© 2015 Chevron Corporation. All rights reserved.
Gorgon Project Update
October 30, 2015
© 2015 Chevron Corporation. All rights reserved.
Jansz-Io Wells Opened to Pipeline
The Jansz-Io field subsea infrastructure is fully complete, and the first two wells
have been opened into the pipeline. Below is a photo of a remote operated vehicle
preparing the first subsea tree for gas to flow to the plant site.
2
© 2015 Chevron Corporation. All rights reserved.
Gas Turbine Generator 2 Startup
The second of five gas turbine generators (GTG 2) has started up and is now
synchronized with GTG 1.
3
GTG 1
GTG 2
© 2015 Chevron Corporation. All rights reserved.
LNG Train 3
Delivery of modules required for LNG Train 3 continues with nine of the 13 modules
on Barrow Island. Only four of the total 51 modules remain to be delivered.
4
LNG Train 2 LNG Train 1 LNG Train 3
© 2015 Chevron Corporation. All rights reserved.
Fired Heaters
Commissioning activities are complete on the Fired Heater required to start up
the Train 1 Acid Gas Removal Unit.
5
© 2015 Chevron Corporation. All rights reserved.
LNG Jetty
Pre-commissioning activities are well under way on the eight LNG and two
condensate loading arms.
6