Gas Field Engineering - Deliverability Tests

Embed Size (px)

Citation preview

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    1/51

    GAS FIELD ENGINEERING

    Deliverability Tests

    1

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    2/51

    CONTENTS

    5.1 Radius of investigation5.2 Time to stabilization5.3 Introduction to Deliverability Testing

    5.4 Flow-after-flow tests5.5 Isochronal tests5.6 Modified Isochronal tests5.7 Classifications, limitations, & use of Deliverability tests

    2

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    3/51

    LESSON LEARNING OUTCOMES

    At the end of the session, students should be able to:

    Understand radius of investigation & stabilization time

    Calculate deliverability of gas wells by using various flowtests

    Understand classifications, limitations , and the use ofdeliverability tests

    3

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    4/51

    Radius of Investigation

    4

    r e = radius of reservoir boundary

    r i = radius of investigation

    r w = radius of wellbore

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    5/51

    Why do we care about radius ofinvestigation?

    5

    To tell if the flow has been stabilized.Flow is transient before r inv reaches r e

    Flow is stable i.e. pseudo-steady state if r inv = r e

    Result Analysis is different for transient vs pseudo-steady state

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    6/51

    Radius of Investigation

    for r inv < r e .

    As long as the radius of investigation is less than r e,stabilization has not been reached and the flow is said to be

    transient . Gas well tests often involve interpretation of dataobtained in the transient flow regime.

    If r inv = r e the flow is pseudo-steady-state.

    When the radius of investigation reaches the exterior boundary,r e , of a closed reservoir, the effective drainage radius is given by

    r d = 0.472 r e

    6

    (4.65)

    (4.66)

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    7/51

    Time to Stabilization

    Time to stabilization can be determined by

    7

    (4.63)

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    8/51

    ExampleCalculating Radius of Investigation

    Solu t ion Using Eq, time to stabilization is

    Using Eq, the radius of investigation is

    8

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    9/51

    Gas Well Deliverability-Before

    9

    Early estimates of gas well performance were conducted byopening the well to the atmosphere and then measuring theflow rate.

    Such open flow practices were:-- wasteful of gas,-- dangerous to personnel and equipment, and-- damaging to the reservoir.-- provided limited information to estimate productive

    capacity under varying flow conditions

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    10/51

    Gas Well Deliverability-Now

    10

    The productivity of a gas well is now determined withdeliverability testing. It provides:

    -- Rate-pressure behavior for the well in form of aninflow performance curve (IPR) or gas backpressure curve.

    -- Finds theoreticalmaximum flow ratepossible for the wellcalled AbsoluteOpen Flow (AOF).

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    11/51

    Gas Well Deliverability Testing

    The stabilized flow capacity or deliverability of a gas wellis required for planning the operation of any gas field.

    The Absolute Open Flow (AOF ) potential of a well is definedas the rate at which the well will produce against a zerobackpressure . It cannot be measured directly but may beobtained from deliverability tests .

    Most common types of deliverability tests:

    Flow-after-flow test

    Isochronal test

    Modified isochronal test

    11

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    12/51

    Test Schematic

    12

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    13/51

    Analyzing Deliverability Test

    13

    There are two basic relations currently in used to analyzedeliverability test data:

    -- Empirical relationship of Rawlins and Schellhardt based on500 wells data.

    C = flow coefficientn = deliverability exponent

    -- Theoretical relationship by Houpeurt derived from radialdiffusivity equation accounting for non-Darcy flow effects.

    a = laminar flow coefficientb = turbulence coefficient

    http://petrowiki.org/images/6/61/Vol4_page_0007_eq_001.pnghttp://petrowiki.org/File:Vol4_page_0005_eq_001.png
  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    14/51

    Flow-after-Flow Test

    Figure (5.1) Conventional flow rate and pressure diagrams.

    14

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    15/51

    Flow-after-flow tests

    15

    The test is often referred to as a four-point test , because manytests are composed of four flow rates, as required by variousregulatory bodies.

    This test is performed by producing the well at a series ofstabilized flow rates and obtaining the corresponding stabilizedflowing bottom-hole pressures .

    In addition, a stabilized shut-in bottom-hole pressure isrequired for the analysis.

    A major limitation of this test method is the length of timerequired to obtain stabilized data for low-permeability gasreservoirs.

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    16/51

    Analysis of Flow-after-flow tests

    16

    log = log + log ( 2 2 )

    Dividing both sides by n and re-arranging to bring pressureterms on left hand side because pressure is dependent variable

    (the one that is not controlled) whereas qsc is independentbecause it is changed at will).

    log ( 2 2 ) =

    log

    log

    Compare this to the equation of straight line:y = mx +C

    m = 1/n

    Rawlins and SchellhardtsEmpirical Equation:

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    17/51

    Empirical Method

    Eqn. reveals that a plot of ( P 2) = P 2 R P 2w f versus q s c onlog-log scales should result in a straight line having a slope of 1/n.

    Once a value of slope m has been determined from the plot, ithas to be inversed to find n .

    C can then be calculated byusing data from one of the tests

    that falls on the line.Then AOF is calculated. AOF is used for these tests. AOF ismaximum rate at which the well could flow against thetheoretical back pressure at the sand face

    17

    (4.30)

    log ( 2 2 ) =1

    log 1

    log

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    18/51

    Figure (5.2) Deliverability test plot

    A plot of typical flow-after-flow data is shown in Figure

    18

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    19/51

    Theoretical Methods

    Deliverability equations based on theoretical methods are :

    1. Pressure solution technique

    2. Pressure-squared technique

    3. Pseudo pressure technique

    19

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    20/51

    Example 5-1Stabi l ized Flow Test An alysis

    A flow-after-flow test was performed on a gas well located in alow-pressure reservoir. Using the given test data, determine thevalues of n and C for the deliverability equation, AOF , and flowrate for P wf =175 psia .

    Solu t ion

    Flow-after-flow Test Data are shown in Table 5-1.

    A plot of q s c versus ( P 2R P 2w f ) is shown in Figure(5.2)

    20

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    21/51

    Table (5-1) Flow-after-flow Test Data

    21

    p R = 201 psia(p R)2 40401 psia 2

    Test q sc p wf (p wf )2 (p R)2 - (p wf )2(mscfd) (psia) (psia 2) (psia 2)

    1 2,730 196 38,416 1,9852 3,970 195 38,025 2,376

    3 4,440 193 37,249 3,1524 5,550 190 36,100 4,301

    For AOF, P wf = 0, thus (p R)2 - (p wf )2 = 40401 - 0 = 40401 psia 2

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    22/51

    1,000 10,000 100,000AOFFlow Rate, qsc (mscfd)

    p w

    f =

    0

    Note that the fraction hasbeen inversed tocompute n directly.

    Also note that the twopoints selected forcalculating n are bothfalling on the line. YouCan also read pointsfrom the line itself whichsometimes gives betteraccuracy.

    The origin should bethe biggest corner box

    and can not be zeroEvery log cycle increasesby a multiple of 10

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    23/51

    From test4 which falls on the line, calculate C:

    Therefore, the deliverability equation is

    23

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    24/51

    Isochronal Test

    24

    The isochronal test is a series of single-point

    tests developed to estimate stabilized

    deliverability characteristics without actually

    flowing the well for the time required to achieve

    stabilized conditions at each different rate .

    - The flow-after-flow tests are very accurate but

    take a long time to run specially for tight reservoir.

    h l

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    25/51

    Isochronal Test

    25

    - The flow-after-flow tests are very accurate but

    take a long time to run specially for tight reservoir.

    -To speed up the testing process, the isochronaltests were developed.

    -Isochronal tests faster yet fairly accurate

    -Isochronous means time dependent, i.e.processes where pressure data must be taken atfixed time intervals.

    h l

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    26/51

    Isochronal Test

    26

    Why Isochronal Tests are Quicker?

    Because less time is required to build to

    essentially initial pressure after short flow

    periods than to reach stabilized flow at each

    rate in a flow-after-flow test.

    Th b hi d I h l T

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    27/51

    Theory behind Isochronal Tests

    27

    - The isochronal test is based on the principle that the radiusof drainage during a flow period does not depend upon rate.

    - The r d depends only on the length of time for which thewell is flowed.

    - Therefore, the pwf measured at the same time periodsduring each rate cycle correspond to the same radius ofdrainage.

    - Thus, isochronal test data can be analyzed using the sametheory as a flow-after-flow test , even though stabilized flowis not attained.

    h l

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    28/51

    Isochronal Test

    28

    Shut in periodsare different

    Pressure buildsUp to Pavg

    h l

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    29/51

    Isochronal Test

    A deliverability test designed as a series of drawdown

    and buildup sequences such that:

    each drawdown is at different qsc,

    each drawdown is of the same duration and the flowrate does not necessary reach rate stabilization

    each buildup reaches pressure stabilization (i.e. P wf

    builds up to the same pressure as it was at the start of

    the test) where data must be delivered at fixed times.

    29

    h l

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    30/51

    Isochronal Test

    Flow the well at a fixed rates for a set period of time t ,noting the P wf at several fixed time intervals t 1, t 2, t 3, t 4 etc.

    Shut-in the well and wait until pressure is almost stabilize.

    Perform the above cycle four times but each time at adifferent rate .

    The behaviour of the flow rate and pressure with time wasillustrated in the earlier Figure for increasing flow rates.

    30

    E l 5 2

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    31/51

    Example 5-2Iso ch ron al Test

    An isochronal test was conducted on a well located in areservoir that had an average pressure of 1952 psia. The wellwas flowed on four choke sizes , and the flow rate and flowingbottom-hole pressure were measured at 3 hr and 6 hr for eachchoke size. An extended test was conducted for a period of 72 hr

    at a rate of 6.0 MMscfd, at which time p w f was measured at 1151psia . Using the data in Table 5-2.The slopes of both the 3-hr and 6-hr lines are apparently equal.(see Fig. 5-4). Use the first and last points on the 6-hr test tocalculate n from Eqn. gives.

    31

    R P

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    32/51

    Table (5-2) Isochronal Test Data

    32

    Average Reservoir pressure = 1952 psia

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    33/51

    Figure 5-4 Deliverability data plot Example 5-42. 33

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    34/51

    Using the extended flow test to calculate C using Eqn:

    Solu t ion

    1. Given the data in Table 4-2, the deliverability equation for q sc inmscfd is

    2. To calculate AOF , set P wf = 0 :

    3. In order to generate an inflow performance curve , pickseveral values of P wf and calculate the corresponding q sc

    34

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    35/51

    Well inflow performance responses are shown in Table 5-3.The inflow performance curve is plotted in Figure 5-6.

    Table 5-3 Well Inflow Performance Responses

    35

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    36/51

    Figure 5-6. Well inflow performance response Example 5-2. 36

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    37/51

    Modified isochronal tests

    In normal isochronal test, time for pressureto build up to during sh ut -in may beimpractically long.

    Modified isochronal test shortens test timesbecause well does not build up to averagereservoir pressure after each flow period

    Why Needed?

    http://petrowiki.org/File:Vol5_page_0781_inline_001.pnghttp://petrowiki.org/File:Vol5_page_0781_inline_001.png
  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    38/51

    Modified isochronal tests

    The modified isochronal test is lessaccurate than the isochronal test becausethe well does not build up to

    What is the downside?

    p & q history of a typical modified isochronal test

    http://petrowiki.org/File:Vol5_page_0781_inline_001.png
  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    39/51

    p w f & q history of a typical modified isochronal test

    Equal Shut in times thatare = or > flow periods

    Shut in pressure is notReaching P avg

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    40/51

    Modified isochronal tests

    Conducted like an isochronal test, except theshut-in periods are shorter and of equal

    duration.

    The shut-in periods should equal or exceed thelength of the flow periods.

    A final stabilized flow point usually is obtainedat the end of the test but is not required foranalyzing the test data.

    Test Procedure

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    41/51

    Shut-in sandface pressure p s is used instead of P avg

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    42/51

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    43/51

    Rawlins-Schellhardt analysis technique

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    44/51

    Rawlins-Schellhardt analysis technique

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    45/51

    Wellhead Deliverability

    In practice it is sometimes more convenient to measure thepressures at the wellhead .

    These pressures may be converted to bottom-hole

    conditions by the calculation procedure suggested byCullender and Smith.

    However, in some instances, the wellhead pressures mightbe plotted versus flow rate in a manner similar to bottom-hole curves.

    Classifications Limitations

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    46/51

    This may be known directly from previous tests, such as drill-stem or deliverability tests, conducted on the well or from theproduction characteristics of the well.

    If such information is not available , it may be assumed thatthe well will behave in a manner similar to neighbouringwells in the same pool, for which data are available.

    Time to stabilization may be estimated using Equation (4.63) .

    Radius of investigation can be found from Equation (4.65) .

    Classifications, Limitations,and Use of Deliverability Tests

    46

    Classifications Limitations

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    47/51

    If time to stabilization is of the order of few hours, flow-after-flow test may be conducted.

    Otherwise, one of the isochronal tests is preferable.

    Classifications, Limitations,and Use of Deliverability Tests

    47

    Classifications Limitations Use of Deliverability Tests

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    48/51

    Classifications, Limitations, Use of Deliverability TestsNext Figure shows types, limitations, and uses of deliverabilitytests. In designing a deliverability test, collect and utilize all

    information which includes:logsdrill-stem testsprevious deliverability tests conducted on that wellproduction historygas and liquid compositionstemperaturecore samplesgeological studies

    Knowledge of the time required for stabilization is a veryimportant factor in deciding the type of test to be used for determining the deliverability of a gas well.

    48

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    49/51

    Figure. Types, limitations, and uses of deliverability tests. 49

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    50/51

    Thank You

    50

  • 8/9/2019 Gas Field Engineering - Deliverability Tests

    51/51

    Q & A