FREIGHT OPERATIONS Implementation of Operation Chetak Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

Embed Size (px)

Citation preview

Page 1: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed
Page 2: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

FREIGHT OPERATIONSFREIGHT OPERATIONS

• Implementation of Operation Chetak Running time of trains was calculated on absolute basis

i.e. running was calculated at the speed of 75 Kmph and 60 Kmph (for Sumo rake). Analysis of detention is done against these timings. This has led to improvement in running of trains. Diesel loco utilization improved by 0.47% and electric loco utilization improved by 2.96%.

• Extended Crew runs Emphasis was put on extended crew runs so as to cut

down detention at major terminals like Varanasi, Roza, Ambala and Ludhiana. Average 800 crack trains were run per month during 2009-2010as against 598 cracks per month in the last year. The extended crew runs have led to reduction in running timing of power house rakes being received at MGS, 38-40 hrs. which used to be 60 hrs.

Page 3: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

• Breaking the mould :- Divisions are being encouraged to provide out of box solution to

problems. Shortage of diesel locos led to running of long haul jumbo empties

over Moradabad division. Now 22 loaded BCN wagons are being run in Haridwar –

Rishikesh / Harawala section with single WDG-3 loco as against 14 which were run earlier and full empty rake of jumbo is run with a single power on this section

Multi has been replaced by single WDG4 on PTK-JAT section. Running of Down trains through to PBH and UP trains on FD loop To overcome shortage of jumbos N.R. used premium BCN rakes

for internal loading and were able to achieve 4 loadings during their premium validity . This helped to maximize loading despite the shortage.

Delhi division streamlined movement between GZB-SBB by making it direction wise reducing the running time to 20-30 min from 1-1:30 hrs. LKO division is also attempting similar exercise.

Formulated guidelines regarding sidings of PCOs Standardizing statistical formats for divisions.

Page 4: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

• Enabling through IT :- New Operating website URL

http://10.2.2.19/dept/operating/index.htm Enables Operating Officers have topic wise availability of

circulars : Rate Freight Circulars, Freight Marketing Circulars, Traffic Transportation Circulars and many other useful links.

Archival formats of Central Control to be generated from FOIS and record keeping to be made digital, reducing requirement of storage space and manpower.

• Concept Plan:- Divisions have been asked to make long time plan for

enhancement of freight terminal capacity and line capacity. LKO ,MB divisions have been reviewed.

Page 5: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

REVENUE EARNING LOADING (In Million Tonnes)

SN SN COMMODITY COMMODITY

TARGET TARGET APR TO MARAPR TO MAR

ACTUAL ACTUAL APR TO MARAPR TO MAR %age %age

Variation Variation over last over last

year year

%age %age Variation Variation

over over Target Target 2009-102009-10 2008-092008-09 2009-102009-10

1 FOODGRAIN 14.50 14.97 18.62 24.38 28.412 FERTILIZER 6.60 6.36 6.75 6.13 2.273 POL 5.75 5.73 6.35 10.82 10.436 CEMENT 3.02 2.74 2.49 -9.12 -17.554 IRON & STEEL 0.13 0.03 0.02 -33.33 -84.625 CONTAINER 5.72 6.13 6.64 8.32 16.087 OTHERS 5.48 4.15 4.39 5.78 -19.898 TOTAL 41.20 40.11 45.26 12.84 9.85

Northern Railway has achieved everbest loading during 2009-2010

Page 6: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

OPERATING PERFORMANCE

S.N. ITEMS APR - MAR APR - MAR

% age variation 2008-2009 2009-2010

1 THROUGH PUT (Wagons per day) 12400 13487 8.77

2 TOTAL RECEIPTS (Wagons per day) 6200 6746 8.81

3 TOTAL DESPATCHES (Wagons per day) 6200 6741 8.73

4LOADED RECEIPTS (Wagons per day)

4970 5709 14.87

5 WAGON TURN ROUND (Days) 1.35 1.34 -0.74

6REVENUE LOADING EARNING (Crores Rs.)

3568.08 4296.85 20.42

7 REVENUE LOADING (Million tonnes) 40.11 45.26 12.84

8DIESEL LOCO UTILISATION (Kms/loco/day)

531.5 534 0.47

9ELECTRIC LOCO UTILISATION (Kms/loco/day)

489.5 504 2.96

10CRACK TRAINS RUN (per month)

598 800 33.78

Page 7: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

Status of FOIS projects on Northern Railway

Note :- For TMS Phase-II of Phase –II , 139 New locations have been sanctioned

DIVINRMS TMS (PHASE - I) TMS (PHASE - II)

Sanctioned Commissioned Sanctioned CommissionedSanctioned

Ph I of TMS PhIICommissionedPh I of TMS PhII

DLI 8 7 13 12 7 3

MB 2 2 6 6 4 2

UMB 6 6 20 20 4 3

LKO 3 3 7 7 4 1

FZR 5 5 16 16 4 4

TOTAL 24 23 62 61 23 13

Page 8: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

Status of FOIS projects on Northern Railway

DIVINICMS CMS COA

Sanctioned Commissioned Sanctioned Commissioned Sanctioned Commissioned

DLI 6(12) 6(10) 13 13 6 6

MB 5(10) 5(10) 7 7 5 5

UMB 6(12) 6(12) 5 5 4 4

LKO 3(7) 3(7) 8 8 6 6

FZR 6(10) 6(10) 7 7 4 4

NDBH 1(14) 1(14) 0 0 0 0

TOTAL 27(69) 27(67) 40 40 25 25

Page 9: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed
Page 10: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

Achievements and Innovations

• Total number of amendment slips issued as under:- * G&SR Book - 17 * Operating Manual - 01 * Block Working Manual - 03 * Accident Manual - 03 * Master Amendment Slip for LC gate working - 01

• Operating Safety Seminars & Meetings organized at HQs level – 02

Page 11: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

ZRTI/ Chandausi

Achievements:-

• Committee of 3 SAG officers (COM/G,CEGE & CE/P&D) visited ZRTI/CH for improvement/ upgradation of the training facilities at ZRTI/CH. • The problem of messing charges to be realized from trainees has been resolved.

• Training courses on Disaster Management for Supervisors has been introduced.

• Training Modules of Induction Course for multi skilled group ‘D’ staff approved and implemented.

• The Training Modules of Induction Course for multi skilled group ‘C’ Category, “Station Assistant” has also been approved and implemented.

• UTS Training to all ASM/SM Initial, Promotional & Refresher classes has been introduced.

Page 12: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

Innovations:-

• Long awaited reprint of G&SR book of N.Rly with latest Correction Slip no.147 dt.05.04.10 has been approved for printing and will be supplied to all Divisions by April.

• New revised Operational forms for train operations has been approved and supplied to the divisions for smooth operations.

• Data Base of SWRs with Station diagrams and Traffic LC gates on proper prescribed proforma with details of Civil & Police authorities, Fire Brigades, Hospitals and NGO etc of all the stations of N.Rly being prepared.

• Establishing a Work Station for training of Optg staff of NR on IT matters to assist in IT projects (under process)

Page 13: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed
Page 14: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

Functions of Operating Planning Cell in Head Quarter.

•To co-ordinate with divisions ,examining, and finalizing of works pertaining to Plan Head-11(New lines ,gauge conversion), 15 (Doubling) and 16 (Traffic facility).•Monitoring of the progress of on going works under plan head- New line, Gage conversion, Doubling, Traffic facility etc.•To co-ordinate with Non interlocking works.•To examining ESP’s keeping in view the operating facilities. •To prepare preliminary Works Programme of Vol-II complete in all respect and sending it to Railway Board.•To examine plans of level crossing gates.•Examining and processing of Private Siding Proposals.

Page 15: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

Improvements- Planning cell• Development of works Programme Data Base.• Development of Data Base of Private Siding

proposals.• Short CSL running line identified over Northern

Railway network- 1 station completed and works at 51 stations are under progress.

• JPO for finalizing check list for processing Engine Scale Plan.

• Policy for provision of R&D lines at Private Container Sidings issued.

• PI/RRR commissioned at 37 stations yards during 2009-10.

Page 16: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

Performance of Planning Cell• 60 number of works were sanctioned in vol V (2009-10) within

GM Power.• A total No. of 33 works were proposed to Rly Board out of which

11 nos of works have been sanctioned by Railway Board in Vol II (2010-11).

• Works under progress:-1. New Lines Works: 122. Doubling works: 153. Traffic Facility works: 494. Law Book: 195. Volume V works: 64

• No. of ESP’s finalized other than level crossing gates - 63• 3 works under Plan head 15 & 25 works under Plan head 16 were

completed during 2009-10

Page 17: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

Streamlining of Procedures for Streamlining of Procedures for Private Siding proposalsPrivate Siding proposals

• A separate cell headed by Sr.Scale Officer setup to process Private Siding proposals

• Clearly delineated procedure for processing of proposals– Ensures availability of appropriate operational

facilities and accurate traffic projections.– Ensure all charges payable to Railways are

submitted.– Ensures timely execution of work and

commissioning

Page 18: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed
Page 19: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

SPECIAL TRAINS RUN2009-2010

SPECIAL TYPE APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR

SUMMER SPECIAL 818 1089 1081 42 0 0 0 0 0 0 0 0

PARA-MILITARY SPECIAL

3 56 2 0 18 7 3 5 0 0 0 4

DURGA PUJA SPECIAL

0 0 0 0 0 508 0 0 0 0 0 0

MELA SPECIAL 0 0 16 0 0 0 0 0 0 72 66 85

DIWALI/WINTER SPECIAL

0 0 0 0 0 0 1338 569 552 439 0 0

UNION SPECIAL 0 0 0 0 0 0 0 0 0 0 0 0

YATRA SPECIAL 6 5 5 2 12 5 11 11 10 14 11 11

EXTRA SPECIAL 1 48 10 511 347 24 0 6 9 5 360 468

TOTAL 853 1198 1114 555 377 544 1352 591 571 530 437 568

Page 20: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

TRAINS INTRODUCED/EXTENDED/ FREQUENCY INCREASED DURING 2009-10

  IntroductionTotal

ExtensionTotal

Increase in Frequency

Total

  NR FR NR FR NR FR

Duronto 4 7 11     0     0

Yuva 0 2 2     0     0

Mail/Exp. 4 12 16 2 3 5 4 3 7

Passenger 0 0 0 1   1     0

EMU 4 0 4 1   1     0

Total 12 21 33 3 3 6 4 3 7

Page 21: FREIGHT OPERATIONS Implementation of Operation Chetak  Running time of trains was calculated on absolute basis i.e. running was calculated at the speed

Months Punctuality %Apr-09 77.30%May-09 79.00%Jun-09 82.80%Jul-09 83.50%

Aug-09 84.60%Sep-09 75.00%Oct-09 66.90%Nov-09 66.60%Dec-09 67.80%Jan-10 40.00%Feb-10 59.00%Mar-10 66.70%

Cummulative 70.80%

Punctuality %age of Mail/Express TrainsPunctuality %age of Mail/Express Trains

Note : The COA system became operational in October’09, Thus heralding real-time feeding of time and 1 minute Punctuality