Upload
jerome-wilson
View
76
Download
4
Embed Size (px)
Citation preview
CORNHUSKERS WIND ESTATE
P.O. Box 17000Kernel Street, Nebraska 84673-9864
CEO: Jerome Wilson
1
Table of Contents1. Project Description and Goals............................................................................................ 4
1.1 Project Scope.................................................................................................................................. 41.2 Workflow and Methodology.......................................................................................................4
2. Project Site and Area........................................................................................................... 7
3. Met Tower.............................................................................................................................. 83.1 Location, Instruments and Data................................................................................................8
4. Wind Data............................................................................................................................ 124.1 Process of Quality Control and Analysis...............................................................................134.2 Wind Climate and Wind Data Analysis................................................................................15
5. Wind Flow and Resource Modeling...............................................................................255.1 Flow Model and Input Data..................................................................................................... 26
5.2 Resource Grids..........................................................................................................................................285.3 Resource Grid 1........................................................................................................................................285.4 Resource Grid 2......................................................................................................................................285.5 Resource Grid 3......................................................................................................................................28
5.2 Results and Wind Maps............................................................................................................ 28
6. Site Assessment and GIS Analysis..................................................................................326.1 Setbacks........................................................................................................................................ 326.2 Set Back Matrix.......................................................................................................................... 33
7. Project Wind Turbines...................................................................................................... 357.1 Technology and Specification..................................................................................................38
Siemens SWT 2.3............................................................................................................................................38Clipper 2.5 C96................................................................................................................................................39G.E 2.75-103.....................................................................................................................................................39Suzlon S88 2.1.................................................................................................................................................40Vestas V80-1.8.................................................................................................................................................40Vestas V112-3.0..............................................................................................................................................41
8. Layout Design and Micro Siting...................................................................................... 428.1 Final Layout and Design of Turbines....................................................................................42
9. Site Suitability Analysis.................................................................................................. 43
10. Wind Farm Estimated Productions..............................................................................4610.1 Preliminary estimated AEP calculations.............................................................................46
WTG’s Comparison.......................................................................................................................................4810.2 Modeled AEP Calculations of Final Layout.......................................................................49
11. Project Economics............................................................................................................ 5011.1 Financial model and input data.............................................................................................5111.2 Debt/Equity, Taxes and Abatements....................................................................................53
12. Environmental Analysis and Biological Impacts.......................................................5311.1 Fatal Flaws Analysis................................................................................................................ 5411.2 Noise, Shadow Flickering, Visibility, Safety, Radar, Telecommunication..................6211.3 Biological Impacts.................................................................................................................... 66
2
11.3 Water Resource and Soil Erosion.........................................................................................6711.4 Public Health and Safety Considerations............................................................................6911.5 Ground Transportation and Traffic....................................................................................7011.5 Solid and Hazardous Waste................................................................................................... 7111.6 Air Quality and Climate Impacts.........................................................................................7111.7 Socioeconomics and Land Values.........................................................................................7211.8 Archaeological and Cultural Resources..............................................................................73
13. Grid Interconnection....................................................................................................... 7413.1 Capacity, Voltage and ECC analysis....................................................................................7413.2 Loads, System Protection and Conditions..........................................................................76
14. Permitting.......................................................................................................................... 7914.1 Federal, State and Local......................................................................................................... 7914.2 Land Use and Building Permits............................................................................................81
15. Land Agreements, Land Owners Consideration.......................................................8215.1 Terms, Rights and Compensation........................................................................................ 8215.2 Royalty, Indemnification and Reclamation Provisions....................................................8315.3 Public Outreach........................................................................................................................ 84
16. Construction...................................................................................................................... 8416.1 Collection Lines, Service Roads and Logistics...................................................................8516.2 Contracting and Building Site...............................................................................................86
17. Post Construction Monitoring and O&M...................................................................87
18. Project Lifetime, Decommissioning and Remediation..............................................88
19. Conclusion.......................................................................................................................... 89
3
1. Project Description and Goals
1.1 Project Scope
Selection of site for the installation of the met tower is a very complex job.
Hence, various factors are involved which will need to be addressed before
finalizing the location. The goal of this project is to design a 50MW or better
wind farm. We want to have the maximum possible energy output and at the
best price while maximizing the use of land and funds. The typical amount
of wake loss should be below 5% for the entire project and no more than 2-
3% for each turbine. This wind farm will be the most cost efficient and
affordable route with the highest possible profits.
1.2 Workflow and Methodology
4
The objective of the project is to identify a wind resourceful area in Brown
County, Nebraska where future wind power projects can be installed.
Detailed wind resource assessment is considered essential for estimation of
the wind power potential and evaluation of the most promising site for wind
farm development. In order to achieve this objective, a met tower was
erected at the selected site displayed in Fig.2. The complete measurement of
wind data comprised of four anemometers for measuring wind speed, two
wind vanes for wind direction measurement, one temperature, and humidity
sensors. The wind speed is the most essential site indicator; therefore,
anemometers were installed at three different heights to determine wind
shear individuality.
The project from Windographer is imported directly into WAsP, where data
created were observed, generalized, and predict wind climates. Observed
wind climate refers to the general nature of the cleaned data for the entire
area around the met tower. The generalized wind climate is the specific wind
climate around the met tower at the given heights and locations of
instrumentation. To generate the predicted wind climate, which is the
climate for given turbine locations, the data is further analyzed to account
for the topography of the site, and how the topography may affect the
behavior of the wind around each turbine site. The predicted wind climate is
used to calculate wake effect losses at each site, and ultimately, the annual
energy production for each turbine and the site as a whole. Once the project
has been imported into WAsP from Windographer and the predicted wind
climate has been calculated, we created three resource grids to begin
building the wind farm. The vector map for all of the possible surrounding
areas is presented at 500, 250 and 50 meter resolution, from which we
5
selected an area which appeared to have good wind resources and
topography.
Wind Atlas Analysis and Application Program (WAsP) was then used to
assess wind resource assessment, horizontal and vertical extrapolation of
wind data can then be performed through WAsP. It contains a complete set
of models to calculate the effects on the wind on sheltering obstacles,
surface roughness changes, and terrain variations.WAsP also calculates the
ruggedness index (RIX), which uses numerical values to indicate how rough
the terrain is, and as a result, whether or not the flow of the wind will likely
become separated and more turbulent or not. A RIX value of ~0% means
that flow will stay attached, whereas a value greater than 0% means that
flow will likely become separated in some places. While we did not
encounter any obstacles with this project site, there is still on obstacle layer
present in the project in WAsP. Obstacles are defined as anything which
could affect the behavior of the wind, or which we would need to create
siting setbacks.
Furthermore, once the collected data was retrieved and stored on the servers.
Data is then validated manually and through wind data retrieval software to
screen the data for any inconsistency or error and the missing data is
reported. The reason for erroneous data like faulty sensor were immediately
detected and rectified to improve the reliability of the data. Data validation
was done by verification of data records, time sequences, and range test.
Relational checks were made by verifying relationships between different
physical parameters. It is a critical step because accuracy of the WAsP
predictions depends on the accuracy of the met tower location. After the data
6
is being validated, the data is being processed for usage. Validated 10 min
data steps were converted into hourly average data base using WAsP.
Average wind speeds and annual wind speed values are then calculated from
the software. Wind rose is developed for the wind direction data received
from the site. Temperature data was also received and monthly averages
were calculated. The complete data set of approximately 23 months was
analyzed to conclude the results of the wind farms feasibility.
2. Project Site and Area Brown County lies in the north central region of Nebraska. It is bordered on
the north by the Niobrara River and Keya Paha County, to the west by
Cherry County, to the south by Blaine and Loup Counties, and to the east by
Rock County. Brown County is twenty-six miles wide and averages forty-
six miles in length containing 1,214 square miles of territory. Brown County
is divided into three physiographic regions. The largest portion of the county
is in the Sand Hills region. It is composed of sandy loam soil and is very
hilly. There are numerous lakes and marshes to be found in the valleys. In
the northeast corner of the county the land is classified into the Holt Table
category, characterized by gently rolling plains. On the county's western
border lies the Niobrara River Valley which is one of Nebraska's most
naturally scenic and beautiful regions.
The chosen site for the wind farm is basically just an agricultural farmland
just north of two major cities, Johnstown and Ainsworth. Within the area
just southeast towards the right bottom corner of the project site there are
multiple crop circles, which indicate that there are a lot of farming activities
7
present. On the other hand, North side of the project area has little to no
farming activities present. There is a canyon running through from north to
south of the site location, which is displayed as blue lines running through
the project. The met tower location and the site are also easily accessible by
dirt roads, making this area an ideal location to construct a wind farm
project.
Figure 1- Google Earth Sat Image of Project Area
3. Met Tower
3.1 Location, Instruments and Data
Figure 2 is a Google map image of the monitoring site meteorological tower
location and the surrounding area.
8
Figure 2 -Google Map Image of Met Tower Location
Figure 3 is a Google Earth sat image of the meteorological tower of the
monitoring site location, which displays agricultural activities and semi dry
flat land features.
Figure 3-Google Earth Sat Image of Met Tower Location
The data used for the present analysis are from September 14, 2007 to July
30, 2009 for the site. The tubular meteorological tower data used was given
for the met tower located at 42°43'36.55"N and 100° 1'14.58"W. The
selected site for the installation of the met tower is an elevated area
9
approximately 2500 ft. Surrounding areas consist of agricultural farmlands,
whereas, the population is mostly on the southeast corner of the project area.
Instrumentation is located at 10, 30 and 60 meters providing wind speed, 30
and 60 meters for wind direction, and 2 meters for temperature of the given
heights. The Met Tower is configured with anemometers (to measure wind
speed), which are capable of recording wind pressure or wind velocity. Since
speed and pressure are so closely related, many anemometers are able to tell
us both values.
This consists of three hemispherical cups attached at right angles to each
other and then placed on the met tower. The moving air would then push the
cups until they were moving in circles. The rotating cups in turn rotate the
inner shaft along a vertical axis of rotation. Then the inner shaft transports
the information to computers, which record the number of times the cups
rotate and then calculates the average wind speed. Correspondingly, wind
vanes measure wind direction. The wind vane is mounted on a central
rotation shaft, which allows the vane to move freely. The surface area of the
vane is unevenly distributed on either side of the shaft. The side with the
larger surface area will be pushed further by the wind and therefore, the
smaller surface area will point in the direction the wind is blowing from.
Additional data, such as pressure and temperature, will be recorded through
an air pressure and temperature sensor mounted on the met tower. Typically,
this is used to determine the overall density of the air in the project area for
the application of the power formula. The wind data is sampled
continuously, recorded approximately over 10-minute intervals by a data
logger, and then transmitted remotely using a modem and internet
10
connection. From this data, we can then find minimum, maximum, and
standard deviation values for each height, as well as turbulence intensity,
wind power density, and surface roughness, among other values.
After taking into account the topography factors, the following results are
attained for the annual data, including wind speed and direction collected at
the met tower. The met data included 10 minute average of wind speed and
direction.
ParameterMeasured Emergent
Discrepancy
Mean wind speed [m/s] unknown 8.1 unknownMean power density [W/m²] unknown 496 W/m² unknown
Figure 4-Results from Observed Wind Climate
The complete dataset runs from September 2008 to July 2009. As shown
below, the information provided in Figure 5 gives all location information
for the meteorological tower used for this project, as well as average
environmental conditions, and calculated wind power and wind shear
coefficients. The wind power coefficients are especially important because
they give us the wind power density at 80 meters above ground, which is
essential for calculating power in the wind, and ultimately, project
economics. The data was processed using Windographer software.
Data Set Summary Variable ValueLatitude N 42°43'36.55"
LongitudeW 100° 1'14.58”
Elevation 789 mStart date 9/14/2007 0:00
11
End date 7/30/2009 0:00Duration 23 monthsLength of time step 10 minutesCalm threshold 0 m/sMean temperature 16.8 °CMean pressure 92.14 kPaMean air density 1.109 kg/m³Power density at 50m 362 W/m²
Figure 5-Met Tower Dataset Summary
4. Wind Data
Before WAsP can project and estimate wind speeds, direction and power
production at chosen locations, the provided wind data has to be analyzed.
The 10 minute wind measurements are analyzed and a statistical summary of
the observed, site specific wind climate is calculated. The output is a wind
rose and the wind speed distributions in different sectors. A Weibull
distribution function is then fitted to the measured histogram to provide
scale and shape parameters A and k for each sector (see figure 6). The
Weibull distribution is well established for use with wind statistics as the
natural distribution often fits the Weibull shape .The observed wind data is
converted into a generalized wind climate also shown in Figure 5. The wind
observations have been cleaned with respect to site conditions such as,
buildings, surface roughness etc. This information was acquired from
different sources and was then converted into a map format which is
readable by WAsP.
12
Figure 6-Met Data of Wind Data
4.1 Process of Quality Control and Analysis
Figure 7 displays the Flags by Rules code for the data set, to begin the
quality control process a data set was given in excel format with two sheets
from two different time periods. In order to connect both sheets they were
appended in Windographer and then configured the codes. Ex.CH1Avg. the
data set in excel were then decoded by labeling what type of sensor, what
height it’s at and the units it’s using. It was then imported into the program
and it calculated the three main graphs, the vertical wind shear profile, the
monthly mean wind speeds, the wind frequency rose and the diurnal wind
speed profile. After data set sheet one has been calculated, in order to
13
combine both data into one program, sheet two was appended from the same
data logger/met tower to avoid having the same properties for the data.
After data has been appended, configured and calculated. The start of the
Quality Control Process was flag by rules, where we were able to flag for
odd data, negative wind speeds or wind speed in the negative direction,
icing, tower shadowing, Standard deviation range, Wind speed max and min
range. The primary purpose of quality control of observational data is
missing data detection, error detection and possible error corrections in order
to ensure the highest possible reasonable standard of accuracy for the
optimum use of the data. The first flag we added to the data was the “invalid
temperature flag” which flags for values of temperature outside possible
range of -40 to 50 degrees Celsius. Anything invalid is also considered to be
one time step. We then checked for “invalid wind speed” that is outside the
range of 0 to 30 for winds below 0 and greater 30 m/s. We could also test for
“invalid wind direction” outside the range of 0 to 360 degrees for invalid
wind outside range of 360 degrees.
Furthermore, we can then check for “icing” and the reason why we chose to
check for icing last is because we want to be able to have good data before
we start searching for environmental errors. These are typically more
complicated code because they require an “and” command and they also
require two to three time steps intervals because one time step is too often.
However, for this project we used the three time step; first icing we checked
for was “icing wind speed” which flags for sensors which are frozen and
then we checked for “icing wind direction” which also flags for sensors
which are frozen. Lastly, there are many other ways to search for data if you
14
know something happened by flagging manually by finding the date with
bad data you don’t like and apply it to icing or invalid code; there is also the
flag by scatter plot which allows you to flag for bad data between two
sensors and flag by tower shadowing where the tower is either speeding up
or slowing down the sensor based on the wind direction.
Figure 7-Flag by Rules
4.2 Wind Climate and Wind Data Analysis
Figure 8 gives the wind speeds from each pair of anemometers at 10m, 30m,
and 60m have been consolidated for both the power law and log law
calculations. As shown, both power law and log law approach yield
comparable results at the heights of measured data. This indicates the
amount of wind the turbines capture at certain heights. It is of crucial
importance in wind energy; its knowledge allows designating the energy
efficiency of the turbine. However, for extrapolating upwards 80m to 100m,
the log law yields slightly more conservative values than the power law for
the increased wind speed at higher elevations. Because the data shows the
shear declining going from 10m to 60m AGL, the more conservative log law
is the more appropriate for extrapolating upwards from 60m AGL.
The wind shear has a complex effect on the aerodynamics as the wind speed
experience by each blade. Refraction by wind shear is of paramount
15
importance in determining propagation paths of wind turbine noise. Wind
shear refraction shapes propagation paths in all directions, strongly affecting
intensity of sound at nearby homes and communities. Vertical wind shear is
a principal cause of noise levels generated from the turbines. Also it may
contribute to periodic fluctuations in electrical power output of the wind
turbine generator. Not only is that but, for the wind farm project the vertical
wind shear is an important design parameter because and it strongly
influence the lifetime of major components, such as blades and gearbox.
Figure 8-Vertical Wind Shear Profile
Figure 9 shows the wind speeds at each anemometer height, which are 60m,
30m and 10m as they plotted against time to depict the seasonal trends.
Wind speeds typically increase with increased height above the ground. The
collected data follows the pattern. The fall through March-April are the
windiest, and through August-September are the least windy.
16
Figure 9- Monthly Wind Speed Profile
Figures 10 show the mean diurnal profile of the wind data which is related to
the cost of energy. The monthly profiles are important because they
incorporate average values for each month in all years given. This can give
the developers and utilities an idea of what months they can expect more or
less wind power in, aiding in future forecasting. As shown in the diagram,
based on this location wind speeds at 1200hrs (12:00 noon) to 1800hrs (6:00
p.m) slows down drastically. Also, from about 7:00 a.m to 9:00 a.m wind
speeds increased for the remainder of the day. This basically means that
there is a lower capacity for this site.
Diurnal wind speed profiles are important for the same reason developers
and utilities need to know what time of day the wind power is greatest or
least to help with forecasting. It is essential that enough power is supplied to
the grid at all times; so accurate wind forecasting is essential. So to
17
recapitulate, diurnal profiles elaborate on the lower wind speeds increase
during the day while the upper wind speeds decrease respectively.
Figure 10-Diurnal Wind Speed Profile
Figure 11 is a wind direction frequency rose, illustrating the dominant wind
direction(s) for the given tower data which is observed from the southeast.
This is the most important during project development, as it will drastically
affect the layout of the wind turbines at the wind farm. Wind turbines are
placed perpendicular to the prevailing wind direction to minimize wake
effect losses and turbulent load on the wind turbines. This can have a
significant effect on project economics due to reduced energy production or
the need to replace fatigued turbines.
This rose is also important during project operation, as turbines will need to
be yawed toward the prevailing wind direction, should it ever deviate from
18
the average direction. For the wind farm project, predictable impacts of the
tower can be seen when the wind must go around the tower “in the tower
shadow” to reach one of the anemometers. The sensor in the shadow of the
tower sees turbulent wind often at reduced wind speeds, though the absolute
difference in wind speeds may be small, the ratio can be an identifiable
marker for the impact of the tower. This can be seen graphically in figure 8
above. The wind speed data from the anemometer not in the tower shadow is
used when the wind is coming from directions that will cause tower shading
Figure 11- Wind Frequency Rose
.The total energy wind rose shown in Figure 12 which portrays slightly
similar characteristics to the wind direction frequency does make a huge
difference in total energy consumed by the wind turbines. It’s exclusively
for plotting the proportion of wind energy coming from each direction
19
sector. Windographer uses the wind power density calculated for each wind
speed sensor for each time step, sorts them by direction sector and calculates
the total energy available for each direction over the entire period of the data
set, or the portion you have chosen in your filter settings.
The total energy wind rose is used in wind projects to portray the amount of
energy that will come into the wind project from various directions. The
wind rose helps developers site the turbines in such a way as to minimize
wake losses from other turbines developed at the site. The graph displays the
portion of the total wind energy coming from each direction sector. This
information is ultimately important when predicting the project economics,
therefore helping investors to properly analyze the layout of the wind farm
for project optimization output.
Figure 12-Total Energy Wind Rose
20
The probability distribution function displayed in Figure 13is typically
described using a Weibull distribution. There are two commonly used
factors to describe the characteristics of this distribution function, the
Weibull k and Weibull c factors. The Weibull k value is a unit less measure
indicating how widely the wind speeds are distributed about the mean with
values. The Weibull c is the scale factor for the distribution related to the
annual mean wind speed.
The best fit Weibull distribution parameters for the measured data at 60 m
are k = 2.50m/s and c = 8.99 m/s displayed in the figure. The distribution
shown in identifies that the most frequent winds are between 7 m/s and 10
m/s, as measured by the speed sensor at 60m.
21
Figure 13-Probability Distribution Function
Figure 13 illustrates the frequency percentage of time that the wind at 60m is
at a given wind speed, which shows how the wind speed distribution varies
throughout the year. To make the graphs more legible to read, representative
distributions are shown only for selected months. As can be seen, the months
July, August, and September are slightly shifted to the left indicating lower
average wind speeds in those months. Likewise, the more windy winter
months show similar shifts to the right. Windographer also calculates the
Weibull distribution curve along the histogram created for the frequency
distribution. It uses the maximum likelihood algorithm, which is also
illustrated in the figure 14 below.
22
Figure 13- Monthly Wind Speed Distributions at 60m
Weibull Weibull2 Mean Proportion Power RK c Above Density Squared
Algorithm (m/s) (m/s) 7.902 m/s (W/m2)Maximum likelihood 2.49 8.898 7.894 0.475 476.6 0.99228
Least squares 2.483 8.916 7.91 0.477 480.5 0.99188WAsP 1/2/1900 12:00 8.907 7.903 0.476 476.9 0.99255
Actual data(89,188 time
steps) 7.902 0.476 476.9Figure 14
The wind speed sensor summary shown in figure 15 below is created in the
table’s tab of Windographer. It is a culmination of the entire sensor
information, as well as information that can be calculated from the known
values at sensor height. We have all of the important information for a
sensor at 80 meters, or hub height. This is still synthesized data, and was
23
calculated using the log law for 60-meter sensor data. Noted, “MoMM”
stands for mean of monthly means.
VariableSynthesized 80 m
60m WS A
60M WS B
CH3Avg
CH4Avg
CH5Avg
CH6Avg
Measurement height (m) 80 60 60 30 30 10 10Mean wind speed (m/s) 8.431 7.997 7.905 6.739 6.654 5.367 5.327MoMM wind speed (m/s) 8.245 7.869 7.755 6.63 6.553 5.301 5.276Median wind speed (m/s) 8.344 7.9 7.8 6.5 6.4 4.9 4.8Min wind speed (m/s) 0.4 0.4 0.4 0.4 0.4 0.4 0.4Max wind speed (m/s) 24.862 19.9 25.5 23.4 23.7 20.9 21.3Weibull k 2.422 2.51 2.445 2.273 2.286 1.9 1.915Weibull c (m/s) 9.486 8.993 8.892 7.589 7.497 6.045 6.003Mean power density (W/m²) 532 443 436 286 275 173 169MoMM power density (W/m²) 506 426 418 276 266 168 165Mean energy content (kWh/m²/yr) 4,661 3,880 3,819 2,507 2,407 1,515 1,476MoMM energy content (kWh/m²/yr) 4,433 3,736 3,659 2,415 2,328 1,472 1,443Energy pattern factor 1.594 1.558 1.588 1.694 1.691 2.033 2.023Frequency of calms (%) 0 0 0 0 0 0 0Possible data points 98,640 98,640 98,640 98,640 98,640 98,640 98,640Valid data points 89,983 79,897 89,715 91,490 92,925 88,073 86,973Missing data points 8,657 18,743 8,925 7,150 5,715 10,567 11,667Data recovery rate (%) 91.22 81 90.95 92.75 94.21 89.29 88.17
Figure 15-Wind Speed Sensor Summary
Figure 16, 17, and 18 shows the annual statistics for certain values, which
can be found by selecting a certain data column (sensor values) in the table’s
tab of Windographer. Figure16 gives the annual statistics for the 80 meter
synthesized wind speed data, Figure 17 shows the annual statistics for the 60
meter wind direction sensor, and Figure 18 shows the annual statistics for
the 30 meter wind direction sensor. These tables give us a good idea of how
much of the data is good data, as well as how much is bad.
24
# YearPossib
le ValidRecove
ryMea
nMedia
n MinMax
Std. Dev.
Weibull k
Weibull c
Data Points
Data Point
sRate (%)
(m/s) (m/s)
(m/s)
(m/s) (m/s) (m/s)
1 2007 15,69615,61
0 99.457.95
3 8.196 0.5 20.4 3.202 2.673 8.923
2 2008 52,70452,64
9 99.9 8.39 8.313 0.5 25.5 3.619 2.469 9.447
3 2009 30,24029,96
1 99.088.61
4 8.546 0.52 26.2 3.602 2.556 9.689All
Data 98,64098,22
0 99.578.38
9 8.359 0.5 26.2 3.557 2.515 9.438MOM
8.244
Figure 16 – Annual Statistics 80m Synthesized Wind Speed
Year Possible Valid Recovery Mean Valid Recovery Median Min MaxStd. Dev.
Data Points
Data Points Rate (%) (°)
Data Points Rate (%) (°) (°) (°) (°)
1 2007 15,696 14,503 92.4 231.6 14,542 92.65 210 1 359 85.92 2008 52,704 49,946 94.77 216 50,010 94.89 198 1 359 86.53 2009 30,240 20,325 67.21 246.3 28,564 94.46 199 1 359 87.7
All Data 98,640 84,774 85.94 224.6 93,116 94.4 200 1 359 86.8
Figure 17 – Annual Statistics 60m Wind Direction
Year Possible Valid Recovery Mean Valid Recovery Median Min MaxStd. Dev.
Data Points
Data Points Rate (%) (°)
Data Points Rate (%) (°) (°) (°) (°)
1 2007 15,696 14,710 93.72 218 14,799 94.29 199 1 358 86.32 2008 52,704 50,407 95.64 188.6 50,706 96.21 178 1 359 88.23 2009 30,240 28,742 95.05 246.2 28,928 95.66 216 1 359 89.3
All Data 98,640 93,859 95.15 210.1 94,433 95.73 190 1 359 88.7
Figure 18 – Annual Statistics 30m Wind Direction
5. Wind Flow and Resource Modeling
25
In order to create wind energy models of the proposed area, I used
Windographer and Wasp to determine the coordinates of met tower location,
wind data generated from the project site, and maps were imported for
further analysis. WAsP uses these sets of data to generate the overall wind
statics of the project site. Along with the power curve, WAsP is able to
create outputs. A summary of the procedure is shown in figure 19.
Figure 19- Flow Model Procedure
5.1 Flow Model and Input Data
We used the WAsP flow model to create wind resource modeling for the
area in which will be feasible for project development. Following the
process described earlier in the Workflow and Methodology section, three
resource grids were created, one at 500 meter resolution, and a zoomed-in
resource grid at 250 meter resolution and 50 meter resolution to aid in the
proper placement of wind turbines. In figure 20 below is an image from
resource grid 1of the mean wind speed flow over the project area display
five row of turbines spaced approximately 12 diameters apart.
26
MetData Excel Windographer WAsp
Furthermore, the thin brown snake-like lines you see running throughout the
map are called contour lines. The contour lines allow you to infer general
terrain characteristics from their patterns. Whereas, the lines close to
together means that there are steep sections and lines spaced widely apart
indicate more gentle slopes. Hence, in order to get major output from the
wind turbines it’s best to place them in areas with lines that are close
together displaying higher elevation. On the left side and bottom of the map
you notice some numbers running along the outside of the map. These
numbers represent two grid systems that can be used to find your exact
location, they are the latitude and longitude given at equally spaced intervals
between corners. Also, in the bottom right color of the image you can
identify the color scale which shows the least amount of wind resource and
to greatest amount of the project area. (A more detailed explanation of color
scale is mentioned in 5.2 results and wind maps).
27
Figure 20-Wind Speed Vector Map of Project Area
5.2 Resource Grids
Figures 21, 22, and 23 contain the Grid Setup Table from the Resource Grid
Report for resource grid 1, 2 and 3. Here we are given the basic information
about the resource grid, including how many columns and rows it contains,
and at what height it was evaluated.
5.3 Resource Grid 1Structure: 44 columns and 44 rows at 500 resolutions give 1936 calculation sites.Boundary: (408415, 4715884) to (430415, 4737884)Nodes: (408665, 4716134) to (430165, 4737634)Height a.g.l.: 80m
Figure 21- Resource Grid 1 Setup
5.4 Resource Grid 2Structure: 49 columns and 42 rows at 250 resolutions give 2058 calculation sites.
28
Boundary: (410410, 4725606) to (422660, 4736106)Nodes: (410535, 4725731) to (422535, 4735981)Height a.g.l.: 80m
Figure 22 - Resource Grid 2 Setup
5.5 Resource Grid 3Structure: 145 columns and 136 rows at 50 resolutions give 19720 calculation sites.Boundary: (411341, 4728220) to (418591, 4735020)Nodes: (411366, 4728245) to (418566, 4734995)Height a.g.l.: 80m
Figure 23-Resource Grid 3 Setup
5.2 Results and Wind Maps
Figure 24 is a spatial view of resource grid 1 mean wind speed vector map,
which displays the best possible wind resource in the area for the placement
of the wind turbines. The warm colors like brown, orange, red etc. indicates
higher wind speeds. Cool colors like purple, dark blue, light blue etc.
indicates lower wind speeds, while also accounting for spacing guidelines,
wake effect, etc. The color overlay on the map allows you to compare
different areas of the project site using the color scale located in the bottom
right corner of the map (seen figure 27), which shows highest wind speeds at
9.43 m/s and lowest wind speeds at 7.14 m/s.
29
Figure 24-Mean Wind Speed Vector Map
The power density data mapping in figure 25 from the resource grid 1
purpose is to determine the cost efficiency in the distribution of wind power.
The colors on a power density map can be categorized as the blue to light
blue areas is considered as poor density, areas from light blue to green is
considered to fair, areas with yellow to orange is considered to be good and
areas orange to red is considered to have excellent density. The color scale
shown at the bottom (seen figure 28) gives a general idea of which area is
poor, fair, good or excellent for wind power distribution.
30
Figure 25-Power Density Vector Map
Figure 26 displays the RIX (Ruggedness Index) data of the resource grid 1
vector map. One objective measure of the steepness or ruggedness of the
terrain around a site is the so called ruggedness index or RIX, defined as the
percentage fraction of the terrain steeper than some critical slope. If the RIX
value is greater than 0%, parts of the terrain are steeper than 0.3 and flow
separation may occur in some sectors. This situation is generally outside the
performance envelope of WAsP and prediction errors may be expected.
Large RIX values will lead to large errors in the flow modeling
31
Figure 26-RIX Vector Map
Figure 27 contains the result tables from the Resource Grid 1 report of the
project area. It shows the mean speed values in meters per second, the power
density in watts per meter squared, and the ruggedness index values (as a
percentage) for the resource grid area selected. RIX values greater than 0%
mean that the terrain may be rough enough to result in flow separation of the
wind. This can mean a more turbulent load on our wind turbines, resulting in
shorter useful lifetimes or higher maintenance costs. Resource grid 1 has a
maximum RIX value of 11.5%, which unfortunately, is very high.
Mean Speed [m/s]Maximum Value: 9.43 m/s at (421665, 4737134)Minimum Value: 7.23 m/s at (420165, 4726134)Mean Value: 8.23 m/s
32
Power Density [W/m²]Maximum Value: 813 W/m² at (421665, 4737134)Minimum Value: 369 W/m² at (420165, 4726134)Mean Value: 538 W/m²
RIX [%]Maximum Value: 11.5% at (425665, 4728134)Minimum Value: 0.0% at (430165, 4725634)Mean Value: 1.50%
Figure 27-Resource Grid I Results
6. Site Assessment and GIS Analysis
6.1 Setbacks
Setbacks are established to minimize risk of damage or injury from
component failure on property and personnel. The setbacks are usually a
multiple of the total turbine height, from tower base to upper extreme point
of the rotor, as seen in Figure 28 below is a general illustration of how to
measure the rotor diameter, the difference between the hub height and the
turbine’s total (maximum) tip height.
Figure 28-Turbine Dimensions
33
Generally the setbacks can vary from 3-5 times the overall turbine height.
Larger setbacks are sometimes required for special areas. In contrast to these
standards, Brown County with more rural development, use building
setbacks and doesn’t necessarily have to distinguish the wind turbines
separately. However, for this project setbacks weren’t of much concern due
to the layouts of the turbines. The wind farm is out of range from any water
bodies, transmission lines, airport, cultural areas, towns, oil/wells, forest,
roads, homes and buildings as shown in figure 29. This image displays
buffer distances of 500m created in Google Earth, which are surrounding
homes that may seem to be in project range.
Figure 29-Buffer Zone of Project Layout
6.2 Set Back Matrix
34
Figure 30 contains the setback considered during the wind farm
development based on my turbine layout. Given that most of setbacks were
not a concern for this particular wind project, the primary focus is listed in
the table below. The set back matrix basically illustrates certain buffers
created within and out of the zone. Hence, as far as home/buildings it was
assumed that the setback matrix of 500m and 300m respectively were a safe
distance to determine go zone or no zone.
This is significantly important for the wind farm project because as a
developer it’s required to keep land owner rights in consideration. A wind
turbine within less than 500m of a home or building brings about many
issues whereas the visibility, noise and shadow flicker may be of great
concern for the project development. Building large wind turbines in close
proximity to the public has a negative impact on health such as disturbed
sleep due to noise, racing pulse, heart palpitations, headaches, feeling of
nausea etc. which may be due to the wind turbines noise, shadow flicker or
pressure.
Setback Matrix DistanceHome/Buildings 500m/300m
Figure 30-Set Back Matrix Table
7. Project Wind Turbines
35
For this wind project, the turbines that we will be choosing from include the
Vestas V80-1.8, Vestas V112 3.0, Suzlon S88 2.1, Siemens SWT 2.3,
Clipper 2.5 and G.E 2.75, all at 80 meter hub heights. Each turbine is rated
between 1-3 megawatts of nameplate capacity. Figure 31 displays a graph of
the power curves for each turbine using the data that was imported into
Windographer. From this graph, we can gather important information about
each turbine relative to the site that it would be placed at. For instance, we
can see that the Vestas V80-1.8 MW has the highest cut-in speed, as well as
the lowest cut out speed, meaning that it could possibly be a less economical
choice for this site. Hence, the wind turbine that would be more economical
for my project is the Vestas V112 3.0 MW.
Figure 31-Wind Turbine Power Curves
The cut-in speed which is recorded on the power curve indicates the speed at
which the turbines first starts to rotate and generate power. Then the rated
power, which is when the power output reaches the limit that the electrical
36
generator is capable of and the rated speed measured signifying the wind
speed at which it is reached. Hence, typically from there is the maximum
level and there is no further rise in output power. Lastly, the cut-out speed
recorderd is a braking system employed to to bring the rotor to a standstill.
Due to the forces on the turbine structure continue to rise and at some point
there is a risk of damage to the rotor. A more detailed illustration on the
power curve is shown below in figure 32.
Figure 32-Typical Wind Turbine Power Curve
The power curves also incorporate calculations for loss factors, listed in
Table 33 below. Each value will be changed according the conditions for a
given site. The overall loss factor for this site is 16.005%. Loss factor
calculations can significantly affect wind turbine efficiency and, ultimately,
model selection.
37
Figure 33-Turbines Loss Factor
In figure 34 the wind speed is predicted at hub height for each turbine site
and the power production can then be estimated. The predictions for all
turbines will be presented and separate results for the Clipper 2.5 C96, G.E
2.75, Siemens SWT 2.3, Suzlon S88 2.1, Vestas V80-1.8 and Vestas V112-
3.0 turbine sites. A conservative energy production loss factor of 16% was
assumed in the calculation. The details of the loss factor can be found in
figure 33 mentioned earlier in the report.
Based upon the calculations in figure 35 below, it seems that the G.E 2.75 is
the best choice of turbine for this site with a Net Capacity Factor (NCF) of
44.58 percent. The net capacity factor of a wind turbine is the ratio of its
actual output over a period of time, to its potential output if it were possible
for it to operate at full nameplate capacity indefinitely. Figure 35 displays
the wind turbine output summary for each of the six selected turbines. Here
we can see the net capacity factor for each turbine, how much of the data
was good quality, annual power production estimates, etc. Data in this table
is very useful in determining which turbine would be the best choice for a
given site.
Valid Hub Height
Percentage Of Time
Simple Mean
38
At
TimeWind Speed Zero Rated
Net Power Net AEP NCF
Turbine Steps (m/s) Power Power (kW) (kWh/yr) (%)Clipper 2.5 C96 (80m) 89,983 8.43 12.91 7.48 964.6 8,450,058 38.58
Siemens SWT 2.3 (80m) 89,983 8.43 7.24 6.43 1,024.30 8,972,990 44.54Souzlon S88 2.1 (80m) 89,983 8.43 7.31 5.74 809.8 7,094,204 38.56Vestas V112 3.0 (80m) 89,983 8.43 7.24 20.97 1,297.80 11,368,622 43.26Vestas V80-1.8 (80m) 89,983 8.43 12.91 3.51 679.8 5,955,221 37.77
GE 2.75-103 (80m) 89,983 8.43 3.5 9.6 1,226.00 10,739,874 44.58Figure 35-Wind Turbine Summary Table
7.1 Technology and Specification
Siemens SWT 2.3
General data Manufacturer: Siemens (Germany) Model: SWT-2.3-101 Nominal power: 2,300 kW Rotor diameter: 101 m Available model Wind class: IEC IIb Swept area: 8,012 m² Power density: 3.49 m²/kW Number of blades: 3 Power control: Pitch
Rotor Minimum rotor speed: 6 rd/min Maximum rotor speed: 16 rd/min Start-up wind speed: 3 m/s Nominal wind speed: 12 m/s Maximum wind speed: 20 m/s
Gear box Gear box: yes Speed number: 3 Ratio: 1:91
Generator
39
Type: ASYNC Number: 1 Output voltage: 750 V
Tower Minimum hub height: 80 m Maximum hub height: 100 m
Clipper 2.5 C96
General data Manufacturer: Clipper (USA) Model: Liberty C96 Nominal power: 2,500 kW Rotor diameter: 96 m Wind class: IEC IIb Swept area: 7,239 m² Power density: 2.9 m²/kW Number of blades: 3 Power control: Pitch
Rotor Minimum rotor speed: 9,6 rd/min Maximum rotor speed: 15,5 rd/min Start-up wind speed: 3,5 m/s Nominal wind speed: 15 m/s Maximum wind speed: 25 m/s
Generator Type: SYNC PM Number: 4 Maximum generator output speed: 15,5 rounds/minute Output voltage: 690 V
Tower Hub height: 80 m
G.E 2.75-103
General data Manufacturer: GE Energy (USA) Model: 2.75-103 Nominal power: 2,750 kW Rotor diameter: 103 m No more available Wind class: TCIII Swept area: 8,333 m² Power density: 3.03 m²/kW Number of blades: 3
40
Rotor Start-up wind speed: 3 m/s Nominal wind speed: 13,5 m/s Maximum wind speed: 25 m/s
Generator Type: ASYNC DF Number: 1
Tower Minimum hub height: 75 m Maximum hub height: 123,5 m
Suzlon S88 2.1
General data Manufacturer: Suzlon (India) Model: S88-2.1 Nominal power: 2,100 kW Rotor diameter: 88 m Available model Wind class: IEC IIa Swept area: 6,083 m² Power density: 2.9 m²/kW Number of blades: 3 Power control: Pitch
Rotor Maximum rotor speed: 17,8 rd/min Start-up wind speed: 3,5 m/s Nominal wind speed: 14 m/s Maximum wind speed: 25 m/s
Gear box Gear box: yes Speed number: 3 Ratio: 1:98,8 - 1:118,1
Generator Type: ASYNC Number: 1 Maximum generator output speed: 1830 rounds/minute Output voltage: 600 - 690 V
Tower Hub height: 79 m
Vestas V80-1.8
General data Manufacturer: Vestas (Denmark)
41
Model: V80/1800 Nominal power: 1,800 kW Rotor diameter: 80 m Wind class: IEC IIa Offshore model: no Swept area: 5,027 m² Power density: 2.8 m²/kW Number of blades: 3 Power control: Pitch
Rotor Maximum rotor speed: 17 rd/min Start-up wind speed: 3,5 m/s Nominal wind speed: 15 m/s Maximum wind speed: 30 m/s Manufacturer: Vestas
Generator Type: IND Number: 1 Output voltage: 690 V
Tower Minimum hub height: 60 m Maximum hub height: 78 m
Vestas V112-3.0
General data Manufacturer: Vestas (Denmark) Model: V112/3.0 MW Nominal power: 3,000 kW Rotor diameter: 112 m Wind class: IEC II/III Swept area: 9,852 m² Power density: 3.29 m²/kW Number of blades: 3 Power control: Pitch
Rotor Minimum rotor speed: 6,2 rd/min Maximum rotor speed: 17,7 rd/min Start-up wind speed: 3,5 m/s Nominal wind speed: 15,5 m/s Maximum wind speed: 25 m/s
Gear box Gear box: yes Speed number: 4 Ratio: 1:113,0
Generator Type: SYNC PM
42
Tower Minimum hub height: 84 m Maximum hub height: 119 m
8. Layout Design and Micro Siting
8.1 Final Layout and Design of Turbines
Figure 36 below displays the final layout of the project with the G.E 2.75
MW wind turbines. There are 28 turbines placed in the most wind
resourceful areas in order to capture the maximum amount of wind coming
from the predominant direction in which the turbines are faced. Each turbine
was spaced approximately 10-15 RD apart from each other to reduce wake
loss.
43
Figure 36 - Final Layout
9. Site Suitability Analysis
Figure 36 shows the turbulence intensity for the 60 meter wind speed data.
Turbulence Analysis window allows you to observe how the turbulence in
the wind varies with wind speed, wind direction, month, or hour of day. One
important component of turbulence analysis is the turbulence intensity. The
44
turbulence intensity, or TI, is a dimensionless number defined as the
standard deviation of the wind speed within a time step divided by the mean
wind speed over that time step. It is a measure of the gustiness of the wind.
High turbulence can lead to increased turbine wear and potentially increased
operations and maintenance (O&M) costs. Lower wind TI is often higher
when calculated as can be seen in figure 38. At low wind speeds, the
turbulence is of little consequence to the wind turbine itself. Turbulence at
higher wind speeds is often of greater interest and concern to wind turbine
manufacturers.
Figure 37-Turbulence Intensity at Wind Speeds
Figure 38 shows the IEC turbulence ratings relative to the representative TI.
A point of primary interest is the mean TI at 15 m/s, which 0.1% shown in
the Turbulence Intensity summary table below. This indicates relatively high
turbulence that may preclude the use of low wind speed turbines that would
45
maximize energy production at this site. The potential wind loading due to
extreme winds must be addressed during the turbine selection process.
Figure 38-Turbulence Intensity at 60m
The turbulence analysis summary table, shown in figure 39 repeats three
numbers that appear in the 15 m/s bin in the table of turbulence versus wind
speed: the number of records in that bin, the mean turbulence intensity in the
bin, and either the characteristic turbulence intensity or the representative
turbulence intensity in the bin, depending on which edition of the
International Electro technical Commission (IEC) standard you have
selected. The table also reports the IEC turbulence category that results from
these 15 m/s statistics. If you view the Turbulence vs. Wind Speed table,
Windographer will highlight the 15 m/s value that corresponds to the key
value in the summary table.
46
During project development of the wind turbine, the question arises about
the selected turbine class on-site in that the wind turbine will be operating
and the wind class depends on the site’s turbulence intensity (TI). According
to IEC3 Turbulence category the wind turbine for this project is a class C
displayed in the table above and defines that a representative turbulence
intensity standard is being used. Depending on the wind class, the wind
turbine may be more or less solid and stable in order to withstand loads, to
which the turbines will be exposed to on site. The importance of turbulence
is important to design and choice of an appropriate wind turbine for the site
distinctiveness. Being that the wind turbine class for this project is the
highest at class C, the stronger the turbines structure must be designed in
order to withstand the impulsive and long term fatigue loads and extreme
wind measures.
10. Wind Farm Estimated Productions
10.1 Preliminary estimated AEP calculations
The Cornhuskers wind estate accommodated approximately 5 utility-scale
turbines to produce electricity. For economic purposes, the G.E 2.75 on an
47
Figure 39-TI Summary Table
Quantity ValueData points in 15 m/s bin 805
Mean TI at 15 m/s 0.1Representative TI at 15 m/s 0.13
IEC3 turbulence category C
80m tower was selected. This turbine features GE’s 50.2 meter proprietary
blade design that offers a 9 percent AEP increase over the 2.5-100. Focusing
on performance, reliability, acoustic emissions, efficiency, and multi-
generational product evolution. GE’s 2.75-103 wind turbine creates more
value.
In figure 40 below is a layout of the wind farm displaying the each turbines
wake losses with the indication of tan colored, cone shaped image with
calculates the wake loss percentage as seen below. The red lines highlighted
at the tips illustrate the total amount of wake losses of the wind behind the
turbine. In its wake, the turbine is less effective at generating energy for a
certain distance in the downwind direction due to turbulence created by the
upwind turbine. Hence, when sitting a wind farm, it is important to space
turbines as to minimize the impact each has on the others’ power production
capacity and the results shown in figure 41 ais a summary table comparing
all wind turbines. The measured AEP and wake loss percentage from the
wind farm is summarized including the total, average AEP, maximum and
minimum per turbine.
48
Figure 40-Mean Wind Speed Vector Map of Wind Farm Layout
WTG’s Comparison
Valid Hub Height Percentage Of Time AtSimple Mean
TimeWind Speed Zero Rated Net Power Net AEP NCF Wake
Turbine Steps (m/s) Power Power (kW) (kWh/yr) (%) Loss %Clipper 2.5 C96 (80m) 89,983 8.43 12.91 7.48 964.6 8,450,058 38.58 2.8
Siemens SWT 2.3 (80m) 89,983 8.43 7.24 6.43 1,024.30 8,972,990 44.54 2.32Souzlon S88 2.1 (80m) 89,983 8.43 7.31 5.74 809.8 7,094,204 38.56 1.97Vestas V112 3.0 (80m) 89,983 8.43 7.24 20.97 1,297.80 11,368,622 43.26 2.47Vestas V80-1.8 (80m) 89,983 8.43 12.91 3.51 679.8 5,955,221 37.77 1.58
GE 2.75-103 (80m) 89,983 8.43 3.5 9.6 1,226.00 10,739,874 44.58 2.15Figure 41-Wind Turbines Summary Table
49
10.2 Modeled AEP Calculations of Final Layout
Wind statistics at the turbine hub are converted in power using the power
curve of selected turbine models obtaining the gross Annual Energy
Production (AEP). Declared power curve from the turbine manufacturer are
individually corrected based on the average air density at every turbine site.
Information on air density is derived from measurements or mesoscale data
for the site. Single turbine array losses by direction are determined using
analytical wake models. This approach includes the wake effects in the wind
field as a post-processing step. Other technical losses like turbine
availability, electrical losses, icing etc. are assessed based on traceable
experience and industry standards in order to obtain the net AEP. Figure 41
below provides the statistics for the wind farm, the total, mean, minimum
and maximum gross and net annual energy production (AEP), as well as the
total wake loss calculated in WAsP. In addition, the mean wind speed, mean
power density and ruggedness index RIX. The predicted power production
of the wind farm is 331 GWh. The wake effects are very small here because
the wind farm consists of one row of turbines at right angles to the
prevailing wind direction.
Parameter Total Average MinimumMaximu
mNet AEP [GWh] 330.583 11.807 11.48 12.141
Gross AEP [GWh] 337.862 12.067 11.67 12.452
Wake loss [%] 2.15 - - -Figure 41 - Modeled AEP Calculation
50
11. Project Economics
The economics of a wind project depend on the cost of financing, when the
turbine purchase agreement was executed, construction contracts, the type of
machine, the location of the project, and other factors. Cost components for
wind projects include wind resource assessment and site analysis expenses;
the price and parts of the turbine and tower; construction expenses;
permitting and interconnection studies; utility system upgrades,
transformers, protection, and metering equipment; insurance; operations,
warranty, maintenance, and repair; legal and consultation fees. Other factors
that will impact your project economics include your financing costs, the
size of your project, and taxes.
If you own or are a part owner of a commercial scale wind project, the
power purchase agreement (PPA) will be an integral part of your revenue
generation. The PPA is a contract between the owner of a wind farm and a
utility that sets the price of all the power that is sold. Securing a PPA is a
crucial step in the planning stages of a wind project, as it obligates the
agreeing entity to buy your electricity at a certain price for a certain number
of years; this allows you to estimate how much revenue your project will
generate. Various state and federal tax incentives are available for wind
projects. However, to take advantage of these benefits, you will need to
thoroughly understand the eligibility requirements and structure your project
accordingly. The Federal Production Tax Credit (PTC) is an important
incentive, but it can be difficult for private individuals to use to its full
advantage because they lack the ongoing tax liabilities needed for the
incentive. Careful consideration of your personal financial situation and
51
consultations with a tax advisor are recommended for anyone who is
considering investing in a wind project.
11.1 Financial model and input data
Figure 42 below illustrates the development and operating cost site
assessment for the project. The project will need to perform archeological,
environmental impact, and other studies before permits to build are issued.
Your local or state permitting agency may also require other studies and
fees. Common permits are building, conditional and special use, FAA, and
access road. Your local or state zoning authority will be able to help you
determine what permits your project will need to obtain. Legal costs in
permitting can get expensive for projects in areas where possible litigation
might occur from parties affected by the project and often a building permit
fee is based on total project cost. Interconnection studies for the project were
made and depending on the size of the project and where the propose
interconnection is located. Three phase lines are required for large
generators, but you can’t assume that any three phase line can carry the
power from the turbines. You may incur significant unanticipated costs if the
power line near the site does not have the capacity to handle more
electricity. Transmission lines are very expensive to build and difficult to
site.
The interconnection study will outline what impact your project will have on
the power system. The results of this study may require that your project pay
for significant system upgrades to mitigate these issues. Working with an
expert through the interconnection process to make sure that the utility is not
52
adding unnecessary additional costs to the proposed upgrades is making it
difficult to develop the project. If a smaller project can interconnect onto a
distribution line, then it can benefit from a lower cost interconnection
without the necessary substation elements needed for connecting to power
lines. Distribution lines are the lines that bring the energy to the customer,
whereas transmission lines are for transmitting electricity from point to point
using higher voltages to minimize line losses. Also, an installation costs are
all the expenses required to construct and get the turbine up and running
once it arrives. Connecting the turbine to the grid is often done through a
team effort involving the contractor, representatives from the turbine
manufacturer, and engineers from the utility company that owns the power
lines.
Once the project is up in the air and spinning there are periodic and annual
expenses that will need to be accounted for. Some of these expenses will
happen every year such as preventative maintenance of the machines. Other
expenses may happen less frequently or sporadically such as replacement of
parts that have worn out. The best way to understand what is appropriate for
the project is to understand the risks associated with owning a wind project
and ways to mitigate those risks by talking to people who own and operate
projects using the same equipment within your region and learning from
their experience.
Development CostInterconnect Study $ 847,000.00
System Impact Study $ 15,000.00 Environmental Study $ 150,000.00
Permitting $ 200,000.00 Transmission Right-of-ways $ 234,800.00
53
Installed Cost per MW $ 1,751,928.25 Turbine $ 3,960,000.00
Total Project $ 134,898,475.07 O & M $ 419,263.03
Insurance Cost $ 2,016,000.00 Depreciation (1-10) years $ 13,489,847.51
Figure 42 - Development and Operating Cost
11.2 Debt/Equity, Taxes and Abatements
In many cases, developing a community wind project necessitates requesting
a loan from a bank. Loan terms for the debt vary, but typically are 10-15
years for conventional bank loans and up to 20 years for bond financings.
The equity investment in a project is the amount of capital that is not
borrowed, but is invested directly into the project upfront. This may come
from private savings or direct investment by members of a cooperative,
partnership, or LLC that is interested in obtaining a desired rate of return
from the project’s ongoing revenues. In order to be financially competitive,
most wind projects need to take advantage of federal and, where available,
state tax incentives. It is critical to understand the role and mechanics of tax
incentives while developing a commercial-scale community wind project
because these incentives can represent one-half to two thirds of the total
revenue stream over the first 10 years of operation due to the Federal
Production Tax Credit (PTC) and Modified Accelerated Cost-Recovery
System (MACRS) or other type of depreciation that can be applied to wind
energy assets.
12. Environmental Analysis and Biological Impacts
54
11.1 Fatal Flaws Analysis
A fatal flaw analysis aims to minimize the investment in feasibility studies
to quickly determine if a site is worth investing significant development time
and capital. Utility scale wind turbines have many siting considerations, and
many of these potential fatal flaws can be identified relatively quickly. The
site must be able to have access for turbine components both new and
existing, and an electrical interconnection or access to one suitable for the
scale of the project. The site must have favorable local ordinances as well as
national impact considerations. Figure 43 below represents a Plat Map of my
proposed site location, which is sited in Brown’s County, Nebraska. There
were approximately 250 landowners in Brown, County. Plat Maps are listed
alphabetically; it gives the legal descriptions of pieces of real property by
lot, street, and block number. However, being that in the figure below there
aren’t no lot, street, nor block number apparent, it shows the land as
subdivided into lots displaying the location and boundaries of individual
parcels with the streets, alleys, easements, and rights of use over the land of
another. Additional information included on the county plat maps are
township names, section numbers, range numbers, lakes and rivers which are
also not apparent on the map provided.
55
Figure 43-County Plat Map
Figure 44 represents the Long Range Radar screening of my geometric
single point location of my project. In order to do so I had to obtain the
latitude and longitude of my project location center point. Input the
coordinates so I can determine the project location sustainability. Whereas,
for my location it’s determined “green” which means there are no
anticipated impact to air defense and homeland security radars. However, if
it was “yellow” impact would me more likely moderate and if it was “red”
the overall impact will be high.
56
Figure 44-Long Range Radar
Figure 45 illustrates the NEXRAD screening of my geometric single point
project location, which I also obtained by finding the latitude and longitude
of the area. After inputting the results, it calculated the potential impacts to
weather radars and the severity of these impacts are described in colors,
which are green, dark green, yellow and orange. Given these points, as you
can see by diagram my project location is proposed to be “green” known as
“NO Impact Zone” which means that impact is unlikely. Hence, NOAA
would not perform any detailed analysis, but would still like to know about
57
the project. As for “dark green” knows “Notification Zone” impacts would
be more possible to occur, “yellow” as the “Consultation Zone” where
impacts are more significant and NOAA would request consultation to
discuss the details of the project and impact analysis, and “orange” the
“Mitigation Zone” also the possibility of significant impacts, requiring
NOAA to request mitigation if a detailed analysis shows that the project will
cause significant impacts.
Figure 45 - NEXRAD Radar
58
Figure 46 explains military operations screening, which shows the
preliminary review of any likely impacts to military airspace. However, by
examining the details in this diagram you can determine the results of the
screening. This shows that there are no likely impacts to military airspace.
59
Figure 46-Miliatry Operations Radar
Figure 47 below displays the “Long Range Radar” screening type and
Geometric type “Polygon” of the project area for all corners. This diagram
was generated by acquire the latitude and longitude of all four corners the
project area. After submitting all the coordinates the proposed diagram was
produced. Not only that but, as you see its “green” which means that there
no anticipated impact to air defense and homeland security radars. However,
if the project area was determined to be either “yellow” or “red” the impact
to air defense and homeland security radars would be moderate to high,
which will require aeronautical study.
60
Figure 47-Long Range Radar
Similar like the “The Long Range Radar” screening type the “NEXPAD”
screening type was generated by acquire the latitude and longitude of all
four corners the project area. After submitting all the coordinates the
proposed diagram was produced. Not only that but, as you see its “green,
referred as the “No Impact Zone” which means that impacts are unlikely and
NOAA will not execute a detailed analysis although they will still want to
know about the project. The severity of impacts is determined in variety of
colors, these are “Dark Green” or “Notification Zone” where there are
possibilities of impacts and it’s optional to consult with NOAA, “Yellow” or
61
“Consultation Zone” shows the possibility of significant impacts and NOAA
would request consultation to discuss the project details and do a detailed
impact analysis. Also NOAA would request mitigation of significant
impacts. “Orange” also referred as the “Mitigation Zone” indicates
significant impacts as well and if a detailed analysis shows that the project
will cause significant impacts a mitigation request will be likely. Lastly, the
“No-Build Zone” which would be “red” displays severe impacts and a
detailed analysis will be required. Also, NOAA would request developers to
refrain from building wind turbines 3 km within the NEXRAD
Figure 48-NEXRAD Radar
62
11.2 Noise, Shadow Flickering, Visibility, Safety, Radar,
Telecommunication
The assessment of suitability of a certain location for the installation of a
wind farm requires the consideration of multiple impact issues; here we’ll
focus on the visual aspects, safety, radar, telecommunication, shadow flicker
from wind turbines and noise pollution. Wind Turbines generate a broad
spectrum of noise including low frequency noise and infrasound which may
be audible or inaudible. It is widely affirmed that exposure to audible low
frequency noise can cause adverse health effects in humans. Most of the
counties with zoning regulations for wind energy have noise standards
established. The most common standard for commercial wind turbines is 50
dBA. Figure 49 is an image of the noise assessment from a wind turbine on
the wind farm; each circle is 1, 3, and 5 RD’s away from the base of the
tower. Between turbines and dwellings the setbacks are often based on
sound levels that are generally acceptable approximately 1000 to 1320 feet.
The noise is propagated outward by distance and this can be calculated with
63
the equation, . For example,
but first in order to find the radius (r), we
have to calculate the diagonal using the equation ,
which then 130 becomes the radius. Moreover, Brown County currently has
neither zoning plan nor setbacks for wind turbines from natural resources,
property lines etc. but the most common setback used for commercial scale
wind turbines in Nebraska is 600 feet from public conservation lands and
wetlands.
Figure 49-Noise Rings
In addition to noise pollution wind turbines also have visual burdens.
Shadow flickering is the phenomenon caused by the moving shadow of the
wind turbine blades moving over a point. The area where flicker is
experienced moves as the sun’s position relative to the ground changes
throughout the day and season to season. As with other shadows, the shaded
64
area is larger but moves quickly in the early and late hours of the day and
smaller but more slowly moving in the middle of the day. It should be noted
that shadow flicker does not induce epileptic seizures as the number of
cycles per second produced by commercial wind turbines; generally less
than one per second is well below the strobe effect that causes seizures 5 to
20 per second. Other concerns are raised that are turbine related, shadow
flickering has the potential to cause nausea, dizziness, and disorientation.
Shadow Flickering occurs in a butterfly-like pattern around each turbine. A
more detailed illustration of the shadow flickering butterfly shaped pattern is
shown in figure 50 below.
65
Figure 50-Shadow Flicker Butterfly
The butterfly-like shape is made up by lines of shadow flicker impact,
similar to the lines on a topographic map. For example, a house with
windows facing the proposed turbine located along the blue line could
expect about 30 hours of shadow flicker in a typical year. Furthermore, the
typical special safety requirements for wind turbine development in
Nebraska are; clearance of rotor blades or airfoil must maintain a minimum
of 12 feet of clearance between their lowest point and the ground. All
commercial/Utility WECS (wind electronic conversion system) should have
66
a sign or signs posted on tower, transformer and substation, warning of high
voltage. Other signs should be posted on the turbine with emergency contact
information. Also, all turbines whether a commercial/utility WECS, should
be installed with a tubular type tower and consideration should be given to
painted aviation warnings on all towers less than 200 feet. Lastly, all wind
turbines and towers should be white, grey or another non-obstructive color.
11.3 Biological Impacts
Wind energy development impacts wildlife populations in two ways: direct
impacts, such as individuals colliding with infrastructure; and indirect
impacts, such as loss and degradation of habitat. Direct impacts occur when
birds and bats collide with or when bats come in close proximity to moving
turbine blades, towers, or transmission lines servicing wind farms. Although
numerous variables including location of turbines, time of year, weather, and
scavenger removal rates make it difficult to determine trends from multiple
wind farms, some patterns have emerged. Recent studies show direct
impacts may increase significantly when turbines are placed in or near major
migration corridors or natural features used during daily animal travel, for
example, mountain passes, large river valleys, and saddles or the edge of
ridge tops and bluffs, or at migration stopover sites or frequently visited
areas such as wetlands and lakes. Because birds and bats tend to follow or
congregate along these natural landscape features, wind turbines placed near
these features have potential for causing an increase in bird and or bat
mortalities. Bats are likely to experience higher direct mortality rates than
birds at many wind farms, Resident bats in Nebraska are usually associated
with trees or wooded areas and wetlands, where the insects on which they
67
feed are abundant. However, bats commonly feed over grasslands and
agricultural fields as well. Recent studies have shown tree roosting
migratory bats are at a higher risk of direct impacts from wind turbines;
three particularly susceptible species are the eastern red bat (Lasiurus
borealis), hoary bat (Lasiurus cinereus), or silver-haired bat (Lasionycteris
noctivagans). Currently there is no clear reason why so many bats are being
killed by turbines and until such reasons are known, extra vigilance should
be used when siting turbines near areas of potential bat stopover and
roosting habitat.
Indirect impacts, such as habitat loss or degradation from wind turbines and
their associated infrastructure, can affect all species in the impacted area,
including plants and non flying animals that are not subject to turbine
collision mortality. These impacts represent an environmental cost that may
be greater than direct impacts. Development of infrastructure can impact
species through loss of habitat due to construction of roads, tower sites,
turbine pads, and other infrastructure within the wind farm. Habitat loss can
result from the physical removal of suitable habitat from the area or through
species’ responses to the change in the habitat which can result in species
being displaced from otherwise suitable habitat near a turbine or other wind
farm infrastructure. These avoidance behaviors could result in a large area of
intact grassland becoming fragmented into smaller use areas, each fragment
being too small to sustain a population of that species over the long term.
11.3 Water Resource and Soil Erosion
68
Wind energy requires no use of water resources for operation. Foundations
are not usually any deeper than a standard basement foundation and do not
interfere with water tables. No particulate or heavy metals are released into
the atmosphere which can contaminate water supplies. The final footprint of
a wind turbine is relatively small, approximately 15 feet in diameter, with
some surrounding area needed for maintenance vehicles. Access roads do
take up some land area and in environmentally sensitive areas can fragment
habitat. Soil erosion is another potential environmental problem that
can stem from construction projects. Erosion impacts can include
increased siltation of streambeds, alteration of stream courses, and
increased flooding, leaving scars on the land. Wind developers can
reduce the risk of serious erosion by minimizing the amount of earth
disturbed during construction, principally by eliminating unnecessary
roads, avoiding construction on steep slopes, allowing buffers of
undisturbed soil near drainages and at the edge of plateaus, assuring re-
vegetation of disturbed soils, and designing erosion-control structures
adequate to the task.
The single most reliable technique for limiting erosion is to avoid grading
roads in the first place. During construction there is significant area
disturbed for road construction, burying of transmission lines, construction
of the foundation, and crane pad site. Erosion is a primary concern and must
be addressed through the building permit process, as with other construction
projects. Top soil should be sequestered during construction and replaced
after construction is complete. During operation, agricultural use can be
continued in the area surrounding the turbines. Most state or local agencies
69
will require that before building and other permits are issued that you attain
an Industrial National Pollutant Discharge Elimination (NPDES) permit. The
permit assures local and state agencies that you have a plan in place to
minimize erosion from the site and potential harmful effects on water quality
in local lakes and streams from run off or oil and other chemicals that might
be spilled during the construction process.
11.4 Public Health and Safety Considerations
The Brown County Health Department, in collaboration with community
partners, accomplishes its mission by providing services relating to:
communicable disease surveillance and control, prevention of chronic
disease and disability, maternal/child health promotion, management of
environmental hazards, licensing and inspection visits, laboratory services,
and preparation for emergency events in the community. Communicable
disease surveillance and control involves investigation of cases and contacts,
provision of needed health care services and education. Management of
environmental problems is focused on anima and rabies investigation,
human health hazard evaluation and follow-up, code enforcement, and well
water testing, evaluation and follow up.
Furthermore, for safety consideration the Brown County Emergency
Operations Plan establishes the standardized policies, plans, guidelines and
procedures that will allow all emergency resources, governmental and non-
governmental, to collectively manage and coordinate the preparation,
prevention, response, recovery and mitigation functions effectively and in a
consistent manner, as a team when disaster strikes. In content and in format,
70
the Local Emergency Operations Plan (LEOP) is consistent with the
National Incident Management System (NIMS) and with the current
nationwide concept embodied in the Integrated Emergency Management
System (IEMS). This Plan provides for performing specific functions across
the full spectrum of hazards. Most responsibilities, tasks and capabilities
apply across a broad range of hazards. By treating them in this manner
shows an integrated approach to disaster management. Unique aspects of
certain hazards are addressed separately, where necessary. Therefore, this is
truly a multi hazard functional plan.
11.5 Ground Transportation and Traffic
Ground transportation and traffic impacts associated with wind energy
projects typically include impacts on the transportation system itself, the
physical properties of the road system and impacts on traffic that uses the
transportation system. Such impacts arise almost entirely during the
construction period. Traffic and transportation issues to consider in siting
wind energy facilities are largely covered within the General EHS
Guidelines and the Toll Roads EHS Guideline. The main challenge with
respect to wind energy facilities lies with the transportation of oversized or
heavy wind turbine components such as, the blades, turbine tower sections,
nacelle, transformers, and cranes to the site. The logistics, traffic, and
transportation study should assess impacts on existing offsite roadways,
bridges, crossings over culverts, overpasses and underpasses, turning radii,
and utilities, as well as whether surface replacements, upgrades, or
resettlements will be required. To reduce delays to other road users and the
potential for other effects on local communities in the vicinity of the
71
proposed route, schedule deliveries outside of peak hours, use only approved
access routes, provide traffic management to stop other traffic where needed,
and provide police escorts where required.
11.5 Solid and Hazardous Waste
Solid wastes need to be collected from dispersed sites and properly disposed
of in a manner consistent with other power plants or facilities. Non
hazardous fluids should be used where possible, and a Hazardous Materials
Waste Plan should be developed if their use can’t be avoided. By performing
major maintenance and repair work off site, certain problems can be
avoided. Ensure that construction wastes are collected from the wind project
site and disposed of at a licensed facility. Waste disposal practices should
not be different in wind power from those required at other power plants or
repair facilities. Anticipate fluid leaks and avoid hazardous leaks by using
non hazardous fluids. Design a Hazardous Materials Waste Plan to address
avoidance, handling, disposal, and cleanup, when necessary. Conduct
turbine maintenance facilities and major turbine repairs off site.
11.6 Air Quality and Climate Impacts
Air quality has a direct impact on human health. Particulate matter in the air,
often as a result of power plant emissions, has been shown to affect
cardiovascular and respiratory health. Construction equipment emissions
would result in localized and temporary air quality impacts during
constructions activities. Unhealthy levels of particle pollution can even
cause otherwise healthy people to get sick. The generation of electricity 72
from the wind does not result in any air emissions. By offsetting more
polluting forms of energy generation, wind energy can actually improve air
quality and our health. A primary benefit of wind energy is the lack of
emission of greenhouse gases or other pollutants. In addition, greenhouse
gases are not emitted in the transportation of fuel to the site, nor are there
risks associated with fuel transported in pipelines. The manufacture and
maintenance of wind turbines does produce some greenhouse gases.
11.7 Socioeconomics and Land Values
Economic impacts to Nebraska are greatest when there are high levels of
local ownership and local manufacturing. The local ownership structure
driven by C-BED Nebraska’s (Community-Based Energy Development) is
popular at present, suggesting that the actual impacts from wind
development in the state may be closer to the high end of the range noted
above if development continues with its current trajectory. However, even in
our low scenarios, wind energy development in the state is expected to
support hundreds or even thousands of jobs for many years into the future.
Finally, creating a vibrant wind industry in the state may allow Nebraskans
the opportunity to capitalize on wind development in surrounding states too.
Nebraska suffers from a declining rural population and, as a result, an
increasing property tax burden on landowners. As the population and tax
base decrease in rural Nebraska, counties increase their property tax rate in
order to produce enough revenue to cover necessary services, which, in turn,
increases the burden on landowners. Wind energy development provides
significant property tax revenue by substantially increasing the property tax
73
base, without increasing the current tax rate levied on landowners. As wind
developers invest in rural Nebraska, they supplement county revenue by
paying tax on their wind facilities, related improvements, and the real
property upon which structure the wind turbines sit. Nebraska Legislative
Bill 1048 created the nameplate capacity tax to replace the central
assessment and taxation of the depreciable tangible personal property
associated with wind energy generation facilities. The tower, nacelle, blades
and any other structure which is involved in the actual generation of
electricity is not to be taxed as depreciable tangible property. Real property
upon which wind generation facilities are based is not exempt from property
tax for ex. concrete pads, foundations, operations and maintenance
buildings, road construction, leasehold value, and lease payments. The land
itself will continue to be taxed as it was prior to construction of the tower.
11.8 Archaeological and Cultural Resources
During project design and site development, important cultural and fossil
resource sites should be avoided and protected or else a mitigation plan
should be developed. Special care should be taken to preserve the
confidentiality as well as the integrity of certain sensitive resources or sites
sacred to Native Americans. Identify and avoid potentially sensitive cultural,
historical, or prehistorically resources and involve all stakeholders early on.
Consult with the Nebraska State Historical Society and other qualified
professional specialists familiar with cultural and fossil resources in the
project development area. Some sensitive resources and sites may be
confidential to Native Americans. Respect this confidentiality and work
closely with tribal representatives to protect these resources by avoiding
74
disruption to these sites. Design project site layout to avoid sensitive
resources, if possible and prepare a monitoring and mitigation plan for
protection of sensitive resources during construction and operation of the
project. Also, an appropriate mitigation of unavoidable impacts and
monitoring to ensure measures are implemented is required. Lastly, allow
adequate time in the project schedule for data and specimen recovery,
mapping, analysis, and reporting.
13. Grid Interconnection
13.1 Capacity, Voltage and ECC analysis
Through my project area there is a 69kV line 3.5 miles long that’s located in
the bottom right corner of the project area connecting from two substations.
One located just out the project area and the other located with the project
area as displayed in the figure as substation 1 and substation 5. A 69kV line
is a single pole, typically 50-70 feet tower height and a right of way width of
70-100 feet. Through an interconnected grid of 69kV, power lines and
distribution substations. Hence, the substations are the hub for serving the
neighborhood electrical needs.
Figure 51 displays the 69kV line as a purple line running through the project
area from substation 1 to substation 5. Also, Figures 52 and 52 shows image
of the substations from an aerial view. Due the dirt roads in the project area
Google earth was unable to give a more detail image of the 69kV lines and
substations being that the project area is surrounded by dirty roads.
75
Figure 51 - Transmission Line
Figure 52-Substaion outside Project Area
76
Figure 53-Substation in Project Area
Furthermore, after locating the transmission lines that run through your
project area it was then possible to calculate the maximum capacity the wind
project can undertake. The power of transmission is then calculated by
determining the voltage, conductor size and its substance. However, the
conductor size chosen for this project is 477 MCM ACSR which acquires an
ampacity of 670 Amps. After gather this information, the calculation to find
the maximum capacity can be determined, using 3 phase current then
multiply it by the transmission line voltage of 69kV, also multiplied by the
Amps of 670 and then multiplied by 0.55 which is the Economic Carrying
Capacity (ECC). Hence, the ECC ranges from 50-55 percentages but for the
project 55 percentages was selected. Lastly, after the calculation of the
maximum capacity was made for this project, the final output was 76.280
kW which is then converted to 76 MW of maximum capacity.
13.2 Loads, System Protection and Conditions
77
The manufacturers of wind turbines must ensure that the turbines they build
are certified to withstand extremes of wind speed. A wind turbine must be
built to withstand winds at hurricane speeds. The energy content of wind is
proportional to the cube of the wind speed, so a turbine subjected to high
wind speeds will be under a massive amount of stress. To reduce the impact
of extreme wind speeds without affecting efficiency, wind turbine
manufacturers build the rotors on wind turbines with few blades, which are
as long and narrow as practical. To gain the most productivity from such
narrow blades they are pitched at an optimum angle to the wind. If a turbine
was built with more blades or very wide blades, such as traditional wind
powered water pumps, it would be subjected to incredibly large forces even
at moderate wind speeds. Extreme loads at a particular site are characterized
by measuring maximum wind speeds in each 10 minute period. Because a
wind turbine will be subjected to varying wind speeds, and therefore
fluctuating forces it needs to be able to withstand the varying load. This is
especially the case where a turbine is situated in an area with a turbulent
wind climate. The components of a turbine will be subjected to repeated
bending, particularly the rotor blades. This flexing and relaxing will
eventually cause cracks to appear in the component which can ultimately
lead to the component breaking. Turbine manufacturers are well aware of
metal fatigue, as it is a well known problem which occurs in many different
industries. Because of this, metal is not generally used for rotor blades, as
there are other, more suitable materials which withstand the repeated
flexing.
Furthermore, the transmission system in the State of Nebraska is split
between the Eastern Interconnection and the Western Interconnection, with
78
the transmission networks in each interconnection operated and planned
separately. The majority of the geographic area and load in Nebraska is
located in the Eastern Interconnection, served primarily by NPPD, OPPD,
and Lincoln Electric System (LES), and is a part of the SPP regional
transmission organization (RTO). The SPP region shares a border with the
Western Electricity Coordinating Council (WECC) in the west, the MISO in
the north, northeast, and southeast, and the Electric Reliability Council of
Texas (ERCOT) in the south. Nebraska sits right at the border between SPP,
WECC, and MISO. In grid connected systems, the only additional
equipment required is a power conditioning unit “inverter” that makes the
turbine output electrically compatible with the utility grid. Usually, batteries
are not needed. Two basic grid interconnection configurations exist, one
with a battery bank and one without. Grid interconnection allows the option
of net metering which basically allows a turbine owner to be credited for the
surplus electricity produced. Currently in Nebraska, systems up to a 25 kW
capacity can be interconnected to the grid using state net metering laws.
Higher capacity systems can be interconnected under special contracts with
the local utility. Connecting your turbine to the grid will require
coordination with the electric utility and an electrician. Talk to your local
utility before installation to determine electrical requirements needed for
interconnection.
Grid interconnection with no battery backup is the cheapest configuration
and requires the least amount of maintenance. Batteries significantly
increase the project cost and require additional maintenance and storage
consideration. Usually battery banks are stored in small sheds to help
maintain optimal operating conditions. Batteries have the potential to
79
produce explosive gas in confined areas, so extra caution and consideration
is necessary for a battery tied system. Battery back-up does make electricity
available if the utility power fails. Wind turbines directly tied to the grid will
not provide electricity to the owner in the event of a power outage.
14. Permitting
14.1 Federal, State and Local
Several permits and approvals are required to build wind projects. Due to the
lack of combustion in the generation of wind energy, air emission and water
discharge issues are virtually nonexistent. In general, local permits and
approvals, especially regarding zoning compliance, become critical path
issues. Visual impacts and impacts to local and migratory bird populations
are also an important issue to address. All of the federal, state and local
permits or approvals that are generally required of electric generating
facilities were identified, and their applicability to wind energy. While the
list is extensive, the NPA does not believe that permitting, which is a normal
process involved for any power resource project, will be a major problem in
the development of wind farms in Nebraska. However, the public policy of
Nebraska for building generation and transmission facilities in Nebraska is
an issue that will need to be addressed.
The Nebraska Power Review Board (NPRB) must authorize the
construction of any type of power generation facility in the state of
Nebraska, including wind turbine generators, the output of which is sold at
80
either retail or wholesale in Nebraska. The application for authorization
consists of a questionnaire requesting a description of the proposed facility
including the identification of alternative locations and unit types, overall
project schedule and total estimated costs. The NPRB examines the
application upon filing and holds a public hearing to discuss concerns and to
discover any issues from the public or alternative generating sources such as,
already functioning power suppliers in the area. The applicant has the
opportunity to answer all questions and to resolve all issues of concern from
parties contesting the application. Under the Nebraska Revised Statutes,
section 70-1024 (http://www.nebraskalegislature.gov/laws/statutes.php?
statute=70-1024), the NPRB must find that the project will serve the public
convenience and necessity before approving any generation or transmission
project.
There is a serious legal question as to whether generation or transmission
facilities sited in Nebraska to serve the export market would meet the public
convenience and necessity criteria. Another regulatory process that may
have to be addressed for the successful creation of an entrepreneurial public
entity in Nebraska, and one which is unfamiliar to public power entities in
Nebraska is a requirement for permission from the Federal Energy
Regulatory Commission (FERC) to be an exempt wholesale generator
(EWG). EWGs are a designated class of independent power producers
created under the 1992 Energy Policy Act. A EWG is defined as a person or
entity determined by FERC to be engaged directly or indirectly and
exclusively in the business of owning or operating an eligible facility and
selling energy at wholesale.
81
14.2 Land Use and Building Permits
The amount of land required for a large wind project varies depending on the
terrain and the final layout of the turbines. A rough rule of thumb is that we
can site 2 to 4 turbines per square mile and still provide adequate exposure
to the wind, proper setbacks from homes and roadways, and appropriate
spacing between turbines. The exact density of the turbines does depend on
local topography, leased land contiguity, environmentally sensitive areas,
and local zoning regulations, amongst other factors. Actual land used by the
turbine is quite small, generally occupying less than a quarter acre. The
majority of the foundation is underground and the concrete pedestal on
which the turbine sits is approximately 20 feet square. A small amount of
additional land is needed for access roads.
Additionally, an owner is ultimately responsible for any development or
construction on their property. In most cases, owners pass the responsibility
of a project to a general contractor or designer to manage and coordinate a
development or construction project. State Law also has requirements that
dictate the involvement of registered professional engineers and architects
for commercial projects. It is suggested that owners monitor the progress of
a project through their professionals to ensure the proper steps are being
followed for design, permitting and inspections. Any pertinent information
an owner can provide design professionals prior to preliminary design will
aid in the success of obtaining a permit. Failure to submit complete
information during any phase of design, permitting or construction can cause
delays in issuing permits, performing inspections, and obtaining certificates
of occupancy.
82
15. Land Agreements, Land Owners Consideration
15.1 Terms, Rights and Compensation
A typical full Wind Lease or Easement Agreement compensates landowners
in both phases of a project, the Development or Study Phase and the
Operations Phase. The Development Phase which is the initial term can last
between 2 and 5 years. If the project is not built by the end of this phase, the
typical Lease Agreement is terminated. Attention needs to be focused on the
length of study and evaluation periods, and the termination words to ensure
that the landowner’s expectations are managed with regards to project
development term and project COD, and control of wind rights. The
amounts paid for study phases typically compensate landowners annually on
a per acre basis, however payment structures can vary with one time
payments also offered.
In addition, the operations phase which is after facility is built. Once the
wind farm is in operation, the operations term begins and ranges from 35 to
50 years. Operations and Royalty payments can follow two basic structures
and the minimum royalty is also common. Paid as a dollar amount per MW
of production on annual basis and usually applied in combination with
number of percentage royalty is also common. This is typically in addition
to the minimum royalty and acts as an “inflation” and production risk
insurance for the landowner. Royalties for projects typically built across the
range from 2%-4% of gross revenue produced from the wind farm driven
primarily by the development costs, risks and the market rate for power in
that region. Percentage royalties typically have a built in inflation
83
adjustment for the landowner, for the PPA price typically escalating each
year and the total payment to the landowner is the product of the PPA price,
the average turbine production and the number of turbines the landowner is
hosting. Additional payments paid to landowners may involve crop damage
payments, access road payments, transmission and collection line payments,
construction staging and lay down area payments, substation payments, and
payments to alter irrigation devices and pivots
15.2 Royalty, Indemnification and Reclamation Provisions
Property owners enter into private contracts or leases with the wind
developer. Annual rent varies and is generally based on wind resource,
capacity and number of turbines. In some cases, land owners form
associations where there is an agreement to all receive the same payment
and may be agreements for those who are part of the association, but who do
not actually have turbines located on their property, to also receive
payments. Also, an indemnity which is an agreement between two parties in
which one agrees to secure the other against loss or damage arising from
some act or some assumed responsibility. In the context of customer-owned
generating facilities, utilities often want customers to indemnify them for
any potential liability arising from the operation of the customer’s
generating facility. Although the basic principle is sound, utilities should not
be held responsible for property damage or personal injury attributable to
someone else. Indemnity provisions should not favor the utility but should
be fair to both parties.
84
15.3 Public Outreach
Wind projects with continuing public outreach efforts tend to generate
greater public support. Beginning public outreach early in the planning
phase and continuing throughout the life of a project will likely contribute to
the ease with which a project is carried out in subsequent phases. Public
outreach also helps develop a public that is informed about the specifics of
the project as well as the tradeoffs associated with different energy
developments. Involving the public in the planning process, asking for and
then making use of input, and answering questions early and often can help
appropriately and proactively address concerns. At the same time, working
with a community that is informed or educated about the issues, but does not
yet have a firm opinion on a specific project may be ideal, but that is rarely
the case. More often, some individuals in a community have diverse levels
of knowledge and opinions on a project or policy. Ongoing outreach and
community engagement can reach broader segments of a community who
may not have yet formed an opinion and who are quietly waiting to learn
about how a wind development might impact them, positively or negatively.
Special efforts must be made to reach out to members of the community who
may be less engaged or less vocal in order to assess the true sentiments of a
community. Public outreach and engagement can’t use an all for one
approach; rather, it must be iterative which can be costly and time
consuming, but is often necessary for a successful wind project.
16. Construction
85
16.1 Collection Lines, Service Roads and Logistics
As displayed in figure 54 the collector system is a series of underground
electric cables that run from each turbine to the electrical substation. Which
are colored coordinated to illustrate the size of the lines, whereas, the blue
lines represent 500 MCM ACSR underground cables and the orange lines
represent 1000 MCM ACSR underground cables. Typically, a series of
turbines is interconnected to create a circuit rather than having a direct cable
from each turbine to the substation. At Cornhusker’s Wind Estate there are a
total of 6 circuits. This is a drawing of a circuit that’s connecting 3-5
turbines per circuit and sends the electrical output to the substation as
displayed in figure 54 as purple icon located almost in the middle wind farm
using a 4/0 overhead cable system displayed as green lines from each circuit.
Furthermore, before construction of the wind turbines begin, access roads
must be constructed. The access roads run from existing roads to the turbines
sites. The access road design must be wide enough so that the large vehicles
used for bringing parts of the wind turbine and the crane used to erect the
wind turbines are able to travel easily. For this project, the roads must be
strong enough to withstand a great number of loads. In an attempt to try
reducing the environmental impacts due to water runoff, the access roads are
unfinished roads made up of processed gravel on top of a stabilizing geo-
textile fabric. Proper design and construction of the access roads is vital to
this project, extra cost will be incurred if there are problems transporting
supplies to the wind turbine sites.
86
Figure 54 - Collection System
16.2 Contracting and Building Site
During the construction period there will be jobs created. However,
construction may be completed by crews that are not from the area, or by
subcontractors in the area. The process includes building access roads,
turbine foundations, and construction of electrical infrastructure to collect
and distribute the energy being produced. The turbine components are
87
shipped into the site and erected. Once the turbines are erected and
commissioned, the project site is restored and wind farm operation begins.
However, these workers can bring a temporary boost to the economy when
they purchase goods and services, rent hotel rooms, and eat in restaurants.
17. Post Construction Monitoring and O&M
Post construction surveys and monitoring studies, including monitoring for
carcasses and conducting surveys such as, breeding bird, nesting raptor,
prairie grouse, and bat acoustic surveys should be conducted to determine
the estimated direct and indirect impacts of the wind farm. These data are
essential for both identifying potential measures to mitigate the impact of
operations at existing sites as well as assessing potential risks associated
with future developments. In general, post construction surveys and
monitoring of birds and bats and other relevant species should be conducted
for a minimum of two years following initiation of project operations.
However, longer term monitoring is encouraged and would provide more
reliable data. Furthermore, operation and maintenance jobs will be created
and continue over the long term. There are local training programs for these
jobs that could mean hires would be of local workers. Once the wind project
is operational, it must be maintained for its lifespan by a qualified firm.
Operating costs also include warranties, administrative fees, insurance,
property taxes, land lease payments, and a contingency fund for unforeseen
problems. How well you maintain your turbine will affect your project’s
lifetime and return on investment. After the useful lifetime of the turbine,
decommissioning costs will be incurred for removal of the machines and
restoration of the site.
88
18. Project Lifetime, Decommissioning and Remediation
The components of a wind turbine are typically designed to remain
operational for twenty years. It would be quite easy, and hardly any more
expensive to design and build some of the components to remain operational
for far longer. However, because most of the major components would be
very expensive to build for a longer life span, it would be a waste to have a
whole turbine standing idle because one part failed years earlier than the
rest. Furthermore, In the event of default, or termination of a lease
agreement, the landowner should specify how much time the wind developer
is permitted to remove the wind turbines from the land. Payment must also
be established during this time period. The landowner must also specify any
increased payment or obligations in the event the wind developer neglects to
remove the wind turbines in the specified period of time.
In order to prevent the wind developer from simply walking away from the
project, the landowner should demand a “decommissioning security,” to be
established as soon as the wind turbines become operational. This security is
generally a specified amount of money which is put aside by the wind
developer to ensure there is sufficient funding available for removal and
reclamation at the end of the project. Typically, the operational life of a wind
turbine is about 20 to25 years. Once electricity production is reduced, an
assessment must be made as to when the facility will be decommissioned.
Decommissioning must be outlined at the planning and design stage. Issues
to be addressed include the removal of above ground structures and
equipment, landscaping or reinstatement of roads and vegetation, as well as
89
measures for the restoration of the environment to its original state to the
greatest possible extent. Each case is different, depending on the size of the
development and geographic properties of the locality.
19. Conclusion
Constructing a wind farm on involves environmental, public opinion, legal,
economic, and safety issues. The research for this report shows that none of
these concerns will impede the development of wind energy on the proposed
site. The community affected by this project supports its development, and
they would benefit from its economic and educational value. Wind energy is
clean, renewable, and local. The report proves that the Cornhusker’s Wind
Estate is feasible, and encourages investors in its development. This project
presents investors with an ideal opportunity to be an environmental leader
and to educate the public about the importance and value of renewable
energy.
90