Fieldwork 4(Final)

Embed Size (px)

Citation preview

  • 8/10/2019 Fieldwork 4(Final)

    1/15

    Mapua Institute of Technology

    ADVANCED SURVEYING FIELD MANUAL

    FIELDWORK NO. 4

    Laying of a Simple Curve on Uneven Ground Using

    Transit and Theodolite

    (Double-Deflection Angle Method)

  • 8/10/2019 Fieldwork 4(Final)

    2/15

    GROUP NO. 4 CHIEF OF PARTY/LEADER: EUGENIO, Jason

    MEMBERS:

    DULAY, Anthony Mark V. GARCIA, Julienne

    ESTAVILLO, Kyle GATCHALIAN, Kenneth

    FIELD WORK NO.3

    LAYING OF A SIMPLE CURVE ON UNEVEN GROUND USING TRANSIT

    AND THEODOLITE (DOUBLE-DEFLECTION ANGLE METHOD)

    OBJECTIVE:

    1. To be able to lay a simple curve on uneven ground.

    2. To be able to lay a simple curve using double-deflection angle method.

    3. To master the use of the transit and theodolite in laying a simple curve.

    INSTRUMENTS:

  • 8/10/2019 Fieldwork 4(Final)

    3/15

    PROCEDURE:

    1. The Professor gives the following data:

    d1 = 0.11

    D = 2.5

    d2 = 1.39

    Location of PC on the site (Note location and not station is now given since d1and d2are

    given.)

    GIVEN: I=d1+6D+d2= (Simple curve with 6 intermediate points.)

    NOTE: Be very careful in assigning the location of PC and the direction of the backward tangent

    so that the curve will not obstructed by any structure.

    VERY IMPORTANT: Before going to the field the student must compute:a. Angle of Intersection I = 49

    b. Total deflection angle I / 2 = 24.5

    c. Length of the long chord C = 380.16

    d. Half d1 d1/ 2 = 0.055

    e. Half d2 d2/ 2 = 0.695

    f. Half D D / 2 = 1.25

  • 8/10/2019 Fieldwork 4(Final)

    4/15

    2.4Loosen the upper clamp and turn the telescope until the reading on vernier equals the

    magnitude of the total deflection angle of the curve. Along this line and with a distance

    equal to the length of the long chord from PC locate the position of PT.

    2.5Set the theodolite on the exact position of PT.

    2.6Level the theodolite and set the horizontal vernier to zero while sighting PC.

    3. To locate the first intermediate point A in the curve mark on the ground the intersection of theline of sight in both instruments with a reading equal to

    .(Note that the first instruments

    reading is referred from the back tangent while the second instruments reading is referred

    from the long chord.)

    4. The next intermediate point B may be located on the ground using the same procedure as in

    step 8, but this time use a reading equal to (d

    .

    5. The third intermediate point C may also be found following the same processes, but now use a

    reading in the horizontal vernier equal to (d

    .

    6 Continue the process to locate other intermediate points on the curve with a gradual increase

  • 8/10/2019 Fieldwork 4(Final)

    5/15

    FINAL DATA SHEET

    FIELD WORK 3 LAYING OF A SIMPLE CURVE ON UNEVEN GROUND USINGF THEODOLITE

    (DOUBLE-DEFLECTION ANGLE METHOD)

    DATE: 11/05/14 GROUP NO.: 5

    TIME: 02:00 PM LOCATION: MIT South Parking

    WEATHER: Cloudy PROFESSOR: Engr. B.Cervantes

    DATA SUPPLIED:

    d1 = 0.11

    D = 2.5

    d2 = 1.39

    Adopt full chord length of 2 m

    GIVEN:

    I = d1 + 8D + d2 = 21.5

    a. Angle of intersection I = 49b. Total deflection angle I/2 = 24.5c. Length of long chord C = 380.16d. Half d1 d1/2 = 0.055

  • 8/10/2019 Fieldwork 4(Final)

    6/15

    SAMPLE COMPUTATION

    Given:

    d1 = 0.11D = 2.5d2 =1.39

    Angle of intersection, I = 49Length of long chord, C =380.16d2/2 =0.695

    D =1.25

    Solution:

    Intersection Angle, I:

    I = d1 + 8D + d2 = 21.5

    Total Deflection Angle, I/2

    I/2 = 49/2

    I = 24.5

    Long Chord, C:

    C = 2 * R * sin (I/2)

    C = 2 * 458.37 * sin (49/2)

    C = 380.16

    First Intermediate Point, A

    A = d1/2

    A = 0.11/2

    A = 0.055

    Second Intermediate Point, B

    B = [(d1+D)/2]

    B = [(0.11+2.5)/2]

    B = 1.305

    Third Intermediate Point, C (Until 20th Intermediate

    Point)

    C [(d1+2D)/2]

    At Intermediate Point A

    Computed Length of the Chord = 0.88

  • 8/10/2019 Fieldwork 4(Final)

    7/15

    Analysis of Data

    In the first part of this fieldwork, we were to lay a simple curve

    on uneven ground, to lay a simple curve using double-deflection

    angle method and to master the use of the transit and theodolite in

    laying a simple curve.

    From the gathered data taken from the said activity, it can be

    seen that every detail gathered was tallied in the given data. The

    summation of deflection angles taken was all equal to 35 which are

    half of the given angle of point of intersection which is 70 degrees.

    And also the chord distances were all equal to 280 meters and so

    close to the length of the main curve.

    Conclusion

    In performing this fieldwork which deals with laying of a

    simple curve on uneven ground using transit and theodolite using

  • 8/10/2019 Fieldwork 4(Final)

    8/15

    Acknowledgement

    Firstly, I would like to thank God for giving me another day

    to do what I have continued and another day to prove myself and do

    all the tasks that life has given me. And also for all the people he

    has given me to love, to care and to make my life more joyful.

    Including my parents, friends, professors, acquaintances, and even

    those people who make my life thrilling.

    Also, I would like to thank my group mates for their effort

    and their time and also their cooperation in participating in this

    fieldwork. Also, I would like to mention about doing their assigned

    tasks and doing it right in order for us to finish the field work on

    time.

    Lastly, I would like to show my gratitude to my professor,

    Engr. Cervantes, for teaching us and guiding us for our activity and

    for imparting his ideas regarding the topic and make it possible for

    us to do it on our own. And at the end of the day, there was another

  • 8/10/2019 Fieldwork 4(Final)

    9/15

    station with vernier A set at zero. The telescope is then reversed by

    plunging it. A foresight to the next station is then taken by turning

    the instrument about the vertical axis on its upper motion, and thedeflection angle is observed. The angle is recorded as right R or left

    L, according to whether the upper motion is turned clockwise or

    counter clockwise. Usually, deflection angles are observed twice,

    once with the telescope in face left and the other in face right

    condition. Immediately after completion of traverse observation, an

    arithmetical check on the angular error of closure should be

    performed to detect any blunder or excessively large error in angular

    measurement.

    To check the angular closure, azimuths are calculated from

    previously known azimuth of a line. The unknown azimuth of a line

    is computed by adding the right deflection angle and subtracting the

    left deflection angle with the forward azimuth of the previous line.

    Thus,

  • 8/10/2019 Fieldwork 4(Final)

    10/15

    azimuth or on the observed deflection angles.

    In the azimuth adjustment method, the computed azimuth

    of the closing line is compared with its previously observed value. If

    both the values agrees each other, there is no error of closure

    otherwise it exist. To remove the error, a correction equal in

    magnitude but opposite in nature to the error of closure is to be

    distributed among the observed deflection angles.

    In the deflection angle adjustment method, the algebraic

    sum of the deflection angles is being computed taking the right

    deflection angles as positive and left deflection angles as negative.

    The general relation to compute the error of closure by this method

    is as follows:

    Forward azimuth of the first side of traverse (at first

    station) + -

    traverse (at terminating station) + 360---- (Equation 28-1)

  • 8/10/2019 Fieldwork 4(Final)

    11/15

    A deflection angle should never be measured without double

    centering the instrument, because the error caused by the line of

    sight not being normal to the horizontal axis of the instrument may

    be too large to be tolerated. Moreover, the angular error of closure

    should not exceed the estimated standard deviation for observing an

    angle from a single setup times the square root of the number of

    instrument stations. In practice, this estimated standard deviation in

    angular measurement is usually taken equal to 0.5 to 1.0 times the

    least count of the instrument used in measuring the angles. If the

    error exceeds the permissible limit, then observation should be

    repeated till permissible limit has been achieved.

    Deflection angle method of traversing is being generally used

    for open looped closed traverse. It is most useful for the location

    survey of linear engineering works such as highways, railways,

    canals and pipelines etc.

  • 8/10/2019 Fieldwork 4(Final)

    12/15

    DOCUMENTATION

    Everyone is looking for a space to

    lay a simple curve

    I t di t i t ith l

  • 8/10/2019 Fieldwork 4(Final)

    13/15

  • 8/10/2019 Fieldwork 4(Final)

    14/15

    XI. Field Work Peer Assessment

    Course: CE1211F Section: B1 Date: November 12, 2014

    FIELDWORK 4:LAYING OF A SIMPLE CURVE ON UNEVEN GROUND BY TRANSIT AND THEODOLITE

    (Double-Deflection Angle Method)

    Group Members:ESTAVILLO, Kyle Score: 20

    EUGENIO, Jason Score: 20GARCIA, Julienne Score: 20GATCHALIAN, Kenneth Score: 20

    CRITERIA EXCELLENT VERY GOOD LIMITED POOR MEMBERS

    TIME ELEMENT Arrives exactly ontime.

    Arrives within the

    grace period of 15

    minutes

    Late for at most

    30 minutes

    Late for more than 30

    minutes

    4 4 4 4

    PREPAREDNESS Knows what exactlyis to be done in thefield

    Familiar with the

    procedure

    Needs further

    explanation

    Does not know what is

    to be done

    4 4 4 4

    COOPERATIVENESS Performs assignedtask willingly and iswilling to help

    group mates

    Performs only

    assigned task

    Performs less

    satisfactory the

    assigned task

    Does not want to help

    at all

    4 4 4 4

    ACCURACY Computes for therequired valueaccurately and insuch a short time

    Computes for the

    required value with

    little assistance

    Computes for

    the required

    value with some

    assistance

    Fails to compute the

    required value

    4 4 4 4

    OVERALL

    CONTRIBUTION ON

    THE GROUPWORK

    Performs an

    important role

    efficiently

    Performs an

    important role

    Performs a

    secondary role

    in a limited

    manner

    Does nothing 4 4 4 4

  • 8/10/2019 Fieldwork 4(Final)

    15/15