Upload
dinu69in
View
125
Download
6
Embed Size (px)
Citation preview
Directions For Numbers 1- 35 : Read each of the following multiple-choice items and thepossible answers carefully. Mark the letter of the correct answer on your answer sheet or asinstructed by your teacher. Remember: Make no marks on this test.
Figure D204.02
1Which of the definitions below defines unexcavated as shown in Figure D204.02?
A Area of compacted earth fill
B Concrete floor that is suspended 6” above the grade
C Location where the earth is not to be dug out
D Location where the ground level that is lower than the surrounding areas
2 In Figure D204.02, what letter represents the “Double Joists”?
A A
B B
C C
D D
Architecture 2 - Foundation PlansPage 1 of 7
Go on to next page
3 In Figure D204.02, what letter represents the “Pier”?
A A
B B
C C
D D
Figure D204.01
4 In Figure D204.01, what number represents the “Girder”?
A 5
B 6
C 7
D 8
5 In Figure D204.01, item 4 is a:
A Column.
B Pier.
C Pilaster.
D Sill.
Architecture 2 - Foundation PlansPage 2 of 7
Go on to next page
6In Figure D204.01, what is item 1?
A Footing
B Foundation
C Pier
D Pilaster
Figure D204.03
Architecture 2 - Foundation PlansPage 3 of 7
Go on to next page
7 At number 10 in Figure D204.03, there are a series of 6’-8” measurements. What do those dimensions locate?
A Piers
B Double Joists
C Girders
D Pilasters
8 What does the foundation illustrated by Figure D204.03 best describe?
A Crawl Space
B Basement
C Rock
D Wood
9 In Figure D204.03, what is specified in the symbol identified by item 8?
A Double joist size, spacing and direction
B Built-up girder size and spacing
C Spacing and direction
D Subfloor sheeting direction and spacing
10 In Figure D204.03, item 4 is a/an:
A Access Door.
B Drain Tile.
C Casement Window.
D Vent.
11 In Figure D204.03, item 5 is a/an:
A Access Door.
B Lavatory.
C Vent.
D Window.
12 In Figure D204.03, item 7 is a:
A Drain tile.
B Pier.
C Pilaster.
D Footing.
13In Figure D204.03, what is item 1?
A Pier
B Double Joist
C Girder
D Pilaster
14What determines the connection between floor joists and the foundation plan?
A Floor joists are vertical members shown in the foundation plan
B Floor joist direction is shown on the foundation plan
C Floor joists are typically made of concrete
D Floor joists are the lowest member of the foundation system
15Which of the definitions below defines “Drain tile”?
A Black plastic with holes on half of its circumference
B Red clay put together with short spaces between the sections
C Black cast iron put together with bells
D White PVC with no holes or spaces
Architecture 2 - Foundation PlansPage 4 of 7
Go on to next page
16Which of the definitions below defines piers?
A Horizontal members used to support the ends of floor joists
B Horizontal members used to support walls
C Vertical members used to support floor systems
D Vertical members used to support roof structures
17Of what does a “Slab foundation” system consist?
A Monolithic concrete floor and footing
B Concrete floor suspended above a closely spaced system of piers
C Pressure treated plywood floor laid on a 4” gravel base
D Wood floor above a “crawl space”
18Which of the definitions below defines live loads?
A Fixed or moving weights that are not a part of the structure
B Framing materials both vertical and horizontal types
C Fixed weights that are part of the structure
D Weights of more than 500 lbs/sq. ft.
19 Which consists of a footing and a poured concrete wall that forms an inverted T?
A A-Foundation
B T-Foundation
C Slab Foundation
D Pilaster
20 The shape of a foundation wall makes a difference in its ability to resist:
A Lateral earth loads.
B Live loads.
C Dead loads.
D Water table.
21 What is the vertical wall that extends from the top of the footing up to the first floor level?
A Knee wall
B Foundation wall
C Partition wall
D Retaining wall
22What is the vertical masonry post used to support the floor system known as?
A Lally column
B Lintel
C Pier
D Wall stud
23What is the difference between a pier and column?
A Bearing capacity
B Soil impact
C Concrete block
D Reinforcing bars
24What does a drain tile remove?
A Waste from the sewage system
B Water that collects around the foundation wall
C Water that collects in the septic tank
D Water standing above the septic tank
Architecture 2 - Foundation PlansPage 5 of 7
Go on to next page
25What should be used to remove excess ground water from around the footing?
A Loose dirt and gravel mix under the footing
B 4” perforated drain pipe
C Non-perforated PVC pipe
D Saw dust and mulch mixture
26How would the correct note for a built-up wooden girder read?
A 3 – 2 x 10 #2 SPF Girder
B W 8 x 14 Girder
C 6 x 12 LVL Girder
D 2 x 10 @ 16” OC Girder
27What do dashed lines drawn parallel to both sides of a foundation wall most likely represent?
A Drain tile
B Footings
C Foundation vents
D Piers
28What would the BEST note for a pier or column footing?
A 2’-0” x 2’-0” x 10” CONC PIER FOOT
B 2’-0” x 2’-0” CONC PIER FOOT
C 2’-0” x 8” CONT CONC PIER FOOT
D 3000 PSI CONC FOOT
29Floor Joist length is determined by all of the following EXCEPT:
A Consideration of live and dead loads.
B Density of earth supporting foundation.
C Material strength of the floor joist.
D Size of the floor joist.
30What is the relationship between floor joists and double joists?
A Both are typically made of concrete.
B They run perpendicular to each other.
C They run parallel to each other.
D Both are vertical foundation members.
31What is the actual size of a 8” x 8” x 16” concrete masonry block?
A 8” x 8” x 16”
B 7-1/2” x 7-1/2” x 15-1/2”
C 7-5/8” x 7-5/8” x 15-5/8”
D 7-3/4” x 7-3/4” x 15-3/4
32 What is the actual thickness of 8” concrete block?
A 8”
B 7-1/4”
C 7-5/8”
D 8-3/8”
33Slab Foundation Systems:
A Must have the monolithic footing.
B Must have separately footing.
C Require labor intensive construction.
D Have pressure treated studs.
34Which is an example of Dead Loads?
A Snow
B People and pets
C Roof shingles
D Furniture
Architecture 2 - Foundation PlansPage 6 of 7
Go on to next page
35How deep should a footing be placed?
A Elevation
B Fill line
C Below frost line
D Grade
Architecture 2 - Foundation PlansPage 7 of 7
Stop here