WELBOND Cement Systems Design
Godwin Nwafor, Weston Brew, Atif MalikSD-1 #71108, MLC UAE
Schlumberger Private
2
Outline
Company Overview Schlumberger/Cementing Services
Objectives
Well Data
Quality, Health, Safety & Environment (QHSE)
Safe Operation Management Tools
Sequence of Operation
Logistics & Contingency Plans
Conclusion
Schlumberger Private
3
Company Overview, Schlumberger Cementing Services
Schlumberger is the leading oilfield services provider, trusted to deliver superior results and improved E&P performance for oil and gas companies around the world.
Cementing supports and protects well casings. Schlumberger’s high-quality cementing solutions are based
on: Best practices Environmentally sound wellsite operations Innovative technologies with safety as the highest priority
Schlumberger Private
4
Objectives
WELBOND Cement Systems are developed to improve
zonal isolation through improved bonding.
To improve the cement-to-pipe and cement-to-formation
bonds by their fluid-loss control and adhesion properties.
Extremely low permeability when set prevents any fluid
movement behind the casing
Good Isolation up to liner lap
Schlumberger Private
5
Well Data Client: MLC Oil & Gas Well: MLC-1 Field: Shamkha Total MD: 12,000ft BHST: 250degF BHCT: 215degF Bit Size: 8 ½”
10.750 in Csg51.00 lbm/ft710 ft
9.625 in Csg47.00 lbm/ft6230 ft
9.625 in Csg53.50 lbm/ft9150 ft
8.500 in10% Excess12000 ft
Float Collar11920 ft
5.000 in DP19.50 lbm/ft8650 ft
7.000 in Csg32.00 lbm/ft12000 ft
Top of Cement8600 ft
Liner Hanger8650 ft
Shoe12000 ft
i- Handbook* - *a mark of Schlumberger
Created on 2/8/2012 9:37:59 PM
Schlumberger Private
6
Quality, Health, Safety & Environment (QHSE) Quality, Health, Safety and Environment (QHSE), is the four
(4) business and operational attributes controlled by the Schlumberger Management System
Applicable WS QHSE Standards: WS Std 001 – Service Delivery WS Std 003 – Maintenance WS Std 005 – Wellsite Operation WS Std 018 – Chemical Product Management
Schlumberger Private
7
QHSE contd … WS Std 023 – Testing & Inspection of Treating Equipment WS Std 30 – Mixing & Pumping of Combustible & Flammable
Fluid MSDS – Material Safety Data Sheet
Schlumberger Private
8
Safe Operation Management Tools Key Service Quality Requirement (KSQR ) i-District: A custom resource management system for use in
district operations (Job ID: 722655) JRI: Service Quality Job Risk Index identifies individual Service
Quality risk and the overall risk of the job. It must be completed prior to job starts.
Hazard Analysis & Risk Control (HARC): A process used in Schlumberger for Quality and HSE risk management, designed to analyze risk(s) prior to performing activities and to define risk control measures in order to reduce the risk.
Management of Change (MOC) – QUEST No: 20120211060327
Schlumberger Private
9
Fluid Placement & SequenceFluid Name Volume (bbl) Density (Ib/gal) Rate(bpm) Time (min)
MUDPUSH II 30.0 13.0 6.0 5.0
WELBOND Slurry
87.8 16.0 6.0 14.5
Stop, Drop Dart 10.0
Mud 118 10.5 5.0 23.5
MUDPUSH II 9.5 13.0 5.0 2.0
MUDPUSH II 2.0 13.0 2.0 1.0
Mud 140.2 10.5 5.0 28.0
Mud 2.0 10.5 2.0 1.0
Thick. Time 5 hrs
Schlumberger Private
10
Chemical/AdditivesBased on calculations, the required additives for WelBOND Slurry:
Additive Description Concentration QuantityFresh Water Base Fluid 3.261 gal/sk 35.5 bbl
Cement Class G 94 Ib of Blend 457sk 19.5 Mton
D175A Antifoam 0.03 gal/sk 13.7 gal
D801 Retarder 0.01 gal/sk 4.6 gal
D080A Saltbond II 0.07 gal/sk 32 gal
D135 GasBlok Stab 0.10 gal/sk 45.7 gal
D600 GasBlok 1.50 gal/sk 685.7 gal
Schlumberger Private
11
Chemical/AdditivesBased on calculations, the required additives for MUDPUSH II:
Additive Description Concentration Quantity
Fresh Water Base Fluid82.60%
H20/Spacer (vol) 34.3 bbl
D182 Spacer Concentrate 3.000 Ib/bbl 124.5 Ib
D047 Antifoam 0.010 gal/bbl 0.42 gal
D031 Weight Agent (Barite) 254.4 Ib/bbl 10, 557.6 Ib
Schlumberger Private
12
Sequence of Operation Safety Meeting Rig up Pressure test line @ 2000 psi Pump MUDPUSH II: 30 bbl @ 6 bpm (13 ppg) – Spacer Ahead Pump WelBOND Slurry: 87.8 bbl @ 6bpm (16 ppg) Stop & Drop Dart Pump NaCl/KCl Mud: 118 bbl @ 5 bpm (13 ppg) Pump MUDPUSH II: 11.5 bbl @ 5 bpm (Spacer Behind), slow
down to 2 bpm the last 2 bbl to shear the Liner Wiper Plug Pins Pump NaCl/KCl Mud: 142.2 bbl @ 5bpm, slow down to 2 bpm
the last 2 bbl to bump the Liner Wiper Plug
Schlumberger Private
13
Sequence of Operation … Bump Plug/Check for returns Release Running Tool, POOH above TOC and reverse
circulate out any excess cement
Schlumberger Private
14
Logistics The required logistics and planning for the job include:
Personnel required for the job Chemicals Equipment
Schlumberger Private
15
Personnel/Crew Requirements include: Crew is current on relevant QHSE (SLB & WS) Job supervisor (JS) and pump operators have done the
same or similar type jobs previously, and/or have completed training and are deemed competent by line management (LM)
Personnel trained and competent for the job Crew Composition: 1 Job Supervisor & 1 Operator
Schlumberger Private
16
EquipmentThe required equipment for the job: CPS 361, Mixing System & Surge Can Batch Mixer Treating Equipment (High & Low Pressure) Liquid Additive System (LAS) & Air Transfer Pump Rig up in compliance with SLB QHSE, WS QHSE Standards
and WS Alerts Equipment is prepared & current on STEM
Schlumberger Private
17
Equipment contd…
Liquid Additive System
Batch Mixer
Cement Pump Skid CPS 361
Cement Silo Capacity: 1 x 1000ft3
(Rig-Provided)
Schlumberger Private
18
Contingency Plans Injury/Emergency: Call rig Medic, assess the injury, if
serious call MediVAC; Maximum Shutdown time: 2hrs Loss of triplex pump: Immediately shutdown the defected
triplex pump and switch to the second triplex pump If the Batch Mixer goes down, we fly mix the WELBOND
slurry If plug doesn’t bump, pump half the volume of the shoe track If the C-Pump goes down, we use the backup
Schlumberger Private
19
Conclusion High quality zonal isolation allows more accurate well testing to
define the reservoir,
Maximizes recovery at the least cost
Provides more effective stimulation through placement focused
on the reservoir,
Provides more effective enhanced recovery and reduced
abandonment costs.
Schlumberger Private
20
Questions & Comments!!!