Upload
ayubkara
View
212
Download
0
Embed Size (px)
Citation preview
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 1/51
1
DETAILED REPORT
SiC MEMBRANE PILOT ULTRAFILTRATION TEST FORPRODUCED WATER TREATMENT
OCELOTE field – HOCOL (COLOMBIA)
August 2012
Prepared by:
Oscar
Andrés
Prado‐
Rubio
Project Manager, LiqTech
David Cardona
Technical profesional, Conconcreto
Revised by:
Tore Svendsen
Application Manager, LiqTech
Linfeng Yuan
Project Manager SiC membranes, LiqTech
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 2/51
2
Table of Contents 1. Introduction ................................................................................................................................ 3
1.1.
Problem description
............................................................................................................
3
1.2. Test objectives ..................................................................................................................... 5
1.3. Test facility .......................................................................................................................... 5
1.4. Facilities description ............................................................................................................ 8
1.5. Experimental methodology ............................................................................................... 13
1.5.1. Operating window identification ‐ Operability investigation .................................... 13
1.5.2. Continuous operation tests ....................................................................................... 14
1.5.3. Chemical cleaning efficiency evaluation ................................................................... 14
1.6. Activities schedule ............................................................................................................. 14
2. Water permeability test ............................................................................................................ 16
3. Experimental evaluation point: Before the skimming tanks ..................................................... 18
3.1. Characteristics of the inlet water – field information ....................................................... 18
3.2. Preliminary tests – conventional ultrafiltration ............................................................ 19
3.3. Operating window identification ‐ Operability investigation ........................................ 20
3.4. Continuous operation ................................................................................................... 25
2.5
Conclusions.................................................................................................................... 30
4. Experimental evaluation point: After the skimming tanks ....................................................... 32
4.1. Characteristics of the inlet water – field information ....................................................... 32
4.2. Operating window identification ‐ Operability investigation ........................................ 33
4.3. Continuous operation ................................................................................................... 37
4.4 Conclusions.................................................................................................................... 41
5. Cleaning in place evaluation ..................................................................................................... 42
6. Final remarks ............................................................................................................................. 43
Evaluation point before skimming tanks: ..................................................................................... 43
Evaluation point after the skimming tanks: .................................................................................. 43
7. Future challenges ...................................................................................................................... 44
8. Appendix: Critical flux estimation ............................................................................................. 45
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 3/51
3
1. Introduction
HOCOL
is
a
private
company,
with
over
half
a
century
of
presence
in
exploration
and
production
of
oil and gas in Colombia. HOCOL currently has exploration projects in the Upper Magdalena Valley,
Lower Magdalena Valley, the Eastern Plains and the Llanos Foothills. Besides, it has engaged
production operations in the states of Huila, Tolima and Meta, pumping the produced crude oil
through their own pipelines in the Alto Magdalena.
Currently, HOCOL has an average production of 32,307 barrels (gross) per day in fifteen fields and
a portfolio of net 2P reserves of 57.7 million barrels and 0.9 giga cubic feet of gas waiting to be
developed efficiently and with high operational excellence. In 2011, the company produced 9.9
million barrels of oil.
HOCOL showed
interest
to
test
new
technologies
for
the
separation
of
oil
in
water
emulsions,
as
a
way to bring innovation into their installations, in that way fulfilling their future expectations in
produced water treatment. A process proposed by the consortium Conconceto/LiqTech, based on
Silicon Carbide (SiC) membrane technology. LiqTech is a Danish company who manufactures the
membrane. For the last 11 years, LiqTech has been at the leading edge in developing and
marketing its own proprietary products to the environmental industry. LiqTech’s core is its ability
to manipulate SiC, which has allowed it making a high value, high performance products for liquid
and gaseous filtration. Conconcreto has joined LiqTech efforts to promote this technology in South
America. Conconcreto is a Colombian company with more than 50 years of experience providing
services in South America, mainly in the construction area. Recently, Conconcreto has created an
innovation
department
to
provide
cutting
edge
technologies
for
domestic
and
industrial
water
treatment. The produced water application is one of the most promising applications of SiC
membranes. LiqTech/Conconcreto and HOCOL have agreed to perform a test of the SiC
membranes for produced water treatment. This test is relevant for the consortium
LiqTech/Conconcreto since it is a great opportunity to improve its understanding of the separation
and at the same time validate the technology under Colombian conditions. The intention of this
test is to gather sufficient data to allow Conconcreto/LiqTech propose a commercial service
solution for the produced water treatment.
1.1. Problem description
The pilot plant testing has been conducted in “Campo OCELOTE”, inside of the crude processing
area referred to as “Fluid Processing Central – CPF” (see Figure 1). During the oil recovery process,
an interesting challenge is to separate the oil and water mixture. This separation is limited by the
stability of the oil in water emulsion. Conventionally, emulsion breakers are added in order to
facilitate the oil separation and to allow the filters to remove the suspended solids. The HOCOL’s
processing area is divided into two sections, first the oil recovery plant and secondly the produced
water treatment plant for reinjection.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 4/51
4
The oil and water mixture coming from all drilling points is sent to the processing area through
two pipelines. Those enter the CPF in a manifold where temperature is adjusted for the
subsequent oil recovery section. The oil treatment process is composed in two (02) Surge tanks,
one (01) Gun barrel and finally two (02) Storage tanks. The outlet stream has an average
concentration of 500 ppm of oil in water (OiW) and total suspended solids (TSS), respectively.
From the oil recovery plant, 55.000 BWPD are sent to water treatment facilities. This section
consists of two skimming tanks, one microflotation unit and two walnut shell filters.
From the skimming tanks there is an oil recovery which is sent back to the oil processing plant. The
treated water goes to the microflotation unit with OiW concentration of around 75 ppm and 500
ppm of TSS.
From the microflotation process, the produced water stream has 7.5 ppm of OiW and 50 ppm of
TSS approximately.
Currently,
the
Microflotation
process
has
been
by
‐passed
and
the
outlet
from
the skimming tanks is sent directly to walnut shell filters. The water at the end of the process
should have a maximum of 5 ppm of OiW and TSS. Finally the produced water is sent to the
storage tanks, and then re‐injected.
Figure 1. Diagram of the fluid processing central CPF at OCELOTE field. Red square shows the oil
recovery plant. Green square shows the produced water treatment plant.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 5/51
5
As an alternative solution for the produced water treatment, the SiC membrane technology offers
reliable performance. This technology exploits the oil droplets and suspended solids size to
achieve the separation. The separation is possible due to the membrane is highly hydrophilic
allowing the water to pass through and retaining the oil drops and suspended solids.
1.2. Test objectives
The objective of the test is to determine the operability of the pilot plant at the field conditions.
Therefore, the necessary information is gathered to evaluate the technical feasibility of this
technology for the produced water treatment which will be reflected in a commercial design. It is
aimed to deliver water with concentrations below 5 ppm of OiW and TSS. The activities involved
during the test are:
Evaluate the
effect
of
the
operation
variables
on
the
separation
performance
at
different
sampling points in the OCELOTE field
Reveal the most appropriate operation conditions given the input water quality and clean
water requirements.
Investigate the inlet characteristics variance at the interesting sampling points in the field.
Investigate the influence of the inlet water quality on the separation performance
Determine the water and oil separation efficiency at field conditions
Determine the total suspended solid separation efficiency at field conditions
Evaluate the sustainable continuous operation of the pilot plant.
1.3. Test facility
The test rig is a Multibrain pilot unit from LiqTech (CFU8), it can be seen in Figure 2. The PID can be
seen in Figure 3.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 6/51
6
Figure 2. Pilot unit located at OCELOTE-CPF. The pilot unit is equipped with a feed pump which
pressurizes the feed stream, a recirculation pump which generates the cross-flow and a pump for
backflush. The pressure and flow rates inside the system are controlled by adjusting the position of
control valves and pump speeds. In addition, the unit is equipped with a BackPulse Hammer (BPH)
The unit consists of three pumps: a feed pump delivering the feed solution into the recirculation
loop, a recirculation pump generating the cross‐flow and a pump sitting at the permeate side for
Backflush. In addition, the pilot unit is equipped with a Back Pulse Hammer (BPH). The BPH system
is a pulse generator, which delivers high frequency water pulses from the permeate side in order
to keep the membrane clean and free of foulants. The filtration membrane element is based on
Silica Carbide (SiC).
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 7/51
7
Figure 3. PID-diagram of the test unit. The LiqTech Multibrain CFU08 is an industrial pilot unit for
water filtration applications
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 8/51
8
1.4. Facilities description
The pilot unit was located inside CPF area, beside the Microflotation unit, this location allow
having the connections for the first and second test points very close to the pilot plant.
The following figure shows the localization of the pilot unit inside the CPF area.
Figure 4. General Layout of CPF area (The precise location is indicated with the red circle in the
layout)
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 9/51
9
The connections for the first and second point of operation with the pilot unit were suitable by
HOCOL, installing a valve for control the feed flow rate (as can be seen in Figure 5 and Figure 6).
Figure 5. First point of connection, outlet surge tanks.
Figure 6. Second point of connection, outlet skimming tanks.
The equipments that complement the pilot plant are:
Transformer: the voltage in the field is 480V. Therefore was necessary to install an
electrical transformer to reduce the voltage to 440V (see Figure 7).
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 10/51
10
Figure 7. Electrical transformer, 480V to 440V, 32A.
Panels: as protection for the equipment, there are different electrical panels that allow
connecting the pilot plant, heater, a pump and the computers that use 440V and 110V
(Figure 8 and Figure 9).
Figure 8. Electric panel for connection 220V and 110V.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 11/51
11
Figure 9. Electric panel for connection 440V.
Cleaning in place unit (CIP): Consist of two plastic tanks with 250 liters of capacity, with a
configuration of pipelines and valves that allow connecting the feed, permeate and
retentate hose’s. In these tanks the chemical cleaning solution with alkaline and acid is
prepared for
the
membrane
cleaning
(Figure
10).
Figure 10. Cleaning in place unit (CIP).
Prefilter: this equipment filters the water through a mesh, where particles with size larger
than 300 micrometers are retained. This is a protection device which avoid that these
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 12/51
12
particles enter the pilot unit, in that way preventing the obstruction the feed channels.
There is a small pump (8 m3/h) to generate flow if necessary (Figure 11).
Figure 11. Prefilter is showed in the left side, pump shown in the right side.
Storage tanks: There are two plastic tanks, the first with 1000 L of capacity, used for feed
of produced water. The emulsion is kept in the tank by strong agitation and temperature
regulation. The second tank with a capacity of 2000 L, is employed for clean water storage
to be used for the membrane washing.
Figure 12. In the left side of the picture is showed the feed tank, and in the right side the clean water
tank.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 13/51
13
1.5. Experimental methodology
In order to evaluate the influence of operating variables on the separation behavior, a stepwise
methodology is proposed. The separation performance is assessed in terms of well‐established
indexes like: flux, permeate quality, recovery and sustainability. The most appropriate operating
conditions are estimated from an analysis of the independent experiments based on the
mentioned indexes. The following inputs, that define the membrane performance, can be
controlled by the membrane pilot unit:
Flow conditions: cross‐flow velocity
Driving force: transmembrane pressure (TMP)
Cleaning: combination of the available cleaning strategies (backpulse hammer,
backflush and cleaning in place)
The separation efficiency is determined by the membrane characteristics, the mixture properties
and how the system is operated. During the filtration of any mixture (e.g. emulsions, suspensions,
solutions), the solvent flux through the membrane is always lower than the pure water flux due to
two tightly coupled phenomena referred to as concentration polarization and fouling.
In order to determine the best way to operate the process, it is important to identify the influence
of the operating conditions on the mentioned phenomena, thus on the separation performance.
For that purpose, an experimental design is used.
1.5.1. Operating window identification - Operability investigation
In order to minimize the number of experiments, a hierarchical structure is employed. The
operating mode selected for the experiments is constant flux, which can be automatically
controlled (in a selected experiment the constant TMP mode is tested, which analogous to the
constant flux operation). The influence of flux increments is evaluated through a conservative
stepwise strategy. This is necessary in order to avoid an initial irreversible fouling and at the same
time more carefully follow the separation performance. In that way viable and reproducible
results can be obtained. An additional advantage of this procedure is that the membrane has an
appropriate time to get used to the environment. The first series of experiments on a new type of
water application are initiated with the smallest flux possible and maximum cross flow velocity.
For this
pilot
unit,
the
transmembrane
pressure
should
be
kept
below
0.3
bars
and
the
cross
‐flow
should be kept as high as 2 m/s (50 m3/h).
The used methodology is called “step up‐down” method for the estimation of the sustainable
flux1. The experiment starts with an initial flux which is gradually increased; each increment is
followed by a relaxation period. After each increment, the transmembrane pressure will increase
as a consequence of the higher desired flux. The transmembrane pressure should reach a
relatively stationary average value, indicating a situation where there is equilibrium between the
1 Beier, S.P. and Jonsson, G. Critical Flux Determination by Fux Stepping. AIChE Journal 56(7). 1739‐1747.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 14/51
14
amount of material being deposited on the membrane surface and material being removed by the
cross‐flow and employed cleaning strategy. This equilibrium is achieved due to the efficiency of
the equipment to remove the reversible fouling.
The idea of the experiments is to find the so called critical flux, since exceeding that point is not
possible to achieve a stationary operation, meaning that there is not equilibrium between the
fouling formation and removal by the cleaning strategy (cross‐flow, backflush or backpulse). Above
the critical flux it is very difficult to maintain a sustainable production due to the formation of a
dominating irreversible fouling. After considerable irreversible fouling, there is a loss of separation
performance which cannot be recovered. It is not recommended to operate the equipment above
the critical flux, thus it is an important parameter to identify. During the experiments for each flux
conditions, the physical cleaning variables are tested such as frequency and intensity. The
frequency of the cleaning strategies has a big influence on the operating cost of the pilot plant.
The separation performance is followed using quantitative measurements of the total suspended
solids and oil in water. The analyses are performed following the standard protocols used in the
field laboratory (ANTEK)2.
The determination of the critical flux methodology is applied at two different points in the
produced water treatment, before and after the skimming tanks. As a preliminary experiment, the
first evaluation point includes a test of conventional ultrafiltration.
1.5.2. Continuous operation tests
Once
the
operating
conditions
are
identified,
the
sustainable
operation
is
evaluated
using
continuous operation. The initial tests are performed at moderated operating time, increasing the
operation window. During the continuous tests, the water quality is determined regularly.
1.5.3. Chemical cleaning efficiency evaluation
As a parallel activity to the experimental design, the efficiency of the chemical cleaning is
evaluated. The objective of the chemical cleaning is to remove the accumulated organic matter,
solids and precipitated salts in both surface and internal structure of the membrane. Thus, recover
the initial stable separation potential of the membrane. The cleaning efficiency is quantified
through
the
water
permeability
assessment.
Using
the
test
results,
the
recommended
cleaning
strategy is refined in order to match an acceptable water permeability recovery at field conditions.
1.6. Activities schedule
The activities are organized in four main areas; every one of these has a time line defined,
including labor, resources and troubleshooting that were necessary for the correct development
of the project.
2 ANTEK is a certified laboratory that makes all quantitative measurements in the field.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 15/51
15
In the following figure, the time line for every area is depicted.
Figure 13. Work schedule for the test period at OCELOTE field-HOCOL
The Assembly and Installation of the pilot unit and was started 27/06/2012. The installation of the
pilot plant was delayed due to the absence of 440V in the field. HOCOL had promised 440V but at
the end there was no way to provide it in the field. Therefore, a transformer was installed. This
activity took
a week.
The experimental phase was divided in two tests: the first sample point used feed water from the
outlet of surge tanks, and the second used water from the outlet of skimming tanks. The order of
the tests was imposed by HOCOL. All these activities were started the 10/07/2012 and finished
03/08/2012.
Closing Operation consisted in un‐mounting of the equipment, cleaning and shut down of the pilot
unit. These activities were started the 04/08/2012 and finished 06/08/2012.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 16/51
16
2. Water permeabil ity test
The
ultrafiltration
membrane
used
for
the
experiments
was
LiqTech‐
103377.
The
water
permeability is used to evaluate the state of the membrane. The permeability is defined as the
ratio between the flux and the applied transmembrane pressure.
In the field, the membrane permeability is estimated according to the water quality available.
There is a limitation since there is not a drinking water line available (see Figure 14a). The cleanest
source available is the outlet of the walnut shell filter 2. This water is not in optimal conditions
neither for cleaning nor for water permeability estimation but there is no other initial water
source. The quality of this water changes a lot as it can be as bad as it is shown in Figure 14b,
which is an extreme case seen in the at the beginning of the experiments.
(a) (b)
Figure 14. Quality of the water available in the field. (a) Drinking water, the color is due to a severe
oxidation of the pipelines. (b) Example of bad quality water from the walnut shell filter 2 (not all the
time was bad ).
The water flux was estimated as a function of the TMP. The results are shown in the Figure 15. It
can be seen how the flux increases very fast by raising the pressure at low TMPs. At higher TMP,
the slope tends to settle. The results are clearer by looking the permeability in Figure 16.
The initial permeability changed from 1550 to 4500 LMH/bar at the lowest TMP evaluated.
However, it rapidly stabilizes around 3000 LMH/bar at TMPs higher than 0.1 bar. At moderate
TMP, a high
recovery
is
achieved
and
the
permeability
tends
to
decrease.
It
is
believed
that
this
effect is due to the quality of the water that was coming from the walnut shell filter (OiW: 1 ppm
and TSS: 3.3 ppm, this average information was provided by the Latin‐American treatment
personal, at HOCOL).
Despite the water quality, the results agree with the expected value of 3000 LMH/bar, reported by
LiqTech3.
3 LiqTech International A/S. CoMem Conduit – OD146mm diameter Round Channels data sheet.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 17/51
17
Figure 15. Water permeability test using water from the walnut shell filter 2 (12/07/12).
Figure 16. Water permeability test using water from the walnut shell filter 2 (12/07/12).
0.00
100.00
200.00
300.00
400.00
500.00
600.00
700.00
800.00
900.00
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4
W a t e r f l u x ( L M H )
Transmembrane pressure (bar)
0.00
500.00
1000.00
1500.00
2000.00
2500.00
3000.00
3500.00
4000.00
4500.00
5000.00
0 0.05 0.1 0.15 0.2 0.25 0.3 0.35 0.4
P e r m e a b i l i t y ( L M H / b a r )
Transmembrane pressure (bar)
Field
Perm
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 18/51
18
3. Experimental evaluation point: Before the skimmingtanks
The test in this evaluation point took place between the 11/07/2012 to 28/07/2012. This period
included testing time and maintenance of the pilot plant due to some unexpected situations.
3.1. Characteristics of the inlet water – field information
In the field, the oil in water and total suspended solids are quantified twice per day. The average
values during the testing days are shown in the following plots. The place where the inlet is taken
is a point where the 3 shown streams are combined.
Figure 17. Oil in water average concentration at the outlet of the oil recovery section. ST: Surge tank,
GB: Gun Barrel (Information provided by Latin-American treatment personal, at HOCOL)
It can be seen in Figure 17 that the OiW outlet concentration of the surge tank 1 is considerably
higher than the other units. The surge tank 2 manages the lowest variance and the Gun barrel
manages lower outlet concentrations, however it has a substantial variance. According to this
record, heavy oil load has been received especially in the middle and at the end of the experiment,
the heaviest load has been seen during the period with continuous operation of the pilot plant.
0.00
100.00
200.00
300.00
400.00
500.00
600.00
700.00
O I W
( p p m )
ST 1
ST 2
GB
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 19/51
19
On the other hand, the total suspended solids concentrations show lower variance and the
concentrations are below 20ppm (see Figure 18). However, there is an atypical event at the end of
the test where there is a tremendous increase in the TSS concentration (six times higher
concentrations). This event took place during the continuous evaluation of the operating point.
It has to be mentioned that these concentrations are average of two samples per day. Therefore,
they do not really represent the variance that can be seen in the field, but give an overview of the
challenges faced during the experiments.
Figure 18. Total suspended solids evolution in the lines at the outlet of the oil recovery section. ST:
Surge tank, GB: Gun Barrel. (Information provided by Latin-American treatment personal, at
HOCOL)
3.2. Preliminary tests – conventional ultrafiltration
The purpose of the first experiment was to provide a fast indication of the fouling challenge in this
evaluation point. The idea was to determine the sustainable flux during conventional
ultrafiltration. An inspection of this data would provide relevant information about how fast the
flux is limited by irreversible fouling. At the same time, this point is a comparison standard to
evaluate the efficiency of the in situ cleaning strategies.
The ultrafiltration test has shown that the critical flux without any in situ cleaning mechanism
occur at relatively low TMP. The summary of the results are shown in the Table 1. For this
experiment, the operating and relaxation time per operating point were 60 and 30 minutes,
0.00
20.00
40.00
60.00
80.00
100.00
120.00
140.00
T S S ( p p m )
ST 1
ST 2
GB
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 20/51
20
respectively. The permeate flow rate increase was initially 0.5 m3/h, but it was decreased along
the experiment.
Table 1. Results from the conventional ultrafiltration operation mode.
Crossflow
(m3/h)
Critical TMP*
(bar)
Critical Flux Average inlet concentration
LMH Permeate (m3/h) TSS (ppm) OiW (ppm)
30 0.7 150 1.2 28.38 117.53
*This TMP has been already affected by an initial irreversible fouling during the experiment
From the preliminary results, it was evidenced that irreversible fouling is formed at relatively low
TMPs and LMH. It has been seen that completely unsustainable operation is achieved already at
170 LMH. These results have been influenced by the initial fouling generated by the quality of the
clean water available in the field (during the permeability test).
From this experiment it can be stated that there is a need of using the in situ cleaning strategies
for this application. The cleaning frequency should be moderate in order to avoid irreversible
fouling formation.
3.3. Operating window identification - Operability investigation
A sequence of experiments were performed in order to determine the sustainable operation
conditions of the plant according to the given water quality. The initial strategy was to emulate
continuous operation by having around 500 L of produced water in the feed tank and recirculating
both retentate and permeate streams. In that way, it was expected to have approximately
constant inlet concentration for each experiment (the variation would be due to the accumulated
material within the equipment). In this scenario, strong agitation and temperature regulation were
provided. The first 3 tuning experiments were performed in this way.
Nevertheless, it was noticed that there was a considerable oil inlet concentration decrease along
the experiments (see Figure 21). This was mainly due to the oil tendency to stick to the feed tank
surface and to some extend within the equipment. Therefore, it was decided to perform the
remaining tuning experiments using a continuous feed stream to the feed tank, while the
retentate and permeate where disposed out of the system. This operation mode brought new
challenges due to the variance of the inlet oil and suspended solid concentrations along the tuning
experiments. Besides,
it
introduces
the
inlet
concentrations
as
variables
within
the
experimental
design. On the other hand, this strategy was advantageous due to the constant monitoring of the
inlet concentrations along the experiments, providing more information about the system, which
is relevant for the plant design and operation.
Due to the variable quality of the clean water used for washing and permeability estimation
between experiments, it was decided that as long as the water coming from the walnut shell filter
2 showed bad aspect, the permeate water would be used for those purposes. This water was
collected in one of the 2000L tanks available.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 21/51
21
The tuning experiments at constant flux started using a low recovery and it was increased step
wise between experiments. The summary of the operating conditions for the experiments are
shown in the Table 2. For the last experiment the constant TMP operating mode was tested. Only
the results certified by ANTEK laboratory are reported.
Table 2. Summary of the operating conditions for the tuning experiments. The experiments labels stand
for Dynamic Ultrafiltration (DUF). It is referred as dynamic due to the operation of the in situ cleaning
strategies.
Test* Crossflow
(auto)
Feed pump
(auto)
Backpulse
(s)
Backflush
(s)
Permeate Retentate
04V04(%) 03V01(%) 03V02(%)
DUF 1 30 29‐38 60 300 40‐90 100 100
DUF 2 30 30‐50 60 300 60‐100 100 70‐100
DUF 3 30 32‐56 60 300 100 60 60
DUF 4
30
28‐42
60
300
80
‐100
40
50
*DUF – Dynamic Ultrafiltration
As an example of the results obtained, the dynamic behavior of the 3th experiment (DUF 3) is
shown in Figure 19 and Figure 20. It can be seen that the backpulse and backflush operation
disturb the system having the noise effect. This disturbance is rejected by the constant flux
controller that manipulates the feed pump. From the flux values in the figure, the challenge of the
separation can be seen due to the low fluxes obtained from the beginning.
Figure 19. Flux profile during the critical flux determination (DUF3)
0.00
50.00
100.00
150.00
200.00
250.00
300.00
350.00
400.00
13:55:12 15:07:12 16:19:12 17:31:12 18:43:12
P e r
m e a t e f l u x ( L M H )
Time (h:m:s)
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 22/51
22
Figure 20. TMP profile during the critical flux determination (DUF3)
The summary of the tuning experiment results are depicted in Table 3. The minimum flux
condition is the starting point. The maximum flux conditions correspond to the point where the
maximum permeate flow was evaluated.
Table 3. Summary of the tuning experiments before the skimming tanks. Values taken by inspectionfrom the display during operation, before the BPH.
Point Min. flux conditions Maximum flux conditions
Average inlet
(ppm)*
Initial
PERM
** LMH TMP REC PERM LMH TMP REC PERM OiW TSS
DUF 1 63 0.10 7 720 200 0.35 19 700 106.50 22.11 1860
DUF 2 125 0.15 17 750 280 0.90 24 310 70.50 3.5 600
DUF 3 175 0.60 33 310 276 1.55 28 172 74.32 7.25 1250
DUF 4 150 0.55 40 260 435 0.95 62 435 65.39 4.07 1500
* From our measurements
** The variance in the initial permeability is highly correlated to the quality of the cleaning water
The results depicted in Table 3 give the range of operating conditions achievable given the inlet
concentrations. It can be seen that the operating window was extended for the last experiments,
where higher TMPs were tested. Despite the first experiment was performed using the highest
average inlet concentrations, it has shown the best permeabilities. This result is expected since the
membrane was new. The second and third experiments are interesting since they have similar
water quality in oil concentration but different suspended solids concentration (TSSDUF3 is more
than 2 times TSSDUF2). The impact in the permeability is evident at minimum and maximum flux
conditions; there is a reduction around 50% from DUF2 to DUF3. This effect is visible in the
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
13:55:12 15:07:12 16:19:12 17:31:12 18:43:12
T M P ( b a r )
Time (h:m:s)
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 23/51
23
maximum flux tested, where a much higher TMP is required in DUF3 to achieve basically the same
flux. It has to be accounted for that during DUF 3 the inlet concentration decreased along the
experiment while during DUF 4 it increases.
The last experiment showed the highest flux at moderate TMPs, with inlet concentrations
comparable to the second experiment. This is an indication that effect of the suspended solids on
the process does not depend entirely of the concentration.
The water quality during the tuning experiments is shown Figure 21 and Figure 22. The data are
certified by ANTEK laboratory. The samples 1‐5 were taken the 20/07/2012 (DUF 3) and the
remaining samples the 21/07/2012 (DUF 4). According to the data reported by the field, the
measured inlet OiW concentrations were considerably lower, between 30% and 65% of the
average values reported by the field laboratory4. This confirms the variability of the concentrations
measured in
the
field,
and
why
average
concentrations
do
not
entirely
represent
the
system.
Figure 21. Oil in water concentration at the inlet and outlet of the pilot plant for the tuning experiments
For the DUF 3 experiment, it can be seen how the OiW concentration decreases along the test.
The situation that generated the change in the feed strategy, as mentioned previously (notice that
the concentration increases in DUF4). The OiW outlet concentration does not necessarily follow
the trend in the inlet concentration in the evaluated flux conditions. From the reported values, all
4 In the field, Latinametican chemical treatment also measures the concentrations along the process.
0
0.5
1
1.5
2
2.5
3
3.5
0
20
40
60
80
100
120
140
160
180
0 1 2 3 4 5 6 7 8 9 10 11 12 13
O i l i n w a t e r o u l t e t ( p p m )
O i l i n w a t e r i n l e t ( p p m )
Sample (1 hour difference)
DUF 3 ‐ inlet DUF 4 ‐ inlet DUF 3 ‐ oulet DUF 4 ‐ outlet
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 24/51
24
permeate water fulfill the required the target (max 5 ppm). The maximum outlet concentration is
around 3 ppm. The oil removal from the inlet stream during the tuning experiments was between
83.6 and 99.4%.
Regarding the total suspended solids concentrations, there is no concentration decrease along the
experiment DUF 3 (see Figure 22). Interestingly, the reduction in the TSS is seen when the feed is
in continuous mode (DUF4). For both experiments, the inlet concentration is between 3 and 10
ppm. The TSS concentrations in the permeate stream are very low, in some cases below the
detectability of the instrument. It means that the equipment is not able to distinguish between
distillated water and the permeate samples. The TSS removal during the tuning experiments was
between 82.3% and 100%. Notice that the 82.3% is the last point in Figure 22, and does not
entirely represent the overall behavior, for all the other samples the TSS removal was above 95%.
Some examples
of
the
water
quality
during
DUF
3 and
DUF
4 can
be
seen
in
Figure
23.
Figure 22. Total suspended solids concentration at the inlet and outlet of the pilot plant for the tuning
experiments
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
0.5
0
1
2
3
4
5
6
7
8
9
0 1 2 3 4 5 6 7 8 9 10 11 12 13
T o t a l s u s p e n d e s
s o l i d s o u t l e t ( p p m )
T o t a l s u s p e n d e d s o l i d s i n l e t ( p p m )
Sample (1 hour difference)
DUF 3
‐inlet DUF
4
‐inlet DUF
3
‐oulet DUF
4
‐outlet
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 25/51
25
(a) DUF 3 (b) DUF 4
Figure 23. Pictures of the inlet water and treated water during the tuning experiments
The shown flux ranges correspond to the tested values. The purpose of the experiments is to
determine a sustainable operation of the system. The precise value for each inlet concentration
can be estimated from a rigorous analysis of the experimental data. However, a qualitative
inspection of the data provides sufficient preliminary information in order to plan the continuous
experiments. From the analysis, it was seen that the sustainable operation was in the
neighborhood
of
0.7
to
1
bar
for
the
evaluated
concentrations.
Higher
TMP´s
would
require
a
considerable increase in the feed channels pressure in order to keep the constant permeate flux.
3.4. Continuous operation
The continuous operation of the system was evaluated at three different operating times (6, 12
and 27 hours). Besides, the system was operated at constant TMP. The biggest challenge for these
experiments is to achieve stable operation given the disturbances in the inlet concentrations. This
issue is particularly difficult to handle due to the frequency and amplitude of the disturbances.
A summary of the pilot plant inputs is shown in the Table 4. Taking advantage of the longer
operation
time,
the
influence
of
different
crossflow,
backpulse
frequency
and
recovery
values
were tested. In other situations the recovery was manipulated in order to increase productivity or
handle disturbances.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 26/51
26
Table 4. Summary of the operating conditions for the continuous operation of the treatment before the
skimming tanks.
Test Crossflow
(auto)
Feed pump
(manual)
Backpulse
(s)
Backflush
(s)
Permeate
Retentate
04V04(%) 03V01
(%)
03V02
(%)
CDUF 2‐ 6h 30 35‐40 60‐90 300 100 40 45
CDUF 4‐ 12h 30‐35 30‐32 60‐120 300 100 55‐60 55‐60
CDUF 5‐ 27h 30‐40 30‐35 60‐90 300 100 40‐70 45‐70
For the continuous operation, the results are shown in table 5. Different exogenous events
affected the length of the experiments. First of all, it can be noticed that the inlet concentrations
are substantially higher than during the tuning experiments. Despite of this situation, the obtained
fluxes are
within
the
expected
values.
During
the
experiment
CDUF
4,
there
was
a problem
with
a
valve in the retentate line that forced a shut down. The operation was recovered after 2 hours.
This prolonged shut down had a negative effect in the plant performance. In the last continuous
experiment (CDUF 5) there was an atypical situation that generated an unsustainable condition.
Since the last continuous experiment is the most interesting, it will be discussed further.
Table 5. Summary of the continuous experiments before the skimming tanks
Point Minimum flux conditions Maximum flux conditions
Average inlet
(ppm) Initial
PERM*
LMH
TMP
REC
PERM LMH TMP REC PERM OiW
TSS CDUF 2 185 0.70 51 250 495 0.95 81 540 221.20 7.33 1200
CDUF 4 135 0.70 35 190 370 0.35 54 925 722.56 16.74 484
CDUF 5 200 0.65 63 280 610 0.60 87 1000 367.91 13.14 2400
* The variance in the initial permeability is highly correlated to the quality of the cleaning water
The operation of the CDUF 5 is shown in Figure 24 and Figure 25. Initially a conservative TMP of
0.4 bar was used, obtaining stable operation for approx 9 hours at an average of 490 LMH with a
recovery of 70%. This was possible due to the quality of the inlet water. Later, the TMP was slightly
raised further increasing the flux and the recovery. At this point, 5 hours of stable operation was
achieved at 0.55 bar with 590 LMH and 80% recovery. This operation window represents the best
evaluated case.
At 10:00 am, there was a material recirculation from the sludge treatment plant trough the line
used for the feed. This material is characterized by high OiW and TSS content, beyond the limits
managed in the produced water treatment plant. The impacts of this event are clear on the flux
and permeate quality. In order to evaluate the plant performance without chemical cleaning, it
was decided to continue the experiment. Nine hours after the incident, the flux had decreased
more than 50% and reached a new stationary operation point at 240 LMH.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 27/51
27
Figure 24. Flux profile during the continuous experiment CDUF 5
Figure 25. TMP profile during the continuous experiment CDUF 5
0
100
200
300
400
500
600
700
800
900
1000
19:54:46 00:42:46 05:30:46 10:18:46 15:06:46 19:54:46
F l u x ( L M H )
Time (h:m:s)
‐1
‐0.5
0
0.5
1
1.5
19:54:46 00:42:46 05:30:46 10:18:46 15:06:46 19:54:46 T M P ( b a r )
Time (h:m:s)
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 28/51
28
The OiW concentration behavior during the continuous tests is depicted in Figure 26. Comparing
the inlet concentrations with the average values reported by the field laboratory, there are big
differences (between 40 and 60%, only in the average values, see Figure 17). Evidently, the
difference at certain points is even higher with the actual concentration being up to 5 times the
average. These concentrations are considerably higher than the values used for the equipment
tuning. Meaning that during some periods the pilot plant was operated at higher TMP´s than
recommended. As a consequence, some oil was able to pass through the membrane. This effect
can be seen along the continuous experiments and it is critical in CDUF 5 after the incident, where
the amount of oil in the permeate stream is far beyond the desired value. Despite the plant
achieved a new stationary operation point, the permeate water quality indicates that the
membrane was saturated with oil. The OiW removal is between 67.4% and 99.5% for most of the
data, with atypical values of 23.4 and 53.4% after the incident in CDUF 5.
The non
satisfactory
OiW
concentration
in
the
treated
water
was
also
influenced
by
some
non
complete recovery of the water permeability between experiments. Due to time constraints, it
was decided to continue the experiments being aware of the possible consequences.
Figure 26. Oil in water concentration at the inlet and outlet of the pilot plant for the continuous
operation
0
50
100
150
200
250
0
200
400
600
800
1000
1200
1400
0 5 10 15 20 25
O i l i n w a t e r o u t l e t ( p p m )
O i l i n w a t e r i n l e t ( p p m )
Sample
CDUF 2
‐inlet CDUF
4
‐inlet CDUF
5
‐inlet
CDUF 2 ‐ outlet CDUF 4 ‐ outlet CDUF 5 ‐ outlet
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 29/51
29
Figure 27. Total suspended solids concentration at the inlet and outlet of the pilot plant for the
continuous operation
In Figure 27, the suspended solid concentrations during the continuous operation are shown.
These values are similar to the average values reported by the field laboratory (see Figure 18).
Operation at higher TMP’s does not have a significant effect in the concentration in the permeate
TSS concentration, due to the incompressible nature of the suspended solids. Despite the
concentration picks, the TSS concentrations in the treated water are kept below 2 ppm. The
suspended solid removal during the continuous experiments is between 92.5 and 100%.
Some pictures of the continuous experiments are shown in Figure 28. In the Figure 28(b), the
operation was satisfactory and the quality evident. In Figure 28(c), the difference between the
expected feed water and the recirculated sludge can be seen. Due to the low residence time in the
machine the effect in the permeate quality is immediate. After the incident, the water looks like in
Figure 28 (d).
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
0
5
10
15
20
25
30
0 5 10 15 20 25
T o t a l s u s p e n d e d s o l i d s o u t l e t ( p p m )
T o t a l s u s p e n d e d s o l i d s i n l e t ( p p
m )
Sample
CDUF 2 ‐ inlet CDUF 4 ‐ inlet CDUF 5 ‐ inlet
CDUF 2 ‐ outlet CDUF 4 ‐ outlet CDUF 5 ‐ outlet
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 30/51
30
(a) CDUF 2 – satisfactory performance (b) CDUF 5 – satisfactory performance
(c) CDUF 5 – incident time (left the sludge fed) (d) CDUF 5 – after incident
Figure 28. Pictures of the inlet water and treated water during the continuous experiments
2.5 Conclusions
From this first testing it can be concluded:
From the laboratory analysis of the average inlet water characteristics, it can be seen that
there is considerable variance from day to day, where the concentration can easily
increase more than 100%
The need of the in situ cleaning strategies is evident, since the sustainable fluxes where
increased more than 3 times (depending on the inlet concentration and nature).
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 31/51
31
The tuning experiments showed a preliminary indication that the concentration and
nature of the suspended solids in this field can be a limiting flux factor, since duplicating
the TSS had a significant effect in the TMP necessary to obtain the same flux. This result is
also influenced by the slope in the inlet concentration. There is a considerable variance in
the nature of the treated water since it comes from several oil wells in the area.
The qualitative analysis of the obtained data indicated that the best sustainable operation
can be achieved with TMP´s between 0.7 and 1 bar.
The tuning experiments showed that the OiW and TSS target concentrations where
achieved, not higher than 5 ppm. The oil and TSS removal were up to 99.4 % and 100%,
respectively.
During the continuous operation of the plant, large disturbances were evidenced in the
feed concentration, even atypical situations. These variables have a significant influence in
the plant performance, implying a significant reduction in the flux. Despite new stationary
operating points were achieved; the oil content in the water indicated the need of a
premature chemical cleaning. The accidental recirculation of the sludge is the worst water
in the field to treat, and still good oil and TSS removal were achieved (up to 99.5 % and
100%, respectively). The recommended operating conditions are 30‐40 m3/h of crossflow,
60 s of backpulse frequency and 300 s of backflush. These results indicate how important
is to monitor the inlet concentrations in order to have an appropriate plant operation. It is
relevant to notice that the OiW and TSS loads during the tuning experiments were
considerably lower than during the continuous operation. Therefore, it is expected that a
longer trial time would provide the necessary information for an improved plant
operation.
In an industrial scale, the plant operation can be adapted to handle the concentration
peaks. One option is to reduce the plant productivity (lower TMP) during abnormal
conditions. It is expected that using this strategy the plant can operate longer time
avoiding a premature chemical cleaning. The alternative is to have a flexible stages design
that allows modifying the plant configuration to guarantee the permeate quality. Both of
these strategies would require continues measurement of OiW content.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 32/51
32
4. Experimental evaluation point: After the skimmingtanks
The test in this evaluation point took place between the 30/07/2012 to 03/08/2012.
4.1. Characteristics of the inlet water – field information
In the field, the oil in water and total suspended solids are quantified twice per day. The average
values during the testing days are shown in the following plots. The place where the inlet is taken
is a point where the outlet of the 2 skimming tanks is combined.
Figure 29. Oil in water concentration at the outlet of the oil recovery section. SK: Skimming tank
(Information provided by Latin-American treatment personal, at HOCOL)
In contrast to the previous feed point, the variance in the inlet concentration is not that high.
There is only one pick the 31st of July during the tuning experiments. The two skimmers behaved
similarly. The average concentration at the inlet of the skimming tanks in those days was between
200 ppm and 400 ppm, the skimming tanks were able to remove around 85% of the oil.
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
90.00
O I W
( p p m )
SK 1
SK 2
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 33/51
33
Figure 30. Total suspended solids concentration at the outlet of the Skimming tanks. SK: Skimming
tanks. (Information provided by Latin-American treatment personal, at HOCOL)
The TSS concentration follows the behavior of the OiW. The variance is moderated having a pick
the 31st of July as well. The purpose of the skimming tanks is to recover the remaining oil in the
water. However, part of the suspended solids is removed too. In these days, approximately 60% of
the solids were removed with the oil. According to the current understanding of the nature of the
suspended solids by the people in the field, parts of the suspended solids are hydrocarbons of
interest (soluble in xylene) and are supposed to be recovered in the skimmers.
4.2. Operating window identification - Operability investigation
The experiments were carried out using a constant feed coming from the skimming tanks and at
constant permeate operation mode. The water for washing and permeability estimation was taken
from the walnut shell filter 2. During this part of the experiment, the water quality from the filter
was exceptionally good (below 1 ppm OiW/TSS). Once again, the tuning experiments started using
a low recovery and it was increased step wise between experiments.
The operating conditions for the tuning experiments are shown in Table 6.
0.00
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
T S S ( p p m )
SK 1
SK 2
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 34/51
34
Table 6. Summary of the operating conditions for the tuning experiments
Test Crossflow
(auto)
Feed pump
(auto)
Backpulse
(s)
Backflush
(s)
Permeate Retentate
04V04(%)
03V01(%)
03V02(%)
DUF 1 30 28‐38 90 300 100 70‐80 70‐80
DUF 2 30 29‐50 90 300 55‐90 50‐60 50‐60
DUF 3 30 28‐58 90 300 60‐100 40 40
As an example of the results obtained, the dynamic behavior of the 3rd experiment (DUF 3) is
shown in Figure 31.
Figure 31. Flux and TMP profile during the critical flux determination
It can be seen that for the given inlet concentration of the last tuning experiment, higher fluxes
are achievable compared to the previous feed point and the noise is reduced. The summary of the
results for the tuning experiments are depicted in Table 7.
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
0
100
200
300
400
500
600
700
800
900
1000
17:45:36 18:28:48 19:12:00 19:55:12 20:38:24 21:21:36 22:04:48
T M P ( b a r )
F l u x ( L M H )
Time (h:m:s)
LMH TMP
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 35/51
35
Table 7. Summary of the tuning experiments before the skimming tanks. Values taken by inspection
from the display during operation before de BPH
Point
Minimum flux conditions Maximum flux conditions Average inlet
(ppm)
Initial
PERM* LMH TMP REC PERM LMH TMP REC PERM OiW TSS
DUF 1 250 0.2 31 1250 501 0.35 46 1200 8.30 3.17 1700
DUF 2 250 0.15 40 1300 692 0.95 71 767 38.58 6.02 1300
DUF 3 315 0.15 74 1600 816 1.65 85 490 22.23 3.21 2400
* The variance in the initial permeability is highly correlated to the quality of the cleaning water
From the table can, it be seen that the initial and final fluxes where increased as well as the
recovery between experiments. High permeabilities are evidenced at minimum flux conditions, a
situation that changes for the maximum flux conditions. Considering the reduced OiW and TSS
load in
the
feed,
the
fluxes
do
not
increase
in
the
same
ratio.
Comparing
the
fluxes
from
DUF
2
and DUF 3 at similar TMPs, the results are comparable despite the differences in the inlet
concentrations (results not shown in the table). The last tuning experiment has shown the highest
flux and recovery (816 LMH and 85%, respectively). The influence of the OiW and TSS
concentrations is not clearly visible from the results.
The water quality during the tuning experiments is shown in Figure 32 and Figure 33. The data 1‐5
were taken the 30/07/2012 (DUF 1), 6‐13 taken the 31/07/2012 (DUF 2) and 14‐22 taken the
1/08/2012 (DUF 3).
Figure 32. Oil in water concentration at the inlet and outlet of the pilot plant for the tuning experiments
0
1
2
3
4
5
6
7
8
910
0
10
20
30
40
50
60
70
0 5 10 15 20 25
O i l i n w a t e r o u t l e t ( p p m )
O i l i n w a t e r i n l e t ( p p m )
Sample
DUF 1 ‐ inlet DUF 2 ‐ inlet DUF 3 ‐ inlet
DUF 1 ‐ outlet DUF 2 ‐ outlet DUF 3 ‐ outlet
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 36/51
36
Comparing the average oil concentration measured during the experiments (Table 7) and the
values reported by the laboratory in the field (Figure 29), our values are between 50% and 100%
higher. There is not a clear trend in the OiW inlet concentrations. Regarding the outlet
concentration, there is only one value that is slightly above the desired limit. The oil removal from
the inlet stream during the tuning experiments was between 55.8 and 100%, but the lowest is an
atypical data since most of them are above 95%.
Figure 33. Total suspended solids concentration at the inlet and outlet of the pilot plant for the tuning
experiments
The suspended solid concentrations are more in accordance with the values reported by the
laboratory in the field, where the biggest difference is 21%. The TSS removal from this inlet stream
is considerable superior compared to the previous feed point, achieving between 91.2% and 100%.
The remarkable low concentrations in the treated water has to be highlighted, in several cases the
removal was 100%. Some examples of the water quality during DUF 2 and DUF 3 can be seen in
Figure 33.
From the inspection of the tuning results, it is expected to have the sustainable operation using
TMPs between 0.8 and 1 bar. Pictures of the treated water can be seen in Figure 34.
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
0.5
0
1
2
3
4
5
6
7
8
9
10
0 5 10 15 20 25
T S S o u l e t ( p p m )
T S S i n l e t
( p p m )
Sample
DUF 1 ‐ inlet DUF 2 ‐ inlet DUF 3 ‐ inlet
DUF 1
‐outlet DUF
2
‐outlet DUF
3
‐outlet
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 37/51
37
(a) DUF 2 (b) DUF 3
Figure 34. Pictures of the inlet water and treated water during the tuning experiments
4.3. Continuous operation
The continuous operation of the system was evaluated for 26 hours without a chemical cleaning.
The system was operated at constant TMP. The biggest challenge is still to achieve stable
operation given
the
disturbances
in
the
inlet
concentrations.
A
summary
of
the
pilot
plant
inputs
is
shown in the Table 8.
Table 8. Summary of the operating conditions for the continuous operation of the treatment after the
skimming tanks.
Test Crossflow
(auto)
Feed pump
(manual)
Backpulse
(s)
Backflush
(s)
Permeate Retentate
04V04(%) 03V01
(%)
03V02
(%)
CDUF 26 h 30‐40 28‐45 60‐90 300 80‐90 40‐50 40‐50
For the
continuous
operation,
the
results
are
shown
in
Table
9 and
data
shown
in
Figure
35
and
Figure 36. Only one point is evaluated due to time constraints. When the experiment started, a
moderate TMP was chosen to start with. Based on the tuning experiments it should provide a flux
of approximately 500 LMH. The initial flux was around 400 LMH which declined with time and
achieved stable operation at around 340 LMH after 5 hours of operation. This flux was maintained
all night slightly increasing the TMP. After 19 hour of operation, it is decided to operate at
constant flux conditions with a target of 440 LMH. The system achieved a new stationary
operating point at a TMP of 1.2 bar. The sustainable flux was very similar to the fluxes obtained for
the previous feed point. However, the operation in this point was more stable and potentially
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 38/51
38
longer operating time between chemical cleanings, specially using the constant permeate
operating mode.
Table 9. Summary of the continuous experiments after the skimming tanks
Operating
point
Minimum flux conditions Maximum flux conditions Average inlet (ppm) Initial
PERM* LMH TMP REC PERM LMH TMP REC PERM OiW TSS
CDUF 26h 310 0.6 63 490 440 1.2 68 390 20.36 2.86 1700
* The variance in the initial permeability is highly correlated to the quality of the cleaning water
Figure 35. Flux profile during the continuous experiment CDUF 26h
0
100
200
300
400
500
600
700
800
13:55:12 18:43:12 23:31:12 04:19:12 09:07:12 13:55:12
F l u x ( L M H )
Time (h:m:s)
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 39/51
39
Figure 36. TMP profile during the continuous experiment CDUF 26h
The water quality during the continuous experiment is shown in Figure 37 and Figure 38.
Figure 37. Oil in water concentration at the inlet and outlet of the pilot plant for the continuous
operation
‐0.5
0.0
0.5
1.0
1.5
2.0
13:55:12 18:43:12 23:31:12 04:19:12 09:07:12 13:55:12
T M P ( b a r )
Time (h:m:s)
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0
5
10
15
20
25
30
35
40
45
0 2 4 6 8 10 12
O i l i n w a t e r o u t l e t ( p p m )
O i l i n w a t e r i n l e t ( p p m )
Sample
CDUF 1 ‐ inlet CDUF 1 ‐ outlet
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 40/51
40
It can be seen in Figure 37 that at the beginning of the experiment the OiW concentration was
rather constant for 18 hours. Only at the end there was a considerable increase in the
concentration. Despite this moderate variation, the OiW content in the treated water was kept
below 1 ppm. The oil removal was between 96.3% and 100%.
Figure 38. Total suspended solids concentration at the inlet and outlet of the pilot plant for the
continuous operation
The suspended solids inlet concentration was stable at the beginning of the experiment whereas
some disturbances appeared towards the end. The TSS removal was 100% in most of the cases,
only one point showed a lower removal (96.4 %). Some pictures of the continuous operation of the
plant are depicted in Figure 39.
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
0.5
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
0 2 4 6 8 10 12
T o t a l
s u s p e n d e d s o l i d s ( p p m )
T o t a l
s u s p e n d e d s o l i d s ( p p m )
Sample
CDUF 1 ‐ inlet CDUF 1 ‐ outlet
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 41/51
41
(a) OiW content (b) Suspended solids
Figure 39. Pictures of the inlet water and treated water during the tuning experiments
4.4 Conclusions
From this first testing it can be concluded:
From the laboratory analysis of the average inlet water characteristics, it can be seen that
there is
considerable
variance
from
day
to
day,
where
the
concentration
can
easily
amplify
several times (eight for OiW and two for TSS).
The tuning experiments of the second sampling point (after skimming tanks) showed
improvements in the maximum flux compared to the first feed point evaluated (before
skimming tanks), around 30%. However, this result is not linearly correlated with the
changes in the inlet concentrations for both points.
The qualitative analysis of the obtained data indicated that the best sustainable operation
can be achieved with TMP´s between 0.8 and 1 bar.
The tuning experiments shown that the OiW and TSS target concentrations where
achieved, not higher than 5 ppm. The oil and TSS removal were up to 100%.
During the continuous operation of the plant, moderate disturbances were evidenced in
the feed concentration. Stationary operation was achieved at moderate flux conditions
first 340 LMH and later 440 LMH, using 30 m3/h cross flow, a backpulse frequency of 60 s,
a backflush frequency of 300 s. At this feed point, it is not that relevant to monitor the
inlet concentration, since the Skimming tanks act storage tanks that buffer the inlet
disturbances. During the continuous operation, the OiW and TSS target were achieved
(concentration below 5 ppm). From the tuning experiments it is expected to have better
fluxes.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 42/51
42
5. Cleaning in place evaluation
The
cleaning
strategy
was
evaluated
through
the
water
permeability
evaluation.
The
results
of
the
experiments are depicted in Figure 40. The initial water permeability of the membrane was 2800
LMH/bar at a TMP= 0.2 bar and using a cross flow of 30 m3/h. The fouling load in each of the
experiments was different mainly due to changes in inlet concentrations, cleaning water quality,
TMP, recovery and operation time. Initially the cleaning strategy consisted of one washing cycle:
1. Flushing with water
2. Alkaline cleaning: 30 min with 1% NaOH, 50 m3/h crossflow
3. Flushing with water
4. Acid cleaning: 30 min with 1% Oxalic acid, 50 m3/h crossflow
5. Flushing with water
Figure 40. Flux recovery after chemical cleaning. The initial water permeability was 2800 LMH/bar.
One cleaning cycle was enough during the first operation days. However, a loss of cleaning
efficiency was evidenced the 14/07/2012 and 21/07/2012. The 21/07/2012, was decided to use 2
washing cycles in order to recover the water permeability. It is acceptable to have a flux recovery
above 70%. After the continuous tests performed on the 24/07/2012, it was difficult to recover
permeability, even after the 2 washing cycles. However, the desired permeability was restored
after the 26/07/2012. Those dates correspond to the second sampling point (after skimming
tanks). It can be concluded that the type of fouling evidenced in the field is reversible to the
desired point in most of the cases.
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
90.0
100.0
R e c o v e r y ( % )
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 43/51
43
6. Final remarks
Evaluation point before skimming tanks:
5.1.1 Inlet water quality
Variance in the inlet water quality: high
Variance in the outlet water quality: low
5.1.2 Operability
Monitoring level required: significant
Changes in the operating conditions: significant
Chemical cleaning frequency: largely depends on the atypical events faced during continuous
operation
Longer operation might show other operation challenges (i.e. scaling and irreversible fouling)
5.1.3 Other aspects
Technical feasibility: it is recommended to include a buffer tank to assist the membrane
operation.
Membranes arrangement: parallel/series configuration with multiple membrane housings
could be exploited
Evaluation point after the skimming tanks:
5.2.1 Inlet water quality
Variance in the inlet water quality: moderate
Variance in the outlet water quality: negligible
5.2.2 Operability
Monitoring level
required:
low
Changes in the operating conditions: low
Chemical cleaning frequency: considerable lower than in the first evaluation point. The
appropriate frequency can be estimated from and OPEX analysis
5.2.3 Other aspects
Technical feasibility: high
Membranes arrangement: parallel/series configuration could be exploited
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 44/51
44
7. Future challenges
It is important to understand further the characteristics of the feed streams, not only
concentrations. This information is not only relevant for the operation but to improve the
cleaning strategies.
The methodology used for the determination of the operative window is impaired by
fluctuations in the inlet concentrations, making the estimation of the sustainable
operation more difficult. Further developments in the tuning strategy are needed.
The variance in the inlet concentration is probably the biggest obstacle to tune the system
and to operate in continuous. Monitoring of the inlet concentration is relevant for the
appropriate operation.
In
the
field
there
are
interactions
between
the
pilot
plant
and
the
existing
installations
at
industrial scale. Further electric protection for the system can avoid damage.
There is a lack of understanding of the interactions between the added chemicals in the
actual treatment and the membrane. Besides, the interactions between the acid and
alkaline solutions and the chemicals added. These topics remain for investigation.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 45/51
45
8. Appendix: Critical flux estimation
The
critical
flux
was
estimated
using
two
different
methodologies
described
in
literature
5
,
referred
to as average pressure and fouling rate methods. Details of the methods can be found in the
mentioned paper. According to the employed methodology during the experiments, the flux is
increased step wise aiming to find where the production becomes unsustainable for the given
input water quality. As mentioned extensively along the report, the variance in the inlet
concentration is the biggest obstacle to determine the critical flux. Therefore, it is better to aim for
identification of the critical flux window for each of the evaluated test points.
The critical flux is estimated using two different methods. Additionally, the step up‐down test
allows identifying when the irreversible fouling starts forming. Small description of the methods is
presented bellow.
a) Average pressure: this method evaluates the average TMP against the average flux along
the experiment. The critical flux is determined by the deviation from linearity, meaning
the presence of a maximum flux.
b) Fouling rate method: this method evaluates the fouling rate (dP/dt) against the average
flux along the experiment. The critical flux is determined for a notable increase in the
fouling rate by increasing the flux.
c) Irreversible fouling: it should be understood as the onset of the irreversible fouling. This
method evaluates the difference TMP for the same flux level steps. When fouling starts to
get irreversible, the TMP cannot be restored when moving from the next step due to the
higher flux
in
between.
It should be mentioned that not all the experiments behave as in the ideal case. It is believed that
the concentration changes along the experiments are the main reason.
8.1 Evaluation before the skimming tanks
For this test point, there are four tuning experiments. The first one does not use the in situ
cleaning strategies, so it is called conventional ultrafiltration (CUF). The remaining experiments use
the backpulse and backflush, so they are referred to as dynamic ultrafiltration (DUF). Good
examples of the obtained plots are shown in Figure 41 and Figure 42. A summary of the results for
all experiments
are
shown
in
Table
10.
5 Beier, S.P. and Jonsson, G. Critical Flux Determination by Fux Stepping. AIChE Journal 56(7). 1739‐1747.
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 46/51
46
Figure 41. Average pressure method for critical flux estimation. Results of experiment DUF4 (Critical
flux at 0.8 bar)
Figure 42. Fouling rate method results for critical flux estimation. Results from CUF experiment
(Critical flux 150 LMH)
0
50
100
150
200
250
300
350
400
450
0.72 0.74 0.76 0.78 0.80 0.82 0.84 0.86
A v e r a g e f l u x ( L M H )
Average TMP (bar)
0
2
4
6
8
10
12
14
16
18
100 110 120 130 140 150 160 170 180 190 200
d P / d t ( b a r / h )
Flux (LMH)
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 47/51
47
Table 10. Critical flux estimation from the tuning experiments before the skimming tanks.
Experiment
Critical flux
Method (Avg P)
Critical flux
Method (dP/dt) Irreversible
fouling flux
(LMH) Flux
(MLH)TMP
(bar) dP/dt
(bar/h)Flux
(MLH)TMP
(bar)dP/dt
(bar/h)
CUF 187.5 0.54 15.63 150 0.65 1.96 150.00
DUF 1* 186.5 0.24 2.09 186.5 0.24 2.09 155.69
DUF 2* 240.23 0.69 2.05 240.23 0.69 2.05 182.30
DUF 3 218.56 0.95 6.53 205.03 0.97 26.21 170.84
DUF 4 352.41 0.80 0.72 352.41 0.80 0.72 341.61
* Critical flux not achieved, then maximum value depicted
Due to time constraints performing the experiment, the critical flux is not achieved in all cases.
However, the information gathered was used in the following experiments. It can be seen in Table
10, that
the
critical
flux
was
not
achieved
in
DUF1
and
DUF2.
Therefore,
the
maximum
evaluated
flux is shown. The results are presented in Figure 43 and Figure 44.
Figure 43. Critical flux from the tuning experiments before the skimming tanks
Only for the conventional ultrafiltration, both methods gave considerable different results
(approx. 25%). From the experiments, it can be seen that the critical flux lies between 200 and 350
LMH. This range is broad and totally depends on the concentrations given during the tuning
experiments. For this reason, the operating TMP is considered as a better way to delimit the
operating window since the operation mode is constant TMP. In Figure 44, the critical TMP
Avg. P
dP/dt0
50
100
150
200
250
300
350
400
CUFDUF 1
DUF 2DUF 3
DUF 4
C r i t i c a l f l u x ( L M H )
Experiment
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 48/51
48
window can be identified between 0.7 and 1 bar. This confirms the conclusions obtained in the
field for this testing point.
In most
of
the
cases
the
onset
of
the
irreversible
fouling
formation
is
lower
than
the
critical
flux
(see Table 10). For that reason, the continuous experiments were performed using a conservative
TMP and sustainable operation was achieved due to the in situ cleaning strategies.
Figure 44. Critical TMP from the tuning experiments before the skimming tanks
8.2 Evaluation after the skimming tanks
For the test after the skimming tanks, there are three tuning experiments. All the experiments use
the backpulse and backflush, and referred to as dynamic ultrafiltration (DUF). Good examples of
the obtained plots are depicted in Figure 45 and Figure 46. The summary of the results of all
experiments are shown in Table 11.
Table 11. Critical flux estimation from the tuning experiments after the skimming tanks
Experiment
Critical flux
Method (Avg P)
Critical flux
Method (dP/dt) Irreversible
fouling flux
(LMH) Flux
(MLH)
TMP
(bar)
dP/dt
(bar/h)
Flux
(MLH)
TMP
(bar)
dP/dt
(bar/h)
DUF 1* 405.03 0.32 ‐0.14 405.03 0.32 ‐0.14 N/A
DUF 2* 573.24 0.69 1.94 573.24 0.69 1.94 486.32
DUF 3 703.28 1.24 11.25 600.97 0.88 1.97 536.87
* Critical flux not achieved, then maximum value depicted
Avg. P
dP/dt0
0.2
0.4
0.6
0.8
1
CUFDUF 1*
DUF 2*DUF 3
DUF 4
C r i t i c a l T M P
( b a r )
Experiment
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 49/51
49
Figure 45. Average pressure method for critical flux estimation. Results of experiment DUF3 (Critical
flux at 1.24 bar)
Figure 46. Fouling rate method results for critical flux estimation. Results from DUF experiment
(Critical flux 645.86 LMH)
In the average pressure method (Figure 45), the deviation from linear behavior occurs in the
maximum flux evaluated. In the second method the critical flux lies between the last two
evaluated points, and then the last with relatively low fouling rate is selected (notice that the
second plot has only 4 points, this is due to a lost in the data for this experiment). The results
from Table 11 are depicted in Figure 47 and Figure 48. Notice that the first two experiments, DUF1
and DUF2, did not achieve the critical flux.
0
100
200
300
400
500
600
700
800
0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40
A v e r a g e F l u x ( L M H )
Average TMP
(bar)
0
2
4
6
8
10
12
400 450 500 550 600 650 700 750
d P / d t ( b a r / h )
Average flux (LMH)
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 50/51
50
Figure 47. Critical flux from the tuning experiments after the skimming tanks
From the experiments, it is difficult to determine if both methods are giving the same results since
only one experiment achieved the critical flux. In that case, the obtained critical fluxes are slightly
different (approx. 16%). For this testing point, it is estimated to have sustainable fluxes between
600 and 700 LMH. Nevertheless, this result depends on the evaluated concentrations. The limited
information was collected in this evaluation point due to time constraints. For evaluation of this
point, more conservative sustainable fluxes are expected. This was confirmed during continuous
operation where
the
system
operated
at
maximum
440
LMH.
Figure 48. Critical TMP from the tuning experiments after the skimming tanks
Avg. P
dP/dt0
200
400
600
800
DUF 1*DUF 2*
DUF 3
C r i t i c a l f l u x ( L M H )
Experiment
Avg. …
dP/dt0
0.5
1
1.5
DUF 1*DUF 2*
DUF 3
C
r i t i c a l T M P ( b a r )
Experiment
Avg. P
dP/dt
7/27/2019 Final_report_HOCOL_test_LiqTech.pdf
http://slidepdf.com/reader/full/finalreporthocoltestliqtechpdf 51/51
Once again, it is relevant to determine the TMP operating window. It can be seen in Figure 48 that
the TMP operating window lies between 0.8 and 1.2 bar. This confirms as well the proposed
operating window investigated during continuous operation. Finally, the onset of the irreversible
fouling formation occurs again at fluxes lower than the identified critical fluxes (see Table 11).