Gas Power Plants Presentation

Embed Size (px)

Citation preview

  • 8/12/2019 Gas Power Plants Presentation

    1/31

    A policy assessment:

    Import of Gas to Fuel starved

    Power Stations

    G. Behari

    Director (OM) CEAFarhan Beg

    NIT Srinagar, India

  • 8/12/2019 Gas Power Plants Presentation

    2/31

    India Country Profile:

    Area: 3.29 million sq. km. (1.27 million sq. mi.)

    Population:1.2208 billion

    Climate: Desert, Mountain, Subtropical, Semi Arid steppe, Moist subtropical

    Purchasing Power Parity: 4735 $Billion (2012 est.)

    All India Installed Capacity: 211766.22 MW (As on 31.01.2013)

    Per Capita Consumption: 879.22 kWh (2011-2012)

  • 8/12/2019 Gas Power Plants Presentation

    3/31

    Department of

    Atomic Energy

    Ministry of

    Power

    Central ElectricityAuthority

    Central ElectricityRegularity

    Commission

    State ElectricityRegularity

    Commission

    Indian Power Sector

  • 8/12/2019 Gas Power Plants Presentation

    4/31

    Inside Indias Electrical Power System:Generation Transmission Distribution

    Centrally owned

    Generation:

    State ownedgenerators

    Private Generators

    Power-GridCorporation

    State OwnedTX

    State ElectricityBoards

    National PowerSystem Desk(POSOCO)

    National LoadDispatch Center

    (NLDC)

    Regional LoadDispatch

    Centers-5(RLDC)

    State LoadDispatch

    Centers-34

    State OwnedDistributionCompanies

    Private DistributionCompanies

    Sub state- LoadDispatch

    Centers-51

    Regional PowerCommittee-5

  • 8/12/2019 Gas Power Plants Presentation

    5/31

    Acknowledging Supply and Demand:

    Gap between demand and supply is wide and growing.

    Demographics and Economics are the reason for it.

    Growing economy and Massive urbanization putting more stress on energy and the

    environment.

    Requiremrnt Availability Shortage %

    Energy(MU) 937,199 857,886 79,313 8.5

    Peak(MW) 130,006 116,191 13,815 10.6

    0

    100,000

    200,000

    300,000

    400,000

    500,000

    600,000

    700,000

    800,000

    900,000

    1,000,000Actual Power Supply Position During 2011-12

    Source: CEA

  • 8/12/2019 Gas Power Plants Presentation

    6/31

    Power supply position:

    All India (2011-12):

    (MW) Energy (MU) PeakRequirement 937,199 130,006Availability 857,886 116,191Shortage 79,313 13,815(%) 8.5% 10.6%

    Requirement Availability Shortage

    Energy (MU) 937,199 857,886 79,313

    Peak 130,006 116,191 13,815

    0100,000200,000300,000

    400,000500,000600,000700,000800,000900,000

    1,000,000

  • 8/12/2019 Gas Power Plants Presentation

    7/31

    Requirement(MU)

    Availability(MU)

    Requirement(MU)

    Availability(MU)

    Energy Peak

    Northern 276,121 258,382 40248 37117

    Western 290,421 257,403 42,352 36,509

    Southern 260,302 237,480 37,599 32,188

    Eastern 99,344 94,657 14707 13,999

    0

    50,000

    100,000

    150,000

    200,000

    250,000

    300,000

    350,000

    Regional power supply position(2011-2012):

  • 8/12/2019 Gas Power Plants Presentation

    8/31

  • 8/12/2019 Gas Power Plants Presentation

    9/31

    Power Generation Capacity:

    57%

    1%

    9%

    19%

    2% 12%

    Coal Diesel

    Gas HydroNuclear Non renewables

    Coal accounts for nearly 57 % of the total power generation

    Abundant coal reservesPower Generation using coal is cheaperEven though abundant coal reserves are a reason for themonopolistic power generation using coal, yet India is facing

    huge coal supply and production issues.

    As on 31.03.2012

  • 8/12/2019 Gas Power Plants Presentation

    10/31

    Indian Coal Scenario:

    Coal Mining started by Messrs Sumner & Heatly of the East India company way

    back in 1774Mines were nationalized in the country with the inception of CIL in 1970 toincrease the influx of investmentsIndian power delivery chain is highly dependent on coal with nearly 70 % of itsgeneration and is experiencing perpetual fuel shortagesFuel shortages are dominant even when India has 10% of the worlds coal

    reserves

    0

    10002000

    3000

    Million

    Tonnes

    Years

    Projected demand-supply of coal by2025

    Demand by powersector

    Supply to powersector

    Source:ObserverResearchFoundation

  • 8/12/2019 Gas Power Plants Presentation

    11/31

    All Figures in MTS NO Description 2011-121.1 Coal requirement for plants designed on

    indigenous coal 4551.2 Coal requirements for plants designed on

    imported coal 201.3 Total 4752. Coal availability from indigenous Sources2.1 From CIL Sources 3472.2 From SCCL 332.3 From Captive Mines 222.4 Total coal availability from indigenous

    sources 4023. Shortfall of indigenous coal 53

    Coal Scenario for 2011-12

  • 8/12/2019 Gas Power Plants Presentation

    12/31

    Energy Demands &Drivers for Alternate Sources ofEnergy:

    1. High Growth Rate in Overall Energy needs:

    Expansion of supply demand gap is due to increasePresently Supply-Demand gap is nearly 12.9%

    2. Increasing reliance on imports of fossil fuels:

    Country imported nearly 80% of its crude oilconsumption in 2009-10Over 48% of the country's total imports bill typically

    goes towards oil imports

    Contd

  • 8/12/2019 Gas Power Plants Presentation

    13/31

    3. Need for a viable solution for rural electrification:A program of grid strengthening and extension was

    initiated in 2005Benefits the 400 million Indians who lack access toelectricity

    4. Electricity peak demand-supply : The electricity shortfall for the fiscal year (2011-2012)was 10.3% with a peak shortage of 12.9%.

    5. Pressure on industry and policy to abate GHG emissions:

    Indiasstrategy for tackling climate change is set out inits National Action Plan on Climate Change (NAPCC),released in 2008

  • 8/12/2019 Gas Power Plants Presentation

    14/31

    Hydro: An Overview

    Globally India ranks 5thin terms of total hydro-potentialHydro electric potential in India is 84000 MW at 60 % load factorwhich is equivalent to 1,48,700 MW installed capacity

    Basin/Rivers Installed Capacity(MW)Indus Basin

    33,832

    Ganga Basin 20,711Central Indian River system 4,152Western flowing Rivers of Southern India 9,430Eastern flowing rivers of Southern India 14,511Brahmaputra Basin 66,065Total 1,48,701

    Basin Wise Assessment:

  • 8/12/2019 Gas Power Plants Presentation

    15/31

    Advantages of hydropower over thermal power:

    Renewable and Non PollutingCost of generation, operation and maintenance is lowerthan the other sources of energy.

    Cost of generation is free of the inflationary effects afterthe final installation.

  • 8/12/2019 Gas Power Plants Presentation

    16/31

    National Policy on Hydropower introduced in 1998Main Points:

    To ensure targeted capacity addition during 9thplan (and the

    subsequent plans)Exploitation of vast Hydro Electric Potential at faster pacePromotion of small and mini hydro projects especially in remote andhilly areas where extension of the grid is comparatively uneconomicalStrengthening the role of PSUs and SEBs in taking up new hydroprojectsIncreasing private investments for development of hydropower in India

  • 8/12/2019 Gas Power Plants Presentation

    17/31

    Issues Impeding Development of Hydro Power:

    Difficult/In-accessible locationsLand acquisition problemsResettlement and Rehabilitation issues

    Law And Order SituationGeological surprisesInter-State DisputesCumbersome process for obtaining the clearances

    from various national bodies

  • 8/12/2019 Gas Power Plants Presentation

    18/31

    Limitations of Hydro Projects:

    Away from load centers; evacuation of power is a bigproblemLack of availability of long term financeProduction risks since the project is planned based in thehistorical data which may not occur in futureDifficulty in Investigations/Implementations due to

    remoteness of the areaLong gestation period

  • 8/12/2019 Gas Power Plants Presentation

    19/31

    Natural Gas Scope:

    Petroleum and Gas emerging as the most dynamic energy sectors in

    the countryClean and an efficient choice for power generation.

    Total Capacity of Gas Based power plants was 18,381 MW as on 31March 2012.

    0

    1

    23

    4

    5

    6

    2003 2008 2013 2018 2023 2028 2033CubicTrillionFeet

    Year

    Supply

    Demand

    Supply And Demand Scenario of Gas In the country:

  • 8/12/2019 Gas Power Plants Presentation

    20/31

    India Renewable Scenario:As on November 2012 12% of total installed capacity (210 GW) through

    renewable sourcesWIND (18.3 GW)Small hydro (3.4 GW)Biomass (1.2 GW)Solar (1 GW)

    Wind,17352.

    65

    Solar,941.28

    Smallhydro,

    3395.31

    Biomass,1150

    Progressive Renewable Sector

    Wind,28352.

    65

    Solar,4741.28

    SmallHydro,4995.31

    Biomass,3250

    2012 2017

    Contd

  • 8/12/2019 Gas Power Plants Presentation

    21/31

    Installed capacity Financialrequirement

    Type 2012 2017 CAGR Rupees(CR)SHP 3395.31 4995.31 10% 8000Biomass 1150 3250 30% 10500Solar 941.28 9941 80% 63000Wind 17352.65 28352.65 13% 67200

    Large cash inflows required to bring about such change.Financial Requirement of such a proposition very high.

    Source Potential inIndia

    Present InstalledCapacity

    (Nov12)

    Wind 60 GW 17.62 GW

    Solar 50 GW 941 MW

    Geothermal 10.6 GW 220 MW

    Biomass 34.9 GW 1150 MW

  • 8/12/2019 Gas Power Plants Presentation

    22/31

    Issues with large scale deployment ofRenewable Energy

    High up-front costs Local Site Issues

    Mature Generation(Hydro power, Biomass,Solar thermal hot water,

    geothermal)

    Technological advancements needed. Need substantial cost reduction through market

    experience (Need to be deployed)

    Developing Generation(Wind, Bio Energy, Solar

    PV)

    Still require substantial RD&D to be deployed Need to be deployed and tested in pilot projects

    R&D Generation(Concentrating Solarpower, Ocean Energy,

    Advanced forms of Bio

    energy)

    Renewable energys are classified into threegenerations each presenting their own issues:

  • 8/12/2019 Gas Power Plants Presentation

    23/31

    Capacity Addition in the 12thplan with 9% GDP GR& 0.9 Elasticity (All Values in MW)

    Type ofCapacity

    Capacity Addition

    Base Case High Gas High Gas + highrenewableScenario

    Thermal 63781 63886 60486

    Coal 62695 50600 47400

    Gas 1086 13086 13086

    Hydro 9204 9204 9204

    Nuclear 2800 2800 2800

    Total 75785 75690 72490Renewables 18500 18500 30000

    Imports 1200 1200 1200

    CoalRequirement(MT)

    842 772 764

    Source:CEA

  • 8/12/2019 Gas Power Plants Presentation

    24/31

    Capacity Addition Requirement during 12thplan (MW) Base Case:

    Type of Capacity Demand Corresponding to 9%GDP GR & .9 Elasticity

    Thermal 63,781

    Coal 62,695

    Gas 1,086

    Hydro 9,204

    Nuclear 2,800

    Total 75,785

    Figures in MW

    Additionally, grid interactive renewable capacity addition of about18500 MW has been projected.

    Source: CEA

  • 8/12/2019 Gas Power Plants Presentation

    25/31

    Coal Demand and Availability:

    Coal Requirement during the year 2016-17 842MT

    Coal Availability from :

    a: CIL 418 MT

    b: SCCl 35 MT

    c:Captive blocks allocated to powerutilities

    100 MT

    d: Coal to be imported by TPSs designedimported Coal

    54 MT

    Total Coal availability 604 MT

    Shortfall 238 MT

    Source: Working group on power-12thplan

  • 8/12/2019 Gas Power Plants Presentation

    26/31

    Capacity Addition Hindrances:

    Thermal:Even though accounting for nearly 80% of Indias total generation, thefuture seems grim. Fuel shortage is acute and supply demand gap of coal isincreasing unabated.

    Hydro:Nearly 9204 MW of power projected for hydro power in the 12th

    plan. Long gestation period and environmental ramifications continueto hold back the hydro power potential of the country to some extent .

    Renewables:Higher initial costs coupled with renewable technologies being in a

    developmental stage present issues for their large scale deployment.Renewable technologies need to be improved and cost effectivedeployments introduced to make renewable energy generation take overfrom the conventional fossil fuel generation.

  • 8/12/2019 Gas Power Plants Presentation

    27/31

    Mitigating shortages: Options available

    Renovation and modernization of existing thermal power plantsCapacity enhancement of existing hydro power stationsReduction of technical and commercial losses through theintroduction of Smart Grid

    Import of Gas to Fuel Starved Power Stations to enhance theirelectricity generation to be sold through ABT

  • 8/12/2019 Gas Power Plants Presentation

    28/31

    Import of Gas to Fuel Starved Power

    Stations: Methodology

    Sample Area Selected: Western RegionImported Gas supplied(In addition to gas already being supplied):Power Stations in Gujarat & Maharashtra (Gas Based)Study Month November 2012Feasible additional generation from these stations.Cost of fuel for this additional generationSale of this addition generation under ABT

  • 8/12/2019 Gas Power Plants Presentation

    29/31

    Resultant Parameters

    Additional Generation = 1900 MU per day(Enhanced Efficiency & auxiliary losses are not considered fortime being)Cost of Imported gas= $13.627/MMSCMD

    (Report of the Committee on the production sharing contractmechanism in Petroleum industry- December 2012)Cost of Addition generation=$19.6 MillionCost of fuel =$19.6 MillionAdditional O&M expenses (to be worked out):would not besubstantialRevenue Realization :additional electricity = Rs 162 crore(equivalent : $30.6 million ; 1$=53 INR)

  • 8/12/2019 Gas Power Plants Presentation

    30/31

    Assumptions

    Efficiency of gas stations does not improve appreciably with highergeneration (could be worked out at a later stage while carrying out

    detailed study)O&M cost of gas station does not increase appreciably with enhancedgeneration (Need to be established, however the enhancement of O&Mcost would not be substantial)No backing down/Non scheduling of gas stations owing to higher cost

    of generationRevenue realization is based on average cost of generation during theyear 2010-11.

  • 8/12/2019 Gas Power Plants Presentation

    31/31

    Import of gas is economically viable if the additional electricity generation issold under ABT

    Issues to be addressed:

    Conclusion

    Source of imported gas

    Transportation of gas up to the Indian coastLanding port of gasStorage of gas at the portTransportation of gas within India