    The paper presents a case studythat proposes practical solutions

    for the restoration of longitudinal

    connectivity of Criul Repede

    River

    In the town of Oradea there are a lot transversal constructionssuch as discharge sills and small dams, that stops migration

    process of various fish species.

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    4/25

    ,

    . / . / .

    ( ).

    ( )

    ( ).,

    ( )

    ( ), 4 .462

    )

    ( )

    ( )

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    5/25

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    6/25

    DOWNSTREAM

    metal semi-cylinder

    discharge sill

    metal hinge

    resistant rubber canal watercourserubber fixing system for the canal

    Figure 1 Positioning the metal semi-cylinder indicative scheme

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    7/25

    left bank right bank

    resistant rubber canal discharge sill

    module M2

    module M1

    watercourse

    bascule for redirecting

    fish towards the rubber canal

    metal grillleft bank metal grid fence

    fish redirecting system(electromagnetic field)

    rubber canal

    discharge sill

    Figure 2 Rubber canal positioning indicative scheme

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    8/25

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    9/25

    electric motoror winch

    metal barmetal oval

    metal cablemetal oval

    mobile bascule or mobile semi-cylinder

    mobile semi-cylinderframework

    metal sheet pile - grid

    left bank

    water level in the rubber canal

    Figure 4 Positioning the electric motor indicative scheme

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    10/25

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    11/25

    The solution, intended for one river bank only, has the advantage ofbeing used as fish passage system upstream of discharge sill, too.

    Another advantage of this system is that they can be dismantled and

    stored (during winter) and used in other areas where rivers are

    crossed by hydrotechnical works with transversal bars.

    The costs for these systems are considered reasonable in contrast

    with conventional systems costs.

    They can work automatically, as the human intervention is required

    only when it comes about supervision.

    Andy Loghin

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    12/25

    !

    !

    Rzvan G.VOICU, [email protected]@gmail.com

    National Institute of Hydrology and Water Management

    Laboratory of Eco-Hydrology, Romnia

    Eric L.KAY, Senior project [email protected]

    KAY ASSOCIATES, Comox, BC. CanadaForest and Industrial Road & Water Management Consultants

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    13/25

    Vassalboro, Maine (Kennebec County)http://flyfishingonly.net/forum/topic.asp?TOPIC_ID=5967

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    14/25

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    15/25

    l = 4mdischarge sill concrete bed

    concrete ramp

    H= 2,5 m(thickness)

    indicative scheme

    h = 3, 8m

    L= 5, 52 mCriul Repede River

    h1= 1,4 m

    Concrete ramp dimensions

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    16/25

    right bank the metal grid 2 left bankmetal stopper

    discharge sill

    metal and concrete fences

    indicative scheme

    concrete ramp

    crenelated metal rail

    metal bars

    Metal grids positioning

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    17/25

    crenelated metal rail

    discharge sill electric motor

    concrete ramp metal frame

    metal frame electric motor

    crenelated metal rail

    concrete bed crenelated pinion

    indicative scheme

    Criul Repede River

    rubber wheel

    Crenelated rail positioning inside the concrete ramp

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    18/25

    telescopic hydraulic cylinder

    crenelated metal rail

    concrete bed crenelated pinion

    indicative scheme

    metal hinge

    metal frame

    electric motor

    metal mobile grid 1 (maximum height)

    bearingbearing

    Telescopic hydraulic cylinder positioning on the metal frame and on the

    metal mobile grid1

    vitess-industrial.ro

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    19/25

    mobile metal grid 1metal bar for opening the grid 2

    the metal grid 2

    metal and concrete fences

    concrete platform

    indicative scheme

    rubber roller

    rubber wheel

    2 cm

    electric motor

    Metal frame fastening system

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    20/25

    rolling metal bar rubber wheel

    metal bar securing the metal frame

    rubber wheel

    indicative scheme

    http://en.wikipedia.org/wiki/Train_(roller_coaster)

    Rollers positioning

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    21/25

    mobile metal grid 2 metal springconcrete platform

    crenelated metal rail

    30dd

    metal bar mobile metal grid 1discharge sill metal frame

    concrete ramp electric motor

    metal spring

    indicative scheme

    Criul Repede River

    30 cm

    Minimum and maximum levels of metal mobile grids 1 and 2

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    22/25

    mobile metal grid 2 - metal spring

    rsc.org

    mobile metal grid 1telescopic hydraulic cylinder

    30dd

    mobile metal grid 1discharge sill electric motor

    concrete ramp metal frame

    indicative scheme

    Criul Repede River 30 cm

    bearing

    Metal grid refolding and system returning on horizontal surface

    Rack railway

    http://www.connectmums.com/wp-

    content/uploads/2012/03/Mt-Pilatus-

    Rack-Railway-3-540300.jpg

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    23/25

    mobile metal grid 1metal fence concrete fence

    mobile metal grid 2

    metal spring

    metal bar for opening the grid 2 discharge sill

    concrete platform

    indicative scheme

    Concrete platform positioning

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    24/25

  • 8/10/2019 Fish passage II - Razvan Voicu,Eric Kay

    25/25

    !

    Rzvan G.VOICU, [email protected]@gmail.com