structural Engineer:

    Builder:

    Supplier:

    Completed September 2018

    Status:

    February 2019 HOW to Prefab

    2018Queen StreetWarkworthAuckland

    The Oaks Retirement villageThe Oaks Project expresses the benefits of lightweight precast concrete panels when building on a site with a high water table and low weight restriction. Litecrete offers the appearance of traditional concrete but allows for a lighter structure and a safer build.

    PROJECT INTENT

    COST (NZD)40M30M 50M 60M 18m 20m 22m 24m 26m

    TIME (months)

    The Oaks Retirement Village

  • The main structure comprised of mild-steel frames, in-situ concrete shear walls, and Rib and Timber Infill concrete floor diaphragms. These structural elements were designed to give the most compact floor-to-beam depth with sufficient strength and stiffness to resist seismic induced loads.

    A lot of planning time was spent exploring options to visually break up the facade while creating as many similar panels and therefore fewer precast molds for maximum production efficiency and minimal cost.

    The Litecrete cladding panels were 150mm thick and covered a two-level height on the building’s exterior. The units were fixed at each corner to the adjacent floor structure with structural steel brackets. It took approximately two days to clad one floor of each building. In comparison to an in-situ methodology, the use of precast panels saved many weeks.

    Precast Litecrete planter boxes were also developed to hang off the structure at level one. The planter boxes were lifted by crane and welded into place, approximately one hour was spent on each unit. Time efficiencies were created by Kalmar Construction by lifting the boxes onto formwork by crane and moved into place by hand. This allowed the crane to be used elsewhere on the project, speeding up the project timeline.

    The Oaks is the largest retirement village that has used precast concrete panels in Warkworth. On completion, the developer held several open days, each attracting up to 800 people. The residents of The Oaks say they love their new home and the facilities it houses.

    All prefabricated elements were delivered to site on a flat-deck truck. A tower crane was used to lift each panel into position and all of the fixing work was carried out from inside the building before the crane hook was released. Prefabrication was, therefore, safer and allowed for higher quality control which resulted in the desired facade.

    The use of precast panels meant fewer trades were required to construct the building’s envelope, decreasing on-site labour and increasing cost efficiencies.

    MATERIAL

    DELIVERY / ASSEMBLY

    FEEDBACK

    The Oaks living room space

    Litecrete panels being lifted by crane into position

    The Oaks under construction

    HOW to PrefabThe Oaks Retirement Village

    REFERENCES

    Tim Ellery (Kalmar Construction Ltd). Personal Communication with Eleni Timoteo. January, 2019.

    Andrew Mortimer (Morconsult Ltd). Personal Communication with Eleni Timoteo. January, 2019.

    Images: Courtesy of Kalmar Construction Ltd For more information on this project visit:realliving.co.nz

    prefabnz.com