G4-7_72

Embed Size (px)

Citation preview

  • 8/9/2019 G4-7_72

    1/6

    Effects of Simulation Models of Overhead

    Transmission Line Basic Components on

    Backflashover Surges Impinging on GIS SubstationsPantelis N. Mikropoulos1 , Thomas E. Tsovilis, Zacharias G. Datsios and Nikos C. Mavrikakis

    High Voltage Laboratory, Schoolof Electrical & Computer Engineering,Faculty of Engineering,Aristotle University of Thessaloniki,Thessaloniki 541 24, Greece

    [email protected]

    Abstract- Overvoltages arising in 150 kV and 400 kV GISsubstations due to backflashover of the incoming overheadtransmission lines were computed with the aid of ATP-EMTPsimulations, by considering the effects of several simulationmodels of the basic transmission line components. The

    protection offered against impinging surges by surge arrestersoperating at the substation entrance is evaluated with respect to

    the basic insulation level of the GIS system. The computedovervoltages vary considerably among tower grounding systemmodels and among insulator string flashover models whereasrather insignificantly among tower simulation models. There isno systematic variation in computed overvoltages amonginsulator string flashover models. Single vertical lossless linemodels and a constant rather than a current dependent

    resistance are considered, in terms of simulation simplicity andsafe design, as satisfactory for simulating transmission linetower and its grounding resistance, respectively, in insulationcoordination studies of substations.

    Index TermsATP-EMTP, backflashover, fast-frontovervoltages, GIS substations, insulation coordination, lightning,overhead transmission lines.

    I. INTRODUCTION

    Lightning surges may impinge on substations due to either

    backflashover in the connected overhead transmission lines,

    that is, flashover of line insulation caused by lightning flash

    to shield wire, or shielding failure in the incoming overhead

    lines, that is, lightning flash to phase conductors. The

    impinging surges may cause substation outages, thus,

    consequently, interruptions in power supply, which result in

    economic losses and affect reliability of power systems. Thus,

    insulation coordination of substations necessitates the

    estimation of the arising backflashover and shielding failure

    overvoltages. This can be accomplished analytically [1] or

    through computer simulations [2].

    For modeling of the basic components of overhead

    transmission lines, that is, the towers and their grounding

    system and flashover of insulator strings, several simulation

    models have been proposed in literature. Specifically, tower

    segments are modeled either as single-phase vertical lossless

    lines with the same [3]-[10] or different surge impedance

    (multiconductor models) [10]-[13] or as a combination of the

    latter and lumped circuit elements (multistory models) [14]-

    [17]. The tower grounding system is represented by models of

    either constant [6], [18] or current dependent grounding

    resistance; the latter models consider the reduction in the

    tower grounding resistance associated with soil ionization

    [19]-[25]. Flashover of insulator strings is represented by

    voltage-dependent switches, considering either the voltage-

    time characteristic of the insulator strings [26], [27] or leader

    progression models [28], [29].

    In the present study the overvoltages arising at the entrance

    of 150 kV and 400 kV GIS substations due to backflashoverof the incoming overhead transmission lines, normally

    associated with higher amplitude and steepness than shielding

    failure overvoltages, are evaluated with the aid of ATP-

    EMTP simulations, by considering several simulation models

    of the basic components of the lines. The computed

    overvoltages vary significantly among tower grounding

    system models and among insulator string flashover models;

    the effect of tower simulation models is rather insignificant.

    The present analysis is important for insulation coordination

    of substations since the computed peak overvoltages are used

    for the evaluation of the substation outage rate as well as for

    the selection of the necessary protection measures.

    II. SIMULATION MODELS OF THE BASIC COMPONENTS OFOVERHEAD TRANSMISSION LINES

    A. Tower Models

    Transmission line towers are divided in segments between

    the crossarms. Each segment is represented by either a

    vertical lossless single-phase frequency-independent

    distributed parameter line or by a combination of the latter

    and lumped circuit elements [3]-[17] (Fig. 1). Thus, tower

    models can be classified into three categories.

    Fig. 1. Tower models: (a) single vertical lossless line models [3]-[10], (b)

    multiconductor models [11], [12] (c) Hara et al. multiconductor model [10],(d) multistory models [14]-[16], (e) Baba & Ishii multistory model [17].

    UPEC2010

    31st Aug - 3rd Sept 2010

  • 8/9/2019 G4-7_72

    2/6

    i. Single vertical lossless line tower models

    By following a simplified approach, towers can be

    represented by a simple geometric shape, such as a cylinder

    or a cone, with surge impedance calculated according to

    expressions derived theoretically or through scale model

    experiments (Table I). Thus, all tower segments between the

    crossarms are represented by using an equal surge impedance,

    ZT() [Fig. 1(a)]. The surge propagation velocity is assumedequal to 85% of the speed of light [6]. The surge impedance

    of the 150 kV and 400 kV line towers under study (Fig. 2)

    according to different tower models is given in Table I.

    Fig. 2. Typical towers of (a) 150 kV and (b) 400 kV double-circuit lines ofthe Hellenic transmission system; the length of insulator strings is 1.86 m and

    3.62 m for the 150 kV and 400 kV line, respectively.

    ii. Multiconductor tower modelsBy representing tower segments by multiconductor vertical

    lossless lines [11] or, for simplicity, by single lossless lines

    [11], [12], the surge impedance of each segment can be

    calculated through expressions derived from electromagnetic

    field analysis. Thus, according to multiconductor models the

    tower segments are simulated as single vertical lossless lines

    with different surge impedance, ZTi [Fig. 1(b)]. Hara et al.

    [10] based on scale model experimental results proposed a

    simulation model, which takes also into account the effect of

    bracings and crossarms by representing the former by lossless

    lines, ZLi, in parallel to the lines of the tower segments, ZTi,

    and the latter by lossless horizontal lines, ZAi[Fig. 1(c)]. The

    surge propagation velocity is assumed equal to the speed of

    light. The surge impedance of the segments of the towers of

    the 150 kV and 400 kV lines (Fig. 2) calculated according to

    models [10]-[12] is given in Table II.

    iii. Multistory tower models

    Each tower segment is modeled as a lossless line in series

    with an R-L parallel circuit [Figs. 1(d) and 1(e)]. The values

    of the surge impedance of tower segments, ZTi, and the

    attenuation coefficient (Table III) are determined by a trial-

    and-error process so as to fit measured [14]-[16] or accurately

    TABLE ITOWER SURGE IMPEDANCE FOR SINGLE VERTICAL LOSSLESS LINE MODELS

    TABLE IISURGE IMPEDANCE ACCORDING TO MULTICONDUCTOR TOWER MODELS

    computed [17] voltage waveforms at several points along

    Japanese large-scale towers. he damping resistances and

    inductances, Ri and L

    i respectively, can be estimated for

    models [14]-[16] [Fig. 1(d)] as

    1 2 3

    2 ln, 1 3Tii i

    ZR h i

    h h h

    = =

    + +

    and 4 42 lnTR Z = (1)

    , 1 4ii iT

    k hL R i

    v= = (2)

    where his the tower height, h1, h2, h3 (m) are defined in Fig.

    1, ki= 2, and vTis the surge propagation velocity equal to the

    speed of light. Baba and Ishii model [17] incorporates fixed

  • 8/9/2019 G4-7_72

    3/6

    TABLE IIISURGE IMPEDANCE AND ATTENUATION COEFFICIENT ACCORDING TO

    MULTISTORY TOWER MODELS

    TABLE IVDAMPING RESISTANCE AND kiACCORDING TO BABA &ISHII [17]

    TABLE VDAMPING RESISTANCE AND INDUCTANCE FOR MULTISTORY TOWER MODELS

    values of Ri (Table IV) and inductances, Li, calculated

    according to (2) by using the values of kigiven in Table IV.The values of the damping resistances and inductances of the

    towers of the 150 kV and 400 kV lines (Fig. 2), calculated

    according to models [14]-[17], are listed in Table V.

    B. Tower Grounding System Models

    Following a simplified approach, a concentrated tower

    grounding system can be represented as a constant resistance

    equal to the low current and low frequency grounding

    resistance, R0 [6], [18]. Alternatively, according to models

    [19]-[25], a concentrated tower grounding system can bemodeled by a current dependent grounding resistance,R(I), so

    as to consider the reduction due to soil ionization in the

    grounding resistance from the initial value of R0. Soil

    ionization occurs when the lightning current, I, flowing

    through the grounding system, results in the electric field

    strength at the surface of the grounding electrodes to attain a

    value equal to soil ionization gradient, E0. The tower

    grounding system can be modeled in ATP-EMTP on the basis

    of the expressions shown in Table VI with the aid of

    MODELS.

    TABLE VICURRENT DEPENDENT TOWER GROUNDING RESISTANCE MODELS

    C.

    Insulator String Flashover Models

    According to [26], [27], flashover of line insulation occurs

    when the voltage across the insulator strings becomes equal

    to flashover strength VFO(kV) determined by the voltage-time

    characteristic of the insulator strings. VFO(kV) is given as [27]

    ( )0.75400 710FOV t D= + (3)

    whereD(m) is the insulator string length and t(s) the elapsed

    time after lightning stroke.

    According to leader progression models [28], [29] line

    insulation flashover occurs when the insulator string length is

    bridged by a leader. The leader progresses when the average

    electric field strength in the unabridged gap becomes equal to

    or higher than a critical value E0. Leader progression models

    employ differential equations (Table VII) to compute the

    leader length,L, at each time instant; flashover occurs whenL

    becomes equal to the gap length, D, that is, the insulator

    string length. Thus, the 150 kV and 400 kV line insulator

    strings were represented by voltage-dependent flashover

    switches with the aid of MODELS by incorporating (3)

    according to [26], [27] and the differential equations shown inTable VII according to leader progression models [28], [29].

    TABLE VIILEADER PROGRESSION MODELS

  • 8/9/2019 G4-7_72

    4/6

    III. OVERVOLTAGES ARISING IN GISSUBSTATIONS

    ATP-EMTP simulations were performed for two 150 kV

    and 400 kV GIS substation configurations (Fig. 3). For both

    substations, the last section of 1.75 km of the incoming

    overhead transmission lines was represented by a sequence of

    J.Marti frequency dependent models, considering the line

    span (350 m) and the tower geometries shown in Fig. 2. The

    underground XLPE power cables were represented by theBergeron model. Surge arresters were modeled as nonlinear

    current dependent resistors taking into account their

    characteristics (Table VIII). GIS bays were represented as

    lossless stub lines with a surge impedance of 75 [2]. The

    step-up transformers were represented by a capacitance pi-

    circuit together with BCTRAN model. Cable connections and

    the surge arrester lead lengths shorter than 3 m were modeled

    by a lumped parameter inductance of 1H/m [2]. The earth

    resistivity was assumed 200 m.

    Fig. 3. Schematic diagrams of the evaluated systems (a) 150 kV and

    (b) 400 kV GIS substations.

    TABLE VIIISURGE ARRESTER CHARACTERISTICS

    The effects of simulation models of towers and their

    grounding system and of insulator string flashover on the

    arising overvoltages in the GIS substations were investigated

    for the following worst case scenario: lightning is assumed to

    strike to the first tower close to the substation, at the time

    instant of positive power-frequency voltage peak of the upper

    phase of the overhead transmission line. Lightning stroke was

    represented by a current source of negative polarity producing

    a current waveshape 7/77.5 s with front upwardly concave

    [21], [30], [31]. The lightning current had an amplitude of200 kA and a maximum steepness calculated according to

    [31]. Finally, simulations were performed with and without

    surge arresters operating at the substation entrance so as to

    evaluate the protection offered against impinging surges with

    respect to the basic insulation level, BIL, of the GIS system;

    the latter is 750 kV and 1425 kV for the 150 kV and 400 kV

    substations, respectively.

    A. Effect of Tower Models

    Fig. 4 shows the computed peak overvoltages arising at the

    entrance of the 150 kV and 400 kV GIS substations by

    Fig. 4. Computed peak overvoltages at the entrance of the (a), (c) 150 kV

    and (b), (d) 400 kV GIS substations; models are numbered according toTables I-III, vertical bars indicate the variation of peak overvoltages among

    tower models, red line corresponds to safety margin of BIL/1.15.

    considering in simulations the tower models presented in

    Section II.A; insulator string flashover was modeledaccording to [27]. From Figs. 4(a) and 4(b) it is obvious that

    the overvoltages, obtained by using a fixed tower grounding

    resistance of 10 , do not vary significantly among tower

    models. Actually, as can be deduced for Figs. 4(c) and 4(d),

    the overvoltages, increasing with tower grounding resistance,

    vary among models within 10% over the range of tower

    grounding resistance of 5-20 ; generally, the differences in

    overvoltages among tower models are less pronounced for

    higher tower grounding resistance. It is noteworthy that

    increasing tower surge impedance within the range given in

    Table I results in a small increase in overvoltage peak,

    especially for lower tower grounding resistance; however,

    this is insignificant when surge arresters are operating at the

    substation entrance. The increase of overvoltage peak due to

    an increase in either tower surge impedance or grounding

    resistance can be explained by the corresponding increase in

    the instantaneous flashover voltage of line insulation. It is

    important that when surge arresters are operating at the

    substation entrance the peak overvoltages are limited to

    values lower than the safety margin of BIL/1.15 [32] (Fig. 4).

    B. Effect of Tower Grounding System Models

    Fig. 5 shows the computed peak overvoltages at the

    entrance of the substations under study for constant and

    current dependent tower grounding resistance by assuming alow current low frequency grounding resistance,R0, of 10 ;

    towers and insulator string flashover were modeled according

    to [6] and [27], respectively. From Fig. 5 it can be deduced

    that the computed overvoltages vary a little among tower

    grounding system models. However, when a higher value of

    R0 is employed in simulations (Fig. 6), differences in

    overvoltages among simulation models increase up to 19%.

    The overvoltages, increasing with R0, are highest when the

    tower grounding system is modeled by a constant grounding

    resistance equal to R0, as suggested by [6] and [18], or

    according to model [25]; this is more pronounced for

  • 8/9/2019 G4-7_72

    5/6

    Fig. 5. Computed peak overvoltages at the entrance of the (a) 150 kV and(b) 400 kV GIS substations; low current and low frequency groundingresistance 10 , red line corresponds to safety margin of BIL/1.15.

    Fig. 6. Computed peak overvoltages at the entrance of the (a) 150 kV and(b) 400 kV GIS substations as a function of low current and low frequency

    grounding resistance; red line corresponds to safety margin of BIL/1.15.

    relatively higher R0. However, when surge arresters are

    operating at the substation entrance the peak overvoltages are

    limited to values lower than the safety margin of BIL/1.15[32] (Figs. 5 and 6) and do not vary significantly, less than

    6%, among tower grounding system models. Summarizing,

    the use in simulations of a constant tower grounding

    resistance, yielding the highest computed overvoltages in the

    substations, may result in a safer design.

    C. Effect of Insulator String Flashover Models

    Fig. 7 shows the computed peak overvoltages at the

    entrance of the 150 kV and 400 kV GIS substations by

    considering in simulations the insulator string flashover

    models presented in Section II.C; towers were represented

    Fig. 7. Computed peak overvoltages at the entrance of the 150 kV and

    400 kV GIS substations; tower grounding resistance 10 ; red linecorresponds to safety margin of BIL/1.15.

    Fig. 8. Computed peak overvoltages at the entrance of the (a) 150 kV and(b) 400 kV GIS substations as a function of tower grounding resistance; red

    line corresponds to safety margin of BIL/1.15.

    according to [6] and were terminated by a constant grounding

    resistance of 10 . The computed overvoltages vary notably

    among models, up to 18%, especially for the 400 kV system.

    They increase with increasing tower grounding resistance

    (Fig. 8), especially when surge arresters are not operating atthe substation entrance. It is important to note that for the

    400 kV system when leader progression models are employed

    in simulations the overvoltages, even when surge arresters are

    installed, are higher than the safety margin of BIL/1.15 for

    tower grounding resistance higher than about 15 . This,

    contrary to common practice [33], indicates the necessity of

    using a higher insulation level for the GIS equipment, and is

    considered as unrealistic since care is normally taken to

    reduce the last tower grounding resistance to values lower

    than 10 . As a general result, due to the non-systematic

    variation in overvoltages among insulation string flashover

    models conscious selection of the latter is needed forinsulation coordination of substations.

    IV. CONCLUSIONS

    The effect of the simulation models of the basic

    components of overhead transmission lines on the arising

    overvoltages at the entrance of 150 kV and 400 kV GIS

    substations due to backflashover of the incoming lines has

    been investigated with the aid of ATP-EMTP simulations.

    Tower simulation model does not affect significantly the

    computed overvoltages, especially with increasing tower

  • 8/9/2019 G4-7_72

    6/6

    grounding resistance. Thus, single vertical lossless line

    models are considered as satisfactory for simulating

    transmission line towers, due to their simplicity, in

    insulation coordination studies of substations.

    Tower grounding system simulation model affects

    considerably the computed overvoltages, which increase

    with tower grounding resistance; however this is

    insignificant when surge arresters are operating at thesubstation entrance. A constant rather than current

    dependent resistance, resulting in higher computed

    overvoltages, is considered as satisfactory in terms of safer

    design for simulating tower grounding resistance in

    insulation coordination studies of substations.

    The computed overvoltages vary significantly however

    non-systematically among insulator string flashover

    models. Thus, conscious selection of the overhead line

    insulator string flashover model is needed for insulation

    coordination of substations.

    ACKNOWLEDGEMENTS T. E. Tsovilis wishes to thank the Research Committee of

    Aristotle University of Thessaloniki for the support provided

    by a merit scholarship.

    REFERENCES

    [1] A. R. Hileman, The incoming surge and open breaker protection, in

    Insulation Coordination for Power Systems. Boca Raton, FL: CRC

    Press, Taylor & Francis Group, New York, 1999.

    [2] IEEE Task Force, Modeling guidelines for fast front transients,IEEETrans. Power Delivery, vol. 11, no. 1, pp. 493506, Jan. 1996.

    [3] C. A. Jordan, Lightning computations for transmission lines withoverhead ground wires, Gen. Elec. Rev., vol. 37, 1934.

    [4] C. F. Wagner and A. R. Hileman, A new approach to calculation of

    lightning performance of transmission lines III A simplified method:

    Stroke to tower,AIEE Trans. Power App. Syst., vol. 79, pp. 589603,Oct. 1960.

    [5] M. A. Sargent and M. Darveniza, Tower surge impedance, IEEETrans. Power App. Syst., vol. PAS88, no. 5, pp. 680687, May 1969.

    [6] IEEE Working Group, A Simplified method for estimating lightningperformance of transmission lines, IEEE Trans. Power App. Syst.,vol. PAS-104, no. 4, pp. 919-932, Apr. 1985.

    [7] C. Menemenlis and Z. T. Chun, Wave propagation on nonuniform

    lines, IEEE Trans. Power App. Syst., vol. PAS101, no. 4, pp 833839, Apr. 1982.

    [8] W. A. Chisholm, Y. L. Chow, and K. D. Srivastava Travel time of

    transmission towers, IEEE Trans. Power App. Syst., vol. PAS104,no. 10, pp. 29222928, Oct. 1985.

    [9] IEEE Working Group on Estimating Lightning Performance of

    Transmission Lines, IEEE guide for improving the lightningperformance of transmission lines, Proposed IEEE P1243 draft, 1996.

    [10]

    T. Hara and O. Yamamoto, Modelling of a transmission tower forlightningsurge analysis,IEE Gener. Transm. Distrib., vol. 143, no. 3,pp. 283289, May 1996.

    [11] A. Ametani, Y. Kasai, J. Sawada, . Mochizuki, and . Yamada,

    Frequencydependent impedance of vertical conductors and amulticonductor tower model, IEE Gener. Transm. Distrib., vol. 141,

    no. 4, pp 339345, Jul. 1994.

    [12] D. Rondon, M. Vargas, J. Herrera, J. Montana, H. Torres, M. Camargo,

    D. Jimenez, and A. Delgadillo, Influence of grounding systemmodelling on transient analysis of transmission lines due to direct

    lightning strike,inProc. Power Tech, St. Petersburg, Russia, 2005, pp.

    1-6.[13] J. A. Gutierrez, P. Moreno, L. Guardado, J. L. Naredo, Comparison of

    transmission tower models for evaluating lightning performance, in

    Proc. Power Tech, Bologna, Italy, 2003, pp. 1-6.[14] M. Ishii, T. Kawamura, T. Kouno, E. Ohsaki, K. Shiokawa, K.

    Murotani, and T. Higuchi, Multistory transmission tower model for

    lightning surge analysis, IEEE Trans. Power Delivery, vol. 6, no. 3,pp. 13271335, Jul. 1991.

    [15] T. Yamada, A. Mochizuki, J. Sawada, E. Zaima, T. Kawamura, A.

    Ametani, M. Ishii, and S. Kato, Experimental evaluation of a UHV

    tower model for lightning surge analysis, IEEE Trans. Power

    Delivery, vol. 10, no. 1, pp 393402, Jan. 1995.

    [16] H. Motoyama, K. Shinjo, Y. Matsumoto, and N. Itamoto, Observationand analysis of multiphase back flashover on the Okushishiku test

    transmission line caused by winter lightning, IEEE Trans. Power

    Delivery, vol. 13, no. 4, pp. 13911398, Oct. 1998.[17] Y. Baba and M. Ishii, Numerical electromagnetic field analysis on

    lightning surge response of tower with shield wire, IEEE Trans.

    Power Delivery, vol. 15, no. 3, pp 10101015, Jul. 2000.[18] A. Ametani and T. Kawamura, A method of a lightning surge analysis

    recommended in Japan using EMTP, IEEE Trans. Power Delivery,

    vol. 20, no. 2, pp. 867875, Apr. 2005.

    [19]

    E. E. Oettle, A new general estimation curve for predicting theimpulse impedance of concentrated earth electrodes, IEEE Trans.Power Delivery, vol. 3, no. 4, pp 20202029, Oct. 1988.

    [20] W. A. Chisholm and W. Janischewskyj, Lightning surge response of

    ground electrodes, IEEE Trans. Power Delivery, vol. 4, no. 2, pp.13291337, Apr. 1989.

    [21] CIGRE Working Group 33.01, Guide to procedures for estimating thelightning performance of transmission lines, Technical Bulletin 63,Oct. 1991.

    [22] K. H. Weck, The current dependence of tower footing resistance,CIGRE 33-88 (WG01), 14 IWD, 1988.

    [23] P. Chowdhuri, Grounding for protection against lightning, in

    Electromagnetic transients in power systems. Research Studies PressLtd., John Wiley & sons inc., New York, 1996, pp. 104-113.

    [24] A. V. Korsuntchev, Application of the theory of similitude to the

    calculation of concentrated earth electrodes, Electrichestvo, no.5, pp.

    31-35, May 1958.[25] Y. Yasuda, Y. Hirakawa, K. Shiraishi, and T. Hara, Sensitivity

    analysis on grounding models for 500kV transmission lines, Trans.IEE Japan B, vol. 121, no. 10, pp. 13861393, 2001.

    [26] M. Darveniza, F. Popolansky, and E. R. Whitehead Lightning

    protection of UHV lines,Electra, no. 41, pp. 3969, Jul. 1975.[27] IEEE Working Group, Estimating lightning performance of

    transmission lines II Updates to analytical models, IEEE Trans.

    Power Delivery, vol. 8, no. 3, pp. 1254-1267, Jul. 1993.[28] K. H. Weck, Lightning performance of substations, CIGRE SC 33,

    Rio de Janeiro, Brazil, 1981.

    [29] A. Pigini, G. Rizzi, E. Garbagnati, A. Porrino, G. Baldo, and G.Pesavento, Performance of large air gaps under lightning overvoltages:

    Experimental study and analysis of accuracy of predeterminationmethods, IEEE Trans. Power Delivery, vol. 4, no. 2, pp 13791392,

    Apr. 1989.

    [30]

    Lightning and Insulator Subcommittee of the T&D Committee,Parameters of lightning strokes: A review, IEEE Trans. Power

    Delivery, vol. 20, no. 1, pp. 346-358, Jan. 2005.

    [31] R. B. Anderson and A. J. Eriksson, Lightning parameters forengineering application,Electra, no. 69, pp. 65102, 1980.

    [32] IEC 60071-2, Insulation Coordination, 1996.

    [33] Joint Working Group 33/23.12, Insulation co-ordination of GIS:Return of experience, on site tests and diagnostic techniques, Electra,

    no. 176, pp. 67-97, Feb. 1998.