View
221
Download
5
Tags:
Embed Size (px)
Citation preview
Fresh Bread and Roll Scaling RoomMSD II Final PresentationErik Webster, Cecilia Enestrom, Kate Gleason, Grant Garbach, Andrew TsaiMay 15th, 2009
Agenda Project Deliverables from Week 3
Review of deliverables completed during MSD I Layout
Options Final Design Implementation Status
Replenishment Process Design Process Implementation Status
Air Quality Improvement Equipment Options Final Design
Project Deliverables from Week 3 AutoCAD drawings for the layout of the scaling area Analysis of equipment needs for sifting and screening
dry ingredients Analysis of the current process ergonomics and
necessary improvements Standardized work practices that will reduce the
process steps, time, cost, and/or labor requirements Application of lean principles to reduce process waste Detailed implementation plans that will allow for the
realization of these improvements
Project Deliverables from Week 3 AutoCAD drawings for the layout of the scaling area Analysis of equipment needs for sifting and screening
dry ingredients Analysis of the current process ergonomics and
necessary improvements Standardized work practices that will reduce the
process steps, time, cost, and/or labor requirements Application of lean principles to reduce process waste Detailed implementation plans that will allow for the
realization of these improvements
Sifting & Screening Equipment Update
SWECO Separators family of machine sizes
Machine Diameter (inches)
Spout diameter (inches)
Square feet of screen surface area*
Motion Generator Horse Power
Maximum Discharge Spout Capacity** in Cubic Feet per Minute (CFM)
Theoretical spout discharge capacity for a free flowing material weighing 45 lbs per cu ft in lbs/min(ppm)
Actual discharge capacity for stone ground wheat based on the 2-6-09 tested rate of 13.5 lbs per minute through 4 mesh (4.75 mm opening)
18 3 1 0.25 13.5 ppm( =0.3 cfm )
24 2 0.33 30 6 4 0.5 2.1 cfm 95 ppm 54 ppm ( =1.2
cfm) 40 8 6 0.5 2.9 cfm 131 ppm 81 ppm ( =1.8
cfm) 48 8 10 2.5 3.2 cfm 144 ppm 135 ppm (= 3
cfm) 60 15 2.5 72 23 5
Sifting & Screening Equipment Update Determined products that could be sifted
Only dry products Either Mesh 4/Mesh 10 or cannot be sifted
40% actual difference in throughput 40” vs 48” Save footprint size Limits target growth 40” cannot handle 2 of largest size bags
Allergen Issue Determined by Wegmans quality to not be an issue
Recommended washing of the equipment at regular intervals
Ergonomics Review
Recommendations were made to: Eliminate lifting scaling bins onto the
third shelf of rolling carts. Avoid scaling workers lifting bags from
the second rack shelf.
Project Deliverables from Week 3 AutoCAD drawings for the layout of the scaling area Analysis of equipment needs for sifting and screening
dry ingredients Analysis of the current process ergonomics and
necessary improvements Standardized work practices that will reduce the
process steps, time, cost, and/or labor requirements Application of lean principles to reduce process waste Detailed implementation plans that will allow for the
realization of these improvements
New Layout Option 1
Advantages Enough space
for bin area Closer to
staging area Disadvantages
Lose 30 pallet locations
Possible issues with congestion with fork lift
More motion for workers staging bags on carts
New Layout Option 2
Advantages Only lose 12 pallet
locations Possibility of using
floor level of rack locations 9-14
Minimal congestion from fork lift
Less motion for workers staging bags on carts
Disadvantages Less space for bin
area
New Layout Status Progress
Recommendation of what short term storage area was given Bin area location Ingredient pallet locations
Bin area was moved into short term storage area
Continued Work Storage locations are still being finalized
by Wegmans workers
Project Deliverables from Week 3 AutoCAD drawings for the layout of the scaling area Analysis of equipment needs for sifting and screening
dry ingredients Analysis of the current process ergonomics and
necessary improvements Standardized work practices that will reduce the
process steps, time, cost, and/or labor requirements Application of lean principles to reduce process waste Detailed implementation plans that will allow for the
realization of these improvements
Project Deliverables from Week 3 AutoCAD drawings for the layout of the scaling area Analysis of equipment needs for sifting and screening
dry ingredients Analysis of the current process ergonomics and
necessary improvements Standardized work practices that will reduce the
process steps, time, cost, and/or labor requirements Application of lean principles to reduce process waste Detailed implementation plans that will allow for the
realization of these improvements
Replenishment System Necessary to ensure replenishment is finished
prior to the arrival of daily batch cards so scaling is not postponed Should be a highly visual, easy to use system
Kanban system Cards and post
Replenishment System Design How will the fork truck be able to replenish the
short term storage before 2pm every day?
Replenishment System Design How will the fork truck be able to replenish the
short term storage before 2pm every day? Need to know average daily consumption of each
ingredient in order for the fork truck driver to know which ingredient needs to be replenished each day.
Replenishment System Design How will the fork truck be able to replenish the
short term storage before 2pm every day? Need to know average daily consumption of each
ingredient in order for the fork truck driver to know which ingredient needs to be replenished each day.
How will we determine the average daily consumption levels?
Replenishment System Design How will the fork truck be able to replenish the
short term storage before 2pm every day? Need to know average daily consumption of each
ingredient in order for the fork truck driver to know which ingredient needs to be replenished each day.
How will we determine the average daily consumption levels? Tabletop simulation 22 days of data
Replenishment System Design How will it be communicated to the fork
truck driver which ingredients to replenish each day?
Replenishment System Design How will it be communicated to the fork
truck driver which ingredients to replenish each day? Kanban cards
Replenishment System Design How will it be communicated to the fork
truck driver which ingredients to replenish each day? Kanban cards
Who will be responsible for collecting kanban cards each day?
Replenishment System Design How will it be communicated to the fork
truck driver which ingredients to replenish each day? Kanban cards
Who will be responsible for collecting kanban cards each day? Scaling workers via Kanban post
Location of kanban post
Replenishment System Design How will the scaling workers determine if
the ingredient has hit its kanban level? Ingredient signs will display their kanban level
Replenishment System Design How will the scaling workers determine if
the ingredient has hit its kanban level? Ingredient signs will display their kanban level
Simple for low quantity kanban levels, but how do scaling workers quickly count replenish levels of >10?
Replenishment System Design How will the scaling workers determine if
the ingredient has hit its kanban level? Ingredient signs will display their kanban level
Simple for low quantity kanban levels, but how do scaling workers quickly count replenish levels of >10? Kanban line
Replenishment System Status Progress
Ingredient signs were made with kanban levels Kanban cards have been made
Continued Work Because storage locations are still being finalized,
Kanban cards must also be finalized Kanban lines must be placed on appropriate racks Floor tape needs to be laid around scaling area
Need kanban post Staff training will be done this Wednesday
Project Deliverables from Week 3 AutoCAD drawings for the layout of the scaling area Analysis of equipment needs for sifting and screening
dry ingredients Analysis of the current process ergonomics and
necessary improvements Standardized work practices that will reduce the
process steps, time, cost, and/or labor requirements Application of lean principles to reduce process waste Detailed implementation plans that will allow for the
realization of these improvements
Risks AssessmentRisk Probability Severity Preventative Actions
Fork truck resources are not available for implementation 1 9 Detailed cutover plan with Wegmans
Operators do not comply with storage locations 9 1Locations will be flexible to adjust to the changing
needs of the system. Operator training.
Capacity of room is not sufficient for new system with anticipated future growth
3 3Several layout alternatives will be considered and
simulation to verified capacity
Manual resources not available for implementation 1 9 Detailed cutover plan with Wegmans
Increase in ergonomic and safety risks 3 9Store ingredients to minimize dangerous lifting
using simulation tool
Fork truck work increases 3 9Simulation tool created to verify fork truck
requirements. Research alternatives to fork trucks
Staging area does not have sufficient capacity 1 1Detailed layout with input from floor supervisors
and operators
The shift time for the scaling operator does not decrease or increases 1 9Time estimated using process flow diagram and
walking distances
Leveling kanban system fails due to process variability 3 3 Simulation tool to verify kanban system validity
Fork truck drivers and operators do not comply with kanban levels for the short-term storage area
9 9Simulation tool to demonstrate validity of the
system. Operator training and involvement.
Needed supplies are not available at start of implementation 3 9 Detailed cutover plan with Wegman's
Air Handling System
Customer Needs Assessment Improve Air quality Reduce Air Particulate size Help improve area cleanliness Will not interfere with sifting process Will not violate OSHA or Wegmans guidelines
Custom Designed Air Handling System
Concepts
Mobile Straight up
Segment 1 2
Selection Criteria Weight Rating Notes Wtd Rating Notes Wtd
Size 7% 10 0.70 10 0.70
Stagnation Points 5% 5 0.25 10 0.50
Serviceability 9% 10 0.90 7 0.63
Change Filters 10% 9 0.90 7 0.70
Steel Grade 6% 10 0.60 10 0.60
Painted Surfaces 10% 10 1.00 10 1.00
Geometric Discontinuities 7% 5 0.35 10 0.70
Ability to stay Laminar 10% 6 0.60 10 1.00
Reduce Particulate size 10% 10 1.00 10 1.00
Increase time between Cleanings 20% 7 1.40 10 2.00
Mobile 5% 10 0.50 1 0.05
OSHA 85dB 7% 5 0.35 8 0.56
Washable 8% 7 0.56 7 0.56
Engineers Rating of design feasibility 10% 9 0.90 9 0.90
Safety 13% 9 1.17 9 1.17
Total Score 11.18 12.07
Rank 2 1
Continue? No Yes
1 not important
10 extremely important
Scale
Selection Matrix for COTS
IQ Air Honeywell Shick Kason
Segment 1 2 3 4
Selection Criteria Weight Rating Notes Wtd Rating Notes Wtd Rating Notes Wtd Rating Notes Wtd
Size 9% 9 0.81 9 0.81 1 0.09 9 0.81
Go/No Go* 30% 3 0.90 3 0.90 9 2.70 3 0.90
Cost 30% 9 2.70 9 2.70 1 0.30 3 0.90
Reduce Particulate size 9% 9 0.81 9 0.81 9 0.81 9 0.81
Increase time between Cleanings 9% 3 0.27 1 0.09 9 0.81 3 0.27
Meets OSHA standards 9% 3 0.27 3 0.27 9 0.81 9 0.81
Safety 9% 3 0.27 3 0.27 9 0.81 9 0.81Engineers Rating of design
feasibility 9% 3 0.27 3 0.27 9 0.81 3 0.27
Total Score 6.30 6.12 7.14 5.58
Rank 2 4 1 3
Continue? N N Y N
1 Worst *Note: Go no go criteria includes, servicability, ability to change filters, steel grade3 geometric discountinuities, ability to stay laminar, mobile and washable.9 Best
ConceptsAir Handling Equipment Selection Matrix
Scale
Recommendations
As a best practice, Wegmans should implement at least one sifting piece of equipment to reduce foreign material. Recommendation for equipment: Sweco
vibratory sifter with Mesh 4 To improve bakery air quality, improve
safety, and reduce health concerns, Wegmans should implement an air handling system equipped with dust collection Recommendation for equipment: Shick