A) POR PESO
MATERIALES UNIDAD AFECTO (IGV) PESO UNIT. PESO TOTAL
CLAVOS PARA MADERA CON CABEZA DE 1" kg 27.08 1.00 27.08
CEMENTO PORTLAND TIPO I (42.5KG) BOL 90.00 42.50 3,825.00
YESO EN BOLSAS DE 25 KG. BOL 2.71 25.00 67.71
SOLDADURA CELLOCORD kg 9.80 1.00 9.80
MADERA EUCALIPTO p2 13.54 1.45 19.63
MALLA CUADRADA CRIPADA GALVANIZADA # 10 m2 588.88 50.00 29,443.41
PINTURA ESMALTE SINTETICO gal 54.16 4.50 243.73
PINTURA ANTICORROSIVA gal 54.16 4.50 243.73
FIERRO CORRUGADO DE 1/2", GRADO 60 m 52.80 1.02 53.86
TUBO DE FIERRO NEGRO DE 2" X 2mm X 6.4 m m 1,422.52 15.00 21,337.80
OTROS KG 1,600.00 1.00 1,600.00
OTROS: SE CONSIDERA 01 VIAJE DE MATERIALES
MATERIALES COMO: CANDADO, CERROJO, ALDABA, CORDEL, GASOLINA, OTROS
ARCOS Y OTROS.
PESO TOTAL 56,871.76
B) POR VOLUMEN
EN AGREGADOS Y MADERA
DESCRIPC. UNIDAD AFECTO IGV VOL. UNIT. VOL. TOTALARENA GRUESA m3 8.55 1.00 8.55
PIEDRA CHANCADA DE 3/4" m3 10.95 1.00 10.95
VOLUMEN TOTAL 19.50
CAPACIDAD DEL CAMION (M3)
NUMERO DE VIAJES
REDONDEO 20.00
2- FLETE TERRESTRE
UNIDAD QUE DA COMPROBANTE
CAPACIDAD DEL CAMION ( M3 ) 15.00
COSTO POR VIAJE ( S/. ) 350.00
CAPACIDAD DEL CAMION (KG) 10,000.00
FLETE POR KG 0.04
AFECTO IGV SIN IGV
FLETE POR PESO 2,200.00
FLETE POR VOLUMEN -
COSTO TOTAL FLETE TERR. 2,200.00 -
RESUMEN FLETE TOTAL
AFECTO IGV SIN IGV
FLETE TERRESTRE 2,200.00 -
FLETE FLUVIAL -
FLETE EN ACEMILA -
FLETES TOTALES S/. 2,200.00 -
FLETE POR PESO = Peso
Total * Flete / peso
FLETE POR VOLUMEN = #
de viajes * costo/viaje
CALCULO DEL FLETE
PROYECTO : "INSTALACION DE UN ESTADIO DEPORTIVO EN EL CENTRO POBLADO DE ACOPALCA, DISTRITO DE HUANCAYO, PROVINCIA DE
HUANCAYO - JUNIN"
COMPONENTE N03 : MALLA OLIMPICA
NOTA:
PARA EL CALCULO DEL FLETE,
NO SE CONSIDERA EL
TRASPORTE DE LOS
AGREGADOS, PUESTO QUE
TODOS LOS INCLUIDOS EN EL
CUADRO DE LA IZQUIERDA
PRESENTAN PRECIOS CON EL
MATERIAL PUESTO EN OBRA.
UNIDAD DE TRANSPORTE