32
GLAST LAT Project SVAC Workshop , February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area GLAST Large Area Telescope: Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence Detector (ACD) Subsystem Performance Calibration and Verification Alex Moiseev Robert Hartman David Thompson NASA Goddard Space Flight Center With contributions from Luis Reyes, Eric Charles, Larry Wai, and others Gamma-ray Large Gamma-ray Large Area Space Area Space Telescope Telescope

GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

Embed Size (px)

Citation preview

Page 1: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 1

GLAST Large Area Telescope:GLAST Large Area Telescope:

SVAC WorkshopFebruary 27-28, 2006

AntiCoincidence Detector (ACD) Subsystem Performance Calibration and Verification

Alex MoiseevRobert HartmanDavid Thompson

NASA Goddard Space Flight CenterWith contributions from Luis Reyes, Eric Charles, Larry Wai, and others

Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope

Page 2: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 2

ACD Pre-Shipping TestsACD Pre-Shipping Tests

ACD System-level Tests of numerous configurations have been performed during and after ACD integration at Goddard from the mid-May to August 2006

The idea of the tests during integration was to perform the tests after every major step in the integration in order to eliminate the need to do some disassembling in the case of discovering the problems later.

Current ACD Full Functional test contains TrigOps to test ACD Performance; in the earlier stages we run parts of tests to save the time

ACD Performance test – test of ACD capability to detect charged particles; subject of this test is to determine mip peak positions and pedestals for every ACD channel. For the ribbons it is a light yield along the ribbon length

ACD Testing software was still in development stage during ACD tests at Goddard, which created additional problems

Page 3: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 3

ACD Pre-Shipping Tests (cont.)ACD Pre-Shipping Tests (cont.)

“Partial” performance tests during ACD integration: 1. Light tightness tests – performed after every tile/ribbon row installed Purpose of this test is to ensure that there is no light leak in installed parts. If High Voltage (HV) is applied, light leak can severely damage the PMT. Light leak can be:– in the tile light-tight wrapping (made of black tedlar), especially at the tile edges where tedlar can crack– in the tile fiber connector area where the irregular shape connector is wrapped – in the fiber cable Sumitube black tubing – possible pin-holes; also in tubing-to-optical connector joining points– in the area of fiber cable coupling to the PMT housing – most often occurs– around tile mounting holes The sequence of this test:– cover whole ACD by light tight tent; run “Rate Monitor” script to get every channel “normal” rate at nominal HV– open the tent; run “Rate Monitor” script with HV 300 V less than nominal. Get rates. If none of the channel rate exceeds “normal” rate by more than 10%, raise HV by 100 V and repeat the test – if some excessive rate is found, locate light leak by covering parts of failing channel and using “pencil” light source to detect the leak place– test is completed and ACD is ready for further integration, if all rates with open tent are within 10% of the normal rate

Page 4: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 4

ACD Pre-Shipping Tests – PartialACD Pre-Shipping Tests – Partial Performance testsPerformance tests

2. Particle detection capability – performed several times during the integration to check that mip peak positions are in reasonable places in corresponding PHA histograms

3. High Voltage selection – performed after all tiles installed to select the value of operating HV. Every FREE board (up to 18 PMT) has its own HVBS, and the idea is to select optimal HV when the “weakest” channel has a mip peak separated from pedestal by approximately 400 ADC counts. This provides us necessary VETO threshold precision setting and desired range of signals in “Low range” – ideally to 6-8 mips. In spite of careful PMT assignment to FREE board to reduce the range of mip peak position variation across FREE (R. Hartman), there are still some channels peaking at ~800 ADC counts. This reduces the range of signals in “Low range”, but has no affect on ACD efficiencyHV values vary from board to board from 720V to 840V.

Page 5: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 5

Selected HV ValuesSelected HV Values

FREE card

GARC number

Chosen HV, Volts

Range of tile mip peak positions, except ribbons (pedestals subtracted)

Limit of mip signals in PHA Low Range, in mips

1L 0 740 400-800 0 – (3.5 – 7)

1R 1 760 400-800 0 – (3.5 – 7)

2LA 2 720 400-650 0 – (4.5 – 7)

2LB 3 730 400-700 0 – (4 – 7)

2RA 4 715 400-650 0 – (4.5 – 7)

2RB 5 745 400-800 0 – (3.5 – 7)

3L 6 820 400-800 0 – (3.5 – 7)

3R 7 800 400-800 0 – (3.5 – 7)

4LA 8 755 400-700 0 – (4 – 7)

4LB 9 740 400-700 0 – (4 – 7)

4RA 10 760 400-850 0 – (3 – 7)

4RB 11 745 400-900 0 – (3 – 7)

These HV are recommended for ACD operation; all calibrations are made with these HV values; change of any of them would require full ACD recalibration

Page 6: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 6

Full FunctionalFull Functional TestTest

• A successful Full Functional Test of the fully integrated flight ACD was performed before and after vibration/acoustics and at four temperatures: +35 C, +23 C, 0 C, and -25 C.

• Document numbers are ACD-PROC-000270 (functional/performance) and ACD-PROC-000352 (margin).

• The test covers all aspects of the ACD functional areas such as – Voltages, currents, temperatures– Commanding– Electronics performance– Detector operation– Margin testing (varying electronics voltages and clock

frequencies)

Page 7: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 7

Full FunctionalFull Functional TestTest – Basic Power On Notes – Basic Power On Notes

• Voltages – 28 V and 3.3 V supplied by the GASU. The flight GASU may be supplying slightly lower voltages than the engineering GASU. It is important to re-test the ACD with only one set of LVDS drivers enabled (default power-on mode is both sets on). High Voltage (0-1250 V) generated within the ACD.

• Currents – measured by the GASU. The ACD power cannot be measured directly, because the DC-DC converters in the GASU consume some power.

• Commanding – checks that all registers can be written and read, including broadcast commands; checks parity error detection

• Electronics Setup

– Check settings for maximum number of PHA values per GARC

– Check enable/disable settings for each PHA channel

– Verify setting of PHA threshold (zero-suppress threshold)

– Check (but not change) bias for 3.3 V line on each GARC

– Check electronics noise level in GAFE (analog ASIC)

Page 8: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 8

Full FunctionalFull Functional TestTest – Timing/TCI Tests – Timing/TCI Tests

• Hold Delay – optimize time that the PHA signal is held before sampling

• Hitmap Delay – test operating range for delays in the Hitmap discriminator to match the TACK arrival time

• Hitmap Timing – check Hitmap Delay settings at different widths of Hitmap discriminator

• Test Charge Injection (TCI) with notes about some anomalies observed:

– VETO threshold – excess counts seen on one channel at cold temperatures

– High Level Discriminator threshold – one channel shows unexpected counts

– PHA Regular Range (low and high sections) – nonlinearity increased (although not badly) when ACD was integrated onto the LAT

– PHA High Range (low and high sections) – high section is quite nonlinear, but not a problem.

– Hardware Counters

Page 9: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 9

Unexpected Counts Testing Anomaly PR ACD-02334-009Unexpected Counts Testing Anomaly PR ACD-02334-009

• During each of the cold cycles during the thermal vacuum test, we observed 2-4 excess counts on one electronics channel of the ACD during a test.

• The test was done using charge injection and was a test of a high VETO threshold (5 strobes; should have recorded no counts).

• Either the VETO threshold was not set properly, or the test charge was larger than expected.

• The excess counts appeared on the last GAFE of the last GARC, suggesting a possible end-of-test-cycle clearing error, possibly due to timing, but we have no way to confirm this suspicion.

• It is also possible that we have a channel with an instability, because this same error was seen on this channel in chassis cold tests.

• The operational performance of this channel is excellent at all temperatures.

• If we found excess VETO rate in orbit, we could re-set the threshold. It has very wide dynamic range.

Page 10: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 10

High Rate Testing Anomaly PR ACD-02334-016High Rate Testing Anomaly PR ACD-02334-016

• During two of the four transitions from hot to cold during the thermal vacuum test, we observed high rates (up to 5 KHz) on one tile detector of the ACD. Temperature was between 10 C and –15 C.

• The high rate in both cases settled down to a normal rate (< 100 Hz) by the time temperature stability was achieved.

• The test script that was running collected only rate data, so we have no other information about the output from that tile. We do not even know which of the two phototube signals might have given the high rate, because the hardware counters sum the signals.

• This channel (both phototubes) produces good data in every functional test we have done, including a run at 0 C.

• Because it is a transient problem, not even seen in every transition, we have been unable to diagnose this problem. Generally noise decreases with lower temperature. It was not seen in chassis tests.

• If a high rate on a channel appeared in orbit, we have the option of disabling a phototube signal. Loss of one signal would be acceptable for ACD performance.

Page 11: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 11

ACD Monitored ParametersACD Monitored Parameters

Monitored Parameter Family Parameter Name

Bias DAC LE and HE Bias Slope, Offset and Preferred Setting

GAFE Noise Vernier sharpness; Noise Threshold

Veto Step (AcdVetoCal) Veto slope; Veto offset

HLD Step HLD slope; HLD offset

Low (Regular) Range PHA linearity

calibration

Low_slope;Low_offset;Low_MSE;High_slope;High_offset;High_MSEAuto_LE_mean; Auto_LE_step; Auto_HE_mean

High Range PHA linearity calibration Low_slope; Low_offset; Low_MSE; High_slope; High_offset; High_MSE

Pedestal (script) Mean value; Distribution Width

AcdHitMap Delay Channel Hit Map delay; Hitmap Delay mean; HitMap delay SD; HitMap Delay optimal

ACd Hold Delay Channel Hold Delay; HoldDelay optimum; HoldDelay StDev

HVBS HV intercept; HV slope; HV Current

FREE FREE currentVoltage Temperature

Histograms MIP peak position; MIP peak width; Pedestal position

Rates Hardware rates; Software rates

Now moving to Performance tests

Page 12: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 12

ACD Performance tests at GoddardACD Performance tests at Goddard

Date of Performance Test

Description of Mechanical/Environmental Test preceding the Performance Test

Performance Test temperature and pressure

Performance Test name or number

07/10/2005 After completion ACD integration Reference

07/13/2005 After Z-axis vibration along OZ Post-Z

07/16/2005 After completion all vibration tests Post-vib

07/21/2005 Pre-thermal tests after completion all mechanical tests

Ambient, normal pressure Pre-thermal

07/24/2005 After hot survival Ambient, vacuum 1

07/26/2005 During max cold operational -25C, vacuum 2

07/27/2005 During max hot operational +35C, vacuum 3

07/28/2005 During max cold operational -25C, vacuum 4

07/29/2005 During max hot operational +35C, vacuum 5

07/29/2005 During max cold operational -25C, vacuum 6

07/31/2005 During max hot operational +35C, vacuum 7A

08/02/2005 During max cold operational -25C, vacuum 8

08/03/2005 At expected operational 0C, vacuum 9

08/04/2005 Ambient Ambient, vacuum 10

08/05/2005 Ambient Ambient, normal pressure 11

List of Performance tests at Goddard, summer 2005

Page 13: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 13

Test ResultsTest Results

Test 11 and Reference

0

5

10

15

20

25

30

Mean = 1.2 Percent

MIP peak position – difference between test 11 (after completion of all tests at GSFC) and reference. We accept mip peak variation by ±10% - looks good

Thermal variation: mip peak position difference between -25C and reference (ambient, 23C). Signals increase by 0.8-0.9%/degree C, exactly as we measured two years ago during ACD design

Run 2 to Reference

0

5

10

15

20

25

Mean = 36 Percent

Page 14: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 14

Test Results ( cont.)Test Results ( cont.)

Run 5 (+35C) to Reference

0

5

10

15

20

25

30

35

-20

-18

-16

-14

-12

-10 -8 -6 -4 -2 0 2 4

Mor

e

Mean = -7.8 percent

Again mip peak position thermal variation – now at increased temperature (+35C), or 12C higher, caused ~10% of mip peak position decrease – same 0.8-0.9%/degree C

Rough estimate of temperature monitoring in flight: we want to set VETO thresholds (in off-line analysis, where it has to be more precise) with the precision of better than 0.05 mip. This corresponds to a maximum 7C temperature change, and to the requirement that the temperature stability has to be monitored with 5C precision to maintain 0.05 mip VETO (off-line) threshold stability

Page 15: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 15

Pedestal Thermal variationPedestal Thermal variation

Pedestal Thermal Variation

0

5

10

15

20

25

30

Thermal Variation coefficient, ADC bin/degree C

We found that pedestals stay stable (within 2-3 ADC counts) over long time (~ 3 months) if no external changes are made

Pedestals react differently on temperature change:

Again estimate of temperature stability in flight: similar to mip peak position estimate. Assuming we need 0.05 mip peak position knowledge, this corresponds to a minimum of 20 ADC bins. For the worst channels with largest pedestal thermal variation coefficients, this corresponds to ~10C temperature monitoring accuracy. This is a weaker requirement than for mip peak position (5C).

Page 16: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 16

Veto threshold thermal behaviorVeto threshold thermal behavior

We conducted extensive analysis of VETO threshold behavior with temperature change. Results are placed in large spreadsheet and can be available by request.

Conclusion for the temperature monitoring – re-calibration (use of different VETO setting matrix) is needed if temperature changes by more than 8-10C

Combining all thermal tests: ACD Calibration parameters have to be created for every 10C temperature

range

Page 17: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 17

Moving to SLACMoving to SLAC

ACD passed pre-ship review and was shipped to SLAC in the middle of August 2005

ACD post-delivery tests at SLAC demonstrated excellent stability of mip peak positions and pedestals position

Now we are moving to ACD tests being a part of LAT

Pedestals Difference mean and Post-delivery

0

5

10

15

20

25

Bin

Mip peak position difference: Post-delivery and reference

010

203040

5060

-14

-10 -6 -2 2 6 10 14

Difference, %

Page 18: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 18

MIP Peak position monitoringMIP Peak position monitoring

During ACD standalone tests we used TrigOps test to determine mip peak position for every tile. ACD trigger was used for triggering, which allowed about ±30 degrees of incident angle variation. This overestimates mip peak position due to presence of large particle paths in the tile

Use of the tracking information allows to select quasi-normal incidence events and makes mip peak position determination be independent on the test conditions (triggering and incident flux). But it moves mip peak position on PHA histogram to the left and creates disconnection in mip peak position monitoring

Scheme of mip peak position monitoring

Initial ACD tests after integration (June 2005)

Mip peak position

reference file 1 created (MPRF1)

ACD Mechanical and Environmental

tests at GSFC – comparison with

MPRF1

After-Delivery and ACD CPT

tests 12/30/05Comparison with

MPRF1

ACD Tests with LAT – B2/B30 runs on

01/16/06Use quasi-normal incidence events.

Create new MPRF2

Use new MPRF2 in all later tests. Correct it if

needed

Use ACD Trigger Use L1T and quasi-normal incidence events

Assum

e ACD

Perfo

rman

ce

Did n

ot chan

ge

Page 19: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 19

MIP Peak position monitoring (cont.)MIP Peak position monitoring (cont.)

Now only with using L1T trigger (3-in-a-row) and selection of quasi-normal incidence events:

Mip peak position is determined very well for the top tiles because of many of events cross ACD tiles under quasi-normal angles

Calibration of side tiles is not so obvious (especially 3-rd row tiles) because of small fraction of events crossing side tiles under quasi-normal angles

Side tiles: There is a possibility of correcting pulse-heights by the particle path length in a tile. I’d like to avoid using this approach for large angles because of seemingly mip peak position underestimate with this technique for large angles. Eric Charles will discuss path length correction for large angles

Side tiles calibration in flight: Assuming LAT trigger with engine 9 (leaking protons), running with 256 prescale, we will need about 150 hours of total running time to get enough statistics to calibrate side tiles, or 30 minutes without a prescale

Page 20: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 20

Tiles Light YieldTiles Light Yield

• Light Yield for all ACD Tiles was measured in the laboratory before ACD integration

• Light Yield was measured directly for 3 top tiles (6 PMTs, or channels) and propagated to all other tiles:

First the average ADC sensitivity Afl was measured using directly measured light yield LYi for 6 channels:

where Pi and Gi are correspondingly mip peak position and PMT gain for i-channel

Light Yield LY for every channel was calculated according to:

6

1 ,6

1

i flii

ifl GLY

PA

flfl GA

PLY

Page 21: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 21

Tiles Light YieldTiles Light Yield

Now we determined Light Yield for every tile, using SVAC runs at SLAC:

• Using Light Yield determined directly for each of top tiles (50 PMTs, or channels, see Luis Reyes talk for details), we again determined ADC sensitivity A

• Using determined A, we calculated Light Yield LY for every ACD channel, including that were used for A determination (top tiles)

Flight Light Yield

0

5

10

15

20

25

30

Number of Photoelectrons

LY Difference between SVAC and GSFC

0

5

10

15

20

25

LY Difference, p.e.

LY for every ACD channel (PMT)

Average = 22.2 p.e.

Difference between LY measured at Goddard, and measured at SLAC (0.8±1.4 p.e.) Two independent measurements; data analyzed by two different people (Alex and Luis)

Page 22: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 22

Tiles Light Yield UniformityTiles Light Yield Uniformity

Light Yield across the tile - Example for Tile 22 (very central tile on the top)

X

Y Y

Xacross fibers

along fibersalong fibers

across fibers

Edge effect <10% at

3cm

PMT side

PMT side

? Still <20%

PMT 0 PMT 1

Page 23: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 23

Tiles Light Yield Uniformity (cont.)Tiles Light Yield Uniformity (cont.)

Light Yield across the tile - Example for Tile 2 (bent tile on the top)

Tile bending area

X X

Y Y

Across fibers Across fibers

Along fibers Along fibers

Slight attenuation in fibers

Page 24: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 24

Tile Light collection – Edge effectTile Light collection – Edge effect

Edge effect – light collection reduction toward the tile edge

All tiles were checked on the light collection uniformity (tomography)

We required the light yield at the tile edge to be not less than 0.7 of that average, with starting decrease not far than 3 cm from the tile edge)

We also required that light collection variation across the tile to be within ±10% of its average

I am continuing checking tiles light yield uniformity; so far all checked tiles met and exceeded these requirements

Page 25: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 25

RibbonsRibbons

Scintillating Fiber Ribbons cover the gaps between tiles in order to provide detection of the particles which sneak through that gap

There are 8 ribbons in ACD – 4 run along X-axis, and 4 – along Y-axis

All ribbons go from one side PMT to the opposite side PMT, which is ~ 3 meters. Thus every ribbon is viewed by PMT at both ends.

Y-ribbon covers gaps between tiles on the top and on +y and –Y sides; X-ribbons cover gaps on +X and –X sides

Ribbons provide “per-design” ~ 4 photoelectrons from the event crossing ribbon in the center. Light from any other point of ribbon hit is larger for the PMT which is closer to the hit. Opposite side PMT is redundant in this case. Signals from both ribbon PMTs are Or-ed with the detection threshold of 1 – 1.5 p.e. This corresponds to 30-80 ADC counts depending on PMT

Due to the strong light attenuation in a ribbon (λ~1.2m), its detection efficiency strongly depends on the hit position.

Page 26: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 26

Ribbons TestsRibbons Tests

Light Yield along the ribbon 601 - example

PMT 1PMT 0

Lig

ht

yiel

d i

n p

ho

toel

ectr

on

s

Y Y

Z Z

Z Z

Top Top

Side Side

Side Side

Light Yield overestimated

along sides due to off-angle

paths

Ribbon part

under tile bent

Center of the ribbon

λ~110cm

Z=0 corresponds to

the

grid (b

ottom of A

CD)

Page 27: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 27

Ribbons Tests (cont.)Ribbons Tests (cont.)

Direct determination of ribbons light yield: from B2/B30 ground muon runs

Straight muon selection criteria (see Luis Reyes talk) were applied to the area of 10cm across ribbon by 20cm along ribbon

Example for the center of ribbon 602:

Fraction of events detected only by tiles with threshold 0.3 mip – 0.99

Fraction of events detected by:

Ribbon threshold One ribbon PMT + tiles

Both ribbon PMT + tiles

1 p.e. (40 counts) 0.9993 0.99966

1.5 p.e. 0.9987 0.99946

2 p.e. 0.9983 0.9993

In order to determine ribbon light yield this geometry was simulated assuming known tiles light yield. Obtained light yield value for this example was 4.8 p.e.

Page 28: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 28

Ribbon Tests (cont.)Ribbon Tests (cont.)

Ribbon PMT End Center End

500 0 11.1 7.5 4.8 2.0 2.6

1 2.7 3.2 5.3 12.0 9.0

501 0 10.7 7.9 4.8 1.7 2.8

1 2.2 2.6 4.4 11.4 7.8

502 0 1.3 1.6 3.0 8.5 5.7

1 11.9 7.1 4.0 1.1 2.0

503 0 2.3 2.7 4.5 10.0 8.4

1 11.4 7.7 4.4 1.8 2.4

600 0 10.1 2.8 5.8 3.0

1 1.6 2.6 4.1 3.9 6.8

601 0 1.6 1.7 4.1 3.1 6.4

1 8.5 6.6 2.4 4.4 1.9

602 0 8.9 7.3 2.7 4.4 2.4

1 1.7 1.9 3.8 4.8 7.6

603 0 1.5 2.5 3.8 4.7 9.2

1 12.9 8.8 3.3 4.1 2.3

Efficiency was determined for every ribbon in 3 points. Light yield was determined by matching simulations and experimental results, and combined with that determined by the same way as for tiles

Black – as determined in GSFC

Red – current test

Page 29: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 29

Ribbons - conclusionsRibbons - conclusions

• Ribbons performance meet requirements to provide required ACD efficiency – will be shown later

• Obtained ribbons light yield values can be used in simulation model

• Suggested detection threshold for the ribbons is 1 p.e., which corresponds to from 30 to 80 ADC counts

Situation: Such a low threshold can create false Veto

Selecting given area (see slide 11) – no one ribbon yielded signal above 1 p.e. threshold. It was checked for many areas – same result. Detection threshold of 1 p.e. is safe

Page 30: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 30

Whole ACD Performance SimulationWhole ACD Performance Simulation

Whole ACD performance was simulated by Geant 3

Isotropic flux of incident particles was used

All gaps correspond to -20C (lowest expected operational temperature, worst case)

Light Yield for tiles and ribbons are taken as measured in SVAC tests

ACD has an overall efficiency of ≈0.99985 at VETO threshold of 0.3 mip and ribbons threshold of 1 p.e.

Failure of one FREE board – up to 18 tiles run with single PMT – still OK

Page 31: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 31

ConclusionConclusion

Now we have in our hands all needed ACD parameters

We have a clear scheme of ACD parameters monitoring

And, of course, there are always some new things are found. We need to understand their nature, but the main thing is to determine their impact on ACD required operation, and, if these new found effects do affect ACD operation, find out how to tolerate them

Page 32: GLAST LAT Project SVAC Workshop, February 27, 2006 ACD subsystem Alex Moiseev 1 GLAST Large Area Telescope: SVAC Workshop February 27-28, 2006 AntiCoincidence

GLAST LAT Project SVAC Workshop , February 27, 2006

ACD subsystem Alex Moiseev 32

Essentially none of the tests done on the ACD on the LAT have been done in a flight-like configuration:

1. The flight configuration planned only one of the two sets of VETO drivers enabled.

2. Testing has largely been done with both sets enabled.

3. Using both sets reduces the voltage on the ACD electronics by about 0.1 V, putting it close to the lower limit of the ACD operating range.

4. The ACD pedestals are voltage-dependent, so this lower voltage changes the operating points. Such changes differ in both magnitude and sign from channel to channel.

5. Neither the pre-installation calibrations (which were done with a different GASU) nor any calibrations that have been run in this non-standard configuration necessarily represent the ACD as it will be operated in flight.

6. A flight software change is needed in order to turn off one set of drivers (the power-on default is both sets on).

7. Once this change has been made, we need to re-run all the calibration scripts for the ACD and adjust operating parameters accordingly.

A Reminder about ACD CalibrationsA Reminder about ACD Calibrations