Upload
farhan-beigh
View
220
Download
0
Embed Size (px)
Citation preview
8/12/2019 Gas Power Plants Presentation
1/31
A policy assessment:
Import of Gas to Fuel starved
Power Stations
G. Behari
Director (OM) CEAFarhan Beg
NIT Srinagar, India
8/12/2019 Gas Power Plants Presentation
2/31
India Country Profile:
Area: 3.29 million sq. km. (1.27 million sq. mi.)
Population:1.2208 billion
Climate: Desert, Mountain, Subtropical, Semi Arid steppe, Moist subtropical
Purchasing Power Parity: 4735 $Billion (2012 est.)
All India Installed Capacity: 211766.22 MW (As on 31.01.2013)
Per Capita Consumption: 879.22 kWh (2011-2012)
8/12/2019 Gas Power Plants Presentation
3/31
Department of
Atomic Energy
Ministry of
Power
Central ElectricityAuthority
Central ElectricityRegularity
Commission
State ElectricityRegularity
Commission
Indian Power Sector
8/12/2019 Gas Power Plants Presentation
4/31
Inside Indias Electrical Power System:Generation Transmission Distribution
Centrally owned
Generation:
State ownedgenerators
Private Generators
Power-GridCorporation
State OwnedTX
State ElectricityBoards
National PowerSystem Desk(POSOCO)
National LoadDispatch Center
(NLDC)
Regional LoadDispatch
Centers-5(RLDC)
State LoadDispatch
Centers-34
State OwnedDistributionCompanies
Private DistributionCompanies
Sub state- LoadDispatch
Centers-51
Regional PowerCommittee-5
8/12/2019 Gas Power Plants Presentation
5/31
Acknowledging Supply and Demand:
Gap between demand and supply is wide and growing.
Demographics and Economics are the reason for it.
Growing economy and Massive urbanization putting more stress on energy and the
environment.
Requiremrnt Availability Shortage %
Energy(MU) 937,199 857,886 79,313 8.5
Peak(MW) 130,006 116,191 13,815 10.6
0
100,000
200,000
300,000
400,000
500,000
600,000
700,000
800,000
900,000
1,000,000Actual Power Supply Position During 2011-12
Source: CEA
8/12/2019 Gas Power Plants Presentation
6/31
Power supply position:
All India (2011-12):
(MW) Energy (MU) PeakRequirement 937,199 130,006Availability 857,886 116,191Shortage 79,313 13,815(%) 8.5% 10.6%
Requirement Availability Shortage
Energy (MU) 937,199 857,886 79,313
Peak 130,006 116,191 13,815
0100,000200,000300,000
400,000500,000600,000700,000800,000900,000
1,000,000
8/12/2019 Gas Power Plants Presentation
7/31
Requirement(MU)
Availability(MU)
Requirement(MU)
Availability(MU)
Energy Peak
Northern 276,121 258,382 40248 37117
Western 290,421 257,403 42,352 36,509
Southern 260,302 237,480 37,599 32,188
Eastern 99,344 94,657 14707 13,999
0
50,000
100,000
150,000
200,000
250,000
300,000
350,000
Regional power supply position(2011-2012):
8/12/2019 Gas Power Plants Presentation
8/31
8/12/2019 Gas Power Plants Presentation
9/31
Power Generation Capacity:
57%
1%
9%
19%
2% 12%
Coal Diesel
Gas HydroNuclear Non renewables
Coal accounts for nearly 57 % of the total power generation
Abundant coal reservesPower Generation using coal is cheaperEven though abundant coal reserves are a reason for themonopolistic power generation using coal, yet India is facing
huge coal supply and production issues.
As on 31.03.2012
8/12/2019 Gas Power Plants Presentation
10/31
Indian Coal Scenario:
Coal Mining started by Messrs Sumner & Heatly of the East India company way
back in 1774Mines were nationalized in the country with the inception of CIL in 1970 toincrease the influx of investmentsIndian power delivery chain is highly dependent on coal with nearly 70 % of itsgeneration and is experiencing perpetual fuel shortagesFuel shortages are dominant even when India has 10% of the worlds coal
reserves
0
10002000
3000
Million
Tonnes
Years
Projected demand-supply of coal by2025
Demand by powersector
Supply to powersector
Source:ObserverResearchFoundation
8/12/2019 Gas Power Plants Presentation
11/31
All Figures in MTS NO Description 2011-121.1 Coal requirement for plants designed on
indigenous coal 4551.2 Coal requirements for plants designed on
imported coal 201.3 Total 4752. Coal availability from indigenous Sources2.1 From CIL Sources 3472.2 From SCCL 332.3 From Captive Mines 222.4 Total coal availability from indigenous
sources 4023. Shortfall of indigenous coal 53
Coal Scenario for 2011-12
8/12/2019 Gas Power Plants Presentation
12/31
Energy Demands &Drivers for Alternate Sources ofEnergy:
1. High Growth Rate in Overall Energy needs:
Expansion of supply demand gap is due to increasePresently Supply-Demand gap is nearly 12.9%
2. Increasing reliance on imports of fossil fuels:
Country imported nearly 80% of its crude oilconsumption in 2009-10Over 48% of the country's total imports bill typically
goes towards oil imports
Contd
8/12/2019 Gas Power Plants Presentation
13/31
3. Need for a viable solution for rural electrification:A program of grid strengthening and extension was
initiated in 2005Benefits the 400 million Indians who lack access toelectricity
4. Electricity peak demand-supply : The electricity shortfall for the fiscal year (2011-2012)was 10.3% with a peak shortage of 12.9%.
5. Pressure on industry and policy to abate GHG emissions:
Indiasstrategy for tackling climate change is set out inits National Action Plan on Climate Change (NAPCC),released in 2008
8/12/2019 Gas Power Plants Presentation
14/31
Hydro: An Overview
Globally India ranks 5thin terms of total hydro-potentialHydro electric potential in India is 84000 MW at 60 % load factorwhich is equivalent to 1,48,700 MW installed capacity
Basin/Rivers Installed Capacity(MW)Indus Basin
33,832
Ganga Basin 20,711Central Indian River system 4,152Western flowing Rivers of Southern India 9,430Eastern flowing rivers of Southern India 14,511Brahmaputra Basin 66,065Total 1,48,701
Basin Wise Assessment:
8/12/2019 Gas Power Plants Presentation
15/31
Advantages of hydropower over thermal power:
Renewable and Non PollutingCost of generation, operation and maintenance is lowerthan the other sources of energy.
Cost of generation is free of the inflationary effects afterthe final installation.
8/12/2019 Gas Power Plants Presentation
16/31
National Policy on Hydropower introduced in 1998Main Points:
To ensure targeted capacity addition during 9thplan (and the
subsequent plans)Exploitation of vast Hydro Electric Potential at faster pacePromotion of small and mini hydro projects especially in remote andhilly areas where extension of the grid is comparatively uneconomicalStrengthening the role of PSUs and SEBs in taking up new hydroprojectsIncreasing private investments for development of hydropower in India
8/12/2019 Gas Power Plants Presentation
17/31
Issues Impeding Development of Hydro Power:
Difficult/In-accessible locationsLand acquisition problemsResettlement and Rehabilitation issues
Law And Order SituationGeological surprisesInter-State DisputesCumbersome process for obtaining the clearances
from various national bodies
8/12/2019 Gas Power Plants Presentation
18/31
Limitations of Hydro Projects:
Away from load centers; evacuation of power is a bigproblemLack of availability of long term financeProduction risks since the project is planned based in thehistorical data which may not occur in futureDifficulty in Investigations/Implementations due to
remoteness of the areaLong gestation period
8/12/2019 Gas Power Plants Presentation
19/31
Natural Gas Scope:
Petroleum and Gas emerging as the most dynamic energy sectors in
the countryClean and an efficient choice for power generation.
Total Capacity of Gas Based power plants was 18,381 MW as on 31March 2012.
0
1
23
4
5
6
2003 2008 2013 2018 2023 2028 2033CubicTrillionFeet
Year
Supply
Demand
Supply And Demand Scenario of Gas In the country:
8/12/2019 Gas Power Plants Presentation
20/31
India Renewable Scenario:As on November 2012 12% of total installed capacity (210 GW) through
renewable sourcesWIND (18.3 GW)Small hydro (3.4 GW)Biomass (1.2 GW)Solar (1 GW)
Wind,17352.
65
Solar,941.28
Smallhydro,
3395.31
Biomass,1150
Progressive Renewable Sector
Wind,28352.
65
Solar,4741.28
SmallHydro,4995.31
Biomass,3250
2012 2017
Contd
8/12/2019 Gas Power Plants Presentation
21/31
Installed capacity Financialrequirement
Type 2012 2017 CAGR Rupees(CR)SHP 3395.31 4995.31 10% 8000Biomass 1150 3250 30% 10500Solar 941.28 9941 80% 63000Wind 17352.65 28352.65 13% 67200
Large cash inflows required to bring about such change.Financial Requirement of such a proposition very high.
Source Potential inIndia
Present InstalledCapacity
(Nov12)
Wind 60 GW 17.62 GW
Solar 50 GW 941 MW
Geothermal 10.6 GW 220 MW
Biomass 34.9 GW 1150 MW
8/12/2019 Gas Power Plants Presentation
22/31
Issues with large scale deployment ofRenewable Energy
High up-front costs Local Site Issues
Mature Generation(Hydro power, Biomass,Solar thermal hot water,
geothermal)
Technological advancements needed. Need substantial cost reduction through market
experience (Need to be deployed)
Developing Generation(Wind, Bio Energy, Solar
PV)
Still require substantial RD&D to be deployed Need to be deployed and tested in pilot projects
R&D Generation(Concentrating Solarpower, Ocean Energy,
Advanced forms of Bio
energy)
Renewable energys are classified into threegenerations each presenting their own issues:
8/12/2019 Gas Power Plants Presentation
23/31
Capacity Addition in the 12thplan with 9% GDP GR& 0.9 Elasticity (All Values in MW)
Type ofCapacity
Capacity Addition
Base Case High Gas High Gas + highrenewableScenario
Thermal 63781 63886 60486
Coal 62695 50600 47400
Gas 1086 13086 13086
Hydro 9204 9204 9204
Nuclear 2800 2800 2800
Total 75785 75690 72490Renewables 18500 18500 30000
Imports 1200 1200 1200
CoalRequirement(MT)
842 772 764
Source:CEA
8/12/2019 Gas Power Plants Presentation
24/31
Capacity Addition Requirement during 12thplan (MW) Base Case:
Type of Capacity Demand Corresponding to 9%GDP GR & .9 Elasticity
Thermal 63,781
Coal 62,695
Gas 1,086
Hydro 9,204
Nuclear 2,800
Total 75,785
Figures in MW
Additionally, grid interactive renewable capacity addition of about18500 MW has been projected.
Source: CEA
8/12/2019 Gas Power Plants Presentation
25/31
Coal Demand and Availability:
Coal Requirement during the year 2016-17 842MT
Coal Availability from :
a: CIL 418 MT
b: SCCl 35 MT
c:Captive blocks allocated to powerutilities
100 MT
d: Coal to be imported by TPSs designedimported Coal
54 MT
Total Coal availability 604 MT
Shortfall 238 MT
Source: Working group on power-12thplan
8/12/2019 Gas Power Plants Presentation
26/31
Capacity Addition Hindrances:
Thermal:Even though accounting for nearly 80% of Indias total generation, thefuture seems grim. Fuel shortage is acute and supply demand gap of coal isincreasing unabated.
Hydro:Nearly 9204 MW of power projected for hydro power in the 12th
plan. Long gestation period and environmental ramifications continueto hold back the hydro power potential of the country to some extent .
Renewables:Higher initial costs coupled with renewable technologies being in a
developmental stage present issues for their large scale deployment.Renewable technologies need to be improved and cost effectivedeployments introduced to make renewable energy generation take overfrom the conventional fossil fuel generation.
8/12/2019 Gas Power Plants Presentation
27/31
Mitigating shortages: Options available
Renovation and modernization of existing thermal power plantsCapacity enhancement of existing hydro power stationsReduction of technical and commercial losses through theintroduction of Smart Grid
Import of Gas to Fuel Starved Power Stations to enhance theirelectricity generation to be sold through ABT
8/12/2019 Gas Power Plants Presentation
28/31
Import of Gas to Fuel Starved Power
Stations: Methodology
Sample Area Selected: Western RegionImported Gas supplied(In addition to gas already being supplied):Power Stations in Gujarat & Maharashtra (Gas Based)Study Month November 2012Feasible additional generation from these stations.Cost of fuel for this additional generationSale of this addition generation under ABT
8/12/2019 Gas Power Plants Presentation
29/31
Resultant Parameters
Additional Generation = 1900 MU per day(Enhanced Efficiency & auxiliary losses are not considered fortime being)Cost of Imported gas= $13.627/MMSCMD
(Report of the Committee on the production sharing contractmechanism in Petroleum industry- December 2012)Cost of Addition generation=$19.6 MillionCost of fuel =$19.6 MillionAdditional O&M expenses (to be worked out):would not besubstantialRevenue Realization :additional electricity = Rs 162 crore(equivalent : $30.6 million ; 1$=53 INR)
8/12/2019 Gas Power Plants Presentation
30/31
Assumptions
Efficiency of gas stations does not improve appreciably with highergeneration (could be worked out at a later stage while carrying out
detailed study)O&M cost of gas station does not increase appreciably with enhancedgeneration (Need to be established, however the enhancement of O&Mcost would not be substantial)No backing down/Non scheduling of gas stations owing to higher cost
of generationRevenue realization is based on average cost of generation during theyear 2010-11.
8/12/2019 Gas Power Plants Presentation
31/31
Import of gas is economically viable if the additional electricity generation issold under ABT
Issues to be addressed:
Conclusion
Source of imported gas
Transportation of gas up to the Indian coastLanding port of gasStorage of gas at the portTransportation of gas within India