    Summary of radio network planning

    ZTE University

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    2/33

    Objectives

    At the end of this course, you will be able to: Describe the contents and flow of site survey

    State the basic principle of site selection

    Master the using of site survey tools

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    3/33

    Contents

    Site survey summary

    Preparation of site survey

    Working flow of site survey

    Data audit and documents output Site survey tools

    Site survey instances

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    4/33

    Function

    Provide basic data for planning and imitation; Make planning more reasonable and reduce risk;

    Reduce the cost of network

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    5/33

    Goals

    Know the feature of field, landform andsubscribers, estimate the subscriber number and

    traffic

    Integrate coverage, traffic density, site condition

    and cost

    Output BTS site type, site location , distribution

    and antenna configuration which satisfying

    customers requirements. Make site survey of each site and prepare three

    candidate sites for substitution

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    6/33

    Working flow

    Single site record

    Collection andcheck

    Execution

    Site surveyplanreparation

    Rightdata?

    Requirementanalysis

    OutputSite surveyreportSite surveyreport

    N

    Y

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    7/33

    Contents

    Site survey summary

    Preparation of site survey

    Working flow of site survey

    Data audit and documents output Site survey tools

    Site survey instances

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    8/33

    Requirement analysis

    Target of network (coverage and capacity) Customers suggestion on site type (micro cell,

    repeater, indoor coverage etc.)

    Existing network situation of coverage area (site

    distribution of other operators)

    Working interface with customers

    Schedule and resource of site survey

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    9/33

    Output of requirements analysis

    Collect and analyze all the requirements formcustomer, combined with network planning and

    site survey documents. Output report of

    requirements analysis.

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    10/33

    Tools Function

    necessary

    GPS Altitude, latitude and longitude of BTS

    Compass direction and environment

    Digital camera photo the environment of site

    ruler For measurement

    vehicle One vehicle for each team

    Notnecessary

    map Digital map, scan map, paper map

    Range finder Measure distancetelescope Increase sight scope

    test equipment Test the coverage of site

    Tools

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    11/33

    Site survey plan

    According to the project and requirements report,make detail site survey plan, including goal,

    organization, personnel, tools, schedule and

    outputs.

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    12/33

    Contents

    Site survey summary

    Preparation of site survey

    Working flow of site survey

    Data process and documents output Site survey tools

    Site survey instances

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    13/33

    Site survey flow

    Site location

    selection

    Information

    collection and

    analyzing

    Site adjust Not suitable

    Cell parameters

    design

    Site survey

    record table

    end

    startSite initial

    information

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    14/33

    Site initial information

    Latitude and longitude of sites from planning Site location provided by operators

    The location of old substitute sites

    Sites of other operators

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    15/33

    No. Common principle for site selection1 Site should be in the ideal position of honeycomb structure

    2 The BTS density should match the traffic density

    3 The height of BTS should lower then the highest building and higher thenthe average building

    4 Avoid high buildings or potential blocking constructions, which may affectthe coverage

    5 Avoid radio station, radar or other strong interference equipments

    6 Avoid choose the top of hill or woods

    7 Necessary condition for site building

    8 Select the equipment rooms with little expansion cost or buildings with

    less rent

    9 Try to select the existing telecom station, micro wave station, so to reusethe power supply

    10 The feasibility, cost and performance should be considered before themicrowave is used as transmission

    11 Dual band sites should be at same site in urban area

    Principle of site selection

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    16/33

    Information collection and analysis

    Traffic distribution survey Traffic distribution in serving area

    Economy level, average income and consumption

    habits.

    Forecast subscriber increase trend

    Radio propagation environment survey

    Location information of BTS (longitude, latitude, altitude)

    Description of the overall environment

    Description of barriers

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    17/33

    Cell parameter design

    BTS type Site configuration

    Antenna parameters

    Antenna heightAzimuth

    Tilt down angle

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    18/33

    Site survey record table

    Altitude, longitude and precision of GPS Geographic description of BTS

    Important area

    Direction Transmission system

    Repeater basic information

    Co-site description

    Picture of site

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    19/33

    Contents

    Site survey summary

    Preparation of site survey

    Working flow of site survey

    Data audit and documents output Site survey tools

    Site survey instances

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    20/33

    Data audit and documents output

    After the site survey, all the documents should becollected by team leader, who will pass them to

    network planning technical manager

    After check and audit, Network planning manager

    will pass these documents to project manager.

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    21/33

    Check and audit

    Check and audit from technical view, make surethe site survey result is true, accurate, reasonable

    and feasible:

    Fill up

    If there is any questions about sites, communicate withcustomers and put it into MOU.

    If the environments is not good for sites, suggestion

    must be given to customers for improvement.

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    22/33

    Output report

    After gather and audit, provide the followinginformation in the final report

    BTS site survey reportChinese, English

    Coverage area list

    BTS site information list

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    23/33

    Contents

    Site survey summary Preparation of site survey

    Working flow of site survey

    Data audit and documents output Site survey tools

    Site survey instances

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    24/33

    GPS

    Main indices Receive sensitivity

    Navigation

    Physical index

    Power

    Keys on panel

    Power key

    Turn page Input

    Exit

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    25/33

    GPS

    Basic operate power on, light, shut down

    Automatic location

    Location and navigation operation

    Navigation on route

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    26/33

    GPS

    Notes for longitude/latitude measurement GPS needs 3 satellites for location

    The measurement mode is WGS84

    The angle unit is degree

    Try close to site to measure

    Deviation compared with digital map

    The precision of digital map

    GPS measurement deviation The test spot is not same as planned

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    27/33

    Compass

    Main function Direction and tilt down angle

    Landform measurement: include orientation, slope

    degree, fix level

    Vertical angle

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    28/33

    1viewfinder 2Aim board

    3Magnetic needle 4Horizontal

    dial 5Vertical dial

    6Vertical scale indicator

    7Vertical level organ

    8batholith level organ

    9Magnetic needle fix helix

    10thimble 11lever

    12Glass cover

    13Box and needle round board

    Structure

    Magnetic needle Horizontal dial

    Vertical dial

    Aim board Viewfinder

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    29/33

    Compass

    Antenna direction Stand under the antenna or tower with instrument in

    hand

    Make the upper cover face you, aim board point to

    antenna Wait for the needle stop, the degree of the needle N

    pole is the direction of antenna.

    Antenna tiltdown

    Keep the compass close to the character surface ofantenna, and keep the bleb in the middle for some time

    Read the degree, which represent the tiltdown angle of

    this character surface.

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    30/33

    Contents

    Site survey summary Preparation of site survey

    Working flow of site survey

    Data audit and documents output Site survey tools

    Site survey instances

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    31/33

    Unreasonable location

    BTS site close to high voltage cable Wrong: One BTS is close to a high voltage cable,

    antenna is at the same level as power cable and the

    distance to power cable is no more than 10 meters.

    Right: move the BTS 50 meters away from the powercable for safety

    BTS is on the hill in urban

    In order to cover a city, a BTS is built on a hill with 300

    meters high. As the BTS is so high that all the MS in this city can

    receive the signal, which make other BTS traffic idle,

    This site is congestion, and cause many MS fail to call.

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    32/33

    Unreasonable planning

    Less BTS sites in dense urban area Total 29 frequencies available for one city, so only 5

    sites were build.

    Limited by frequency resources, there is no large

    capacity sites which cant satisfy the traffic requirement. Solution: Another 8 new BTS sites were built to fit the

    large traffic.

  • 7/27/2019 GBO_007_E1_1 GSM Summary of Radio Network Planning-34

    33/33