22
First Trip Analysis Presented by: Steven Cannon, Substation Lineman Chugach Electric

First Trip Analysis

  • Upload
    vina

  • View
    38

  • Download
    0

Embed Size (px)

DESCRIPTION

First Trip Analysis. Chugach Electric. Presented by: Steven Cannon, Substation Lineman. Chugach Overview. Alaska’s largest electrical utility Provides generation, transmission, and distribution services Generation mix 90% gas, 10% hydro 65,000 members. Chugach System. 230kv-12.4kv lines - PowerPoint PPT Presentation

Citation preview

Page 1: First Trip Analysis

First Trip Analysis

Presented by:Steven Cannon, Substation Lineman

Chugach Electric

Page 2: First Trip Analysis

Chugach Overview• Alaska’s largest electrical utility • Provides generation, transmission, and

distribution services• Generation mix 90% gas, 10% hydro• 65,000 members

Page 3: First Trip Analysis

Chugach System

• 230kv-12.4kv lines• 50 substations and switchyards• 87 power transformers• 323 circuit breakers

Page 4: First Trip Analysis

Alaskan Rail Belt• The Alaska Railbelt system

– Electrically Islanded• The Railbelt system

– 850 MW Peak – Four generation areas:

Fairbanks, Anchorage, Beluga, and the Kenai Peninsula.

• The Anchorage area – Anchorage and Beluga

generation – Tied to both the Fairbanks and

Kenai Peninsula systems through single transmission ties

– 138 kV tie north to Fairbanks– 115 kV tie south to the Kenai.

Page 5: First Trip Analysis
Page 6: First Trip Analysis
Page 7: First Trip Analysis

Why First Trip Analysis?

• Analyze breakers “in the field” condition

Page 8: First Trip Analysis

Lubrication• Grease is composed of soap and oil• Oil provides lubrication• Soap gives consistency to hold lubrication• Oil eventually separates from the soap• Time causes soap to harden and gum up• Harden soap slows down breakers

Page 9: First Trip Analysis

Advantages of Capturing First Trip

• Breaker can be tested in energized state• Test can be performed in about 10 minutes• Overlay breaker operations

Page 10: First Trip Analysis

Qualifications for Operator

• Know how to read breaker control schemes• Be qualified to switch• Be computer literate• Understand safety rules for working in a

substation

Page 11: First Trip Analysis

ConnectionsCB Analyzer Hookup

• Insight into condition of a circuit breaker’s bearings, lubrication, trip and close circuits, auxiliary switch, main contact speed, DC supply and tailspring adjustment.

Page 12: First Trip Analysis

TRIP COIL PLUNGER

LATCH

Page 13: First Trip Analysis

Interpreting Graphs

Page 14: First Trip Analysis

Breaker 1616

Page 15: First Trip Analysis

Breaker 1616 DC Prints

DC (-)

DC (+)

TC Amp Probe

CC Amp Probe

Page 16: First Trip Analysis

DC LEADS

CT LEADS

Page 17: First Trip Analysis
Page 18: First Trip Analysis

Main Bearings

Page 19: First Trip Analysis

Latch Bearing

Page 20: First Trip Analysis

Breaker 1616 Results

Page 21: First Trip Analysis

Important Tips• Change batteries often• Come to the breaker prepared• Label wires to apply leads• Catch the first trip• Catch multiple breaker operations• Save each shot before moving the Profile• Periodically upload shots to computer• Develop a backup plan

Page 22: First Trip Analysis

Questions?