8/22/2019 Final Assgnmt Project Management-1
1/78
APBITSC | 1
Table of ContentsProject Charter .............................................................................................................................................. 3
Project Description .................................................................................................................................... 3
Project Scope ............................................................................................................................................. 4
Business Objectives and Success Criteria .................................................................................................. 4
Stakeholders .............................................................................................................................................. 5
Vision ....................................................................................................................................................... 10
Milestones ............................................................................................................................................... 10
Business Risks .......................................................................................................................................... 10
Approvals ................................................................................................................................................. 11
Project scope ............................................................................................................................................... 12
Target Users ............................................................................................................................................ 13
Resources ................................................................................................................................................ 13
Project goal .............................................................................................................................................. 14
Project Justification ................................................................................................................................. 14
Project requirements .............................................................................................................................. 14
Success criteria ........................................................................................................................................ 15
SWOT Analysis ......................................................................................................................................... 15
Project Work Breakdown Structure ............................................................................................................ 17
Project General WBS ............................................................................................................................... 17
The Project schedule ................................................................................................................................... 18
Project estimation ....................................................................................................................................... 18
Assumptions ............................................................................................................................................ 18
Schedule estimation ................................................................................................................................ 20
Effort Estimation ..................................................................................................................................... 21
Cost Estimation ........................................................................................................................................ 22
Cost Estimating ........................................................................................................................................ 22
Hardware and software cost estimate .................................................................................................. 22
System development estimates............................................................................................................ 23
Networking estimates.......................................................................................................................... 23
8/22/2019 Final Assgnmt Project Management-1
2/78
APBITSC | 2
On-going support estimate .................................................................................................................. 24
Admin estimate cost ............................................................................................................................ 24
Cost Budgeting ........................................................................................................................................ 25
Cost control ............................................................................................................................................. 25
Risk Management ........................................................................................................................................ 28
Risk Management Planning ..................................................................................................................... 29
Project Purpose ................................................................................................................................... 29
Project Scope ....................................................................................................................................... 29
Roles and Responsibilities ................................................................................................................... 29
Risk Documentation ............................................................................................................................ 30
Overview .............................................................................................................................................. 31
Risk Identification .................................................................................................................................... 31
Risk Analysis ............................................................................................................................................ 33
Cost Risk .............................................................................................................................................. 34
Scheduling Risk .................................................................................................................................... 35
Technical Risk ...................................................................................................................................... 35
Compatibility Risk ................................................................................................................................ 36
Programmatic Risk ............................................................................................................................... 36
Transition Risk ..................................................................................................................................... 37
Analysis Summary ................................................................................................................................ 38
Risk Mitigation ......................................................................................................................................... 39
Risk Monitoring and Control ................................................................................................................... 43
Conclusion ................................................................................................................................................... 45
Individual Journal Reflections...................................................................................................................... 47
Appendices A: Detailed Work Breakdown Structure .................................................................................. 56
Appendices B: Project Schedule .................................................................................................................... 1
Appendices C: Proposed Hardware Specification ......................................................................................... 2
Appendices D: Primary Connection between branches ................................................................................ 5
Appendices E: Backup Connection between branches ................................................................................. 8
ISDN components description ................................................................................................................... 8
Appendices F: System Development Methodology .................................................................................... 10
8/22/2019 Final Assgnmt Project Management-1
3/78
APBITSC | 3
Advantages .............................................................................................................................................. 10
RAD Tools ................................................................................................................................................ 11
References .................................................................................................................................................. 15
- Academic Books............................................................................................................................... 15
- Online Resources ............................................................................................................................. 15
Workload Matrix .............................................................................................Error! Bookmark not defined.
Project Charter
Project DescriptionAsia Pacific Basic IT Support Centre (APBITSC) system is a project that is used to assist the
manner in which basic (firstlevel) hardware and software technical support will be managed and
centralized for the Asia Pacific Regional Offices. In addition to this, another of its objectives is to
8/22/2019 Final Assgnmt Project Management-1
4/78
APBITSC | Project Charter 4
overcome the lack of technical expertise and duplication among the various offices within Asia
Pacific Region.
The project is sponsored by Global Alliance Resources Co. Ltd (GARCL) who is the Key
stakeholders. Other parties include the project manager, Assistant project manager, systemsengineer and analyst. The project deliverables are divided into project management deliverable
and product-related deliverable. The project charter items include the project milestones, a list of
the risks, assumptions, constraints, project strategy, and sign off.
Project Scope
This project will be required to result in overcoming the poor quality of IT support services in
Asia Pacific regional offices. All the reports to be made will focus on the IT field as first priority
to understand and determine project establishment requirements followed by other projectmanagement concerns such as estimation, budgeting, resources allocation, support, and project
development-related aspects.
Company history and issues related to organizational firm wont be included in this project.
Besides that, other projects that are related to business support services implemented in Global-
Alliance Resource Co. Ltd wont be touched as well in order to give much concern on developing
IT support services rather than looking at other unrelated areas.
Business Objectives and Success Criteria
The overall intent of this project is to ensure that the first level hardware and software technical
support are provided centrally for the Asia Pacific Regional offices and that poor service and lack
of expertise is eliminated due to this. Also we aim to ensure that duplication as a result of
providing similar support services is reduced if not eliminated.
The final project should be able to support 24 x7 with reliable primary and backup support staff.
Besides that, the current IT infrastructure must support the new system. All support must be only
from one of the Asia-Pacific regional offices. In addition, all staff must have access to the new
system. Overall, the success criteria will be evaluated by taking into consideration the triple
constraint scope, time, and resources- once all these factors are met and at an appropriate and
8/22/2019 Final Assgnmt Project Management-1
5/78
APBITSC | Project Charter 5
time and manner, then we can conclude that the project is successful. These will be explained in
detail in the project scope section.
Stakeholders
Stakeholder Name Functions. Win Conditi ons Constraints
Project
Sponsor
GARCL-
Global
To provide the
necessary funding
Being able to fund
the project and
Though funding is
available the project
8/22/2019 Final Assgnmt Project Management-1
6/78
APBITSC | Project Charter 6
Alliance
Resource
Co. Ltd
required in making
this project
successful.
seeing that it is
well underway and
finally finished and
successful, and all
the objectives have
been met.
may not be rolled
out in the 8 week
window time, and so
the sponsors may be
forced to increase
some of the funds to
facilitate for the
extra time.
Project
Manager
Rabera
Angwenyi
To facilitate and
assign tasks to
members of the
project, supervise and
their tasks and amend
and approve their
tasks.
Successful
management of the
project team, with
targets met and
work distribution
set out, and reports
given by the project
team on their
progress.
Uncooperative
project members or
simply not being
able to find the right
individuals to
perform the tasks
required, thus
leading to time lost
as tasks have not
been distributed and
the targets not meton time.
Assistant
Project
Manager
Ahmed
Abdul Jalil
Support the project
manager in task
management and
being the extra set of
eyes to foresee that
the project runs
smoothly.
Helping the project
manager where
possible to finally
ensure that all the
tasks are completed
and the project has
been completed
successfully.
Similar problems to
that of the project
manger although his
could be with the
uncooperative
project members
who may not be able
to create necessary
reports on time that
should be handed to
8/22/2019 Final Assgnmt Project Management-1
7/78
APBITSC | Project Charter 7
the project manager.
System
Engineer and
Analyst
Reza Responsible for the
technical aspects of
the system, testing
and ensuring that its
realization is met.
Creation of the new
system that will
ensure that the
centralization of
the system is
achieved. Also
testing the system
and ensuring that
the transition from
the old to new
system is smooth.
System
compatibility with
the current system
may bring about
some problems
when it comes to the
testing and transition
phase.
Database
Designer and
Administrator Pete brook
Responsible for
designing the
database for the
project and ensuring
that all the data
required to be
accessed byemployees is
properly accessed
ensuring that security
is maintained and all
records are intact. If
there is need to carry
on old records, then
their task is to ensure
that the transition for
the new records is
When the new
database is
compatible to the
new software and
all required
documents are
backed up andtransitioned
successfully and
that security is
ensured to secure
all the files and
records of the
organization.
There may be some
problems with
ensuring that the
database is
compatible with the
new systems coding
language and sosome alterations
may need to be
made.
8/22/2019 Final Assgnmt Project Management-1
8/78
APBITSC | Project Charter 8
smooth and they then
are backed up
effectively
Senior
Programmer Susan
Miller
Responsible for the
supervising the
coding of the
APBTSC system
Ensuring that it is
compatible to the
database and also that
it is running properly
and usable to the
employees.
Ensure that the
Junior programmer
designs and
programs the new
system properly
and that all
programming
reports and queries
are addressed and
now the transition
from the old to the
new is smooth.
The senior
programmer may
delay the roll out of
the new system as he
my be waiting on the
junior programmer
to finish coding,
compiling and
debugging. Also he
may face problems
during the
supervision of the
coding from trying
to approve some
ideas that the junior
programmer mayhave.
Junior
Programmer Mary Kent
Concerned with the
actual coding of the
system using a
specific programming
Language and
reporting to the
senior programmer
for approval of if any
query is raised
Designed and
Coded an effective
system that will be
approved, by the
senior programmer
and also that the
debugging and
testing are
successful, in that
The actual
programming may
be a tough task and
to ensure that the
system is compatible
to the database; also
she may find it
challenging to meet
all the requirements
8/22/2019 Final Assgnmt Project Management-1
9/78
APBITSC | Project Charter 9
pertaining to the
coding of the system
Also responsible for
debugging.
there are not bugs
anywhere.
of the senior
programmer and
ultimately client in
the given time.
Network
Administrator Tom
Stevens.
Responsible for
ensuring that the
GARCL company in
the US and that in the
Asia branch can
effectively
communicate in
terms of over the
network. He should
ensure that the
network is secure and
free of any threats or
vulnerabilities.
Being able to
secure the network
that the GARCL
company in the US
and the Asia branch
system, and also
make see that
communication is
efficient with no
lag detected.
The actual securing
may be an uphill
task considering the
time and also seeing
as the internet is
filled with threats
and vulnerabilities,
ensuring this will be
a task in itself.
Customers APBITSC
users
These are the
employees of thecompany that will use
the new system.
Being able to use
the new systemwithout any
hurdles, and also
work efficiency is
noticed as there
should be no
duplication or poor
quality services
Getting used to the
new system afterbeing used to the old
system may take
some time to getting
used to.
8/22/2019 Final Assgnmt Project Management-1
10/78
APBITSC | Project Charter 10
Vision
The Asia Pacific Basic IT Support Centre is a system created For Global Alliance resource Ltd
division in Asia Pacific which has been seeking to create a centralized system to be used in
conjunction with the US headquarters in terms of assisting Basic first level hardware and
software technical support, and to ensure duplication among regional offices is eliminated. The
implementation of this system will ensure that quality of service is improved and that all the
regional offices are able to communicate efficiently with the Headquarters in the US.
Milestones
Event or Deliverable Target Date Responsibi li ty
Project charter approved Week 1 Regional OperationsManager
Project plan completed Week 1 Project Manager
Project plan approved Week 2 Regional Operations
Manager
Project team assembled Week 3 Project Manager
Project execution initiated Week4 System Engineer and
Analyst
Project execution completed Week7 System Engineer and
Analyst
Customer acceptance Week 8 Asia Pacific GARCL
employees
Project closed out Week 8 Project manager.
Business RisksRisk Probabili ty Impact M iti gation
Timing Issues The timing of the 8
weeks roll out may be
This would lead to the
need to get extra
Ensure that all roles are
specified for each project
8/22/2019 Final Assgnmt Project Management-1
11/78
APBITSC | Project Charter 11
less than expected and
may exceed by an extra
week or so.
funding from the
sponsors to cater for
the extra time used
up.
member by the project
manager and reports are
done on time to ensure
everything is timely
User
Acceptance
The users of the system
may have a hard time
adjusting into using the
new system during the
transition to the new.
May take time to
using the system and
so performance during
the first few weeks
may be lower than
expected.
Train staff a few weeks
before to ensure that they
are familiar with the new
system by the time it is
rolled out.
Implementation
Issues.
The system engineer
may have some issues
implementing the new
system concurrently as
they stop using the
current method.
Time in this sense
may be a constraint as
it may take some time
to move from the
current to the new
system.
Ensure that an initial
compatibility test is
performed and that any
necessary features that
need to be done are
performed before the roll
out date.
Approvals
Approval Decision:
Approved, development of detailed project plan is authorized
8/22/2019 Final Assgnmt Project Management-1
12/78
APBITSC | Project scope 12
Approved, project execution is authorized
Approved, but project is on hold until future notice
Revise charter and resubmit for approval
Charter and project proposal are rejected
Role or Ti tle Name and Signature Date
Project Sponsor GARCL Company
Rep....
4thst June 2010
Project Manager Rabera Angwenyi . 4thst June 2010
System Engineer/Analyst Reza. 4thst June 2010
Senior Programmer Susan Miller.. 4thst June 2010
Network Administrator. Tom Stevens... 4thst June 2010
Database Designer and Analyst. Pete brook.. 4thst June 2010
Project scope
This project will be limited to certain scope that shall come out with the required result which is
overcoming the poor quality of IT support services in Asia Pacific regional offices. All the
reports to be made will focus on the IT field as first priority to understand and determine project
8/22/2019 Final Assgnmt Project Management-1
13/78
APBITSC | Project scope 13
establishment requirements followed by other project management concerns such as estimation,
budgeting, resources allocation, support, and project development-related aspects.
Company history and issues related to organizational firm wont be included in this project.
Besides that, other projects that are related to business support services implemented in Global-Alliance Resource Co. Ltd wont be touched as well in order to give much concern on developing
IT support services rather than looking at other unrelated areas.
Target Users
The target users are the employees of Global-Alliance Resource Co. Ltd in Asia Pacific regional
offices. The total employees are 330 in the 9 regional locations which are Malaysia, Indonesia,
Singapore, India, China, Philippine, Japan, Thailand, and Hong Kong. The system requires a
total of 42 support PCs and 6 new servers. The following table shows the distribution ofemployees in all branches.
Asia Pacific Location No of Employees IT Support Desktop PCs
Malaysia 95 10
Singapore 72 8
Thailand 43 4
India 38 4
Hong Kong 7 2
Indonesia 12 3
China 11 3
Australia 45 6
Korea 7 2
Total 330 42
Resources
The Project should be developed in a manner to keep resources without any wastage to be able to
meet budget requirements. The total resources required are listed as follows:
8/22/2019 Final Assgnmt Project Management-1
14/78
APBITSC | Project scope 14
- Technical expertise- Project management expertise- Design and estimation expertise- Implementation teams- Service Providers for connection- Hardware and software.
Project goal
This project is aimed to overcome the lack of IT support services and technical expertise and
duplication in the Asia Pacific regional offices, by implementing a new IT centralized system,
under the name Asia Pacific Basic IT Support Centre (APBITSC) Systemwithin a period of 8
weeks.
Project Justification
- APBITSC will provide centralized processing and database so all branches will avoidduplication and latency of operations
- It will provide a better first level hardware and software support service for all regionaloffices in Asia Pacific
- Increase the quality of first level IT support in all regional offices.- Provides interactive user-friendly interfaces so users can interact effectively with the
system.
- It will help reducing internal operating cost by eliminating redundant IT support servicesfound in various offices
- Increase efficiency and effectiveness of various operations- Provide easy communication between branches.
Project requirements- 42 PCs distributed in different Asia Pacific regional offices- 6 servers (database server, file server, web servers)- Firewalls and routers- Connection links
8/22/2019 Final Assgnmt Project Management-1
15/78
APBITSC | Project scope 15
- Backup connections- Computer accessories- Maintaining internal networks in all branches to be compatible with each other.- Network management and monitoring software- Maintaining platforms to be compatible with APBITSC.
Success criteria
The final project should be able to support 24 x7 with reliable primary and backup support staff.
Besides that, the current IT infrastructure must support the new system. All support must be only
from one of the Asia-Pacific regional offices. In addition, all staff must have access to the new
system.
Overall, the success criteria will be evaluated by taking into consideration the triple constraint
scope, time, and resources as follows:
Scope The completion of this project should meet user requirements and the
objectives made prior to start doing the project with efficient and reliable
development considerations
Time The project must be completed within the time given which is 8 weeks
Resources The project should be completed without any wastage of the resources
provided and with minimal extra resources.
SWOT Analysis
Strengths - Expertise from different countries that are enhanced withtechnical IT support
- Availability of necessary project funds- Availability of IT infrastructure in all branches
8/22/2019 Final Assgnmt Project Management-1
16/78
APBITSC | Project scope 16
- Availability of global networked connectionsWeaknesses - Short project development duration
- Cross regional- Different current platforms implemented in each branch.- Different flow of data input and type in different branches where
it cause problem in creating the centralized database.
Opportunities - Availability of similar systems that are already implemented- Availability of tons of hardware and software solutions on the
internet
- Availability of vendors who can provide hardware and softwarewith different options
Threats - Unstable internet connection- Natural disasters happening in the Asia Pacific area that might
affect the connectivity between branches.
SWOT analysis is being used to assess different situations and factors likely to influence the
project. After conducting it, it is obvious that the system could be enhanced by consulting global
expertise for input to the system requirement and since there is availability of similar system, that
could be used to outline the structure of the system and take the advantage of employing people
who has worked on similar systems. Though, the time given to complete the project is short (8weeks), the development process can be done to meet time requirement by evaluating the
available similar systems architecture and to review their problems faced to overcome them.
Also, internet solutions could be an enhanced factor for the development. Since the fund is highly
available, weaknesses and threats could be overcome by providing similar platform and
infrastructure in all branches besides implementing backup connection using different module to
overcome any connection failure.
8/22/2019 Final Assgnmt Project Management-1
17/78
APBITSC | Project Work Breakdown Structure 17
Project Work Breakdown Structure
Project General WBS
1.1Scope
1.2Analysis/System
Requirem
1.3Design
1.4Development
1.5Testing
1.8Trainin
1.7Documentation
1.6Deployment
1APBITSC
Refer to Appendices B for detailed Work Breakdown Structure
8/22/2019 Final Assgnmt Project Management-1
18/78
APBITSC | The Project schedule 18
The Project schedule
Refer to Appendices B for Project Schedule
Project estimationIn order to come out with successful project, most aspects of developing the project need to be
estimated to avoid any risk might shows up in future and to allocate required resources prior to
initialization of development process.
Assumptions
- Global-Alliance Resource Co. Ltd has considered a high fund for developing APBITSC.- The team gathered the requirements from end-users and reviewed them with virtual team
partners to determine the scope.- The requirements are well-defined- The requirements of the project dont contradict with the companys roles and objectives.- The Statement Of Work and Work Breakdown Structure were reviewed by the end-users
and virtual team partners.
- The development and operational environment is adequate to support the project.Before conducting the estimation, a checklist of various aspects in the project must be done to
ensure the estimation is based on related basis.
The following table shows the pre-estimating checklist of APBITSC development:
Project process Yes No Not necessary
Requirements
Are the project requirement clearly defined and understood?
Are the criteria for meeting each requirement defined?
Are the project requirements baselined?
Is there a client approved plan for requirements changes?
Has a requirement traceability Matrix been developed?
Have the requirements been validated against the business
8/22/2019 Final Assgnmt Project Management-1
19/78
APBITSC | Project estimation 19
objectives?
Have you considered all of the processes that must be followed
during the project life cycle?
Have you considered all of the interfaces that must be adhere
to?
Scoping
Has a statement of work (SOW) been reviewed/ approved by
client?
Has the statement of work been reviewed by virtual team
partners?
Has a Work Breakdown Structure been reviewed by the client?
Has the WBS been reviewed by virtual team partner?
Risk
Is there an approved risk management plan?
Was a client representation involved with the risk management
plan?
Environment
Is the process of identifying, acquiring, establishing, and
verifying the environment understood and included in the plansfor the project?
Is the development environment adequate to support the
project?
Is the operational environment adequate to support the project?
Staff
Are appropriate staffs available for the project?
Are the resources committed to participate in the required
activities?
Is there a training plan to cover deficiencies?
8/22/2019 Final Assgnmt Project Management-1
20/78
APBITSC | Project estimation 20
Schedule estimation
The duration of the development process is 8 weeks starting in (1 June 2010) and ends in (26 July
2010). The overall tasks of development are listed below:
-
Studying objectives and scope by programmers, designers, project managers, testers andother people in charge of the development process.
- Gathering user requirements from the target users who are the 330 employees of Global-Alliance Resource Co. Ltd by conducting various primary research methods.
- Analysis of requirements gathered- System design using appropriate methods that are suitable with the methodology and
programming language chosen
- Prototyping of system interfaces then review them with users to ensure the design meettheir expectation
- Coding the system.- Testing the outcome from coding.- Final implementation of the system in the workplace.
The time frame of those tasks will be discussed in details in scheduling part in appendices B
8/22/2019 Final Assgnmt Project Management-1
21/78
APBITSC | Project estimation 21
Effort Estimation
The efforts estimation will be conducted by identifying all the tasks required to develop the
project and the resources related to them. Besides that, estimating the cost per hour of each task.
The cost estimation here will be a generalized estimated cost since the cost estimation will be
explained in details in the next part.
Task
ID
Task name Resources type Resourc
es
quantity
Rate
per
hour
Effort
hours
required
Estimated
effort cost
T001 Studying user
requirements
and scope
Project
management
expertise
1 RM 100 4 days* 8
hours = 32
Hours
RM 3,200
T002 Gathering user
requirements
and analysis
System analyzing
expertise
2 RM 100 10 days *
8 hours =
80 Hours
RM 16,000
T003 System design
and prototyping
Design expertise 2 RM 54 16 days *8
hours =
128 Hours
RM 14,000
T004 Coding the
system
Programming
expertise
4 RM 208 18 days* 8
hours =
144 Hours
RM
120,000
8 RM 69 RM 80,000
T005 Testing the
system
Testing expertise 5 RM 66 3 days*10
hours = 30
RM 10,000
T006 Allocating
hardware
Hardware and
software
- - - RM
214,000
T007 Allocating
networking
Networking
devices and links
- - - RM
154,600
T008 Implementation
of project
Technical
assistance expertise
7 RM
312.5
4 days* 12
hours = 48
RM
105.000
8/22/2019 Final Assgnmt Project Management-1
22/78
APBITSC | Project estimation 22
Cost Estimation
According to Ghosh A (2007) Project cost management may be defined as management of the
processes involved in planning, estimating, and controlling costs so that the project can be
completed within the approved budget.
Cost Estimating
Cost Budgeting
Cost Control
Therefore, the cost estimation of developing APBITSC will be examined in three levels which
are cost estimating, cost budgeting, and cost control.
Cost Estimating
There are different types of cost to be estimated during the development of APBITSC. Costs
estimates to be considered are hardware and software, system development, network, on-going
support, and admin estimates. Technique of cost estimating to be used here is Determine
Resource Cost Rates which is estimating or collated actual per unit human and material resource
rates. The following tables show the estimation cost of each project development requirement per
unit
Hardware and software cost estimate
Hardware Price Per unit Quantity Total
Desktop computers RM 3,000 42 RM 126,000
Servers RM 8,000 6 RM 48,000
Office equipments (Printers, Fax machine, andother accessories) for the server rooms
RM 30,000 - RM 30,000
Software and platforms RM 10,000 - RM 10,000
Total RM 214,000*
Hardware specifications will be listed in Appendices C
8/22/2019 Final Assgnmt Project Management-1
23/78
APBITSC | Project estimation 23
System development estimates
Task developer Cost Number ofpersons
Total
Project manager RM 25,000 1 RM 25,000
System analyst RM 8,000 2 RM 16,000
Senior programmers RM 30,000 4 RM 120,000
Junior programmers RM 10,000 8 RM 80,000
Designers RM 7,000 2 RM 14,000
Testers RM 2,000 5 RM 10,000
Technical assistants (for systemimplementation)
RM 15,000 7 RM 105,000
Total RM 370,000
Networking estimates
Networking item Price Quantity Total
Primary connection implementation (VPN) RM 40,000 - RM 40,000Secondary connection implementation (ISDN) RM 25,000 - RM 25,000
Router for the main server (Cisco 4500 Internetrouter)
RM 24,000 1 RM 24,000
Router for other servers (Cisco 2600MX) RM 11,000 2 RM 22,000
Firewall (Cisco PIX) RM 8,200 3 RM 24,600
Cabling RM 10,000 - RM 10,000
Total RM 145,600
Refer to Appendices D & E for network specifications.
8/22/2019 Final Assgnmt Project Management-1
24/78
APBITSC | Project estimation 24
On-going support estimate
Item Cost
Disaster recovery RM 80,000
Depreciation cost RM 40,000
Total RM 120,000
Admin estimate cost
Admin item Cost
Travel between branches RM 50,000
Facilities RM 30,000
Licensing RM 10,000
Total RM 90,000
8/22/2019 Final Assgnmt Project Management-1
25/78
APBITSC | Project estimation 25
Cost Budgeting
Cost budgeting involves aggregating the estimated cost of individual activities that are identified
in Cost Estimating previously to establish a total cost baseline for measuring project
performance. Besides that, to come up with the total amount required to develop the project. The
Cost Budgeting technique used here is Cost Aggregation
The following table shows each requirement stage cost and the total cost required:
Project Area estimates Cost
Hardware and software RM 214,000
System development RM 370,000
Networking RM 145,600
On-going support RM 120,000
Admin RM 90,000
Total RM 936,600
Therefore, the total amount required to develop APBITSC is RM 936,600.
Cost control
After estimating and budgeting the cost, the project team will start to conduct the project with the
estimated cost after it is provided by Global-Alliance Resource Co. Ltd. Hence, the cost need to
be controlled and monitored to meet the budget requirement and to avoid over-budget problem
which may lead to failure of the project. Earned Value Analysis technique will be used for thepurpose of cost control in APBITSC as it is shown below.
BCWS (Budget Control of Work Scheduled): it is the planned cost of the total amount of work
scheduled to be performed by the milestone date.
In this case it is the estimated cost calculated in cost estimating up to 4 weeks that is RM 320,000
8/22/2019 Final Assgnmt Project Management-1
26/78
APBITSC | Project estimation 26
BCWP (Budget Cost of Work Performed): the planned (not actual) cost to complete the work that
has been done to date.
After starting the project, the planned budget to be spent in the fourth week is RM 362,800
(exclude hardware and software estimated cost) which will be spent in the implementation phase.
So BCWP in week 4 = RM 362,800
ACWP (Actual Cost of Work Performed): the actual cost incurred to accomplish the work that
has been done to date. Hence, in the fourth week of project development, the actual cost spent
during 4 weeks is RM 390,000 which is more than the estimated cost to be incurred up to the
fourth week.
ACWP = RM 350,000
The following table shows the Cost Variance and Schedule Variance for the first 4 weeks
development of APBITSC.
Schedule Variance (SV) SV = BCWPBCWS
SV = 362,800320,000
= 42800
Cost variance (CV) CV = BCWPACWP
CV = 362,800350,000
= 12,800
The cost variance for the first 4 weeks which is
RM 12,800 is the remaining part from the
planned cost of the first 4 weeks development
process.
We can see that the cost variance of the first 4 weeks is RM 12,800 so we can conclude that the
estimated cost for APBITSC development is precise and the project will be developing on the
estimated budget. The remaining cost will be added to the other 4 weeks development in case of
any shortage of budget. The following chart shows the SV and CV of APBITSC for the first 4
weeks.
8/22/2019 Final Assgnmt Project Management-1
27/78
APBITSC | Project estimation 27
0
50000
100000
150000
200000
250000
300000
350000
400000
Week 1 Week 2 Week 3 Week 4
BCWS
BCWP
ACWP
8/22/2019 Final Assgnmt Project Management-1
28/78
APBITSC | Risk Management 28
Risk Management
According to (Kendrick, 2003) Every Project has a risk. Risk is the product of loss and
likelihood. It is any undesirable event associated with the work or project at hand. There is
always at least some level of uncertainty in a projects outcome. High tech projects like this one
for GARCL are particularly faced with risk because they have high variations, and each have
unique aspects and objectives to them that differ from previous projects in some material way.
Project risk management is undertaken primarily because to improve the chances that a project
will achieve its objectives. It develops a credible foundation for the project showing that it is
possible and what is not feasible should be avoided or transformed.
Before Global-Alliance Resource Co. Ltd (GARCL) implements the project Asia Pacific basic IT
Support Centre System (APBITSC), it is vital to analyse it in all scopes using the riskmanagement processes below so as to achieve the objectives of the clients and to determine the
project as feasible and avoid or transform certain features that may hinder this.
RISK MANAGEMENT PLANNING
RISKS MITIGAION OR RESPONSE PLAN
RISK ANALYSIS
RISK IDENTIFICATION
RISK MONITORING AND CONTROL
Risk Management Process.
8/22/2019 Final Assgnmt Project Management-1
29/78
APBITSC | Risk Management 29
Risk Management Planning
According to (Kendrick, 2003) risk and project planning allow one to be able to distinguish
among and to deal with the three reasons for project failure, which are: Impossible and unrealistic
projects where the objective lies outside the technical capabilities of available; the second being,
they have a perfectly written down deliverable but the rest of the objective is unrealistic; the last
reason being where the deliverable is feasible and the objective too, but too little thought is put
into the work and no useful results emerge.
Below is the project plan for Asia Pacific basic IT support Centre System.
Project Purpose
This document describes how we will perform the job of managing risks for Asia Pacific basic IT
support Centre System It defines roles and responsibilities for participants in the risk processes,
the risk management activities that will be carried out, the schedule and budget for risk
management activities, and any tools and techniques that will be used.
Project Scope
This document describes the risk management process for the Asia Pacific basic IT support
Centre System project and assigns responsibility for carrying out the activities. These activities
are applicable to the development, integration and test of the new system which his supposed to
be used in the Asia Pacific region office for the GARCL Company.
Roles and Responsibilities
Role Responsibility
Project Manger The Project Manager will assign a Risk Officer to the project, and identify
this
Individual on theprojects organization chart. The Project Manager and
other
members of the Project Management team including the Senior
Programmer, Database Analyst, System Engineer and Risk Officer shall
meet on a bi weekly
frequency; to review the status of all risk mitigation efforts,
review the exposure assessments for any new risk items, and redefine the
project's
8/22/2019 Final Assgnmt Project Management-1
30/78
APBITSC | Risk Management 30
Top Ten Risk List.
Risk Manager The Risk Officer has the following responsibilities and authority:
coordinate the risk identification analysis activities and report the risk
resolution status to the management
Project Member
Assigned a Risk
The Risk Officer will assign each newly identified risk to a project
member, who will
assess the exposure and probability for the risk factor and report the
results of that
analysis back to the Risk Officer. Assigned project members are also
responsible for
performing the steps of the mitigation plan and reporting progress to theRisk Officer
biweekly.
Risk Documentation
The following table identifies the risk documentation that will be beneficial in identifying the
risks of the APBITSC and their analysis and mitigation process.
Risk list The risk factors identified and managed for this project will be
accumulated in a risk
list, which is located in the risk identification section.
These will be the ten risk items that currently have the highest estimated
risk exposure.
Closing Risk. A risk item can be considered closed when it meets the following criteria:
the planned mitigation actions have been completed and theEstimated risk exposure of probability is low.
8/22/2019 Final Assgnmt Project Management-1
31/78
APBITSC | Risk Management 31
Overview
Below we shall explain all the other steps included in the Risk Management process for the Asia
Pacific Basic IT Support Centre. These will include the Risk Identification, Risk Analysis, Risk
Mitigation and Risk Monitoring and Control.
Risk Identification
According to (AIRMC, 2002) Risk identification sets out to identify an organizations exposure
to uncertainty. Risk identification should be approached in a methodical way to ensure that all
significant activities within the organization have been identified and all the risks flowing from
these activities defined
Risk identification determines the risks that might affect the project and documenting these
characteristics, throughout the project lifecycle. For this process to be successful, the project team
decided to have a formal risk assessment workshop for a brainstorming session so as to be able to
decide on the main risks that were going to face this project another important element that was
added to make sure that we were able to cover all the bases of the risks involved was to have an,
interview session at the beginning of each life cycle phase so as to ask heads of project parts to let
the Risk office know what the risks they discovered were.
Role Task Concerned with Risk.
Project ManagerConcerned with the risks that affect
scheduling, cost and a general l overview of
the entire system so that this is reported to the
management, being the sponsors GARCL.
Risk Office Concerned with collecting all the risk factors
from the parties involved in the risk process,
and coming up with a document that is to be
presented to the management.
Senior Programmer Concerned with identifying any risks that will
affect the programming and coding of the
system, thus leading to an unsuccessful or
delayed roll-out. This report will be submitted
to the Risk Office.
8/22/2019 Final Assgnmt Project Management-1
32/78
APBITSC | Risk Management 32
Database Designer and Analyst Concerned with the risks related to the
database and compatibility issues of the
system. This report will be submitted to the
Risk Officer.
System Engineer Concerned with the finding risks that may
affect actual functioning of the system, its
technicalities and testing. This report will be
submitted to the Risk officer.
Network Administrator. Concerned with finding risks that may affect
the network aspects of the project in relation to
the connection between the Regional office and
the headquarters. This report will be submittedto the Risk Officer.
In the case of this project (APBITSC), there are seven categories of risk identification to be
considered: Below is the table concerned with the risks that have been identified in relation to the
Asia Pacific Basic IT Support Centre System.
Category of Risk Risk Involved
Cost Risk This is the possibility of the available budget
being exceeded. Cost risks include the
possibility that additional resources will have
to be expended to solve technical, schedule or
Programmatic problems.
Scheduling Risk This is the possibility of the development
program failing to meet scheduled milestones.Schedule risks include the possibility that
difficulty will be experienced in achieving
scheduled technical accomplishments, or that
procurement and/or integration and test
8/22/2019 Final Assgnmt Project Management-1
33/78
APBITSC | Risk Management 33
durations will be exceeded.
Technical Risk This is the possibility that a technical
requirement of the system may not be achieved
in the system life cycle. Examples of technical
risks include the failure to meet performance
requirements, testability or verification
requirements, and the failure to meet
integration requirements.
Compatibility Risk This is the possibility of the new system not
being compatible with some of the old
features, that the company may want to retain,
this involves areas like the Database andprogramming areas..
Programmatic Risk This is the possibility of events which are
detrimental to the system development but
which are beyond the control of the project
manager.
Transition Risk This is the possibility of the system not having
a smooth transition phase from the current tothe new system, not only from a technical
standpoint but also with the new users of the
system who are the Employees in the Asia
Pacific Regional Offices.
Risk Analysis
Asia Pacific basic IT Support Centre System (APBITSC) will use Qualitative Risk Analysis in
order to do the analysing conditions to determine and prioritize their impact on project objectives.
This process focuses on prioritizing the risks identified in terms of impact on the project
objectives. When the impacts are identified, actions can be taken and decided to determine the
risk probability. The result is the status of the project can be determined because reliable and
8/22/2019 Final Assgnmt Project Management-1
34/78
APBITSC | Risk Management 34
qualitative data are available. Then the probability or impact risk rating matrix can be constructed
with assumptions to test the possible consequences to the project. Below is the Risk Matrix that
will be used to qualify the risks according to their level or risk and likelihood.
Cost Risk
The risks that would be involved with the cost are:
a) The Budget being exceeded. There is the possibility that the budget that will be set asidefor this project by the sponsor GARCL will be exceeded. This is because there is the
likelihood of their being some technical problems on the way such as incompatible
systems and software which would lead to having to buy more software to allow the
system to run perfectly.
b) Another problem that would make the budget to be exceeded would be the timing factor.The project team may have difficulties in in rolling out the project on time, and this would
mean that more money has to be put in to cater for the extra man hours to pay the team forthe extra time they are spending. This type of risk would be categorized as a Medium-
High risk because, the Likelihood of it happening is Medium but in the event of it
happening, then this would mean that the Impact is high as this GARCL will have to put
in more money for the project to be a success.
8/22/2019 Final Assgnmt Project Management-1
35/78
APBITSC | Risk Management 35
Scheduling Risk
Risks involved for the scheduling of this project would be:
a) There is a risk that the project may not be rolled out on time. This is because thesystem may have a few issues with technicalities and testing and so this may delay the
actual timing of the system being completed and rolled out. This may be due to certain
changes from the project sponsors, and since these have to be taken into consideration,
changes will be made and this will take up time that would delay the schedule that
was set for this specific project. This risk is deemed as being Medium and critically
risky because, chances of there being delays in the whole process will definitely be
there but this should be handled by the project manager to ensure that it does not
happen. Even the least of events would cause the schedule to fall out of places, andthis would be detrimental because this also means that the costing of the project will
increase due to the extra time spent on the project.
Technical Risk
Risks involved when it comes to the technical aspect of this project are:
a) There is a possibility that there would be some technical problems that may come in theway of the project being completed. This could be due to the fact that there are some
technical transition problems from the old to the new system or even testing of the
system. The technical team may find some problems when they test the system and this
may delay the actual roll out of the system. This would have a low-medium risk status as
they likelihood of this usually happening is low, as the team will be testing every phase of
the system to ensure that there are not so many hitches towards the end of the project. The
impact would be medium in the sense that once the technical problem has been identified,
then the technical team would solve the problem to allow the project to proceed properly.
8/22/2019 Final Assgnmt Project Management-1
36/78
APBITSC | Risk Management 36
Compatibility Risk
Some of the compatibility risk that may arise would be:
a) Some of the compatibility problems that are predicted are the new system not beingtotally compatible with some of the old features of the system, this could mean that
even the new database would not be able readily able to transfer previous records to
the new system, and so a compatible software has to be sort and time taken by the
Database Analyst to ensure that this takes place. Also the programming language
necessary to write the system and ensure that the system may experience some
compatibility problems with the new database and therefore extra time which in this
case is a liability has to be taken into consideration to ensure that a good balance is
found to ensure that all aspects of the system are compatible. This risk would beconsidered a Medium-Medium risk as in the event that this occurs which is not that
probable since the technical team would already have had an idea of the language and
database to use hence the medium its impact would not that be great as the technical
experts will be able to know a suitable language to use based on their experience to
ensure that all aspects of the system are all compatible.
Programmatic Risk
a) This is a risk that usually affects the technical aspect of the system. This is wherebythe programmer has some problems with the actual coding of the system either
because of syntax problems or the testing process of the system to ensure it has no
bugs. This we consider a Low-Low risk as the programmer will be chosen based on
their expertise and the company trusts that the programmer will be able to understand
the compatibility of the system to other technical aspects of the system, and in this
way the system will be coded and tested. In the event that this happens, then the
impact can be considered as Low because the programmer uses a software language
that will indicate where the problems are, and so she can be able to go to the specific
line of code and fix it up.
8/22/2019 Final Assgnmt Project Management-1
37/78
APBITSC | Risk Management 37
Transition Risk
a) Some of the issues related to transition risk is usually the users of the new system. Theymay have a hard time being able to adjust from the old system and thus take some time in
being able to use the system. This would be considered as a Medium-High risk, becausemeasures would have already been taken to ensure that the users are familiar to the
system, but in the event that this happens, then this would be a highly risky because the
users cannot be able to use the system effectively and efficiently meaning that most of the
work is not being done properly and this would be detrimental to attaining the goals of the
organization.
b) Another transition problem that may arise would be the actual roll out of the new systemfrom the old- to the new system. This would be considered as a Low-Medium risk
problem, as it would not usually happen that the system does not transition well as prior
periodical checks would have already been done before, thus its likelihood being low, but
in the event that this occurs, then its impact would be medium, as the new system would
be able to be rolled out on time or effectively, but this would mean that the regional
offices are able to use the older system as the project team finds a fast way to ensure that
in no time, the new system is ready for use.
8/22/2019 Final Assgnmt Project Management-1
38/78
APBITSC | Risk Management 38
Analysis Summary
High
1
Medium
0.5
Likelihood
Low
0.1
Low 15 Medium 50 High 100
Impact
High (>50 to100) Medium (>10 to 50) Low (1 to 10)
Medium
TECHNICAL RISK
High
COST RISK
(1 x50) 50
Critical
SCHEDULING
RISK
(1X100) 100
Low Medium
COMPATIBILITY
RISK
(0.5X50) 25
High
TRANSITION
RISK
(0.1X100) 10
Low
PROGRAMMATIC
RISK
(0.1X10) 1
Low
(0.1X50) 5
Medium
8/22/2019 Final Assgnmt Project Management-1
39/78
APBITSC | Risk Management 39
Risk Mitigation
According to (Stoneburner, Gogoen, & Feringa, 2002) Risk mitigation is a systematic
methodology used by senior management to reduce mission risk. Risk mitigation can be achieved
through any of the following risk mitigation options:
a) Risk Assumption. To accept the potential risk and continue operating the IT system or toimplement controls to lower the risk to an acceptable level
b) Risk Avoidance. To avoid the risk by eliminating the risk cause and/or consequence (e.g.,forgo certain functions of the system or shut down the system when risks are identified)
c) Risk Limitation. To limit the risk by implementing controls that minimize the adverseimpact of a threats exercising a vulnerability (e.g., use of supporting, preventive,detective controls)
d) Risk Planning. To manage risk by developing a risk mitigation plan that prioritizes,implements, and maintains controls
e) Risk Transference. To transfer the risk by using other options to compensate for the loss,such as purchasing insurance.
The goals and mission of an organization should be considered in selecting any of these risk
mitigation options. It may not be practical to address all identified risks, so priority should be
given to the threat and vulnerability pairs that have the potential to cause significant mission
impact or harm. Also, in safeguarding an organizations mission and its IT systems, because of
each organizations unique environment and objectives, the option used to mitigate the risk and
the methods used to implement controls may vary. For the project we are working on, we will
look at each risk and find a migration methodology that can be applied together with the person
in charge of ensuring that this follows through.
Risk Mitigation Responsibility
Scheduling risk Risk Avoidance will be applied
to this risk. The reason for this is
that most projects usually face
unforeseen circumstances along
the project path. These could be
GARCL Sponsor
Project Manager
Risk Officer
8/22/2019 Final Assgnmt Project Management-1
40/78
APBITSC | Risk Management 40
like project staff resigning or
other technical issues, therefore
we shall ensure that the project
manager assigns something like
a 4day grace period in the
8weeks for any issues that have
not been addressed to allow the
project to be rolled out on time.
This schedule then has to be
checked by the Risk Officer and
approved by the Sponsor.
Cost Risk Risk Limitation will be appliedto this risk. As we know most
projects tend to not keep to the
expected dates that they should
be working in. This leads to
more manpower and hours put
in, leading to more money that
has to be used by the sponsor.
We will therefore limit this risk
by ensuring that the scheduling
of the project is in such a way
that there is some grace period
that will cater for those unseen
issues, be they technical, or
design based. This will ensure
that the project does not go into
overtime thus saving the sponsor
adding in more money. The
project manager will use the
schedule to plan for the costing
Project ManagerGARCL Sponsor
Risk Officer
8/22/2019 Final Assgnmt Project Management-1
41/78
APBITSC | Risk Management 41
which will be viewed by the risk
office and confirmed by the
project sponsor.
Compatibility Risk Risk Planning will be
implemented in this part. This
will mean that all the people
involved with the technicalities
of the system who in this case
are the senior programmer
together with his team, the
database analyst and senior
programmer will meet anddecide on which are the
appropriate approaches,
languages, database versions and
testing equipment to use, so as to
avoid any compatibility
problems in future. This plan
will be viewed and approved by
the Risk Officer.
Senior Programmer
Database Analyst
Risk Officer
Transition Risk Risk Transference we think
would be an effective
methodology to use here. For
transition the main focus is the
employees who will have to use
the new system they may be
unfamiliar with it and this may
impact the organizations
performance for the first few
months, so to avoid this the
project manger suggests to the
Project Manger
GARCL sponsor
Risk Officer
8/22/2019 Final Assgnmt Project Management-1
42/78
APBITSC | Risk Management 42
sponsor that some of the
management are taken for a
training workshop that will help
them in better understanding the
project such that when it is rolled
out they will be able to adjust
well.
Technical Risk Risk Limitation will be applied
in this case, as seen before
because all the people
responsible with the
technicalities of the systemwould have already met and
planned before and decided on
the appropriate database,
programming language etc. and
this therefore limits the technical
risks that may arise during this
project. These steps are then
approved by the risk officer.
System Engineer
Database Analyst
Risk Officer
Programmatic Risk Risk Limitation will be applied
in this case, as seen before
because all the people
responsible with the
technicalities of the system
would have already met and
planned before and decided on
the appropriate programming
language and this therefore limits
the programmatic risks that may
arise during this project. These
Senior Programmer
Junior Programmer
Risk Programmer
8/22/2019 Final Assgnmt Project Management-1
43/78
APBITSC | Risk Management 43
steps are then approved by the
risk officer.
Risk Monitoring and ControlWhen dealing with risk control and monitoring according to (Stoneburner, Gogoen, & Feringa,
2002) we have to ensure that we address the greatest risks and strive for sufficient risk mitigation
at the lowest cost, with minimal impact on other areas.
The following risk mitigation methodology describes the approach we will use to control
implementation of the (APBITSC).
Step 1 Prioritize Actions
Based on the risk levels presented in the risk analysis report, the implementation actions are
prioritized. In allocating resources, top priority should be given to risk items with unacceptably
high risk rankings these are the Cost and Scheduling risk. We have to ensure that the priority
goes on from the High from Low in terms of risk level.
Step 2 Evaluate Recommended Control Options
The controls recommended in the risk control process may not be the most appropriate and
feasible options for a specific organization and IT system. During this step, the feasibility (e.g.,
compatibility, user acceptance) and effectiveness (e.g., degree of protection and level of risk
mitigation) of the recommended control options are analyzed. The objective is to select the most
appropriate control option for minimizing risk.
Step 3 Conduct Cost-Benefit Analyses
To aid management in decision making and to identify cost-effective controls, a cost benefit will
be conducted for this project. This has been shown above in the Cost analysis after estimation.
Step 4 Select Control
On the basis of the results of the cost-benefit analysis, management determines the most cost-
effective control(s) for reducing risk to the organizations project to be successful. The controls
8/22/2019 Final Assgnmt Project Management-1
44/78
APBITSC | Risk Management 44
selected should combine technical, operational, and management control elements to ensure
adequate security for the IT system and the organization.
Step 5Assign Responsibility
Appropriate who have the appropriate expertise and skill-sets to implement the selected control
are identified, and responsibility is assigned.
RISK CONTROL TASK PARTICIPANT
The status and effectiveness of each mitigation
action is reported to the Risk Officer every two
weeks.
Risk Officer
The probability and impact for each risk item is
reevaluated and modified if appropriate
This is done by each member who is concerned
with their own risk according to the mitigation
table above, and approved by the risk officer.
If any new risk items have been identified, they
are analyzed as were the items on the original
risk list and added to the risk list.
Risk Officer
The Risk List is regenerated based on the
updated probability and impact for each
remaining risk
Risk Officer
Any risk factors for which mitigation actions
are not being effectively carried out, or whose
risk exposure is rising, may be escalated to an
appropriate level of management for visibility
and action.
Risk Officer
8/22/2019 Final Assgnmt Project Management-1
45/78
APBITSC | Conclusion 45
Conclusion
The six project management areas examined for developing APBITSC are in fact the best areas to
manage the project effectively because they almost cover and examine every single aspect of the
project.
For the project charter , this is an important document that can be used to breakdown the tasks of
the individuals in the project, it gives a clear indication of which task belongs to who and the role
that they will play in the entire project , this reduces confusion and provides a systematic method
of task assignment.
Project scope process discussed about the overview of developing the project and identifying
project goals and recourses required. These help to set a fixed goal for developers to be followed
as steps and aims to be achieved. Identifying the resources helps to determine methods of
resources allocation and estimation of cost. Project scope contains overall requirements and
success criteria that are indeed helpful to determine success or failure of the project. Also, SWOT
analysis that is a part of project scope was very crucial to identify different strong and weak
elements around the project.
Work breakdown structure was one of the important processes that show all the tasks involved in
the project in details. It is crucial in case of classifying every task and its sub-tasks. Besides that,
it gives a clear picture of which task to start and which to finish. Also, it helps in determining cost
estimation by identifying all resources required throughout the whole tasks.
Regarding project schedule, it is another critical and crucial process that helps the project
manager to plan the time and the period required for each task in order to keep developing each
task up to date and results by completion of project on time.
Project estimation helps to come out with planned cost and efforts so the company can prepare
for that earlier. Besides that, the project manager is able to allocate efforts needed and determinelocation of development based on the efforts and costs. The estimation was very crucial since it is
the critical standards to determine project budget, resources, devices, and expertise to develop
APBITSC.
8/22/2019 Final Assgnmt Project Management-1
46/78
APBITSC | Conclusion 46
The Risk management methodology is one of the most important in any project it is very
essential in identifying any risks that may be faced during the life cycle of the project therefore
putting forth the correct measures in trying to avoid them. It is very essential also in preparing the
team on the scheduling and cost estimation processes by allowing the members to identify the
risks and taking corrective measures so as to prevent the project from not being rolled out on time
or failing.
8/22/2019 Final Assgnmt Project Management-1
47/78
APBITSC | Individual Journal Reflections 47
Individual Journal Reflections
Conducting this assignment has taught me a great deal so many crucial learning outcomes that
would benefit me in the near future in working environment since the case study of developing
APBITSC is very practical where it is easier to experience managing projects that closely
resembles current projects in the workplace. Managing the project in every stage and performing
its activities in sequence taught me to understand the project development flow and working on
related tasks. Therefore, I learnt that completing a project cannot be conducted by just
distributing the tasks among group members but it indeed requires team work and heavily
communication among the group members. Fortunately, all the group members were very hard-
working in achieving each task without any communication barrier encountered.
Team work has taught me a lot in working in projects with relying on each other effort to produce
an outcome. We had several meetings and communicated among each other using online meeting
as well to keep the project development up to date. Besides that, every task in the assignment was
done in sequence and relating to other members tasks. Every member in the group was freely
allowed to give out their views on any point related to the assignment so we put our heads
together to come out with this assignment using different ideas and insights. In team work
environment done in this assignment, I would absolutely have no obstacle to work with other
teams in future working environment since I have already learnt how to handle many team work
issues and be able to have effective communication among group members.
Regarding other outcomes gained through developing this project, I learnt a lot about theory of a
project and common steps to be made in any project development initialization and completion.
Working on project charter taught me how to conduct it in any project and how it is used as a
notice to inform the participants of the project to know more about the important factors.
Therefore, now I am able to create a project charter for any project which is a task that I didnt
know before how to do and even what was it about. The project charter based on researching is
very important because it will also be used by project managers to conduct a project within a
specific scope, quality, time, cost and also resources constraints.
Besides that, I learnt how to define the project scope by identifying every stage in the project to
be conducted and target users, also identifying the resources required to develop the project.
8/22/2019 Final Assgnmt Project Management-1
48/78
APBITSC | Individual Journal Reflections 48
Moreover, determining success criteria to be a role to be followed during the development in
order to meet them at the completion of the project. Doing SWOT analysis was another great
outcome by identifying and determining the strengths, weaknesses, opportunities, and threats that
are related to developing the project and how to provide a fixed plan to take corrective action
when any threat arises by taking into consideration the opportunities and make a use of the
strengths to solve the weaknesses.
I also learnt how to create work break down structure (WBS) for the project which is a tool to
show all the stages in details starting from planning and ending up by delivering the project to the
end-users. A note to be enlightened that WBS can be done according to the project requirements,
so WBS of any project might be different from other projects but the point here is learning how
to conduct it in general for any purpose and project.
My individual task in this project was estimation so conducting it for this case was so helpful for
me to learn how to estimate different requirements in any project. Starting by schedule estimation
which was a part to be done with the group members to identify the different tasks of the project
and to come up with required tasks and time frame. That was followed by effort estimation
which is estimating the cost of developers who will pay an effort for the development process
such as programmers, project managers, system analysts, and designers. Cost estimation was the
last part conducted in Estimation and it was done according to project cost estimation techniques
by identifying cost estimating, cost budgeting, and cost control. Every level of those was
explained and done effectively to come up with total estimated cost of the whole project. I learnt
a lot from applying those techniques and I am definitely able to conduct estimation for any
project in future using academic and well-defined methods of estimation.
Other parts of this project that are project scheduling and risk management were assigned to my
other groupmates, but all group members discussed about different aspects in every individual
part in order to come out with whole great work. On the other hand, all group members shared
ideas and suggest resources for doing the individual tasks.
There were some challenges encountered in order to complete this assignment. Firstly, the lack of
knowledge in project management that required us to read several books in project management
and refer to online resources but there were different approaches proposed by different authors
8/22/2019 Final Assgnmt Project Management-1
49/78
APBITSC | Individual Journal Reflections 49
that create confusion in some cases which ended up by discussion with the group members to
choose the proper method and reference to follow. Another challenge was time constraint to work
on this assignment besides other assignments and final year project in the same time so it
required me to manage time in order to get all assignments and project done prior to the due date.
To sum up, this assignment was really one of the most beneficial works for my knowledge and
future reference as well. I would like to thank Ms Hemalata for her guidance and support through
this assignment, also thanks to my group members Alireza and Elizabeth who showed great team
work interaction and hard-work.
8/22/2019 Final Assgnmt Project Management-1
50/78
APBITSC | Individual Journal Reflections 50
As an IT student, focusing on technical computer stuffs has been always the only concern
in my studies. Working on such a critical and major assignment has added new ideas and skills to
my project management knowledge and understanding capabilities. During my studies I have
passed few management modules; although they all have been helpful to me but none of them
discussed about methods of managing the projects.
In order to complete this project management, the methodology selected to be used,
PMBOK is vital due to the efficiency and usefulness of the methodology to be able to handle the
organization well. Other than that, with the detail information acquired and listed all in the
Project Charter, Scope as well as the Work Breakdown Structure have helped a lot in managing
the departments in the organization for a better future. Other focus such as the scheduling,
estimation of account runs within the organization and the risk management also helped to get the
assignment done professionally.
Learning Outcome
The learning outcome of this assignment is where the organization has been assigned the
people and departments well in order to run the organization more systematically and
professionally with the least problems occur by the help of the PMBOK methodology. Apart
from that,
For the completion of this project, almost every chapter learnt during the lecturers is used.
Among the chapters done during the lectures, following are the ones that used for the completion
of this project:
Project charter Project scope Work breakdown structure (WBS) Estimation Change management Monitoring and Control Managing communications Quality Management
Work Breakdown Structure:
8/22/2019 Final Assgnmt Project Management-1
51/78
APBITSC | Individual Journal Reflections 51
It was an interesting and challenging job to develop the work break down structure since it plans
the entire project. All the tasks and activities which need to be done in order to manage and
develop the project successfully should be mentioned and classified in WBS. It allows the
development of Gantt chart which plans the sequence of the tasks and the time that each task
needs to be applied. Pert chart will implemented upon the Gantt chart. Hence, it is obvious how
important the WBS is in development any project.
Project Estimations
This is another part which was not really easy at all, first as an international student, it was
somehow hard for to estimate the cost of some equipments, offices and the salaries in Asia as the
project was located in Asia pacific. I learnt that different types of estimation and it were quite
challenging to choose one to be applied and how to relate it to the project.
Project Charter
Doing the project charter was quite interesting, as it needs to understand the whole project, its
purpose, the objectives, goals, deliverables, etc. As well as identifying them in a project.
From this perspective and with the studies and researches we accomplished, I am able to
understand the subject matter with more specific understandings. Different types of project
risks, risk management process and different estimations and scheduling techniques are thetopics that I have learnt in taking this module and applying its assignment. They all helped me
to be able to implement real business management plans in future.
Applying theories and concepts learnt in this subject has helped me in completing this
assignment because in this subject, Project Management, the lecturer has taught us in different
style which I think is effective and very attractive, which made me able to succeed in applying
the theories and concept in the topics such as how to develop a quality management and in
dividing tasks like work breakdown structure and project charter. The lecturer made us
understand it, not to just theoretically read the slides and points. As far I understand more about
this subject, I feel more capabilities in understanding project management systems.
Participating in an active, clever and friendly group, hardworking and influencing
environment are the factors to achieve success in applying the concepts. Using project
8/22/2019 Final Assgnmt Project Management-1
52/78
APBITSC | Individual Journal Reflections 52
management concepts and techniques help me in other subjects and other aspects of my life since
the framework, style and format of the assignments, and concepts I had learnt, will boost me up
in completing other assignments and projects especially when it involves time management,
quality management and cost management. At the same time this can enhance my work and
career in communication and documenting a professional work.
Conclusion
As to conclude of the entire assignment process my group and I have been through, it
helps me in understanding the module and the studies. The theories I have learnt in the module
have also helped us in completing the assignment by applying most the theories. With these
knowledge and theories obtained, we have known how to manage the project well for the
assignment.
At the end I would like to appreciate my lecturer Mrs. HemalataVasudavan for her efforts to
teach this professional subject to our class and my diligent group mates for the efforts they have
made in order to do this assignment.
8/22/2019 Final Assgnmt Project Management-1
53/78
APBITSC | Individual Journal Reflections 53
Throughout the whole project management module and during the assignment period, various
experiences were gained concerning the project management module and how to work in a team.
We were able to work as a team coherently and with the guidance of our lecturer able to deliver
the assignment in good time. At the beginning of this project, tasks were divided among the three
members of the team; the methodology to be used for the project was chosen and agreed by all
group members and each did research on it in order to ensure the success of the project. The
project was very challenging since we were not so familiar with some of the tasks that were
supposed to accomplish. The assignment group part which includes project charter, scope and
WBS was done by all three group members and the other 3 individual methodologies divided out
among the group members. We were able to research and come up with a detailed report on all
the processes and knowledge areas.
During the lectures of project management module, I learnt a lot on the following chapters:
Project charter Project scope Work breakdown structure (WBS) Project scheduling Estimation Risk management Monitoring and Control Project failures
I was able to apply theories and concepts learnt in this subject or in other subjects to help myself
in completing this assignment. The lecturer taught us in a way that we were able to apply the
theories and concept in the topics such as risk management and in di