Upload
mitchell-brown
View
223
Download
0
Embed Size (px)
Citation preview
DDForward Muon
Installation and Commissioning
Dmitri DenisovFermilab
Director’s review 7/12/1999
PlanForward muon detectorsMini-drift tubes installationForward trigger detectors installationMuon shieldingCommissioning of forward muon detectors
DD Forward Muon Detector Upgrade
Forwardtrigger: scintcounters
Shielding
Forward tracker: mini-drift tubes
Completely new forward muon system for Run II
DD1 < || < 2A,B,C-layers
Forward Muon System
5,000 scintillation counters 50,000 mini-drift tube channels Each plane consists of 8 octants Total detectors weight is ~100ton with
coordinate accuracy of 1mm/10m
DD Mini-drift Tubes
Here will be individual mini-drift tube picture
DD Pixel Picture
Here will be individual pixel picture
DDForward Muon Trigger
System Assembly Status
All parts for all 48 octants are at Fermilab: counters, mounting brackets, etc.
43 out of 48 octant frames are made
Calibration system production is keeping pace with octants assembly
30 out of 48 octants assembled and tested and ready for installation:
all tubes, fibers, cables are tested calibration with r/a source and
LED calibration system is performed and documented
On schedule
DD Octant assembly
High quality picture of assembled octant will be here
DDForward Muon
Tracking Assembly Status
All 2300 mini-drift tubes for A layer are tested at Fermilab, all 2100 C layer tubes are at Fermilab, tests are under way
Production of B layer tubes continues at JINR: 50% completed
Assembly of A layer octants
Critical items for installation keep A layer octants assembly and
testing on schedule finish B/C layers drawings and procure
all materials
Tests of assembled octant in Lab F
DD Installation of Mini-drift Tubes
Octants are mounted individually on 3 supports, which are attached to magnet (A and B layers) or C layer trusses
Required accuracy of installation is 10mm, required accuracy of octant survey is 0.5mm
After octants are installed survey connection to gas system connection to slow control system connection to front-end electronics connection to high voltage system
Current status: design of octants mounts is finished, production started
DD MDT Mounts
Slide of C layer MDT mounts on C trusses
DDScintillation Trigger
Counters
Installation Each plane of counters consists
of 8 octants Octants are bolted together to
form planes (A and B layers) or “half” planes for C layer
Planes are installed on supports mounted on magnet (A and B layers) or C layer trusses (C layer)
Required installation accuracy is 10mm, required survey accuracy is 2mm
After installation survey connections to high voltage system connections to front-end
electronics
DD Pixels Installation
Drawing of pixels A layer plane installed will be here
DD Shielding and C Layer Trusses
While C layer trusses exist from Run I considerable modifications are required to support 100 ton shield
The shield 20” iron, 6” polyethylene, 2”
lead
Operating the shield Data-Taking Position Transport Position
Design is finished, production of parts is underway with assembly to follow
DD Data Taking Position
DD Transport Position
DD Shielding
C truss reinforcement going on at MAB C North truss pieces delivered
to Lab G for preass’y & survey C South truss ass’y underway
Stacking Lead + Poly into boxes at DAB
Poly & Boxes in High-bay.
EF Plug core
DD Time Schedule for Installation
Resource loaded schedule for forward muon detectors installation is developed
Assembly of C layer trusses and forward shielding starts in November 1999 and ends in February of year 2000
Installation of forward tracking detectors starts in April and ends in August 2000
Installation of forward trigger detectors starts in May and ends in September 2000
DD Installation Schedule
Here will be forward muon part of Bill’s schedule
DD Technician Manpower
“All” - refers to effort assigned to all tasks in the schedule
“Install.” - refers to effort assigned to a subset of installation tasks
Muon Fwd Tech EffortFNAL
0
5
10
15
20
25
Jan-
99
Mar
-99
May
-99
Jul-9
9
Sep
-99
Nov
-99
Jan-
00
Mar
-00
May
-00
Jul-0
0
Sep
-00
Nov
-00
Jan-
01
FT
Es
All
Install.
Actual
Plus Reqs
DD Commissioning of Mini-drift Tubes
Commissioning of each mini-drift tubes octant includes the following major tasks gas leaks test and operation of
gas flow monitors high voltage system check and
dark current measurement commissioning of front-end
electronics muon detection efficiency
measurement using cosmic rays Most of the tasks are similar to
tests of mini-drift tubes octants in Lab F
Commissioning will be done by joint efforts of physicists from JINR (6), Fermilab(1), NIU(1), PNPI(1), UW(1) and other D0 Collaboration groups
DD Cosmic Ray Tests at Lab F
Here will be event display picture of cosmic muon in Lab F per Mont’s request
DDCommissioning of Forward Trigger
Detectors Commissioning of each scintillation
counters octant will include test of high voltage system
operation light leak test response of counters to r/a source operation of calibration system commissioning of front-end
electronics determination of high voltage for
each group of counters and settings for electronics thresholds
Most of the tasks are similar to tests performed in Lab F during tests of assembled octants
The commissioning will be done by joint efforts of physicists from IHEP (5), NeU(1), Fermilab (1), NIU(1) and other D0 Collaboration groups
DDResults of Scintillation
Counters Commissioning in Lab F
Distribution of 96 counters response to r/a source
Stability of PMT gain over 6 months period for single octant
RMS is about 10%
Gain stability over 6 month is 3%
DD Manpower for Commissioning
Total number of detectors to be commissioned 50,000 channels of mini-drift
tubes and front-end electronics 5,000 scintillation counters and
same number of TDC/ADC electronics channels
The time for commissioning is short and determined by detector roll-in schedule
8-9 physicists will be required to perform each of the above tasks with help from electronics engineers and technicians
Most of these physicists are visitors from IHEP and JINR
DD Summary
We have good understanding of all installation aspects, but detailed engineering drawings and safety reviews have to be done: 1 additional engineer for ~ half a year
At some point techs participating in detector assembly come free, but to keep installation running in parallel with detectors production we need ~4 additional techs
Commissioning heavily relies on visitors from IHEP, JINR and PNPI, their presence and support
DD Mini-drift Tubes
Eight 1*1cm2 cross section cells mounted in a single gas volume
Tubes length is from 1m to 6m
Fast gas mixture of CF4(90%)+CH4(10%) provides maximum drift time of 60ns
Coordinate accuracy is ~0.5mm
High detection efficiency Tubes are produced at JINR
(Dubna) and delivered to Fermilab where they are assembled into octants
DDTrigger
Scintillation Counters
Bicron 404A scintillator with Kumarin WLS bars along two edges
1” diameter fast PMT with resistive base
About 45 different sizes from 15cm up to 1.2m
Minimum number of photoelectrons is 60 for largest counter
Time resolution is 1ns Counters are produced at
IHEP (Protvino) and delivered to Fermilab for assembly into octants
DD MDT Mounts
Here will be slide of MDT A layer installation scheme
DD Data Taking Position
DD Transport Position
DD Open Position
DD Open Position
DD Assembly Plan
Shielding boxes ass’y Assemble & install North + South
EF plugs Assemble/Test North/South C
bottom truss and shield Assemble/Test North/South C top
truss Installation of North+South C
truss components Installation of mini-drift tubes and
scintillation counters Assembly trusses and shield on
the sidewalk Move trusses into collision hall
DD Test Results of Mini-drift Tubes in Lab F
Summary of test results of 2300 mini-drift tubes in Lab F Total measured 2302 (100%) Rejected during tests 64
(2.8%)
Out of 64 rejected tubes the statistics is the following Gas leaks 47 (73%) Broken damping resistors 9
(14%) Wire tension 7 (11%) High dark current 1 (2%)
We expect low detector failure rate during commissioning