40
East End Crossing 1 East End Crossing (EEX) – USA Case submitted by Stanford University – Global Projects Center, João Vitor Dutra Santos Quick Facts Project Type: River crossing consisting of the reconstruction of a road interchange and the construction of one four-lane bridge and one tunnel Size and Scope: Approximately 51.8 lane miles (2.8 for the bridge, 21 for the Kentucky portion and 28 for the Indiana section), 2-3 north bound and 2-3 south bound lanes Delivery Mode: DBFOM, Public-Private Partnership Location: East End of Louisville, KY, near Prospect, and southern Indiana, near Utica Cost: $1.25 Billion USD: $750 million for the Kentucky approach, $200 million for the Indiana approach and $300 million for the East End Bridge (2013, including financing costs) Project Sponsors: Indiana Finance Authority (IFA) and Indiana Department of Transportation (INDOT) Project Developer: WVB East End Partners, Members: Walsh, VINCI and Bilfinger First Critical Event: 1996, INDOT and Kentucky Transportation Cabinet (KYTC) initiated the Ohio River Major Investment Study to address future travel across the Ohio River, near Louisville Construction Start: May 28, 2013 Construction End: Expected for October 2016 Key Features: The East End Crossing is part of the bi-state Ohio River Bridges Project, for which both Kentucky and Indiana are responsible. While the latter selected a DBFOM, P3 delivery mode for the East End corridor, Kentucky chose a more traditional design-bid-build process for the other part of the project, the Downtown Crossing

Global Projects Center - East End Crossing

Embed Size (px)

Citation preview

Page 1: Global Projects Center - East End Crossing

East  End  Crossing      

1  

East End Crossing (EEX) – USA

Case submitted by Stanford University – Global Projects Center, João Vitor Dutra Santos

Quick Facts

• Project Type: River crossing consisting of the reconstruction of a road

interchange and the construction of one four-lane bridge and one tunnel

• Size and Scope: Approximately 51.8 lane miles (2.8 for the bridge, 21 for the

Kentucky portion and 28 for the Indiana section), 2-3 north bound and 2-3 south

bound lanes

• Delivery Mode: DBFOM, Public-Private Partnership

• Location: East End of Louisville, KY, near Prospect, and southern Indiana, near

Utica

• Cost: $1.25 Billion USD: $750 million for the Kentucky approach, $200 million

for the Indiana approach and $300 million for the East End Bridge (2013,

including financing costs)

• Project Sponsors: Indiana Finance Authority (IFA) and Indiana Department of

Transportation (INDOT)

• Project Developer: WVB East End Partners, Members: Walsh, VINCI and

Bilfinger

• First Critical Event: 1996, INDOT and Kentucky Transportation Cabinet

(KYTC) initiated the Ohio River Major Investment Study to address future travel

across the Ohio River, near Louisville

• Construction Start: May 28, 2013

• Construction End: Expected for October 2016

• Key Features: The East End Crossing is part of the bi-state Ohio River Bridges

Project, for which both Kentucky and Indiana are responsible. While the latter

selected a DBFOM, P3 delivery mode for the East End corridor, Kentucky chose

a more traditional design-bid-build process for the other part of the project, the

Downtown Crossing

Page 2: Global Projects Center - East End Crossing

East  End  Crossing      

2  

Figure 1: Border of Kentucky and Indiana, with the East End Crossing Project

highlighted. (http://eastendcrossing.com/bridge-maps/)

Figure 2: Various fragments of the East End Crossing (http://eastendcrossing.com/projec

t-overview/)

Page 3: Global Projects Center - East End Crossing

East  End  Crossing      

3  

Project Description

Overview

The East End Crossing consists of a $1.25 billion project that connects Clark County,

Indiana, to Jefferson County, Kentucky, approximately eight miles northeast of

Louisville. Along with the Downtown Crossing (a $1.45 Billion USD project featuring a

new six-lane bridge and a reconfigured junction of the Interstate 65, connecting

downtown Louisville to Jeffersonville, Indiana), the East End Crossing is part of the Ohio

River Bridges Project, an infrastructure plan to increase cross-river mobility and alleviate

traffic congestion. The East End Bridge will feature two convex diamond towers with

two lanes in each direction. In Kentucky, a new four-lane section will be added to the

Gene Snyder Freeway (also known as I-265 or KY 841), linking its termination at U.S.

42 to the bridge. Additionally, there will be a remodeled interchange at U.S. 42 and a

tunnel beneath this highway. The Indiana role will be to extend the Lee Hamilton

Highway (SR 265) from SR 62 to the bridge. A new interchange will be built at Old

Salem Road, and an existing interchange at I-265/IN 62 will be reconstructed.

The project’s delivery mode is a DBFOM Public-Private Partnership with the Indiana

Finance Authority (IFA). WVB East End Partners, a consortium of Walsh Investors,

VINCI Concessions and Bilfinger Project Investments, was awarded the concession, with

a four-year construction period (from 2013 to 2016) and a 35-year operations term. The

concessionaire will be responsible for the operations and maintenance of the East End

Crossing and the bridge will be tolled, with toll collection administered by a different

concessionaire, chosen by the State of Indiana. IFA will make availability payments over

the concession term to WVB in exchange for providing and operating the asset. Funding

for these payments to the concessionaire will come from tolls. During construction, a

combination of state and federal funds, such as fuel taxes, will be used to make milestone

payments, with contributions from the state of Indiana and also from Kentucky.

Page 4: Global Projects Center - East End Crossing

East  End  Crossing      

4  

Indiana Finance Authority (IFA) Background

IFA is the entity responsible for providing financial solutions and overseeing debt

issuance in the State of Indiana. It was established in May 15, 2005, after the

consolidation of multiple financial entities, among which was the Indiana Transportation

Finance Authority (see Appendix A). According to the Authority, the merger was “in

order to provide economic efficiencies and management synergies and enable the State of

Indiana to communicate as one voice with the various participants in the financial

market”. IFA has over $7.4 billion in assets and owns more than 20 properties throughout

Indiana.

Objective

The East End Crossing has the purposes of expanding cross-river mobility, relieving

transit congestions and connecting highways previously separated by the Ohio River.

Each day, approximately 225,000 vehicles cross the three bridges connecting Louisville

and southern Indiana (125,000 cross the seven-lane Kennedy Memorial Bridge, 75,000

travel through the six-lane Sherman Minton Bridge and 25,000 are using the Clark

Memorial Bridge on a daily basis), and the need for a new one was imminent since the

early studies, dated back to 19961. On September 9, 2011, the Sherman Minton Bridge

was closed for an undetermined length of time, after the discovery of cracks in its

supporting beams. The bridge remained closed for almost six months, exacerbating the

demand for construction of the Ohio River Bridges Project. By facilitating the movement

of people and goods, the project aims to stimulate the economy of both Kentucky and

Indiana. The easy access to downtown Jeffersonville is expected to create a new business

area and lead to the creation of over 11,000 new jobs in Indiana alone over the life of the

project.

For procurement purposes, the Ohio River Bridges Project was divided into two

components, Downtown Crossing and East End Crossing. Each state took responsibility

                                                                                                               1  Informal   discussions   on   the   need   for   new   corridors   date   back   to   as   early   as   the   1960s,   after   the  conclusion  of  the  Kennedy  Memorial  Bridge.  

Page 5: Global Projects Center - East End Crossing

East  End  Crossing      

5  

for one portion as a way to share the duty. Before the start of construction, many cost

increases required that Indiana, the main party responsible for the East End Crossing

Project, seek alternative funding sources. While Kentucky chose a traditional design-

build contract for the Downtown Crossing, Indiana opted for an availability payment-

based public-private partnership2. Since 2006, the Indiana General Assembly granted the

Indiana Finance Authority permission to enter into P3s. The East End Crossing is the

second project of its kind administered by the IFA, the first one being the 2006 lease of

the Indiana Toll Road. Despite financial difficulty after drops in traffic during the Great

Recession and a possible change in management, the Toll Road lease contract still have

65 years left and is likely to generate future profits, because of recent increases in heavy

truck traffic (Puentes, R. 2014).

Approach

As the need for new alternatives to cross the Ohio River and connect KY and IN became

apparent, Indiana Department of Transportation and Kentucky Transportation Cabinet

developed an Environmental Impact Statement (EIS) from 2001 to 2003 and originated

the idea for the Ohio River Bridges Project. In 2003, INDOT and KYTC initiated the

work on the design phase and produced the first cost estimate. Due to future price

increases, traditional Federal and State transportation funding sources would not be

enough to finance the whole project, and even with some design modifications, the

project was not deemed financially feasible. As an alternative solution, KY and IN

endorsed a plan to use tolling income to complement the available state and federal

infrastructure budget. For the financing of the East End Crossing, Indiana opted for a

public-private partnership, because according to state estimates this approach would

reduce costs and get the project concluded within five years. During an eight-month

procurement process, a Request for Qualifications (RFQ) was issued to concessionaires

interested in the project, and six responses were received. The pre-selected ones were

invited by IFA and INDOT to propose. A draft Request for Proposal (RFP) was then

                                                                                                               2  A  Memorandum  of  Understanding  signed  by  KY  and  IN  defined  that  each  state  would  be  responsible  for  one  of  the  two  crossings.  

Page 6: Global Projects Center - East End Crossing

East  End  Crossing      

6  

given to four short-listed teams. Finally, WVB East End Partners was selected as the

winning proposer, with a construction cost of $763 million, 23% less than the IFA’s

estimates.

After the approval of the Ohio River Bridges Project and the determination of a PPP

delivery method for the East End Crossing, the discussion regarding tolling options

initiated. According to research from both Kentucky and Indiana, the best approach

would be to implement an Open Road Tolling (ORT) system, through which toll

collection is done using an electronic system instead of toll booths. Therefore, there

would be two payment alternatives3:

• Transponders: the gadgets should be installed in each car and will charge the

driver whenever he/she crosses the bridge.

• Video Toll: for pre-registered vehicles, money will be directly drawn from a

prepaid account, whereas non-registered ones will have their license plate

registered by camera and the bill sent to the owner’s address.

Due to the fact that no crossing between Kentucky and Indiana has been tolled for

decades, there was a growing concern regarding the adverse results of this expense on

environmental justice (EJ) populations. In order to avoid a disproportionately high

impact, the Indiana Department of Transportation (INDOT) will adopt a Tolling

Mitigation Plan, focused on low-income and minority groups. To further assess the

effects on EJ communities, a draft of the Economic Effects Assessment went public on

June 27, 2013, succeeded by three public opinion surveys and open house meetings held

in the end of July. Enrollment in the mitigation program would give to its members a

dollar amount in the form of state income tax credit, and be based on income, area of

residence and Federal Earned Income Tax Credit (FEITC), according to the following

table:

                                                                                                               3  Financial   and   enforcement   provisions   regarding   the   tolling   system   are   determined   by   a   bi-­‐state  Tolling  Body  and  may  be  altered  before  implementation  starts  according  to  future  decisions.  

Page 7: Global Projects Center - East End Crossing

East  End  Crossing      

7  

Children Maximum Income (Earned or Gross Adjusted) Single Filing Joint Filing

3 or more $43,998 $49,078 2 $40,964 $46,044 1 $36,052 $41,132 0 $13,660 $18,740

Table 1: Income Limits for FEITC in 2011 (http://kyinbridges.com/wp-content/uploads/ Appendix-B_CAI-Admin-Cost-Estimatess.pdf; source: IRS.gov)

The research with EJ populations concluded that tolling would not have a significant

effect on their lives. Only 30% claimed that tolling would make them change their

commuting routes, and 65% declared tolling would not have any effect on their lifestyle.

WVB East End Partners

The East End Crossing concession was awarded to WVB East End Partners, a consortium

of Walsh Investors LLC, the construction branch of Chicago-based The Walsh Group,

VINCI Concessions and Bilfinger Project Investments, the PPP division of Bilfinger SE.

Walsh is the fourth largest highway contractor in the U.S., according to Engineering

News-Record, and delivered to INDOT the Super 70 highway, located in Indianapolis, in

the end of 2007. VINCI is a French operating company focused on PPPs with a network

of highways in excess of 4,000 km. Bilfinger is a 130-year old multinational company

that employs 70,000 people and has a strong presence on the transportation infrastructure

sector. On November 16, 2012, IFA selected WVB as the preferred bidder. According to

the proposal, the East End Crossing would be completed in October 2016, 8 months prior

to the deadline, and at a cost of $763 Million. Without implementing substantive scope

changes to the project, WVB suggested a price that was 23% less than IFA’s 2012 cost

estimates.

The concession contract covers the design, build, financing, operation, and maintenance

of the East End Crossing for 35 years. The East End Bridge will be tolled, with toll

collection managed by the State of Indiana. WVB compensation will be composed of

Page 8: Global Projects Center - East End Crossing

East  End  Crossing      

8  

milestone payments (during construction) from the infrastructure budget and availability

payments (along the operations phase) supported by tolling income (see Appendix B).

Location

Every day, more than 225,000 vehicles cross the Ohio River in the Louisville area, the

majority of which travel over the Kennedy Memorial Bridge or the Sherman Minton

Bridge. To maintain cross-river mobility and allow traffic increases without causing

congestions, the construction of new bridges across the Ohio River was suggested in the

Ohio River Major Investment Study (ORMIS), in 1997. On July 2002, the Governors of

Kentucky and Indiana announced plans for two bridges, one in downtown Louisville and

another in the east end of the city. The Downtown Crossing would be adjacent to the

Kennedy Memorial Bridge in Louisville, and the East End Bridge location would be 8

miles upstream, connecting the east end of Louisville, near Prospect, to southern Indiana,

near Utica.

The East End Tunnel will extend under US 42 and the historic Drumanard Estate, in

Kentucky. A partial interchange will also be constructed in the area to allow northbound

I-265 traffic to exit onto US 42. In Indiana, the project will follow the SR 265, with the

addition of a new interchange at Old Salem Road and the reconstruction of the SR

265/SR 62 interchange.

Figure 3: East End Crossing (http://transportation.ky.gov/SASHTO/Louisville%20South

ern%20Indiana%20Ohio%20River%20Bridges%20Project.pdf; pg. 8)

Page 9: Global Projects Center - East End Crossing

East  End  Crossing      

9  

Internal Project Characteristics

Finance and Funding

The East End Crossing delivery mode is a PPP, sponsored by the IFA. Based upon the

PPP agreement, the State of Indiana will partner with a concessionaire to design, build,

finance, as well as operate and maintain portions of the East End Crossing. The

concessionaire will be responsible for lifecycle work relating to pavement surfaces, new

bridges and existing structures, as well as patrolling, winter maintenance and roadway

repair. The exclusions will be the operation of the Electronic Toll Collection System,

conducted by a toll system provider, Kapsch TrafficCom, and the maintenance of the

Drumanard Tunnel, for which the Commonwealth of Kentucky will also be accountable.

Milestone payments will be made to the winning team for the completion of specific

sections of the project. The IFA will be contractually obligated to make these payments

accordingly, employing a combination of state and federal funds (see Appendix B).

Availability payments will not be outstanding until substantial completion. To support its

obligations, the concessionaire will guarantee private sector financing, including both

private equity and debt. WVB will use debt financing in the form of Private Activity

Bonds (PABs), both short and long term, and each of the three owners of the

concessionaire will contribute with an equal proportion of equity. The debt-equity ratio is

expected to be 89:11. Moreover, to secure availability payments under the concession

agreement, Indiana will commit to a share of toll revenues from the project.

The Indiana Department of Transportation (INDOT) has committed a total of $570

Million USD for the East End Crossing in federal and conventional state funds through

2018, as explained in the following table:

Page 10: Global Projects Center - East End Crossing

East  End  Crossing      

10  

Budget ($YOE

– million) 2012 2013 2014 2015 2016 2017 2018 Total

State Funding 15,724 24,365 24,941 18,709 16,498 16,861 10,800 127,898

Federal Formula

Funding 26,885 57,600 66,800 74,835 65,993 67,443 43,200 402,756

Federal

Discretionary

Funding

31,500 7,900 0 0 0 0 0 39,400

Total 74,109 89,865 91,741 93,544 82,491 84,304 54,000 570,054

Table 2: Estimated Indiana and Federal conventional funding for the East End Crossing

(http://updates.kyinbridges.com/wp-content/uploads/2012/08/2012-08-01-Initial-Financia

l-Plan-ORBP-signed.pdf; pg. 24)

Considering the expected project cost, the approximate values of the funding sources

used by the State of Indiana will be $392 million for milestone payments (both state and

federal, including a $162 million TIFIA loan), as well as $201 million in other state and

federal funding. $489 million in Milestone Private Activity Bonds (Series A), and $19

million in Long-term Private Activity Bonds (Series B) will be underwritten by private

banks such as Bank of America Merrill Lynch, Goldman Sachs, J.P. Morgan and RBC.

The Commonwealth of Kentucky also contributed to financing the East End Crossing

project, providing $94.2 million in state and federal funding. $78 million will be the

equity contribution of WVB and up to $45 million should be available in a reserve

account for unforeseen events. All funding sources are described in the following pie

chart:

Page 11: Global Projects Center - East End Crossing

East  End  Crossing      

11  

The final financing strategy will be subject to future market circumstances. Kentucky

and Indiana have developed preliminary financing plans that depend on the delivery

method chosen by each state. It may vary according to additional finance approaches,

such as borrowing through the Transportation Infrastructure Finance and Innovation Act

(TIFIA), which provides credit assistance to significant surface transportation projects.

Contracts

Over the course of the year 2011, the Louisville and Southern Indiana Bridges Authority

(LASIBA), the entity responsible for evaluating delivery options, identified the most

viable models. The bi-state organization has a board of 14 directors, 7 from each state. It

was originally created as a contracting and managing agency for the whole project;

however, the decision to divide the project in two portions reduced LASIBA to an

advising entity. For the East End Crossing, the selected approach was a PPP concession.

On March 9, 2012, IFA and INDOT issued a Request for Qualifications to teams

interested in designing, building, financing, operating and maintaining the project. After

pre-selecting four teams and issuing a draft Request for Proposal for each of them, the

final decision was announced on November 16, 2012. WVB East End Partners, a three-

Funding  Sources  

Milestone  Payments  from  IN  

Other  IN  State  and  Federal  Funding  

Milestone  Private  Activity  Bonds  (Series  A)  

Long-­‐Term  Private  Activity  Bonds  (Series  B)  

KY  State  and  Federal  Funding  

WVB  East  End  Crossing  Equity  Contribution  

Page 12: Global Projects Center - East End Crossing

East  End  Crossing      

12  

entity consortium focusing on financing, designing and constructing major highway and

bridges project, was named the preferred bidder for a 35-year contract, and will act as the

special purpose vehicle. The SPV selected Walsh and VINCI to be the lead contractors,

who made a design agreement with Jacobs Engineering Group to be the lead engineering

firm.

Since the Ohio River Bridges Project is a two-state development, there is also a need for

negotiating the roles and responsibilities of Kentucky and Indiana in the overall project,

especially concerning the sharing of tolling revenues and the financial approach

implemented by each party. Kentucky is in charge of financing and constructing the

Downtown Crossing, whereas Indiana is responsible for the upriver East End Crossing. In

general, the agreement between the states comprises budgeting matters, environmental

and workforce commitments, operations and maintenance, as well as toll collection and

enforcement.

Technical Elements

To finance the Ohio River Bridges Project, both states used alternative funding sources,

such as tolling. In order to gain legislative authority to impose tolls, Kentucky and

Indiana amended statutes and entered into an agreement with the Federal Highway

Administration. As soon as it is open to traffic, in the end of 2016, the East End Bridge

will be ready to be tolled, even though a grace period may be implemented to guarantee

that drivers will get used to dealing with the new system. Tolls will be operated in

accordance with a policy based on the use of high speed, electronic non-stop tolling, and

the project will be Kentucky’s first endeavor in electronic tolling.

Due to the fact that operations will start no sooner than 2016, many decisions regarding

tolling policies have not been discussed yet. The states selected in February 2015 a toll

services operator (eTrans KY Inc., of Louisville) to oversee the work of the tolling

provider, and a revenue control manager (KPMG LLP). A procedure to include more

Page 13: Global Projects Center - East End Crossing

East  End  Crossing      

13  

details about toll rates, start date, charge methods and tolling account maintenance is

currently under development.

Initial toll rates for three classifications of vehicles have been approved, using three

different methods. In the case of transponder, motorists will install the equipment in their

vehicles and set up a pre-paid account from which toll fees will be automatically

withdrawn every time a vehicle crosses the gantry. Drivers will be able to choose from a

national transponder that operates with other tolling systems or a local one, compatible

only with the Ohio River Bridges tolls. Registered vehicles will likewise require a pre-

paid account; however, payment deduction will occur when video monitors capture the

license plate. Finally, for non-registered vehicles, it is likely that the license plate will be

video-captured and the bill sent to the driver’s matching address4.

The initial estimates for tolling prices are shown on Table 3. The tolling body will discuss

more comprehensive criteria for frequent commuters and truck categorization in future

meetings. To be even with inflation, toll rates will be annually adjusted by 2.5% or

according to the Consumer Price Index, whichever is greater. Increases will normally

take effect on July 1st.

Toll Rates Passenger

Vehicle

Medium

Trucks

Heavy

Trucks

Frequent Commuter Discount $1.00 N/A N/A

Transponder $2.00 $5.00 $10.00

Registered Video (Video

License Capture) $3.00 $6.00 $11.00

Non-Registered Vehicle

(Video License Capture) $4.00 $7.00 $12.00

Table 3: Expected values for initial toll rates (http://eastendcrossing.com/tolls/)                                                                                                                4  Tolling  authorities  and  contractors  will  still  decide  final  enforcement  policies.  

Page 14: Global Projects Center - East End Crossing

East  End  Crossing      

14  

Risk and Risk Mitigation

With construction costs 23% below estimates, a quick 8-month procurement period and

strong political support, the process that culminated in the East End Crossing has shown

multiple examples of success so far. Nonetheless, a project valued at more than $1 billion

dollars has multiple risks associated with its scope. One of the most critical lies in the

delivery mode. The first PPP in the State of Indiana, the Indiana Toll Road, filed for a

pre-packaged Chapter 11 bankruptcy in 2014, 8 years after the concessionaire was

awarded the right to operate the road for 75 years. Even after taking precautionary

measures to avoid financial restructuring, unexpectedly low traffic volumes can affect the

success of a tolled highway project.

The funding amount available for the East End Crossing will also be vulnerable to risks

that cannot be fully anticipated. The states assumed that future state and federal funds

would be ready for use within the time frame of the budget planning cycles. Although a

default is unlikely to occur, there is risk in these projections. The mitigation strategy

chosen in Kentucky was to include the project in the current biennial budget and

Highway Plan at the funding levels. Indiana, on the other hand, added the project to

INDOT’s internal budgeting and financial control systems, and IFA will detail the annual

amount of funds to meet payment requirements.

Moreover, forecasts for traffic and revenues are subject to change, even after careful

reports and sensitivity analysis are performed. If they are less than the expected values,

the project’s ability to repay its debt may be in jeopardy. In the event tolls are insufficient

to cover the agreement obligations, the states will provide additional funds to supplement

their share of toll revenues.

Access to capital markets for bonding toll revenues, as well as the availability of a TIFIA

loan, can also be hampered by economic conditions. Market volatility can limit access or

increase financing costs. For the East End Crossing, the private sector is the financing

Page 15: Global Projects Center - East End Crossing

East  End  Crossing      

15  

provider, and has a demonstrated track record of securing bank financing for concessions

projects.

Additionally, taxpayers’ dissatisfaction with the project could be a threat to the East End

Crossing. Even though most of the population approves the construction of a new

corridor, few locals are outraged with some of its aspects, such as the tunnel. They argue

that spending hundreds of millions to preserve one historic property is an unreasonable

cash disbursement, and filed lawsuits with the hope to prevent it from being built. Despite

isolated examples of discontentment, acceptance regarding the project has normally been

widespread.

Inflation is another source of risk, as the rate for highway construction has been very

volatile over the past several years. In the case of contingency, the considered amount

may be insufficient to compensate every unexpected cost. A PPP concession helps

transfer much of these two risks to the private sector. Regarding the project schedule,

delays in the receipt of approvals, unanticipated site conditions and lack of coordination

can defer the East End Crossing agenda. According to the Initial Financial Plan (INDOT

& KYTC, 2012), extensive effort was put into the acquisition of permits and in the

geotechnical analysis to try to prevent delays from happening.

Finally, moving forward with a toll mitigation program for EJ populations demands

further investigation of potential risks. There is no standard for income-eligibility

program between KY and IN, therefore both would have to plan, implement and operate

a mutual and fair program. Also, litigation challenges may pose a legal concern, as

implementing a toll discount program may include litigation costs to defend it. Data

security should be of interest as well, mainly because a mitigation program would

demand that those in charge handle income data with security and confidentiality,

according to IRS standards.

Page 16: Global Projects Center - East End Crossing

East  End  Crossing      

16  

Risk Category Assignment Level of Severity

Construction WVB Low

Design WVB Low

Enforcement WVB Low

Environmental Impact Public Moderate

Finance WVB Moderate

Land Acquisition Public Low

Maintenance WVB Low

Market WVB Moderate

Operations WVB Moderate

Performance Shared High

Political Shared Moderate

Table 4: Risk assessment

Page 17: Global Projects Center - East End Crossing

East  End  Crossing      

17  

External Project Characteristics

Economic Conditions

The last bridges constructed in the greater Louisville area to connect KY and IN were the

Kennedy Memorial and the Sherman Minton, back in the 1960s. Since then, the

population of the two states grew nearly 40 percent5, and so did traffic congestions. In

order to improve cross-river mobility and avoid safety hazards, the ORMIS, an

investment study, was developed during the 1990s. Its final report suggested the need for

two bridges across the Ohio River, one near the Kennedy Bridge in downtown Louisville

and another 8 miles upstream.

The Ohio River Bridges Project is expected to positively affect the region’s economy by

creating jobs and increasing the level of salaries. The impact on market access and

transportation efficiency is anticipated to surpass the adverse consequences of tolling on

the household income. Indiana alone is expected to gain over eleven thousand direct new

jobs over the project’s life, mainly because of the possibility to create a new business

environment in downtown Jeffersonville, IN. As a consequence, government revenue

should increase, and the surplus can be used to improve public services.

Legal / Legislative Conditions

In January 2011, the Mayor of Louisville and the Governors of Kentucky and Indiana

announced a proposal to investigate design options that could reduce the cost of the Ohio

River Bridges Project and speed construction. After the evaluation of multiple alternative

delivery options, a PPP approach to the East End Crossing was announced on December

29, 2011. On March 5th of the following year, the governors signed a memorandum of

understanding to honor their agreement and to define the roles and responsibilities of

each state. Four days later, IFA and INDOT issued a Request for Qualifications (RFQ)

directed towards concessionaires interested in designing, building and financing the East

End Crossing, as well as operating and maintaining portions thereof. On April 23rd,

                                                                                                               5  Data  from  the  U.S.  Census  Bureau.  

Page 18: Global Projects Center - East End Crossing

East  End  Crossing      

18  

Indiana authorities released a short list of the teams that would be invited to propose on

the project, and on May 2nd a draft RFP was handed to the four pre-selected teams.

The Ohio River Bridges Project is a bi-state proposal and requires legislative authority of

both parties to impose tolls and allow public-private partnerships. In order to authorize

tolling, Kentucky revised a legal document named Section 175B.030, and Indiana also

amended its tolling and P3 statutes in 2012. The latter state established itself as a national

example for leveraging private sector capital to finance, construct and maintain

transportation infrastructure projects. Indiana General Assembly approved legislation

over the last years endorsing IFA’s participation in public-private partnerships, such as

the Toll Road project in 2006. The aim has been to rapidly alleviate traffic congestions in

existing highways by taking advantage of the private sector expertise. In the middle of

2012, the Federal Highway Administration (FHWA) issued a revised Record of Decision

and accepted the toll agreement.

Social / Civic Conditions

Due to the East End Crossing location, various civic concerns emerged with the approval

of the project. The tunnel beneath the historic Drumanard Estate is arguably the most

controversial of them. The property, designed by prominent architects, is listed on the

National Register of Historic Places. Its landscaping is associated with Frederick Law

Olmstead, the creator of New York’s Central Park. Digging the 2000-foot long tunnel to

bypass the estate was the alternative with the least intense impact on the environment and

on historic places, but it will cost more than $130 million dollars to construct6. Many

taxpayers are upset about this forecasted cost, and there are formal requests to the

Kentucky Heritage Council that the Drumanard Estate lose its historical title, in a bid to

eliminate the tunnel and reduce the overall price of the project.

Considering that none of the Ohio River crossings near Louisville has been tolled for

decades, the impact of this expense on the population was also a source of social concern.

                                                                                                               6  Local  newspapers  say  that  the  final  cost  may  escalate  to  as  high  as  $300  million.  

Page 19: Global Projects Center - East End Crossing

East  End  Crossing      

19  

FHWA researched the effects on both EJ and non-EJ communities, and the results

demonstrated that the average individual cost for an EJ population car is likely to increase

by a greater percentage, when compared to a non-EJ population car. To gauge public

opinion, meetings have been promoted during development period, and surveys have

been conducted to better understand perspectives and inputs of EJ communities. These

studies focused on racial minorities and low-income residents, as well as on small

businesses that use vehicles to commute through the Ohio River on most days. By asking

those groups to indicate the burdens that may result from tolling, KYTC and INDOT

could understand usage patterns and perceptions around tolling and therefore identify

potential mitigation measures (such as toll subsidies, discounted rates and annual

reimbursement). Despite initial worries, surveys indicated that the impact caused by

tolling on EJ populations was less significant than EJ leaders previously forecasted, with

almost 65 percent of these individuals claiming that tolling would not alter their

lifestyles.

Table 4: Tolling impact on commuting behavior (http://kyinbridges.com/wp-

content/uploads/Appendix-E5_Qk4-Comparison-of-Surveys-IQS-Community-and-Leade

r-2.pdf; pg. 3)

Page 20: Global Projects Center - East End Crossing

East  End  Crossing      

20  

Political Conditions

In July 2002, the two governors of Kentucky and Indiana signed a historic agreement to

pay for the Ohio River Bridges Project. The contract was based on the ORMIS, released

in 1997, which indicated the need for two new river crossings, one in downtown and

another in the east end portion of Louisville. According to the 2003 Record of Decision

(ROD)7, the project was expected to have a year-of-expenditure cost of $2.5 billion.

However, in 2007, a more detailed financial plan escalated the cost to $4.1 billion, due

mainly to inflation. Traditional federal and state funding sources were initially proposed,

along with potential alternative approaches, such as tolling. In July 2010, LASIBA,

INDOT and KYTC submitted the formal financial demonstration document and

concluded that traditional revenue sources could not exceed $1.9 billion and, therefore,

were not enough to fund the Ohio River Bridges Project. In response to this $2.2 billion

shortfall, cost-saving modifications had to be made. By eliminating pedestrian and bike

paths, as well as reconstructing interchanges on the existing footprints instead of building

new ones, savings of over $1.0 billion could be applied. Moreover, preliminary estimates

suggested that tolling revenues would generate from $800 million to $1.2 billion in

funding capacity, deeming the project viable.

On December 29, 2011, Kentucky and Indiana reached consensus on a plan to finance

and construct the project. Responsible for the East End Crossing, the state of Indiana

chose a P3 as the delivery mode. The political conditions for this approach were

favorable, because the Indiana General Assembly had passed legislation over the last

several years authorizing IFA to take part in public-private partnerships. With the claim

that the private sector helps saving money from taxpayers by bringing new ideas into the

project, Indiana selected the winning concessionaire on November 16, 2012, after an

eight-month procurement process.

                                                                                                               7  ROD  is  used  to  document  the  decision  reached  by  FHWA  at  the  conclusion  of  the  process.  Issuance  of  ROD  allows  FHWA,   INDOT  and  KYTC   to  proceed  with   federally   funded  design,   construction  and  land  purchases  after  all  permits  have  been  obtained.  

Page 21: Global Projects Center - East End Crossing

East  End  Crossing      

21  

The protests against tolling and the construction of the East End Tunnel also demanded

political involvement. The intense opposition was due to the high cost of the structure

built to preserve a historic estate. A group named “Say NO to Bridge Tolls”, known for

holding informational sessions and promoting protests in opposition to tolling fees, has

been advocating to change the historic status of the property and to avoid the construction

of the tunnel, but did not meet much success. This community group campaigns for the

downsizing of the project and the veto of tolls, alleging that the fee will compromise the

effectiveness of the transportation system and limit job creations.

Environmental Conditions

So as to evaluate project alternatives in terms of their environmental impact, FHWA,

INDOT and KYTC started to prepare a primary version of the Environmental Impact

Statement (EIS) in 1998. By evaluating alternatives for improving cross-river mobility,

the document aimed to address elements such as traffic congestions, safety problems and

inadequate freeway rerouting. The Final Environmental Impact Statement (FEIS) was

developed in 2003, and later modified to be financially feasible, result in less impact and

become the selected alternative.

Quantitative Impacts

To

FEIS Selected

Alternative

FEIS Modified

Selected Alternative

Acres of prime farmland

converted 57 57

Section 4(f) Properties

used 8 8

Number of historic

districts impacted 10 10

Number of historic sites

impacted 24 23

Number of archeological 7 7

Page 22: Global Projects Center - East End Crossing

East  End  Crossing      

22  

sites impacted

Air Quality Impacts No violations, project

demonstrates conformity

No violations, project

demonstrates conformity

Number of impacted

Historic Properties 18 13

Acres of terrestrial

wildlife/habitat impacted 237.3 194.4

Acres of wetlands

impacted 13.28 9.68

Number of stream

crossings (including Ohio

River Project)

24 23

Number of floodplains

crossed 6 5

Total acres of

encroachment 178.35 80.03

Number of Owner/Tenant

Residential Unit

Relocations

65/15 55/15

Number of Business/Not-

for Profit Facility

Relocations

79/1 23/1

Number of Agricultural

Properties Impacted 18 18

Number of Community

Resources Relocations 0 0

Table 5: Summary of environmental impacts (http://www.in.gov/ifa/files/111110_01_SD

EIS_Exec_Summary.pdf; pg. S-21)

Page 23: Global Projects Center - East End Crossing

East  End  Crossing      

23  

In spite of the general acceptance towards the project, some individuals express strong

opposition to some of its components, such as the tolls and the financial impact it may

cause to commuters. A lawsuit was filed by two groups, River Fields and the National

Trust for Historic Preservation, against the FHWA in September 2009. It was an attempt

to veto the ROD for the Ohio River Bridges Project. Moreover, conflicting opinions have

been stated concerning whether to build one or two bridges, or even that they are both

badly needed and a light-rail option would be more appropriate.

A different concern relates to the “heat island” effect in Louisville. According to the

Urban Climate Lab at Georgia Tech, the city has the highest index of this phenomenon in

all the United States. Part of the explanation lies in the fact that the tree coverage is very

sparse in the metro area. Furthermore, the meteorological conditions of the Ohio River

Valley contribute to trap part of the heat within the city boundaries. The addition of over

400,000 tons of asphalt will increase an already intense effect and push the temperatures

in Louisville even higher.

Uncertainties

As in most of the large infrastructure developments, the general level of satisfaction with

the East End Crossing was uncertain. The construction work has been responsible for

traffic interruptions and lane restrictions. In order to inform local residents about the

current stage of the project, WVB and INDOT provided a newsroom section on the EEX

website. Weekly updates and traffic alerts are posted on the page, and its users can also

forward the news to a desired email address or cell phone. The website also features a

FAQ section about rock blasting, with the aim to tranquilize local residents in case their

houses shake slightly. Moreover, WVB sends relevant information to local newspapers

and radio stations, while INDOT provides a contact representative to answer questions

and concerns.

The selected design for the project was also a source of uncertainty. The proposal

featured on the 2003 FEIS had a cost estimate of $2.5 billion, but the 2007 FEIS Selected

Page 24: Global Projects Center - East End Crossing

East  End  Crossing      

24  

Alternative increased the year-of-expenditure cost to $4.1 billion, mainly because of

inflation and construction cost adjustments. To reduce costs, design adjustments and

additional revenue options, such as tolling, had to be identified and implemented. Despite

being financially feasible, this modified alternative was uncertain, especially concerning

toll acceptance. As a way to determine the impact of the fees on commuters, INDOT and

IFA held public meetings and conducted surveys. After analyzing the results, the

agencies proposed that a reduced fee is applied to EJ populations, as they would be the

social group most affected by tolls.

Additionally, the delivery method Indiana selected was of concern. The East End

Crossing is the second public-private partnership in the state, after the 2006 Indiana Toll

Road. Because of the Great Recession, this highway faced dramatic drops in traffic

volume, and did not have enough toll-paying vehicles to break even. Various viability

studies, such as the ORMIS, the updated Financial Plan and the SFEIS, endorse the Ohio

River Bridges’ success. However, uncertainty still exists, considering that meeting

projections depends not only on the project itself, but also on external economic and

social conditions.

Page 25: Global Projects Center - East End Crossing

East  End  Crossing      

25  

Case Conclusion

Current Operations

The East End Crossing is currently under construction. The work started in the beginning

of 2013, and conclusion is forecasted for the last quarter of 2016. The ongoing

construction activities are:

• Underground tunnel blasting near the intersection of US 42 and KY841

• Removal of existing concrete pavement, surface blasting and rock

excavation along KY 841 to prepare the grade for a new northbound

pavement

• Work on the upper portion of the two towers for the cable-stayed bridge

• Reconstruction of the SR 265/SR 62/Port Road interchange in Indiana

Figures 4 and 5: construction of the East End Bridge (www.eastendcrossing.com/east-

end-crossing-schedule-overview)

The upcoming work in Kentucky includes the structural steel placement for the bridge,

construction of safety walls along KY 841 and construction of the tunnel. The bridge still

needs to have the towers’ structural steel installed, as well as the cable-stay anchor boxes.

Indiana, on the other hand, will finalize on its side the concrete paving activities and

focus on landscaping/aesthetic work.

Page 26: Global Projects Center - East End Crossing

East  End  Crossing      

26  

Many aspects of the tolling policy are still undecided, and must be developed before

conclusion of the construction works in 2016. A Tolling Body composed of finance,

infrastructure and transit authorities of both states, such as IFA and KPTIA, was created

to take official action. This organization, responsible for developing tolling policies and

determining future fee rates, is working with tolling consultants and will hire a tolling

integrator to install and maintain the system. The Tolling Body will also establish more

detailed criteria for trucks, frequent commuters and environmental justice populations

during future meetings.

Dynamics

Since the beginning of the design process, dynamic elements have been part of the East

End corridor project. One of the aspects worth noting is the stakeholders’ support. In

order to authorize the IFA to take part into public-private partnerships, the Indiana

General Assembly easily approved the necessary legislation, like the Senate Bill 473 of

May 2011. As soon as the procurement process reached financial closure in 2013, the

winning concessionaire, WVB East End Partners, INDOT and IFA worked together to

start the construction work. One event served as an incentive to accelerate the job’s pace:

the closure of the Sherman Minton bridge, back in 2011. The bridge was closed for more

than five months due to the discovery of critical cracks in its supporting beams. Different

traffic routes have been developed while the bridge was undergoing repairs. However,

more than 90,000 cars that used to travel through it every day had to choose between two

congested crossings, the Kennedy Memorial Bridge or the Clark Memorial Bridge,

illustrating the need for new corridors. So far, WVB have been successful at meeting pre-

established schedules and quality benchmarks, and the expected date of conclusion is

October 2016.

A different dynamic is related to tolling. Both Indiana and Kentucky were worried about

the consequences the fee would have on their citizens’ budget, and conducted surveys to

gauge the financial impact on daily commuters. For low-income individuals, there is

willingness to switch to non-tolled routes, such as the Clark Memorial Bridge, unless in

Page 27: Global Projects Center - East End Crossing

East  End  Crossing      

27  

circumstances where time is a factor. Furthermore, those who utilize the crossings for

both work and non-work purposes indicated that they would seek to combine and

minimize their number of trips, employing alternatives such as going shopping

immediately after work. To reduce the financial effects on EJ populations, tolling

mitigation policies, such as a reduced fee or an annual reimbursement, have been

proposed, and the states have provided $20 million to TARC (the major public

transportation provider in the Louisville metro area), for an enhanced bus program across

the bridges. The final tolling policy, compliant with FHWA, will be completed before

tolling is initiated.

Effects

From a political perspective, the Ohio River Bridges Project had a positive impact on the

government of both Kentucky and Indiana. When Republican Mitch Daniels, Governor

of Indiana, and Democrat Steve Beshear, Governor of Kentucky, signed off the project

funding in 2011, the news was received with enthusiasm. At that time, the bridges

throughout the Ohio River were under strong criticism, deemed by many as crumbling

and incapable of dealing with the increasing traffic. The confirmation of the project

contributed to calm the nerves and kept the situation under control when the Sherman

Minton Bridge was closed the following year.

The economic effects tend to be positive as well. In spite of some opposition against the

high cost of the project, predictions show that, in the long run, thousands of jobs will be

created and additional economic growth will be enabled. Therefore, the associated

increases in government revenues are expected to compensate the capital disbursement

applied to the design and construction of the Ohio River Bridges Project.

Regarding social aspects, both states are working to mitigate the negative impact that

tolling will have on commuters. Due to the government’s effort to identify the most

vulnerable social groups and willingness to listen to environmental justice communities,

commuters’ acceptance towards this fee has been high. Minor opposition is also headed

Page 28: Global Projects Center - East End Crossing

East  End  Crossing      

28  

for the tunnel underneath the Drumanard Estate, but in general civilians are satisfied with

the project and the positive contribution it will make to the Louisville metro area.

Summary

The East End Crossing is expected to have a positive impact for both Kentucky and

Indiana. A more adequate system linkage will contribute to alleviate traffic congestions

and to improve cross-river mobility. Regarding the economy, predictions show that a new

business area may be developed in Jacksonville, southern Indiana. This state alone is

anticipated to create eleven thousand jobs during the project’s life, which will definitely

be beneficial to those living in the area.

The use of a public-private partnership was an effective approach to test the viability of

such delivery mode in the region, especially after the only concluded P3 project in the

State of Indiana, the Indiana Toll Road, faced serious financial distress. Unlike the former

road, the East End Crossing has been constructed and may start its operations in times of

economic stability; therefore, it will be able to provide a more accurate feedback on the

feasibility of P3s. So far, there has been effective communication between stockholders,

as no major pitfall has been noted and the procurement process was successful and rapid.

The concessionaire is experienced with P3s and could identify private sources of funding

with no difficulty. A brand-new corridor with advanced tolling systems will be delivered,

bondholders will have an investment that is fairly secure8 and users will be given the

alternative to use new bridges at a cost or to cross the Ohio River for free using old

routes.

Despite the relatively favorable public reception, some elements of the project were

received with opposition. Tolling is one example, because before the Ohio River Bridges

Project no bridge in the greater Louisville area was tolled. After holding public meetings

and conducting surveys to measure the impact of tolling, the States decided to promote

mitigation policies that would benefit commuters from EJ populations and prevent them

                                                                                                               8  Fitch rated WVB’s private activity bonds ‘BBB’ and the project’s TIFIA loan ‘AA+’.  

Page 29: Global Projects Center - East End Crossing

East  End  Crossing      

29  

from being the most affected group. The tunnel under the Drumanard Estate is also a

controversial element of the project, due to its high construction cost.

In all, although there is some public resistance, the project has been successful so far with

respect to the use of P3 and the infrastructure component. The public sector supports the

way the private sector raised funds, and the civic sector seems to approve the bridges and

accept tolling. As a consequence, when concluded, the East End Crossing wishes to serve

not only to ameliorate traffic conditions, but also to legitimize the use of P3s in the State

of Indiana.

Timeline of events

Page 30: Global Projects Center - East End Crossing

East  End  Crossing      

30  

Stakeholder Summary Table

Stakeholders

Role

Involvement Advitam P3 Design Subcontractor Middle-Late American Structurepoint Design Firm Subconsultant Middle-Late Bank of America Merrill Lynch Private P3 Finance Early Barnes & Thornburg Bond Counsel Early-Late Bilfinger Project Investments P3 Equity Member Early-Late Bizzack Construction P3 Design Subcontractor Middle-Late Buckland & Taylor Design Firm Subconsultant Middle-Late City of Jeffersonville, IN External Municipality Early-Late City of Louisville, KY External Municipality Early-Late Clark County, IN External Municipality Early-Late Deloitte TIFIA Financial Advisor Early-Middle Fitch External Bond Rating Agency Middle Goldman Sachs Private P3 Finance Early Haydon Bridge Company P3 Design Subcontractor Middle-Late Ice Miller Special Counsel to IFA Early-Late Indiana Department of Transportation Enabling Legislation Early-Late Indiana Finance Authority Public Sponsor Early-Late Indiana General Assembly Enabling Legislation Early International Bridge Technologies Design Firm Subconsultant Middle-Late J.P Morgan Private P3 Finance Early Jacobs Engineering P3 Design Firm Middle-Late James H Drew P3 Design Subcontractor Middle-Late KPMG P3 Financial Advisor Early-Late Macdonald Architects Design Firm Subconsultant Middle-Late Mayer Brown P3 Transaction Advisor Early-Late Milestone Contractors P3 Design Subcontractor Middle-Late Moody's External Bond Rating Agency Middle Nixon Peabody TIFIA Legal Advisor Early-Middle Public Employees of IN & KY External Stakeholders Early RBC Capital Markets Private P3 Finance Early Scotiabank P3 Transaction Advisor Early-Late Stantec Design Firm Subconsultant Middle-Late VINCI Concessions P3 Equity Member Early-Late Walsh Investors P3 Equity Member Early-Late WVB East End Partners P3 Concessionaire Early-Late

Page 31: Global Projects Center - East End Crossing

East  End  Crossing      

31  

Stakeholder Summary Chart

(http://www.transportation.northwestern.edu/docs/2013/2013.01.28_LipinskiSymposium

_Ciambrone.pdf; pg.14)

Page 32: Global Projects Center - East End Crossing

East  End  Crossing      

32  

References9

BRIDGES & TUNNELS 2013. East End Bridge (Interstate 265) [Online]

Available: http://bridgestunnels.com/bridges/ohio-river/east-end-bridge-

interstate-265/

BUSINESS WIRE 2015. Fitch Rates Indian Finance Auth – East End Crossing TIFIA

Loan ‘AA+’. Business Wire

EAST END CROSSING 2015. The project [Online].

Available: http://eastendcrossing.com

FHWA 2015. Project Profiles – Ohio River Bridges East End Crossing [Online]. Federal

Highway Administration.

Available: http://www.fhwa.dot.gov/ipd/project_profiles/ky_eastendcrossing.aspx

FHWA 2012. Revised Record of Decision. U.S. DOT – Federal Highway

Administration.

FHWA 2012. Supplemental Final Environmental Impact Statement. Federal Highway

Administration, Indiana Department of Transportation and Kentucky

Transportation Cabinet.

IFA 2013. Indiana’s P3 Success – East End Crossing. Indianapolis, IN. Indiana

Finance Authority.

INDOT & KYTC 2012. Initial Financial Plan. Louisville, KY. Indiana Department of

Transportation and Kentucky Transportation Cabinet.

INDOT & KYTC 2015. Assessment of Economic Effects of Tolling and Strategies for

Mitigating Effects of Tolling on Environmental Justice Populations. Indiana

Department of Transportation and Kentucky Transportation Cabinet.

PARSONS 2013. Ohio River Bridges [Online]. Parsons Corporation.

Available: http://www.parsons.com/projects/Pages/orb.aspx

                                                                                                               9  In  addition  to  the  references  cited,  over  80  additional  media  articles  and  reports,  both  public  and  private,  were  collected  on  Factiva  and  through  online  searches.  

Page 33: Global Projects Center - East End Crossing

East  End  Crossing      

33  

PUENTES, R. 2014. The Indiana Toll Road: How Did a Good Deal Go Bad. Forbes.

Available: http://www.forbes.com/sites/realspin/2014/10/03/the-indiana-toll-road-

how-did-a-good-deal-go-bad/

STARK, J. 2013. Louisville-Southern Indiana Ohio River Bridges Project – East End

Crossing. Indiana Department of Transportation.

WHITE, C. 2014. East End Bridge remains on schedule. Louisville, KY. The Courier-

Journal

Page 34: Global Projects Center - East End Crossing

East  End  Crossing      

34  

Appendix A – IFA Organization Chart and Pre-Merger Entities

Page 35: Global Projects Center - East End Crossing

East  End  Crossing      

35  

Pre-Merger Entities

Indiana Development Finance Authority

State Office Building Commission

Indiana Transportation Finance Authority

Recreational Development Commission

State Revolving Fund Programs

Indiana Brownfields Program

Page 36: Global Projects Center - East End Crossing

East  End  Crossing      

36  

Appendix B – Project Financing

The concession structure being implemented in Indiana allows the East End Crossing to

be financed with a combination of funding sources from the State of Indiana as well as

debt and equity secured by the concessionaire. The planned approach guarantees that

Indiana’s conventional funding commitments will be used for annual Milestone

Payments, and the concessionaire will be compensated with Availability Payments

thereafter.

To support the project procurement, INDOT guaranteed $570 million in federal and state

funds through 2018, including six annual Milestone Payments of $54 million, additional

construction costs of $173 million and $73 million in previously expended funds. An

additional two amounts of $54 million towards Milestone Payments has also been

committed. Upon WVB’s achievement of substantial completion, Availability Payments

will start. They will be funded through biennial State appropriations, and toll revenues

will be applied to offset the State’s annual obligations.

A summary of the crossing’s estimated financed elements can be found on the following

table. It displays the estimated financing construction costs and the anticipated toll

revenues that will be used to meet the Availability Payment requirements.

Annual Appropriation

Example (Thousands) Total 2018 2019 2020 2023-2052

Annual Project

Financing Repayment

(YOE)

$713,136 $20,375 $20,375 $20,375 $611,259

Tolling Revenue

Contribution (YOE) $3,766,454 $41,337 $43,714 $46,184 $3,534,706

Net Appropriation

Requirement $0 $0 $0 $0

Page 37: Global Projects Center - East End Crossing

East  End  Crossing      

37  

Projected Indiana

Capital Program

(YOE)

$700,000 $700,000 $700,000 $21,000,000

Federal $560,000 $560,000 $560,000 $16,800,000

State $140,000 $140,000 $140,000 $4,200,000

Table 6: East End Crossing annual appropriation example (http://updates.kyinbridges.co m/wp-content/uploads/2012/08/2012-08-01-Initial-Financial-Plan-ORBP-signed.pdf; pg. 31)

Page 38: Global Projects Center - East End Crossing

East  End  Crossing      

38  

Appendix C – Tabulation of Critical Events

Occurrence Critical Event

63 KY and IN establish a cooperative transportation program (Kentuckiana

Regional Planning and Development Agency - KIPDA)

63 Kennedy Memorial Bridge opens to traffic

69 First LMA's transportation plan recommends the extension of I-265

78 Next long-range transportation plan calls for the extension of I-265 one

more time

91 Beginning of the Ohio River Bridge Study

94 Conclusion of the Ohio River Bridge Study

95 KIPDA initiates a Major Investment Study (ORMIS)

96 KIPDA endorses the recommendation of a "two-bridge solution"

97 INDOT and KYTC agree to jointly pursue needed improvements to

cross river mobility

98 FHWA issues a Notice of Intent to indicate the preparation of an EIS

Jul-02 Governors of KY and IN announce the Ohio River Bridges Project

Sep-03 FHWA issues a ROD (first design, later abandoned)

Apr-05 The states hold public meetings to evaluate bridge designs

May-05 Multiple state authorities consolidate and form the IFA

Jul-06 Design alternatives for the East End Crossing are announced

Feb-07 Bids for the project start, but do not meet expectations. Construction is

delayed

May-08 FHWA approves the initial financial plan

Feb-08 INDOT and KYTC release a study arguing that tolls would likely be

implemented

Oct-09 Formation of the Louisville-Southern Indiana Bridge Authority (LSIBA)

Dec-09 Indiana Governor authorizes the state to participate in the project though

an Executive Order

Page 39: Global Projects Center - East End Crossing

East  End  Crossing      

39  

Dec-10 LSIBA confirms the implementation of a tolling system to finance the

project

Jan-11 To reduce costs, the states explore new design options

Sep-11 Sherman Minton Bridge is closed

Oct-11 The states analyze delivery modes and pre-select two options: a design-

build approach and an availability payment concession

Dec-11 Indiana announces that the state would take the lead in the East End

Crossing project

Feb-12 Cost review reduces the price of the Ohio River Bridges Project to $2.6

billion

Feb-12 Sherman Minton Bridge is reopened

Mar-12 Updated financial plan is approved

Mar-12 IFA and INDOT issues RFQ

Mar-12 KY and IN sign Memorandum of Understanding

Apr-12 Due date for RFQ responses

Apr-12 SFEIS (Supplemental Final Environmental Impact Statement) is signed

Apr-12 Four short-listed contractors are announced

May-12 IFA and INDOT issue a draft RFP to the short-listed teams

Jun-12 FHWA issues a Revised ROD, approving the Modified Selected

Alternative

Jul-12 FHWA accepts the Toll Agreement for the project

Nov-12 WVB East End Partners is named preferred bidder

Feb-13 INDOT conducts surveys about tolling to better understand EJ

populations

Mar-13 Financial closure of procurement process

Jun-13 Draft of the Economic Effects Assessment regarding tolling is released

Aug-14 Surveys about tolling mitigation policies are conducted

Sep-14 IFA holds public meetings about the selected proposal and contracts

Apr-15 Fitch rates WVB’s private activity bonds ‘BBB’ and the project’s TIFIA

loan ‘AA+’

Page 40: Global Projects Center - East End Crossing

East  End  Crossing      

40  

Apr-15 Document showing the economic effects of tolling is released

Oct-16 Crossing is expected to open to traffic

Jun-17 Deadline for completion of the East End Crossing