8/10/2019 Fs Engineering Consultant Sdn
1/22
FS ENGINEERING
CONSULTANT SDN. BHD.
GEOMETRIC DESIGN PROJECT FORHIGHWAY ENGINEERING
8/10/2019 Fs Engineering Consultant Sdn
2/22
Organization Chart
Managing DirectorNurafiqah Binti Panot
Project EngineerNoraini Binti Zainudin
Senior EngineerTan Suet LeeGoh Jun Da
Site EngineerGary Julis
8/10/2019 Fs Engineering Consultant Sdn
3/22
Objective
To design a highway which capable ofaccommodating a maximum of traffic volume of
average daily traffic (ADT) of 10,175 vehicles sothat a rise in socio-economy of Samarahan canbe achieved
8/10/2019 Fs Engineering Consultant Sdn
4/22
Project Detail
Proposed road will start from point C(N5158000, E2075500) to point F (N5158500,E2078000) in the map
Rolling terrain
Design standard,R5.
Road category is highway Partial control of access
8/10/2019 Fs Engineering Consultant Sdn
5/22
Road Design
8/10/2019 Fs Engineering Consultant Sdn
6/22
Proposed Elevation
8/10/2019 Fs Engineering Consultant Sdn
7/22
5.00
10.00
15.00
20.00
25.00
30.00
35.00
0 500 1000 1500 2000 2500 3000
SoilProfile(m)
Chainage
Soil profile against Chainage
ExistingLevel
Proposedlevel
8/10/2019 Fs Engineering Consultant Sdn
8/22
Mass Haul Diagram
Total area ofembankment is128844m
Total area of excavationis 93430.3m
Total different is35413m
-40000
-30000
-20000
-10000
0
10000
20000
30000
40000
0 500 1000 1500 2000 2500
Masshaulordinate
Chainage
Mass Haul Diagram
8/10/2019 Fs Engineering Consultant Sdn
9/22
Horizontal Alignment
First curve Second curve
Minimum radius (m) 242.08
Design radius (m) 650 300Length of curve (m) 397 165
Central angle () 35 23
Stopping sight
distance, SSD (m) 211 120
8/10/2019 Fs Engineering Consultant Sdn
10/22
Superelevation
Minimum radius = 275m
Design radius = 650m
e maximum = 10%
e maximum design = 6.15% Length of tangent runout, Lt = 23.1m
Length of runoff, Lr = 71m
Length of fully superelevated = 208.8m
8/10/2019 Fs Engineering Consultant Sdn
11/22
8/10/2019 Fs Engineering Consultant Sdn
12/22
VerticalAlignment
Stopping sight distance (SSD) = 160mLength of curve for sagging = 180mLength of curve for crest = 120mSlope grade = 1.9%
14
16
18
20
700 800 900 1000 1100 1200 1300 1400
Ele
vation
Chainage
Full Vertical Alingment
Proposed elevation
Full curve
8/10/2019 Fs Engineering Consultant Sdn
13/22
8/10/2019 Fs Engineering Consultant Sdn
14/22
Flexible Pavement Structure
DesignCharacteria
Value Comment
ESALY1 ( Base year) = 2.58 million -
ESALDES 69.3 million Traffic category T5
Characteristic subgrade modulusvalue
134.65 Mpa Sub-grade categorySG3,
8/10/2019 Fs Engineering Consultant Sdn
15/22
Option 1 :
Full depth asphaltpavement withunmodified penetration
70/100.Advantages :
- Cost
- Durability- Sources available
- Maintenance
- Long life span
8/10/2019 Fs Engineering Consultant Sdn
16/22
Bridge
Location of bridge : chainage 1+850 to 1+870
Length = 20m
Beam bridge
Cost effective, easy to manufacture
Can resist bending and twisting
8/10/2019 Fs Engineering Consultant Sdn
17/22
Drainage
Types of drainage design:
1. Traversable Ditch with Concrete Lining
2. Symmetrical or V-shaped Ditch
For superelavation at the horizontal alignment, openchannel ditch is used with the frame and vane cratesinlet.
Culvert is also installed to allows water flows
underneath the road, then divert them to low-lyingarea.
8/10/2019 Fs Engineering Consultant Sdn
18/22
Traversable Ditch withConcrete Lining
Symmetrical or V-shapedDitch
8/10/2019 Fs Engineering Consultant Sdn
19/22
Drainage Maintenance
Cutlassing or cleaning off the ditch regularly to avoidthem from silting up and sending water back to the road.
Provide vegetation to reduce soil erosion at the side
slope of the V-shaped ditch.
8/10/2019 Fs Engineering Consultant Sdn
20/22
Conclusion
Route length is 2.615km with one bridge. Road standard of R5 with design speed of
85km/hour.
Design consideration is following the standard Embankment volume > Excavation volume
Therefore, volume of soil needed to fill in forproject purposed is 35413m.
Hopefully can improved the quality of road inSarawak by performing good design, betteroption for road pavement, effective bridge anddrainage system design.
8/10/2019 Fs Engineering Consultant Sdn
21/22
Q & A
8/10/2019 Fs Engineering Consultant Sdn
22/22
END