Furjan Project Tentative Programme

Embed Size (px)

DESCRIPTION

furjan

Citation preview

  • Activity ID Activity Name OriginalDuration

    Start Finish

    FURJAN PROJECT - DUBAIFURJAN PROJECT - DUBAI 319 15-Jul-13 29-May-14

    MILESTONES / KEY DATESMILESTONES / KEY DATES 318 15-Jul-13 29-May-14

    M-001 Commencement Date (Assumed) 0 15-Jul-13

    M-002 Completion of Sub-Structure Works 0 24-Oct-13

    M-003 Completion of Super-Structure Works 0 26-Feb-14

    M-004 Completion of Finishing Works 0 29-May-14

    M-005 Complete Exterior Works & Building Facade 0 29-Apr-14

    M-200 Project Completion 0 29-May-14

    PRELIMINARIESPRELIMINARIES 48 15-Jul-13 31-Aug-13

    P-090 Obtain Building Permit 15 15-Jul-13 29-Jul-13

    P-100 Mobilization of Manpower & Equipment 26 01-Aug-13 31-Aug-13

    P-110 Construction of Site Offices 26 01-Aug-13 31-Aug-13

    P-120 Install Site Utilities and Laydown Areas 26 01-Aug-13 31-Aug-13

    CONSTRUCTIONCONSTRUCTION 296 07-Aug-13 29-May-14

    TANK/PIT LEVELTANK/PIT LEVEL 79 07-Aug-13 24-Oct-13

    EN-1000 Excavation Stage #1 10 07-Aug-13 18-Aug-13

    EN-1010 Installation of Dewatering Tubes 10 12-Aug-13 21-Aug-13

    EN-1020 Excavation Stage #2 (Pit & Footings at GF Level) 10 22-Aug-13 31-Aug-13

    EN-1030 Blinding Concrete at Pit Area 4 01-Sep-13 04-Sep-13

    EN-1040 Waterproofing at Tank/Pit Area 7 05-Sep-13 11-Sep-13

    EN-1050 Screed at Pit Area 4 12-Sep-13 15-Sep-13

    EN-1060 Rebar/Formwork at Tank/Pit Area - Raft 10 16-Sep-13 25-Sep-13

    EN-1070 Concrete Raft at Tank/Pit Area 5 26-Sep-13 30-Sep-13

    EN-1080 Rebar/ Formwork at Tank/Pit Area - Walls 7 01-Oct-13 07-Oct-13

    EN-1090 Concrete Walls of Tank/Pit Area 10 05-Oct-13 14-Oct-13

    EN-1100 Waterproofing at Tank/Pit Area 5 15-Oct-13 19-Oct-13

    EN-1110 Backfill around Tank 5 20-Oct-13 24-Oct-13

    GROUND FLOOR LEVEL - RAFTGROUND FLOOR LEVEL - RAFT 89 19-Aug-13 15-Nov-13

    EN-1120 Solid Block work in footings 10 19-Aug-13 28-Aug-13

    EN-1130 Blinding GF Raft - Part #1 5 29-Aug-13 02-Sep-13

    EN-1140 Waterproofing Part #1 7 03-Sep-13 09-Sep-13

    EN-1150 Screed Part #1 3 10-Sep-13 12-Sep-13

    EN-1160 Rebar/ Formwork Raft Part #1 10 13-Sep-13 22-Sep-13

    EN-1170 Concrete Raft Part #1 4 23-Sep-13 26-Sep-13

    EN-1180 Blinding GF Raft - Part #2 5 18-Oct-13 22-Oct-13

    EN-1190 Waterproofing Raft Part #2 7 23-Oct-13 29-Oct-13

    EN-1200 Screed Part #2 3 30-Oct-13 01-Nov-13

    EN-1210 Rebar/ Formwork Raft Part #2 10 02-Nov-13 11-Nov-13

    EN-1220 Concrete Raft Part #2 4 12-Nov-13 15-Nov-13

    PODIUM SLABPODIUM SLAB 73 27-Sep-13 08-Dec-13

    EN-1230 Rebar/ Formwork - Walls & Columns (GF-P) 60 27-Sep-13 25-Nov-13

    EN-1240 Decking of Podium Slab 60 07-Oct-13 05-Dec-13

    EN-1250 Concrete of Podium Slab 7 02-Dec-13 08-Dec-13

    FIRST FLOOR SLABFIRST FLOOR SLAB 26 09-Dec-13 03-Jan-14

    EN-1260 Rebar/ Formwork - Walls & Columns (P-FF) 14 09-Dec-13 24-Dec-13

    EN-1270 Decking of First Floor Slab 21 09-Dec-13 29-Dec-13

    EN-1280 Concrete of First Floor Slab 5 30-Dec-13 03-Jan-14

    TYPICAL FLOORSTYPICAL FLOORS 54 04-Jan-14 26-Feb-14

    EN-1290 Construction of Floors 2-11 54 04-Jan-14 26-Feb-14

    ARCHITECTURAL WORKSARCHITECTURAL WORKS 146 04-Jan-14 29-May-14

    Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

    2013 2014

    29-May-14, FURJAN PROJECT - DUBAI

    29-May-14, MILESTONES / KEY DATES

    Commencement Date (Assumed)

    Completion of Sub-Structure Works

    Completion of Super-Structure Works

    Completion of Finishing Works

    Complete Exterior Works & Building Facade

    Project Completion

    31-Aug-13, PRELIMINARIES

    Obtain Building Permit

    Mobilization of Manpower & Equipment

    Construction of Site Offices

    Install Site Utilities and Laydown Areas

    29-May-14, CONSTRUCTION

    24-Oct-13, TANK/PIT LEVEL

    Excavation Stage #1

    Installation of Dewatering Tubes

    Excavation Stage #2 (Pit & Footings at GF Level)

    Blinding Concrete at Pit Area

    Waterproofing at Tank/Pit Area

    Screed at Pit Area

    Rebar/Formwork at Tank/Pit Area - Raft

    Concrete Raft at Tank/Pit Area

    Rebar/ Formwork at Tank/Pit Area - Walls

    Concrete Walls of Tank/Pit Area

    Waterproofing at Tank/Pit Area

    Backfill around Tank

    15-Nov-13, GROUND FLOOR LEVEL - RAFT

    Solid Block work in footings

    Blinding GF Raft - Part #1

    Waterproofing Part #1

    Screed Part #1

    Rebar/ Formwork Raft Part #1

    Concrete Raft Part #1

    Blinding GF Raft - Part #2

    Waterproofing Raft Part #2

    Screed Part #2

    Rebar/ Formwork Raft Part #2

    Concrete Raft Part #2

    08-Dec-13, PODIUM SLAB

    Rebar/ Formwork - Walls & Columns (GF-P)

    Decking of Podium Slab

    Concrete of Podium Slab

    03-Jan-14, FIRST FLOOR SLAB

    Rebar/ Formwork - Walls & Columns (P-FF)

    Decking of First Floor Slab

    Concrete of First Floor Slab

    26-Feb-14, TYPICAL FLOORS

    Construction of Floors 2-11

    29-May-14, ARCHITECTURAL WORKS

    FURJAN PROJECT - DUBAI CB-01-Overall Programme 28-Jul-13 14:05

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Summary Page 1 of 2 TASK filter: All Activities

    Primavera Systems, Inc.

  • Activity ID Activity Name OriginalDuration

    Start Finish

    EN-1300 Block Work of Floors GF-11 75 04-Jan-14 19-Mar-14

    EN-1310 MEP Work 90 14-Jan-14 13-Apr-14

    EN-1320 Plaster Work 75 20-Jan-14 04-Apr-14

    EN-1330 Tiling Work 100 25-Jan-14 04-May-14

    EN-1340 Internal Painting Work 115 31-Jan-14 25-May-14

    EN-1350 False Ceiling Work 95 07-Feb-14 12-May-14

    EN-1360 Door Work 90 25-Jan-14 24-Apr-14

    EN-1370 Elevation Work/ Balcony Glass 75 14-Feb-14 29-Apr-14

    EN-1380 Lifts Work (Including T&C) 90 01-Mar-14 29-May-14

    TESTING & COMMISSIONING, SNAGGING & HANDOVERTESTING & COMMISSIONING, SNAGGING & HANDOVER 52 08-Apr-14 29-May-14

    A1110 Testing & Commissioning 45 08-Apr-14 29-May-14

    A1115 Power On 5 25-Apr-14 29-Apr-14

    A1120 Snagging & De-Snagging 45 08-Apr-14 29-May-14

    A1130 Handover 0 29-May-14

    Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun

    2013 2014

    Block Work of Floors GF-11

    MEP Work

    Plaster Work

    Tiling Work

    Internal Painting Work

    False Ceiling Work

    Door Work

    Elevation Work/ Balcony Glass

    Lifts Work (Including T&C)

    29-May-14, TESTING & COMMISSIONING, SNAGGING & HANDOVER

    Testing & Commissioning

    Power On

    Snagging & De-Snagging

    Handover

    FURJAN PROJECT - DUBAI CB-01-Overall Programme 28-Jul-13 14:05

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Summary Page 2 of 2 TASK filter: All Activities

    Primavera Systems, Inc.