© SBM Offshore 2013. All rights reserved. www.sbmoffshore.com
Floating Production Storage and Offloading Technical Challenges – October 21
Kurtz Marketing & Management
2
Presentation by Kurtz Marketing & Management*
on behalf of SBM Offshore
*) KMM is a Dutch-based business development company active in bridging
global high-tech industries and in bringing oil and gas expertise to the
emerging Israeli natural gas industry.
www.kurtzmarketing.com
Agenda
3
FPSO • Market
• Drivers for FPSO
• FPSO Overview
• Mooring Solutions
• History
• Local Content
Future • Technical Challenges
• Key Trends
• Local Content
• Conclusion
• 256 floating production units in service • 157 FPSO’s (61%)
• 77 floating production units are on order • 44 FPSO’s (57%)
FPSO Market Presence
35 12
4
24
38 21
14
Source IMA Report March 2013 4
FPSO Market Outlook
Field developments requiring FPSOs over the next 3 years
More than 50 FPSO projects currently expected to be awarded
Source: SBM Offshore - August 2013
Lease
Sale
Lease or Sale
IR - 07/08/2013
5 1
2
Asia
3
0
1
Other
4
0
3
North America
8
4
5
Africa
14
2
2
South America
• Why use an FPSO? • Remote locations
• Storage
• Payload
• Schedule
• Real estate
• Easy to install
• Relocation
• Hurricane/cyclone environments
• Lease and operate option
• FPSOs were first deployed as an economical solution for
marginal fields.
• FPSOs became an essential component in developing
remote offshore fields as Early Production Systems (EPS)
• Increasing production capacity, turret/swivel technology
and riser advances have allowed their utilization as full
field production facilities
Drivers for FPSO
6
FPSO Overview
Fabrication Vessel Conversion
Vessel Types Aframax, Suezmax, VLCC
Length 250-330m
Beam 35-60m
DWT 80,000 to 320,000
Oil
Production
40,000 to 150,000bopd
Water
Production
20,000 to 180,000
Gas
Production
20-600 mil ft3/day
0.5-17 mil m3/day
Storage 500,000 to +2mil Barrels
Persons on
Board (POB)
50-150
Service Life 10-30 years
7
Spread Moored
8
Turret Moored
9
Shell Spain
Castellon Field, Offshore Spain
1976 – 1986
Tanker Size 60,000 DWT
Storage Cap. 420,000 bbls
Water Depth 100m
Production Rate 20,000 bbls/day
Riser Single 4” ID
Mooring System Single
Anchor Leg System (SALS)
Offloading Side by Side
Contract Turnkey
Supply of Mooring System SBM
FPSO Castellon
10
BHP Petroleum
Jabiru Field, Timor Sea
Offshore Australia
1986 - 2010
Tanker Size 160,000 DWT
Storage Cap. 845,000 bbls
Water Depth 125m
Production Rate 27,000 bbls/day
Riser/Mooring Ext. Disconnectable Turret.
Offloading Tandem
Contract SBM
System Turnkey Supply of Disconnectable
Riser Mooring System
FPSO Jabiru Venture
11
Shell Expro
Teal & Guillemot Fields
Offshore UK
1996 - present
Tanker Size 129,500 DWT
Storage Cap. 850,000 bbls
Water Depth 100m
Production Rate 60,500 bbls/day
Riser 12 Flexibles
Mooring System Internal Turret
Offloading Tandem
Contract SBM Turnkey Supply,
tanker, topsides,
mooring & installation
(first such contract by
operator)
FPSO Anasuria
12
Petrobras
Ishabella Field, Offshore Brazil
2014
Tanker Size 265,000 DWT
Storage Cap. 1,600,000 bbls
Water Depth 2140m
Production Rate 150,000 bbls/day
Riser 55
Offloading Tandem
Mooring System Internal Turret
Contract SBM Turnkey Supply,
re-refurbishment,
lease, operate
FPSO Ilhabela
13
Multiple Conversion
FPSO VI
Nigeria, 1986-1998
Espadarte FPSO
Brazil, 2000-2011
Anchieta FPSO
Brazil, 2012-2030
14
Technology Challenges
FPSO Complexity (Generation 3) Advanced Mooring Technology
Process Intensification
IR - 07/08/2013
FLNG Turret
15
Ultra Deepwater
Beyond 3000m
Deep Reservoirs
Extreme HP/HT
Surface Processing
Seabed Processing
Analogue Oilfield
Digital Oilfield
LNG Plants Onshore
Floating LNG
+ underlying trends for increased safety & environmental performance, and reduced life cycle costs
Risers, logistics, met-ocean data, frontier areas
Drilling costs, completions, trees, risers , sour fluids
Compressors, power supply, reliability, cost
Recovery, performance, manning levels
Cost, schedule, permits, local content, jobs
From To Factors
Key Technology Trends
Local Content: Competitive Advantage
17 IR - 07/08/2013
Brazil:
In-country presence since 1968
First FPSO in 1997
Brasa yard key asset for SBM
Stake in biggest floating crane in
Latin America
Over 2,700 employees
August 2013 17 IR – 09/09/2013
Local Content: Competitive Advantage
18 IR - 07/08/2013
Angola:
In-country presence since 1968
First FPSO in 1999
Paenal yard key asset for SBM:
biggest crane in West Africa
Over 1,400 employees
August 2013 18 IR – 09/09/2013
• FPSO’s have proven safe and
reliable operation experience since
1976
• They make up +60% of the worlds
total offshore production units
• FPSO’s are development solution of
choice for ultra-deepwater (>1500m)
• Their size and complexity have
increased
• They provide a robust solution for the
Levant basin: • Ultra-deepwater
• Complete gas processing offshore
• Condensate storage
• Schedule
• 30 year life