The paper presents a case studythat proposes practical solutions
for the restoration of longitudinal
connectivity of Criul Repede
River
In the town of Oradea there are a lot transversal constructionssuch as discharge sills and small dams, that stops migration
process of various fish species.
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
4/25
,
. / . / .
( ).
( )
( ).,
( )
( ), 4 .462
)
( )
( )
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
5/25
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
6/25
DOWNSTREAM
metal semi-cylinder
discharge sill
metal hinge
resistant rubber canal watercourserubber fixing system for the canal
Figure 1 Positioning the metal semi-cylinder indicative scheme
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
7/25
left bank right bank
resistant rubber canal discharge sill
module M2
module M1
watercourse
bascule for redirecting
fish towards the rubber canal
metal grillleft bank metal grid fence
fish redirecting system(electromagnetic field)
rubber canal
discharge sill
Figure 2 Rubber canal positioning indicative scheme
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
8/25
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
9/25
electric motoror winch
metal barmetal oval
metal cablemetal oval
mobile bascule or mobile semi-cylinder
mobile semi-cylinderframework
metal sheet pile - grid
left bank
water level in the rubber canal
Figure 4 Positioning the electric motor indicative scheme
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
10/25
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
11/25
The solution, intended for one river bank only, has the advantage ofbeing used as fish passage system upstream of discharge sill, too.
Another advantage of this system is that they can be dismantled and
stored (during winter) and used in other areas where rivers are
crossed by hydrotechnical works with transversal bars.
The costs for these systems are considered reasonable in contrast
with conventional systems costs.
They can work automatically, as the human intervention is required
only when it comes about supervision.
Andy Loghin
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
12/25
!
!
Rzvan G.VOICU, [email protected]@gmail.com
National Institute of Hydrology and Water Management
Laboratory of Eco-Hydrology, Romnia
Eric L.KAY, Senior project [email protected]
KAY ASSOCIATES, Comox, BC. CanadaForest and Industrial Road & Water Management Consultants
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
13/25
Vassalboro, Maine (Kennebec County)http://flyfishingonly.net/forum/topic.asp?TOPIC_ID=5967
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
14/25
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
15/25
l = 4mdischarge sill concrete bed
concrete ramp
H= 2,5 m(thickness)
indicative scheme
h = 3, 8m
L= 5, 52 mCriul Repede River
h1= 1,4 m
Concrete ramp dimensions
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
16/25
right bank the metal grid 2 left bankmetal stopper
discharge sill
metal and concrete fences
indicative scheme
concrete ramp
crenelated metal rail
metal bars
Metal grids positioning
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
17/25
crenelated metal rail
discharge sill electric motor
concrete ramp metal frame
metal frame electric motor
crenelated metal rail
concrete bed crenelated pinion
indicative scheme
Criul Repede River
rubber wheel
Crenelated rail positioning inside the concrete ramp
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
18/25
telescopic hydraulic cylinder
crenelated metal rail
concrete bed crenelated pinion
indicative scheme
metal hinge
metal frame
electric motor
metal mobile grid 1 (maximum height)
bearingbearing
Telescopic hydraulic cylinder positioning on the metal frame and on the
metal mobile grid1
vitess-industrial.ro
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
19/25
mobile metal grid 1metal bar for opening the grid 2
the metal grid 2
metal and concrete fences
concrete platform
indicative scheme
rubber roller
rubber wheel
2 cm
electric motor
Metal frame fastening system
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
20/25
rolling metal bar rubber wheel
metal bar securing the metal frame
rubber wheel
indicative scheme
http://en.wikipedia.org/wiki/Train_(roller_coaster)
Rollers positioning
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
21/25
mobile metal grid 2 metal springconcrete platform
crenelated metal rail
30dd
metal bar mobile metal grid 1discharge sill metal frame
concrete ramp electric motor
metal spring
indicative scheme
Criul Repede River
30 cm
Minimum and maximum levels of metal mobile grids 1 and 2
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
22/25
mobile metal grid 2 - metal spring
rsc.org
mobile metal grid 1telescopic hydraulic cylinder
30dd
mobile metal grid 1discharge sill electric motor
concrete ramp metal frame
indicative scheme
Criul Repede River 30 cm
bearing
Metal grid refolding and system returning on horizontal surface
Rack railway
http://www.connectmums.com/wp-
content/uploads/2012/03/Mt-Pilatus-
Rack-Railway-3-540300.jpg
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay
23/25
mobile metal grid 1metal fence concrete fence
mobile metal grid 2
metal spring
metal bar for opening the grid 2 discharge sill
concrete platform
indicative scheme
Concrete platform positioning
8/10/2019 Fish passage II - Razvan Voicu,Eric Kay