Purpose of the project
What’s it all about?
Hundreds of Solar panels in Solar Farm. It’s difficult to figure out damaged solar panel. Our system will collect all power data from each single solar panel. Then we will compare this data with normalized output power of solar
farm. We will display information of solar panels on monitor Power output from defective solar panel will be less.
Schematics of PAC 1710
Single Solar Station
Simplified Block Diagram
Hardware
LPC 1768 mbed rapid prototyping board PAC 1710 precise voltage measurement IC Shunt resistor Other electronic components Breakout module for PAC 1710
Breakout module development
Etching process
Testing ReportsFile Name Expected Outcomes Problems facedI2C Tests 1 to 5 To establish communication
between PAC 1710 and LPC 1768Initially getting garbage values,
Vsource measurement
To measure output voltage of solar panel
Datasheet didn't have proper information
Vsense measurement
To measure output current of solar panel
Datasheet didn't have proper information, didn't work at all
Project Integration Efficient and reliable working code for 3x3 solar system
Faced some programming issue such as structure doesn't work.
Terminal Display To provide 3x3 display pattern on Tera term.
Escape sequence doesn't work properly
Final project To complete a project as per described in the scope
Some of the sensor in the grid wasn't working
Project Management Project Proposal Scope Statement Work Break-Down Structure Gantt Chart Budget Status Reports & Presentations Final Report & Presentation
Planned Gantt Chart
Actual Gantt Chart
Plan
ned
Budg
et
Actu
al B
udge
t
EVA
Wor
kshe
etDate Planned
Value(PV)Actual Value(AV)
Earned Value(EV)
CPI = EV/AC
SPI = PV/AC
07 – June 1248 1248 1248 1 1
15 – June 2496 2496 2496 1 1
24 – June 4784 4784 4784 1 1
04 - July 7280 7310 6117 0.83 0.99
12 – July 8986 9365 8312 0.88 0.95
19 – July 9568 9756 10816 1.11 0.98
25 - July 12896 13021 13558 1.05 1.01
07 - Aug 13756 13796 14248 1.03 1.01
15 - Aug 15643 15712 16387 1.04 1.01
EVA
Wor
kshe
et
1 2 3 4 5 6 7 8 90
2000
4000
6000
8000
10000
12000
14000
16000
18000
Actual: ---------Planned: ---------