Upload
fandhiejavanov2009
View
221
Download
0
Embed Size (px)
Citation preview
7/30/2019 Geotechnical Investigation 1225510757282453 9
1/39
Importance of Proper Geotechnical
Investigation in Engineering Project:
Some case studyJ.N.Jha*, K.S.Gill* & A.K.Chaudhary**
*Department of Civil Engineering, Guru NanakDev Engineering College, Ludhiana
** Department of Civil Engineering, NIT,Jamshedpur
7/30/2019 Geotechnical Investigation 1225510757282453 9
2/39
Introduction
Construction activities increasedmanifold (development of economicactivities)
Different types of complex structuresare coming up (to meet the growingdemand)
Attempt being made to make soilsuitable to project and not theproject to soil.
7/30/2019 Geotechnical Investigation 1225510757282453 9
3/39
Geotechnical Engineer-
very important role to play in thischallenging task.
Geotechnical Engineering Practice-Atpar with the best in the world.
Range of Geotechnical practice varywidely in India.
7/30/2019 Geotechnical Investigation 1225510757282453 9
4/39
Field investigation-Most primitiveequipment are in use
Laboratory testing-Practice varywidely with little standardization andaccreditation.
7/30/2019 Geotechnical Investigation 1225510757282453 9
5/39
Quality of Investigation
India World Standard
Generally Poor quality of theEquipment
Highly sophisticated andmechanized equipment
Calyx Drilling Technique Continuous core sampling (insoils as well)
SPT Equipment unchangedover the years (unreliable)
SPT Equipment with BlowEnergy Directly on top of thesampler
Conventional Static ConePenetration Equipment
Static Cone Test with ElectricCone
Very recently few companies
have electric cone
7/30/2019 Geotechnical Investigation 1225510757282453 9
6/39
Result (Substandard practice)
Substantial difference between actualsoil profiles and available soil profiles(at the time of design as part of
tender specifications)
Variation can be minimized ifstandard practices are followedduring the soil investigation
7/30/2019 Geotechnical Investigation 1225510757282453 9
7/39
Unfortunately this is not the case quiteoften
Who is responsible?
Responsibility squarely rests onGeotechnical community of the country
and is a major failure on our part.
7/30/2019 Geotechnical Investigation 1225510757282453 9
8/39
General and Standard Practice
Tender for a project (informationsupplied)
Subsoil profile and soil characteristicsis of general information only
Owner is not responsible for thecorrectness of this information
7/30/2019 Geotechnical Investigation 1225510757282453 9
9/39
Contractor if desired should satisfythe correctness of information beforesubmitting his offer
To safeguard the owner to avoid anydispute
7/30/2019 Geotechnical Investigation 1225510757282453 9
10/39
Contractor (point of view)
Time interval between issue oftender document and submission oftechnical bid is very short
Soil investigation is expensive
Impossible to carry out soilinvestigation
Bidder accepts the stipulation givenin tender
7/30/2019 Geotechnical Investigation 1225510757282453 9
11/39
Case study
Road over Bridge (ROB)
Bridge :
5 span of 10.7 m with certainembankment on either side
As per tender SPT value 12 to 16 fortop two layer extending up to 7 m.
7/30/2019 Geotechnical Investigation 1225510757282453 9
12/39
Recommend allowable bearingpressure=150 kN/m2 at depth 2 m belowGL for Pier foundation.
Accordingly Piers were constructed onshallow foundation
4 Pier constructed and 5th was underconstruction approach earth embankmentsettled by 2 m and corresponding heavingup of soil 1.5 m
7/30/2019 Geotechnical Investigation 1225510757282453 9
13/39
EMBANKMENT
9m2m SETT LEM ENT BRIDGE
PIER
RAIL LINE
AB UT M ENT
SOIL HEAVE
SOFT CLAY
- 6m
SAND
10.7 m
ROTAT IONAL FAILURE
G.L.
.
7/30/2019 Geotechnical Investigation 1225510757282453 9
14/39
Confirming soil investigation wascarried out
Soil Profile:
Top 1-1.5 m : Sandy Clay
1.5-8 m : Soft marine clay
7/30/2019 Geotechnical Investigation 1225510757282453 9
15/39
10
8
6
4
2
0
12 SAND
14
16
12
29
38
SILT
CLAY
BH-I SPT
(N)
(a) As Per tender
10
8
6
4
2
0
0.1
BH-I SPT
(N)
(b) As Per confirmatory
bore Hole
0.0
0.0
0.0
15
110.3
C=40KN/m2
C=24KN/m2
C=31KN/m2
C=40KN/m2
7/30/2019 Geotechnical Investigation 1225510757282453 9
16/39
Rehabilitation Measure
Piles installed around shallowfoundation and integrated withfoundation
Delay in completion of project,additional cost & dispute
7/30/2019 Geotechnical Investigation 1225510757282453 9
17/39
Petro Chemical Complex
As per Tender
Recommended depth of Pile = 25 m
Test pile failed to take design load
Confirmatory (Bore hole) test 12 such confirmatory bone hole
consistently showed that SPT valuereported in original soil report are higher
Pile depth after confirmatory test =20m Confirmatory soil investigation saved a
major disaster.
7/30/2019 Geotechnical Investigation 1225510757282453 9
18/39
3 2
2 4
1 6
8
0
B H - 3 B H - F
T O P F I L L
S I L T
R O C K
C L A Y
S A N DB H - F ( c o n f ir m a t o r y )
B H - 3 ( t e n d e r)
4
1 2
2 0
2 8
8 16 24 32
S P T (N ) V a lu e s
Dep
th( m )
7/30/2019 Geotechnical Investigation 1225510757282453 9
19/39
Choice of Appropriate foundation
and execution
Optimum foundation design shouldensure
Technical adequacy
Cost effectiveness
Ease of execution
7/30/2019 Geotechnical Investigation 1225510757282453 9
20/39
Reasons
Insufficient and inaccurateinformation at the time of designvariation in strata
Changes in project requirementduring execution.
7/30/2019 Geotechnical Investigation 1225510757282453 9
21/39
Achieving this is easily said thandone-needs engineering judgement
Engineering Judgement comesfrom experience.
Experience comes from badengineering judgement
7/30/2019 Geotechnical Investigation 1225510757282453 9
22/39
Case study
Fertilizer plant in Gangetic belt-possibility of optimum design
Phase-I
Soil strata (Site)
N20 For a depth upto 10-20m
7/30/2019 Geotechnical Investigation 1225510757282453 9
23/39
Type of Soil
Silty sand with high water table
Threat of liquefaction duringearthquake
Foundation Design
7/30/2019 Geotechnical Investigation 1225510757282453 9
24/39
Foundation Design
(Recommended)
Provide RCC cast in situ piles(diameter 400 mm) with pilecapacity
Axial vertical load 50 Tonnes
Uplift - 5 Tonnes
Horizontal capacity=2.5 Tonnes
7/30/2019 Geotechnical Investigation 1225510757282453 9
25/39
To overcome the problem ofliquefaction during earthquake
Provide sand compaction pile 2 to 3rows around RCC piles
7/30/2019 Geotechnical Investigation 1225510757282453 9
26/39
Total requirement
As per design No. of RCC piles 16000 No. of sand compaction piles 32,000
Time required for installation of RCC pilesand sand compaction piles=6 months more than what was originallyplanned
This prompted for the review of foundationdesign
7/30/2019 Geotechnical Investigation 1225510757282453 9
27/39
Sand Compaction Pile
Original design
Spacing of compaction pile 3D and5D with triangular pattern
Spacing 3D (desired improvementin N-values)
Spacing-5D (desired improvement inN values not adequates)
7/30/2019 Geotechnical Investigation 1225510757282453 9
28/39
Additional Recommendation
Spacing of sand compaction pile-4D
Result-Adequate to obtain requireddensification (N-values)
No. of piles (now required)=16000instead of 32000
7/30/2019 Geotechnical Investigation 1225510757282453 9
29/39
Pile capacity (Revised)
Vertical downward-65 tonnes insteadof 50 tonnes original
Uplift capacity=25 tonnes instead of5 tonnes original
Lateral capacity-3.5 tonnes asagainst original 2.5 tonnes
7/30/2019 Geotechnical Investigation 1225510757282453 9
30/39
Requirement of no. of RCC piles(based on revision)=9400 piles
Reduction in no. of piles =40%
Observation:
Performance of the foundation-fullyadequate and satisfactory.
7/30/2019 Geotechnical Investigation 1225510757282453 9
31/39
Phase-II (To double the capacity of
the plant)
Ground improvement Vibro stonecolumn in place of RCC piles and sandcompaction piles
Vibro stone column diameter- 960 mm Load test carried on single column and
group of columns
Footing test conducted for confirmationduring execution.
7/30/2019 Geotechnical Investigation 1225510757282453 9
32/39
Trial Test
Test plot 10 m x 10 m
Vibro stone column
11 m (length), c/c spacing 15 m, 2.15m & 1.8 m
(Triangular pattern
7/30/2019 Geotechnical Investigation 1225510757282453 9
33/39
Standard Penetration Test
Area Depth Layer N Aftertreatment %increase inN Value
Prill Tower 0-2.5
25-11
Silty Clay
Silty Clay
13
20-36
30
17-120
BenefieldArea
0-2.3
2.3-11
Silty Clay
Silty Clay
20
16-34
81
36-123
CompressorHouse
0-3.5
3.5-11
Silty Clay
Silty Clay
11
24-46
01
60-400
7/30/2019 Geotechnical Investigation 1225510757282453 9
34/39
Static Cone Penetration Test
(SCPT)
Depth Pre-treatment
(ConeResistance)
Post-treatment
(Cone
Resistance)2-8m 50-80 kg/cm2 130-300
kg/cm2
7/30/2019 Geotechnical Investigation 1225510757282453 9
35/39
Dynamic Cone Penetration Test
(DCPT)
Depth Pre-treatment(No. of blowsper ft.)
Past-treatment(No. of blows
per ft.)2-10 m 10-40 22-95
7/30/2019 Geotechnical Investigation 1225510757282453 9
36/39
DESCRPTION
1.0
2.0
3.0
4.0
5.0
6.0
7.0
8.0
9.0
10.0
11.0
10 20 30 40 50 60
SOILPROF.
DEPTH
(m)
SPT (N) VALUE
BROWN
CLAYSILT
2.50
5.25
BROWNSILT FINE
SAND
GREY
FINE SAND
GREY SILTY
MEDIUM
TO FINESAND
9.55
X
PRE COMPACTION
POST COMPACTION
POST COMPACTION
PRE COMPACTION
7/30/2019 Geotechnical Investigation 1225510757282453 9
37/39
Vibro Stone Column of 960mm withspacing 2D, 2.25D and 2.5D whereadopted depending on loading
intensity
Substantial saving in time and cost
Subsequently observation during the
operation of Phase-II confirmed asatisfactory behaviour of foundation
7/30/2019 Geotechnical Investigation 1225510757282453 9
38/39
Concluding remarks
Commitment to excellence fromGeotechnical Engineers
Positive attitude to continuouslylearn and to accept change for better
Partnership and team work among allconcerned i.e owner, consultant and
contractor
7/30/2019 Geotechnical Investigation 1225510757282453 9
39/39
Thank you..