Upload
docong
View
220
Download
1
Embed Size (px)
Citation preview
U.S. DEPARTMENT OF THE INTERIOR U.S. GEOLOGICAL SURVEY
FINAL PROPOSAL FORSEISMIC INSTRUMENTATION OF THE
CABLE-STAYED CAPE GIRARDEAU (MO) BRIDGE
SUBMITTED TO
MISSOURI DEPARTMENT OF TRANSPORTATIONand
FEDERAL HIGHWAY ADMINISTRATION OF THE U.S. DEPARTMENT OF TRANSPORTATION
Compiled by
Mehmet felebi1
Open-File Report 97-80 February 1997
This report is preliminary and has not been reviewed for conformity with U.S. Geological Survey editorial standards (or with the North American Stratigraphic Code). Any use of trade, product or firm names is for descriptive purposes only and does not imply endorsement by the U. S. Government
1 USGS (MS977), 345 Middlefield Road, Menlo Park, Ca. 94025
CONTENTS
Contents........................................................................................................!Summary and Disclaimer...................................................................................!Contributors and Affiliations..............................................................................31.0 Introduction...............................................................................................42.0 General Considerations ..............................................................................4
2.1 Goals of the Seismic Array...................................................................42.2 Strategies for Housing the Recording Systems for the Seismic Array..............52.3 Special Considerations for Weather........................................................5
3.0 Permanent Seismic Instrumentation for Cape Girardeau Bridge.............................63.1 General............................................................................................63.2 Specifics .......................................................................................63.3 Approximate Total Cost for the Hardware ...............................................7
4.0 Conclusions and Recommendations.................................................................7
References.....................................................................................................8Appendix A. Symbols Used................................................................................9
Table 1. Cape Girardeau Bridge Instrumentation................................................^Table 2. Approximate Hardware Cost...............................................................12
Figures......................................................................................................13
Summary and Disclaimer
The proposal described herein provides a detailed scheme for seismic instrumentation of the Cape Girardeau Cable-Stayed Bridge now under construction. On October 23, 1996, a meeting was held in Washington D.C. to discuss various possible schemes of instrumentation for the bridge. The meeting was organized under the auspices of two principal organizations: the Missouri Department of Transportation [MODOT] and the Federal Highway Administration [FHWA] of the U.S Department of Transportation. These two principal organizations coordinate the design, construction and related efforts. During the meeting of October 23, 1996, the author was asked to prepare an initial draft for comment and discussion. The initial draft dated November 4, 1996 was discussed during a second meeting in Atlanta, GA on December 5, 1996. Later, on February 7, 1997, a final meeting was held in Menlo Park, Ca. Between representatives of Caltrans, LLNL and USGS to develop this final proposal using the various input put forth by the participants in all the meetings as well as from other technical staff of LLNL, Caltrans and USGS. A list of contributors and affiliations is included in this final proposal.
The hardware for instrumentation will be purchased by funding that will be put together by the two principal agencies. USGS, as part of its earthquake hazard reduction program, will provide input in deployment of instrumentation, establish a mechanism with MODOT and FHWA to maintain the instruments, retrieve, process and disseminate strong-motion response data following events in the future.
Contributors and Affiliations (in alphabetical order of last names)
Dr. Mehmet £elebiTom CoolingJerry DiMaggioChristopher Dumas [FACILITATOR]William Foresterlan FriedlandGlen Fulkerson,Steve HagueDr Francois HeuzeJames HummertDr. Larry HutchingsDr. David McCallenRonald PorcellaDr. Clifford RobleeMarion SalsmanTom ShantzDr. Glenn SmithWilliam StroessnerDr. Philip Yen
USGS,MenloPark,CAWoodward-Clyde, St. Louis, MOUS DOT, FHWA HQ Bridge DivisionUSDOT,FHWA Region 3, Wash. DCUS DOT, FHWA Region 7NCEER, Buffalo, NYFHWA, Jefferson City, MOHNTB, Kansas City, MOLLNL, Livermore, CAWoodward-Clyde, St. Louis, MOLLNL, Livermore, CALLNL, Livermore, CAUSGS, Fresno, CACaltrans, Sacramento, CAUSGS, Menlo Park, CACaltrans, Sacramento, CAUS DOT, FWHA HQ Bridge DivisionMissouri DOT, Jefferson City, MOUS DOT, FHWA, McLean, VA
1.0 Introduction
The acquisition of structural response data during earthquakes is essential to confirm and develop methodologies for analysis, design, repair and retrofitting of earthquake resistant structural systems. Particularly for urban environments in seismically active regions, acquisition of response data, from structures including lifelines such as bridges, by using seismic instrumentation, is one of the basic requirements for a thorough investigation of the effects of earthquakes on the structures. In order to understand the structural responses thoroughly, in addition to structural arrays which should include sensors for soil-structure interaction (SSI) effects, it is necessary to record ground motions at the free-field in the vicinity of the structures. The New Madrid area, the location of the 1811-1812 New Madrid earthquakes, is a seismically active region requiring earthquake hazard mitigation programs including those related to investigation of strong shaking of structures and the potential for ground failures in the vicinity of structures. Discussion of seismicity of the area can be found in References 1 and 2.
The objective of this proposal is to develop possible schemes of seismic instrumentation to be deployed on and in the vicinity of the new Cape Girardeau Bridge (MO) now under construction. Early planning of seismic instrumentation schemes is a necessity in order to cover installation of basic hardware during the construction phases (such as conduits and cables to interconnect the sensors to recorders and conduits for deployment of downhole accelerometers). It is important to note also the proposed instrumentation is for strong-motion recording and not for low-amplitude weak motions. For low-amplitude weak motions, special purpose temporary deployment schemes should be adopted.
In addition to other objectives which require special purpose instruments and hardware, for seismic engineering studies, in general, three different objectives are sought. In planning for the overall scheme, it is important to clearly identify these objectives:
1. Instrumentation of the Superstructure and Pier Foundations.2. Instrumentation of the free-field in the vicinity of the structure including those related to
downhole measurements and horizontal spatial arrays to assess the differential motions at the piers of the long span structure.
3. Ground failure arrays in the vicinity of the structure.
The scope of this proposal is limited to description of seismic instrumentation covering the first two objectives. Details of geotechnical considerations related to the bridge are provided in Reference 2.
2.0 General Considerations
2.1 Goals for the Seismic Array
The general locations where sensors are essential are marked in Figure 1. With the detailed instrumentation scheme outlined below, the following goals will tje met:
a. Detection of the structural response (of the caissons, tower, deck). Whenever appb'cable, sufficient additional sensors for soil-structure interaction (SSI) are added.
b. Spatial variation of ground motion along the total span (3956 ft ~ 1206 m) of the bridge (longitudinal, transverse and vertical).
2.2 Strategies for Housing the Recording Systems for the Seismic Array
There are three possible strategies for implementation of the structural array:
A. A new approach to seismic instrumentation scheme appears to be feasible by taking advantage of the new state-of-the-art recording hardware that includes or can be ordered with GPS capability. GPS capability can be used for common-time recording of events when more than one recording system are used at different locations of a structure such as the long-span cable- stayed Cape Girardeau bridge. Thus, cables and appropriate connections are minimized. Normally, since a bridge is inherently a long span structure, extensive and expensive cabling (and conduits) would be required to interconnect various sensors to the recorder and various recorders to one another. The proposed or alternative (recording system) hardware can be configured to provide combinations of 3-18 channels at different locations (Bent 1, Pier 2, Pier 3, Pier 4 and Pier 15). The recommended strategy would be more economical than having all recording systems in one or two locations with various sensors deployed at different piers, caisson tops, towers and deck connected to the recorders with long cables. The downside of this approach is that for maintenance of the recording systems, several stops and access arrangements would be required
B. All recording systems be placed in one location (e.g. In the room at Pier 2 or 3). This has advantages from maintenance point of view and future transmission of data by phone lines or telemetry such that all data can be downloaded or transmitted from one location. The negative of this approach is the extensive "heavy duty" cabling required between sensors and recorders.
C. All recording systems up to and including Pier 5 be placed on ground in a secure housing at Bent 1 (Missouri side) or Pier 2 or Pier 3. All recording systems from Pier 6 through Pier 15 be located in a secure housing on the Illinois side. This will also require extensive cabling..
2.3 Special Considerations for Weather
In addition, it is essential to consider the general weather requirements for the instrumentation. Cape Girardeau area often is subjected to severe thunderstorms and lightning. Therefore, at each step of the way, lightning protection for the seismic instruments will be required. This is available for the type of recording systems that are cited later on in the proposal. However, special transient protection hardware is necessary for the downhole accelerometers.
3.0 Permanent Seismic Instrumentation for Cape Girardeau Bridge
3.1. General
In Figures 1 through 10, general and detailed strong-motion instrumentation of the Cape Girardeau Bridge and associated free-field arrays are described. Figure 1 shows the general locations where sensors should be deployed in order to record motions of and assess the following responses of the bridge and its vicinity:
a. Free-field motions at the surface and downhole locations reaching competent (i.e.unweathered) rock.
b. Overall motion of the cable-stayed bridge, c. Motions of extreme ends of the bridge as well as intermediate pier locations to provide data
for the translational, torsional, rocking and translational SSI at the foundation levels. Thissetup will also provide insight into the horizontal and vertical spatial variation of groundmotion,
d. Motions of the two towers to assess their translational and torsional behavior - relative to thecaissons and deck levels,
e. Motions of the deck to assess the fundamental and higher mode translational (longitudinal,transverse and vertical) and torsional components.
In this particular description, no specific downhole arrays below the caissons of Piers 2 and 3 are considered. The argument for this is that the motions at the free-field (surface and downhole) in the vicinity of Bent 1 (on the Missouri side) and Pier 15 (on the Illinois side) can be justifiably used as surrogate motions to perform detailed analyses of the bridge deck, piers with towers, towers, piers without towers and caisson tops. Also, no load cells for the cables are included. If desired, these could be added on to the overall list and the costs associated with the load cells also can be summed up to the rest of the hardware detailed below.
However, because of the changes in interlayering of soft and hard rock at Piers 4 and 5, we recommend that three triaxial accelerographs (two downhole and one surface accelerographs) be deployed at approximately 100 ft to the North or South of Pier 5. Theinstrumentation costs for this additional array is included in the cost estimates that follow.
No installation costs are included in this proposal. Such costs will require separate evaluation following decisions to adopt parts or whole of the specific instrumentation proposed.
3.2. Specifics
Figure 2 shows Bent 1 where only a triaxial unit is planned. However, in the immediate vicinity of Bent 1 and Pier 15, within a distance of 100-300 m, it is recommended to provide free-field arrays as shown in Figure 3. These free-field locations, without any feedback from the structure, will be essential in providing the ground motions that may be used as a surrogate for the various piers of the bridge and also for convolution and deconvolution studies of the free-field ground motion. Specific sensors, the particular orientations desired are shown on each figure and are also
summarized in Table 1. Also in Table 1, approximate costs of each unit is provided so that a rough estimate of total cost for required hardware can be made.
Also, as repeated above, because of the changes in interlayering of soft and hard rock at Piers 4 and 5, we recommend that three triaxial accelerographs (two downhole and one surface accelerographs) be deployed at approximately 100 ft to the North or South of Pier 5.
Figures 4-8 show instrumentation at Piers 2, 3 and 4. The specific caisson instrumentation is shown in Figures 4-7. Caisson 2 will be equipped with one vertical sensors only to detect vertical translational and additional horizontal sensors to detect translational (longitudinal and transverse) motions. Caisson 3 will be equipped with one vertical sensors at each of the 3 corners to detect vertical translational and rocking motions, if any and additional horizontal sensors to detect translational (longitudinal and transverse) motions.
Figure 8 shows deck level instrumentation for Pier 4. Essentially, this will be repeated for Piers 5, 10 and 15. At each of the the foundation levels of Piers 5, 10 and 15, a triaxial accelerograph is planned. For specific piers, this might be modified if so desired.
Figures 9-11 show general instrumentation scheme for deck location at the centerline (CL) of the cable-stayed deck, and at the "quarter" locations (LI, L2, Rl and R2).
3.3. Approximate Total Cost for the Hardware
The approximate total cost for the hardware for the instrumentation scheme presented herein is summarized in Table 2. The total shown ($360K) provides an insight of the cost levels that is envisaged. The configuration of the instrumentation can be changed in any other fashion desired and estimates of the total can be easily revised.
To repeat, the cost estimates do not include installation costs. Similarly, the estimates do not include costs for dedicated phone lines (if desired) or telemetry system (if desired) for communicating with the recording systems and transfer of data to another location. However, these can be detailed and added later on once the scheme of instrumentation is finalized and the location of the recording systems are decided upon.
4.0 Conclusions and Recommendations
This final proposal details the seismic instrumentation scheme for the Cape Girardeau Cable- Stayed Bridge now under construction. The scheme described provides extensive strong- motion response recording capability to facilitate different types of studies and to assess the performance of the subject structure during strong-motion events. It is noted that the instrumentation scheme recommended herein can also record low-amplitude motions (M~2-3). These motions can be used to estimate site-specific strong-motion events. However, it is recommendeed that the system be thought of as necessary for recording responses of the structure to moderate to large events.
References
1. Nuttli, O. W., 1974, Magnitude-recurrence relation for central Missippi Valley earthquakes, Seismological Society of America Bulletin, 64, pp. 1189-1207.
2. , Gebtechnical Seismic Evaluation Proposed New missippi River Bridge (A-5076) Cape Girardeau, Mo, Woodward-Clyde Consultants Report 93C8036-500, March 1994.
APPENDIX A. SYMBOLS USED
Symbols for Direction of Sensors:
L: Longitudinal direction of the bridge T: Transverse direction of the bridge V: Vertical
Symbols for type of Sensors:
LC: Load Cell (not recommended in this proposal) FBA: Force-balance accelerometer
Uniaxial [FBA-11],Biaxial [FBA-22],Triaxial [FBA-23],Traxial Downhole FBA-23DH
TABLE 1. CAPE GIRARFEAU BRIDGE INSTRUMENTATION
LOCATION
BENT1PIER 2
PIERS
PIER 4
PIERS
DECK
PIER 10
PIER 15
Top of Tower
Mid-Tower
Deck Level
Caisson TopTop of Tower
Mid-Tower
Deck Level
Caisson Top
Caisson Top
Deck Level
Deck Level
FoundationL1
L2
R1
R2
Deck Level
FoundationDeck Level
Foundation
South EndNorth EndSouth EndNorth EndSouth EndNorth EndN-ESouth EndNorth EndSouth EndNorth EndSouth EndNorth EndN-EN-WS-WN-EN-WS-W
South EndNorth EndSouth EndNorth End
South EndNorth EndSouth EndNorth EndSouth EndNorth EndSouth EndNorth EndSouth EndNorth End
South EndNorth End
Type of Instruments
FBA-23(triaxial)FBA-22(biaxial)FBA-22(biaxial)FBA-22(biaxial)FBA-11(uniaxial)FBA-22(biaxial)FBA-11(uniaxial)FBA-23(triaxial)FBA-22(biaxial)FBA-22(biaxial)FBA-22(biaxial)FBA-11(uniaxial)FBA-22(biaxial)FBA-11(uniaxial)FBA-23(triaxial)FBA-1 1 (uniaxial)FBA-22(biaxial)FBA-23(triaxial)FBA-1 1 (uniaxial)FBA-22(biaxial)FBA-22(biaxial)FBA-1 1 (uniaxial)FBA-22(biaxial)FBA-1 1 (uniaxial)FBA-23(triaxial)FBA-22(biaxial)FBA-1 1 (uniaxial)FBA-22(biaxial)FBA-1 1 (uniaxial)FBA-22(biaxial)FBA-1 1 (uniaxial)FBA-22(biaxial)FBA-1 1 (uniaxial)FBA-22(biaxial)FBA-1 1 (uniaxial)FBA-23(triaxial)FBA-22(biaxial)FBA-1 1 (uniaxial)FBA-23(triaxial)
PURPOSE
Bent 1 motions(L,V,T)Tower top motions (L,T)Tower top motions (L,T)Mid-tower motion (L,T)Mid-tower motion (T)Deck motion (L,T)Deck motion (L)Caisson top (L,V,T) & SSITower top motions (L,T)Tower top motions (L,T)Mid-tower motion (L,T)Mid-tower motion (T)Deck motion (L,T)Deck motion (L)Caisson top (L.V.T) & SSICaisson top (V) & SSICaisson top (L,V) & SSICaisson top (L.V.T) & SSICaisson top (V) & SSICaisson top (L,V) & SSIDeck motion (L,T)Deck motion (L)Deck motion (L,T)Deck motion (L)Foundation(L, V,T) &SSIDeck (V,T)Deck (V)^eck (V,T)Deck (V)Deck (V,T)Deck (V)Deck (V,T)Deck (V)Deck motion (L,T)Deck motion (L)Foundation(L,V,T) &SSIDeck motion (L,T)Deck motion (L)Foundation(L, V,T) &SSI
NO
111111111111111111111111111111111111111
$(K)
$ 3.00$ 2.00$ 2.00$ 2.00$ 1.00$ 2.00$ 1.00$ 3.00$ 2.00$ 2.00$ 2.00$ 1.00$ 2.00$ 1.00$ 3.00$ 1.00$ 2.00$ 3.00$ 1.00$ 2.00$ 2.00$ 1.00$ 2.00$ 1.00$ 3.00$ 2.00$ 1.00$ 2.00$ 1.00$ 2.00$ 1.00$ 2.00$ 1.00$ 2.00$ 1.00$ 3.00$ 2.00$ 1.00$ 3.00
10
FREE-FIELD
FREE-FIELD
FREE-FIELD
MISSOURI SIDE (See Note 1)
ILLINOIS SIDE (See Note 4)
PIERS(See Note 7)
FOOTNOTES:1
23456789
At 50-1 00m from the bent
SurfaceDownholeDownholeSurfaceDownholeDownholeSurfaceDownholeDownhole
Bentl
At bottom of soil layers
FBA-23(triaxial)FBA-23DH(triaxial)FBA-23DH(triaxial)FBA-23(triaxial)FBA-23DH(triaxial)FBA-23DH(triaxial)FBA-23(triaxlal)FBA-23DH(triaxial)FBA-23DH(triaxial)
At SurfaceAt mid-depth (See Note 2)At Solid Rock (See Note 3)At SurfaceAt mid-depth (See Note 5)At Solid RockfSee Note 6)At SurfaceAt mid-depth(See Note 8)At Solid RockfSee Note 9)
At Vs>7000 ft/s or 100 ft below the soil/rock interfaceAt 50-100 m from Pier 15At 3 m below liquefiable zone (N>30)At Vs>7000 ft/s or 100 ft below the soil/rock interfaceAt 100 ft North or South from Pier 5At soil/rock interface (top of weathered rock)At Rock (same as 3 or 6)
111111111
$ 3.00$ 11.00$ 11.00$ 3.00$ 11.00$ 11.00$ 3.00$ 11.00$ 11.00
ADDITIONAL NOTES:
1. Each one of the downholes at East Free-Field, West Free-Field and at Pier 5 should be P-S Suspension Logged.
2. Exact location of the intermediate downhole accelerograph will be determined folowing the observations of the P-S suspension log of the lower (rock) downhole.
3. It is very likely that two separate boreholes will have to be drilled and cased at each of the East, West and Pier 5 locations to deploy two downholes, one each at a different depth. Deployment of two downholes in the same borehole is difficult.
11
TABLE 2. APPROXIMATE HARDWARE COST
SENSOR TYPE
FBA-11FBA-22FBA-23FBA-23DH
RECORDERS
Mt. WhitneyK-2
CABLES
RegularDownhole
CONDUITS
MISCELLANEOUS
CHAN7UNIT
1233
Up to 183-12chan.
QUANTITY
1418106
52
8000 ft.1500ft.
5000ft
CHANNELS
1436301898
UNIT
CfO^ 1.00$ 2.00$ 3.00$12.00
$21.00$13.00
$ 2.00$10.00
$ 3.00
TOTAL
00$* 14.00$ 36.00$ 30.00$ 72.00
$ 152.00
$ 105.00$ 26.00$131.00
$ 16.00$ 15.00$ 31.00
$ 15.00
$ 31.00
$360.00
COMMENTS
Flexible ConfigurationFlexible Configuration
GRAND TOTAL
12
MIS
SOU
RI
SID
E FR
EE
-FIE
LD
AR
RA
YPI
ER
5 F
RE
E-F
IEL
D A
RR
AY
[N
OR
TH
OR
SO
UT
H O
F PI
ER
5]
ILLI
NO
IS S
IDE
FREE
-FIE
LD A
RR
AY
rnrr
rr
f -
!« -*
(NC
O
w PQ
O
W
Q
(N J Q
C/3
^^
PM
J
O
SI
u f
cQ
§
bi
o
O §
(N O
W
Q
e
CA
PE G
IRA
RD
EA
U B
RID
GE
GE
NE
RA
L L
OC
AT
ION
S O
F SE
ISM
IC I
NST
RU
ME
NT
AT
ION
AL
ON
G T
HE
BR
IDG
E
FIG
UR
E
1
«
BB
C
CH
Q B
CM
t
« fH
p tf
*r
i
PLA
N
C U
K
CH
O K
MT
I
CA
PE C
NU
RO
CM
I
SE
CTI
ON
TH
RU
R
OA
DW
AY
FILL
MD
f TO
SC
Atf
MO
Tt:
nvm
r nu
y*u
tf
co f
iem
TO
me
nttn
not
cmr
sccn
on M
O UP
to
me
CLfvt
noH
or m
e to
rn*
or m
e CM
C an
tr r
oom
ie W
IN*
mr a
trrs
or
me
sm/c
ruK
f AND
ro*
>ar
es
s nt
* 75
- in
vat
or m
e nu
ncr
or
nr
CM
C K
HT
tC
TO
Hf
ffO
fST
M.
PU
T.
Mf
CO
MS
lmjC
ltD
___
nu
att
une
KAN
AMD
or. v
is *
r n
o t
on
i t
en*
to *
otom
r fu
ns.
SM
fCT
MO
. S
S.
ELE
VA
HO
N
STEE
L A
TER
NA
TIVE
EN
D K
>T
1
GR
AD
ING
D
ETA
ILS
r*n
r n
i AP
HTAI
I rn
UO
/iir
YA
ND
FR P
O
flA
5076
INST
RU
ME
NT
AT
ION
OF
BE
NT
1
FIG
UR
E
2
MIS
SOU
RI S
IDE
FREE
-HEL
D A
RR
AY
SUR
FAC
E (T
RI-
AX
IAL)
PIER
5 F
REE
-FIE
LD A
RR
AY
[N
OR
TH O
R S
OU
TH O
F PI
ER 5
]
SUR
FAC
E (T
RI-
AX
IAL)
DO
WN
HO
LE (T
RI-
AX
IAL)
IN
TER
MED
IATE
LO
CA
TIO
N
tf
tk J9-** D
OW
NH
OLE
(TR
I-A
XIA
L)
HA
RD
RO
CK
DO
WN
HO
LE (T
RI-
AX
IAL)
INTE
RM
EDIA
TE L
OC
ATI
ON
]^/
DO
WN
HO
LE (T
RI-
AX
IAL)
HA
RD
RO
CK
ILLI
NO
IS S
IDE
FREE
-HEL
D A
RR
AY
SUR
FAC
E (T
RI-
AX
IAL)
DO
WN
HO
LE (T
RI-
AX
IAL)
; [
_»
INTE
RM
EDIA
TE L
OC
ATI
ON
| / D
OW
NH
OLE
(TR
I-A
XIA
L)
HA
RD
RO
CK
FRE
E-F
IEL
D A
RR
AY
S
FIG
UR
E
3
. -
^ .
v_
- *^ a-
e-
9--
0-
- *
SE
CT
ION
A
-A
5 u >
r-r
t-t-
1^
-
J000
321
CAPC
O
WM
DEA
U
S2
»?
SEC
TIO
N C
-C
SEC
TIO
N
0-Q
EUCV
ATIOH
PEER
2 C
AIS
SON
[3 V
ERTI
CA
L, 1
TR
IAX
IAL
, 1
UN
IAX
IAL
SEN
SOR
S]SI
DE
ELEV
ATIO
N
PIER
2
HO
ItS
mm
cuiM
t uo
uuxn
c. S
UOOI
HO
N
rHff
T S
/DC
S A
ND
HtM
NG
n
o /
HC
HAO
MMW
mpn
t on
£»C
H or
THF
roa
n sa
cs.
SHV.L
ec
usco
TO
ervf
i <u
.i CX
POSC
O CO
GCS
or T
HF P
KH* I
N M
O
CA
ST.
SHA
LL
TOP
OT
FQ
OT1
HG
ec fi
ACfo
HKH
fB T
utu
aevt
noH
SHO
HH
turn
na
ani
ime
a u
rn m
ta
tt
ratio
*M
ET
N
O
24
W
IK
A TE
RNAT
TVE
PIER
2
I D
IMEN
SK iN
S ,
CAPE
GlllA
ROEA
U CO
. UO
./ALE
XAtC
ER C
O. I
L.|A
50
76
INST
RU
ME
NT
AT
ION
OF
PEER
2
FIG
UR
E
4
CA
PC C
MM
KA
U
-
* s. .
'\ -
. '
VMHC
S 3-
-6"
h ro
f-f
VU
HfS
9--
0"
TO
I2--
OT
V. V. i V. A
S!
_r-r
SECT
ION!
-
ir-a
r
SE
CTI
ON
C
-C
ELEV
ATI
ON
SID
E
ELEV
ATI
ON
(NO
T
TO
SC
AL
f)
PIE
R
J
TR
IAN
GU
IAR
H
OU
tOIN
C.
SM
OO
TH
O
N
rHff
ff
SlO
fS
AM
P
HA
VIN
G
TWO
IN
CH
NOH/
HV.
HIDT
H O
N CA
CH O
F JH
f ro
nu
S/O
fS.
SH
AiL
K
U
SC
O
TO
fiT
VR
A
LLCX
POSC
O to
ces
or
me
PICK
* IN
N
O
CA
SC
S
HA
LL
T
OP
O
F
OK
TIt
lBU
TIO
N
CA
P K
P
LA
CC
O H
KH
fK
TH
AN
C
LC
VA
TIO
N
SH
OW
N
-
*
if
'
\ iio
r-a
r
SEC
TIO
N 0
-0
-
- *
if-f
f
SUE
STR
UC
TUR
E Q
UAN
TITY
TA
BLE
FOR
PI
ER
3IT
EMO
PCD
CC
D I
VS
SO
H O
f* J
C
ACH
SCAL
C
OH
t IC
TF
CLA
SS g
->
CO
HO
KT
f fr
C -
S.SO
O P
SI)
ndH
Fonc
r i
sim
(SP
IOCC
S)PO
Mro
HC
f t
sntl (I
foxr
CQAT
CO)
cu
YDCU
ro
LOS
IK
OU
AMTI
TY/
».M
*7
8.0
18
4
J.1
X.S
X
IMiJ
SO
rut
O»UH
MC a
MOT
no
sane
n
uo*
SMCI
I NO
M
or
it
sr-
rr-K
STEE
L Al
TER
NA
TIVE
PIE
R
3O
IME
NS
K N
S
-
OPE
GUA
RDED
CO.
yO.
/ALE
XANO
ER C
O. 1
L\ A
50
76
INST
RU
ME
NT
AT
ION
OF
PIE
R 3
FIG
UR
E
5
CA
PC
OR
AR
OEA
U
PIER
3
CA
ISSO
N
PLAN
Mores
. cxcA
mnoN
*io
mar
sum
ar
AS w
ar A
S to
ssm
u to
nc
uueN
SKNS
IMOK
ATTD
AS
IMT
AMSs
Of »
' P
tme
KXMM
T or
mr
5C«
COH
CKCT
t H
AS K
fH f
tUU
OtO
ft
m
OB
XM
OF
THC
OK
OC
tO
CAIS
SON rue
KKMM
T or
om
oix
*fus
ABO
* nc
TOP
or
sai
AMP
KIO
» ru
e ai
sm*u
noM
CAT
sm
u «M
W
nuto
rnn
t mn»
of
SAMP
.AN
Y m
m*
KCHO
VCD
rmv
nx C
ASSA
v H
fus
ABO*
of
sen
SMtU
BC
KC
PIA
CfO
m* A
M C
OU
MU
MT
» I
K O
T Sf
M.
CO
HC
MJt
AT
Frf
ifH
St
oo
nan
iwt
OW
MC
a n
or T
O SC
MX
nu
o*
STEE
L A
ITER
NA
TIV
EPI
ER
3 < A
ISSO
NDI
MEN
SIC
NS
|
CAPE
GIF
AROC
AU C
O. M
O./A
1EXA
NOER
CO.
IL
I A
50
76
Pffi
R 3
CA
ISSO
N [
3 V
ER
TIC
AL
, 1
TRIA
XIA
L, 1
UN
IAX
IAL
SEN
SOR
S]
FIG
UR
E
6
CA
PE
GH
WIO
CA
U
NO
TTS
tXC
AM
TU
N I
HT
O H
OC
K S
HtU
K
AS
NtA
* A
S e
OS
SB
Lt
tO
THE
O
ntf
/VS
fON
S
INO
KA
TfO
AS
TH
T IM
S.
Of
TH
f fN
T*C
V
OiI
Mf
Of If
f
SEA
L C
OH
CK
Tt
HtS
OC
f* I
HC
LU
Of.
IN
TH
C O
fSK
N O
f TH
C O
KO
CfD
C
AIS
SO
N ruf
voLu
tr o
r ow
ner
«eu:
ABO
* ru
t TO
P or
sen
t AM
D en
ow r
ue o
tsna
sum
H C
AP S
HAL
MCMW
V m
a> <
HTH
mm
on
SUMO
.AN
T m
rr*
KCVO
VCD
mou
nt
CASS
KH u
tus
Ago
* of
SIM
. SH
*. K
om
AC
fo u
riK A
H ro
un i
£nr
mss
or
sent
COH
CKCT
C AT
NO
AO
Om
ON
Al
[Xff
NS
C
PIE
R
4
CA
ISS
ON
P
LAN
ma
mw
mc
a n
or r
o SC
MC
nuto
*i N
n M
or
in
STEE
L A
.TER
NATT
VE
-TV
-if
! PIE
R
4 >I
SS
ON
! O
IMEN
SI I
NS
CAPF
Gl
tAR
nfA
U C
O.
MO
./ALE
XAN
OER
CO
. It
PIE
R 4
CA
ISSO
N
[3 V
ERTI
CA
L, 1
TR
IAX
IAL,
1 U
NIA
XIA
L S
ENSO
RS]
FIG
UR
E
7
\
3U
D3 1
~v/v
i vr»
t \j\jw
n H
IT
i ̂pcc.
r \jn.
r i
ITEM
Off
DC
CO
C
AIS
SO
N P
lfK
4
tAC
'
SC
Al
CO
NC
ae
f C
U.
Yl
CLA
SS
B
- 1
CO
NC
KT
t (F
V .
5.S
OO
K
l)
CU
H
RflW
OfC
INC
S
rcC
L (B
tHO
GfS
) if.
pfm
rofK
iHC
srm
fffo
xr
coA
ito)
I*
OUA
MTT
TY/
J.9
94.3
3.1
X4
S0
9.9
X
297. M
O
i MO
L- ra
.^T
10
K~
C
AP
t G
MU
ftOC
AU
\
T4
nort
TH
CSC
ouAH
nncs
«w
mau
oeo
in m
e es
mnt
o TA
BLC
ON s
iftj M
O. t.
V
LAtd
tAL
CO
RfS
rHM
NC
* C
[U
0CD
sn
o/v
JM/5
1
» -
/
, 4
1--
3-
I
r 41
--3-
9-1
-U
K-
Sf*
K f
J-4
)C
UK
. S
P*
STA.
tO
3*t
{
N3 o
NO
Tf-
1HIA
NG
UIA
* H
OM
OtH
C,
SM
OO
tH O
N
/MD
CT
SX
fS A
MD
HtV
IHC
m
O f
tCH
HO
HN
Al
MO
M O
N C
AC
H V
"f f
tMH
SDC
S.
SH4U
. K
USe
D
TO B
fWl
AU
C
XP
OSt
V [
DG
fSo
r TH
C fX
*ro
* PC
*ro*
ciNG
oerA
ns.
see
snee
r no
71
ro
* CA
ISSON
oeT
Ans.
see
snee
r HO
S. tt
mm
i TO
SP
AN (
4-5)
is
nor j
HCiu
oeo
IN m
is c
o*m
*cr
* M
HO
CA
SC S
HA
IL
TOP
OT
Ols
mB
un
OK
CA
P 9C
PL
AC
eO H
KH
CR
mA
N f
LC
mn
ON
SM
Om
t
euv
. ft
foo
f-F
ir-c
r I
a-o
r I
if-o
- :
jr-r
'
j»--
r49
--<r
9'-
f
49'-O
~
98--
0'
t--r r.
!a-
-r \
s--
JL
*L-
5)!t
*
***
* **
*
RU
STI
CA
TIO
N
DET
AIL
(n
or m
soS
t}
ELEV
ATI
ON
noir
IM
S o*
nnc
is n
or m
sou
. ro
uar
SHOT
NO
M
or <
»
VIEV
A
-A
i ST
EEL
/.TE
RN
ATt
VE
PIE
R
4
' D
IME
NS
I )N
S
-
»-«
««
i CAP
E GI
WRD
EAU
CO.
MO./A
LEXA
NOER
CO.
11.
| A
5Q76
INST
RU
ME
NT
AT
ION
OF
PIE
R 4
FIG
UR
E
3
PIE
R 2
UMIT
i -
t.oee
'-tf
sna
omc-
srm
ro u
mr
DE
CK
-CL
(4
SEN
SOR
S)
DE
CK
-LI
(3 S
ENSO
RS)
D
EC
K-L
2 (3
SE
NSO
RS)
; ST
EEL
/ .T
ERN
ATI
VE, C
ABLE
I A
YOUT
AN
D ED
GE
GIR
DER
SH
OR
TEN
ING
SH
EET
OF
2
CAPF
GUA
RnFA
ll CO
MO
./ALE
XAND
ER C
O. I
Ll
A5
07
6
FIG
UR
E
9
N3
N3
10
H«-
CA
PE
OR
AR
OC
MJ
T?
PIE
R 3
L/m
r i
- 2.
off
-i'"
sv
n
ctB
U-^
Ttyt
P u
wi
DECK-CL (
4 SENSORS)
DECK-R1
(3 SENSORS)
DECK-R2
(3 SENSORS)
I CAB
LE
U Y
OU
T A
ND
ED
GE
GIR
DER
SH
OR
TEN
ING
1 S
HEET
2
OF
2 , -
CAPF
H
ff W
DFA
II CO
M
O./A
LEXA
NO
ER C
O.
II. I
A5076
FIG
UR
E
10
INST
RU
ME
NT
AT
ION
FO
R C
EN
TE
R O
F SP
AN
[D
ECK
-CL]
96--
0' o
ur r
o ou
r
£3
Ltf
-O'
t W
t
SB
i ft
1C' -
IT
SM
OU
IOC
*
I-\«
>
j~ S
IK*
mr
cww
nwr
ffiO
THC
SlH
rtC
fll
~ P
UC
CtS
' C
OH
OV
rt S
tAB
SH
OU
LOe*
H
\l--f
SH
OU
LO
f*
C
BR
IDG
f A
HD
pfon
tf et
uoe
(4 S
EN
SOR
S)TY
PIC
AL
SE
CTI
ON
lO'-
f SH
OV
LOC
*
riftf*
atc
mov
.C
ON
DU
ITr
JZ£
TT-M
T
i
INST
RU
ME
NT
AT
ION
FO
R D
EC
K L
OC
AT
ION
S L
I, L
2, R
l an
d R
2ff
'-O"
our
ro o
ur
l^.
r-r
& !
r s
tK*
muc
con
cern
ir f
arc
er
coiic
orrf
SIA
B I
-QO
'M'jI
L
\,--
g-
SH
OU
LO
f*
pfon
tf d
uoe
TYP
ICA
L S
EC
TIO
N
ie--
f SM
OUUX
*u
»r
STD
^fr
ou
fK^
tf
DE
CK
-LI
(3 S
EN
SOR
S)
DEC
K-L
2 (3
SE
NSO
RS)
D
ECK
-R1
(3 S
EN
SOR
S)
DE
CK
-R2
(3 S
EN
SOR
S)
FIG
UR
E
11