Upload
m13naserraja
View
9
Download
0
Embed Size (px)
DESCRIPTION
furjan
Citation preview
Activity ID Activity Name OriginalDuration
Start Finish
FURJAN PROJECT - DUBAIFURJAN PROJECT - DUBAI 319 15-Jul-13 29-May-14
MILESTONES / KEY DATESMILESTONES / KEY DATES 318 15-Jul-13 29-May-14
M-001 Commencement Date (Assumed) 0 15-Jul-13
M-002 Completion of Sub-Structure Works 0 24-Oct-13
M-003 Completion of Super-Structure Works 0 26-Feb-14
M-004 Completion of Finishing Works 0 29-May-14
M-005 Complete Exterior Works & Building Facade 0 29-Apr-14
M-200 Project Completion 0 29-May-14
PRELIMINARIESPRELIMINARIES 48 15-Jul-13 31-Aug-13
P-090 Obtain Building Permit 15 15-Jul-13 29-Jul-13
P-100 Mobilization of Manpower & Equipment 26 01-Aug-13 31-Aug-13
P-110 Construction of Site Offices 26 01-Aug-13 31-Aug-13
P-120 Install Site Utilities and Laydown Areas 26 01-Aug-13 31-Aug-13
CONSTRUCTIONCONSTRUCTION 296 07-Aug-13 29-May-14
TANK/PIT LEVELTANK/PIT LEVEL 79 07-Aug-13 24-Oct-13
EN-1000 Excavation Stage #1 10 07-Aug-13 18-Aug-13
EN-1010 Installation of Dewatering Tubes 10 12-Aug-13 21-Aug-13
EN-1020 Excavation Stage #2 (Pit & Footings at GF Level) 10 22-Aug-13 31-Aug-13
EN-1030 Blinding Concrete at Pit Area 4 01-Sep-13 04-Sep-13
EN-1040 Waterproofing at Tank/Pit Area 7 05-Sep-13 11-Sep-13
EN-1050 Screed at Pit Area 4 12-Sep-13 15-Sep-13
EN-1060 Rebar/Formwork at Tank/Pit Area - Raft 10 16-Sep-13 25-Sep-13
EN-1070 Concrete Raft at Tank/Pit Area 5 26-Sep-13 30-Sep-13
EN-1080 Rebar/ Formwork at Tank/Pit Area - Walls 7 01-Oct-13 07-Oct-13
EN-1090 Concrete Walls of Tank/Pit Area 10 05-Oct-13 14-Oct-13
EN-1100 Waterproofing at Tank/Pit Area 5 15-Oct-13 19-Oct-13
EN-1110 Backfill around Tank 5 20-Oct-13 24-Oct-13
GROUND FLOOR LEVEL - RAFTGROUND FLOOR LEVEL - RAFT 89 19-Aug-13 15-Nov-13
EN-1120 Solid Block work in footings 10 19-Aug-13 28-Aug-13
EN-1130 Blinding GF Raft - Part #1 5 29-Aug-13 02-Sep-13
EN-1140 Waterproofing Part #1 7 03-Sep-13 09-Sep-13
EN-1150 Screed Part #1 3 10-Sep-13 12-Sep-13
EN-1160 Rebar/ Formwork Raft Part #1 10 13-Sep-13 22-Sep-13
EN-1170 Concrete Raft Part #1 4 23-Sep-13 26-Sep-13
EN-1180 Blinding GF Raft - Part #2 5 18-Oct-13 22-Oct-13
EN-1190 Waterproofing Raft Part #2 7 23-Oct-13 29-Oct-13
EN-1200 Screed Part #2 3 30-Oct-13 01-Nov-13
EN-1210 Rebar/ Formwork Raft Part #2 10 02-Nov-13 11-Nov-13
EN-1220 Concrete Raft Part #2 4 12-Nov-13 15-Nov-13
PODIUM SLABPODIUM SLAB 73 27-Sep-13 08-Dec-13
EN-1230 Rebar/ Formwork - Walls & Columns (GF-P) 60 27-Sep-13 25-Nov-13
EN-1240 Decking of Podium Slab 60 07-Oct-13 05-Dec-13
EN-1250 Concrete of Podium Slab 7 02-Dec-13 08-Dec-13
FIRST FLOOR SLABFIRST FLOOR SLAB 26 09-Dec-13 03-Jan-14
EN-1260 Rebar/ Formwork - Walls & Columns (P-FF) 14 09-Dec-13 24-Dec-13
EN-1270 Decking of First Floor Slab 21 09-Dec-13 29-Dec-13
EN-1280 Concrete of First Floor Slab 5 30-Dec-13 03-Jan-14
TYPICAL FLOORSTYPICAL FLOORS 54 04-Jan-14 26-Feb-14
EN-1290 Construction of Floors 2-11 54 04-Jan-14 26-Feb-14
ARCHITECTURAL WORKSARCHITECTURAL WORKS 146 04-Jan-14 29-May-14
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2013 2014
29-May-14, FURJAN PROJECT - DUBAI
29-May-14, MILESTONES / KEY DATES
Commencement Date (Assumed)
Completion of Sub-Structure Works
Completion of Super-Structure Works
Completion of Finishing Works
Complete Exterior Works & Building Facade
Project Completion
31-Aug-13, PRELIMINARIES
Obtain Building Permit
Mobilization of Manpower & Equipment
Construction of Site Offices
Install Site Utilities and Laydown Areas
29-May-14, CONSTRUCTION
24-Oct-13, TANK/PIT LEVEL
Excavation Stage #1
Installation of Dewatering Tubes
Excavation Stage #2 (Pit & Footings at GF Level)
Blinding Concrete at Pit Area
Waterproofing at Tank/Pit Area
Screed at Pit Area
Rebar/Formwork at Tank/Pit Area - Raft
Concrete Raft at Tank/Pit Area
Rebar/ Formwork at Tank/Pit Area - Walls
Concrete Walls of Tank/Pit Area
Waterproofing at Tank/Pit Area
Backfill around Tank
15-Nov-13, GROUND FLOOR LEVEL - RAFT
Solid Block work in footings
Blinding GF Raft - Part #1
Waterproofing Part #1
Screed Part #1
Rebar/ Formwork Raft Part #1
Concrete Raft Part #1
Blinding GF Raft - Part #2
Waterproofing Raft Part #2
Screed Part #2
Rebar/ Formwork Raft Part #2
Concrete Raft Part #2
08-Dec-13, PODIUM SLAB
Rebar/ Formwork - Walls & Columns (GF-P)
Decking of Podium Slab
Concrete of Podium Slab
03-Jan-14, FIRST FLOOR SLAB
Rebar/ Formwork - Walls & Columns (P-FF)
Decking of First Floor Slab
Concrete of First Floor Slab
26-Feb-14, TYPICAL FLOORS
Construction of Floors 2-11
29-May-14, ARCHITECTURAL WORKS
FURJAN PROJECT - DUBAI CB-01-Overall Programme 28-Jul-13 14:05
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 1 of 2 TASK filter: All Activities
Primavera Systems, Inc.
Activity ID Activity Name OriginalDuration
Start Finish
EN-1300 Block Work of Floors GF-11 75 04-Jan-14 19-Mar-14
EN-1310 MEP Work 90 14-Jan-14 13-Apr-14
EN-1320 Plaster Work 75 20-Jan-14 04-Apr-14
EN-1330 Tiling Work 100 25-Jan-14 04-May-14
EN-1340 Internal Painting Work 115 31-Jan-14 25-May-14
EN-1350 False Ceiling Work 95 07-Feb-14 12-May-14
EN-1360 Door Work 90 25-Jan-14 24-Apr-14
EN-1370 Elevation Work/ Balcony Glass 75 14-Feb-14 29-Apr-14
EN-1380 Lifts Work (Including T&C) 90 01-Mar-14 29-May-14
TESTING & COMMISSIONING, SNAGGING & HANDOVERTESTING & COMMISSIONING, SNAGGING & HANDOVER 52 08-Apr-14 29-May-14
A1110 Testing & Commissioning 45 08-Apr-14 29-May-14
A1115 Power On 5 25-Apr-14 29-Apr-14
A1120 Snagging & De-Snagging 45 08-Apr-14 29-May-14
A1130 Handover 0 29-May-14
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2013 2014
Block Work of Floors GF-11
MEP Work
Plaster Work
Tiling Work
Internal Painting Work
False Ceiling Work
Door Work
Elevation Work/ Balcony Glass
Lifts Work (Including T&C)
29-May-14, TESTING & COMMISSIONING, SNAGGING & HANDOVER
Testing & Commissioning
Power On
Snagging & De-Snagging
Handover
FURJAN PROJECT - DUBAI CB-01-Overall Programme 28-Jul-13 14:05
Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary Page 2 of 2 TASK filter: All Activities
Primavera Systems, Inc.