Geotechnical Investigation 1225510757282453 9

Embed Size (px)

Citation preview

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    1/39

    Importance of Proper Geotechnical

    Investigation in Engineering Project:

    Some case studyJ.N.Jha*, K.S.Gill* & A.K.Chaudhary**

    *Department of Civil Engineering, Guru NanakDev Engineering College, Ludhiana

    ** Department of Civil Engineering, NIT,Jamshedpur

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    2/39

    Introduction

    Construction activities increasedmanifold (development of economicactivities)

    Different types of complex structuresare coming up (to meet the growingdemand)

    Attempt being made to make soilsuitable to project and not theproject to soil.

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    3/39

    Geotechnical Engineer-

    very important role to play in thischallenging task.

    Geotechnical Engineering Practice-Atpar with the best in the world.

    Range of Geotechnical practice varywidely in India.

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    4/39

    Field investigation-Most primitiveequipment are in use

    Laboratory testing-Practice varywidely with little standardization andaccreditation.

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    5/39

    Quality of Investigation

    India World Standard

    Generally Poor quality of theEquipment

    Highly sophisticated andmechanized equipment

    Calyx Drilling Technique Continuous core sampling (insoils as well)

    SPT Equipment unchangedover the years (unreliable)

    SPT Equipment with BlowEnergy Directly on top of thesampler

    Conventional Static ConePenetration Equipment

    Static Cone Test with ElectricCone

    Very recently few companies

    have electric cone

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    6/39

    Result (Substandard practice)

    Substantial difference between actualsoil profiles and available soil profiles(at the time of design as part of

    tender specifications)

    Variation can be minimized ifstandard practices are followedduring the soil investigation

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    7/39

    Unfortunately this is not the case quiteoften

    Who is responsible?

    Responsibility squarely rests onGeotechnical community of the country

    and is a major failure on our part.

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    8/39

    General and Standard Practice

    Tender for a project (informationsupplied)

    Subsoil profile and soil characteristicsis of general information only

    Owner is not responsible for thecorrectness of this information

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    9/39

    Contractor if desired should satisfythe correctness of information beforesubmitting his offer

    To safeguard the owner to avoid anydispute

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    10/39

    Contractor (point of view)

    Time interval between issue oftender document and submission oftechnical bid is very short

    Soil investigation is expensive

    Impossible to carry out soilinvestigation

    Bidder accepts the stipulation givenin tender

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    11/39

    Case study

    Road over Bridge (ROB)

    Bridge :

    5 span of 10.7 m with certainembankment on either side

    As per tender SPT value 12 to 16 fortop two layer extending up to 7 m.

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    12/39

    Recommend allowable bearingpressure=150 kN/m2 at depth 2 m belowGL for Pier foundation.

    Accordingly Piers were constructed onshallow foundation

    4 Pier constructed and 5th was underconstruction approach earth embankmentsettled by 2 m and corresponding heavingup of soil 1.5 m

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    13/39

    EMBANKMENT

    9m2m SETT LEM ENT BRIDGE

    PIER

    RAIL LINE

    AB UT M ENT

    SOIL HEAVE

    SOFT CLAY

    - 6m

    SAND

    10.7 m

    ROTAT IONAL FAILURE

    G.L.

    .

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    14/39

    Confirming soil investigation wascarried out

    Soil Profile:

    Top 1-1.5 m : Sandy Clay

    1.5-8 m : Soft marine clay

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    15/39

    10

    8

    6

    4

    2

    0

    12 SAND

    14

    16

    12

    29

    38

    SILT

    CLAY

    BH-I SPT

    (N)

    (a) As Per tender

    10

    8

    6

    4

    2

    0

    0.1

    BH-I SPT

    (N)

    (b) As Per confirmatory

    bore Hole

    0.0

    0.0

    0.0

    15

    110.3

    C=40KN/m2

    C=24KN/m2

    C=31KN/m2

    C=40KN/m2

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    16/39

    Rehabilitation Measure

    Piles installed around shallowfoundation and integrated withfoundation

    Delay in completion of project,additional cost & dispute

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    17/39

    Petro Chemical Complex

    As per Tender

    Recommended depth of Pile = 25 m

    Test pile failed to take design load

    Confirmatory (Bore hole) test 12 such confirmatory bone hole

    consistently showed that SPT valuereported in original soil report are higher

    Pile depth after confirmatory test =20m Confirmatory soil investigation saved a

    major disaster.

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    18/39

    3 2

    2 4

    1 6

    8

    0

    B H - 3 B H - F

    T O P F I L L

    S I L T

    R O C K

    C L A Y

    S A N DB H - F ( c o n f ir m a t o r y )

    B H - 3 ( t e n d e r)

    4

    1 2

    2 0

    2 8

    8 16 24 32

    S P T (N ) V a lu e s

    Dep

    th( m )

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    19/39

    Choice of Appropriate foundation

    and execution

    Optimum foundation design shouldensure

    Technical adequacy

    Cost effectiveness

    Ease of execution

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    20/39

    Reasons

    Insufficient and inaccurateinformation at the time of designvariation in strata

    Changes in project requirementduring execution.

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    21/39

    Achieving this is easily said thandone-needs engineering judgement

    Engineering Judgement comesfrom experience.

    Experience comes from badengineering judgement

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    22/39

    Case study

    Fertilizer plant in Gangetic belt-possibility of optimum design

    Phase-I

    Soil strata (Site)

    N20 For a depth upto 10-20m

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    23/39

    Type of Soil

    Silty sand with high water table

    Threat of liquefaction duringearthquake

    Foundation Design

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    24/39

    Foundation Design

    (Recommended)

    Provide RCC cast in situ piles(diameter 400 mm) with pilecapacity

    Axial vertical load 50 Tonnes

    Uplift - 5 Tonnes

    Horizontal capacity=2.5 Tonnes

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    25/39

    To overcome the problem ofliquefaction during earthquake

    Provide sand compaction pile 2 to 3rows around RCC piles

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    26/39

    Total requirement

    As per design No. of RCC piles 16000 No. of sand compaction piles 32,000

    Time required for installation of RCC pilesand sand compaction piles=6 months more than what was originallyplanned

    This prompted for the review of foundationdesign

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    27/39

    Sand Compaction Pile

    Original design

    Spacing of compaction pile 3D and5D with triangular pattern

    Spacing 3D (desired improvementin N-values)

    Spacing-5D (desired improvement inN values not adequates)

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    28/39

    Additional Recommendation

    Spacing of sand compaction pile-4D

    Result-Adequate to obtain requireddensification (N-values)

    No. of piles (now required)=16000instead of 32000

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    29/39

    Pile capacity (Revised)

    Vertical downward-65 tonnes insteadof 50 tonnes original

    Uplift capacity=25 tonnes instead of5 tonnes original

    Lateral capacity-3.5 tonnes asagainst original 2.5 tonnes

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    30/39

    Requirement of no. of RCC piles(based on revision)=9400 piles

    Reduction in no. of piles =40%

    Observation:

    Performance of the foundation-fullyadequate and satisfactory.

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    31/39

    Phase-II (To double the capacity of

    the plant)

    Ground improvement Vibro stonecolumn in place of RCC piles and sandcompaction piles

    Vibro stone column diameter- 960 mm Load test carried on single column and

    group of columns

    Footing test conducted for confirmationduring execution.

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    32/39

    Trial Test

    Test plot 10 m x 10 m

    Vibro stone column

    11 m (length), c/c spacing 15 m, 2.15m & 1.8 m

    (Triangular pattern

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    33/39

    Standard Penetration Test

    Area Depth Layer N Aftertreatment %increase inN Value

    Prill Tower 0-2.5

    25-11

    Silty Clay

    Silty Clay

    13

    20-36

    30

    17-120

    BenefieldArea

    0-2.3

    2.3-11

    Silty Clay

    Silty Clay

    20

    16-34

    81

    36-123

    CompressorHouse

    0-3.5

    3.5-11

    Silty Clay

    Silty Clay

    11

    24-46

    01

    60-400

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    34/39

    Static Cone Penetration Test

    (SCPT)

    Depth Pre-treatment

    (ConeResistance)

    Post-treatment

    (Cone

    Resistance)2-8m 50-80 kg/cm2 130-300

    kg/cm2

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    35/39

    Dynamic Cone Penetration Test

    (DCPT)

    Depth Pre-treatment(No. of blowsper ft.)

    Past-treatment(No. of blows

    per ft.)2-10 m 10-40 22-95

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    36/39

    DESCRPTION

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

    11.0

    10 20 30 40 50 60

    SOILPROF.

    DEPTH

    (m)

    SPT (N) VALUE

    BROWN

    CLAYSILT

    2.50

    5.25

    BROWNSILT FINE

    SAND

    GREY

    FINE SAND

    GREY SILTY

    MEDIUM

    TO FINESAND

    9.55

    X

    PRE COMPACTION

    POST COMPACTION

    POST COMPACTION

    PRE COMPACTION

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    37/39

    Vibro Stone Column of 960mm withspacing 2D, 2.25D and 2.5D whereadopted depending on loading

    intensity

    Substantial saving in time and cost

    Subsequently observation during the

    operation of Phase-II confirmed asatisfactory behaviour of foundation

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    38/39

    Concluding remarks

    Commitment to excellence fromGeotechnical Engineers

    Positive attitude to continuouslylearn and to accept change for better

    Partnership and team work among allconcerned i.e owner, consultant and

    contractor

  • 7/30/2019 Geotechnical Investigation 1225510757282453 9

    39/39

    Thank you..