TexasDepartment
of Transportation
Paris District
Grayson County Tollway Routing & Feasibility Study:from FM 121 (Gunter) to US 75 (Denison)Public MeetingJune 21, 2011
TexasDepartment
of Transportation
Paris District
TexasDepartment
of Transportation
Paris District
Grayson County’s Future
Dallas North Tollway
Grayson Co.
TexasDepartment
of Transportation
Paris District
Project Goals
Solutions For 2030 and Beyond
Improve Mobility in Grayson County
Relieve Truck Traffic on US 75 and SH 289
Minimize Negative Environmental and Socio-economic Impacts
Maximize Positive Socio-economic Opportunities
Achieve Affordable and Cost-effective Transportation Solutions
TexasDepartment
of Transportation
Paris District
Project Development Process
Feasibility & Routing Study
Preliminary Design Schematic
EnvironmentalAssessment
Final (detailed) Design
Construction
Focus of this stage
Identify Need
Right-of-WayPurchasing
Metropolitan Mobility Plan
TexasDepartment
of Transportation
Paris District
Opportunities for Input & Information
PublicInvolvement
CommunityAdvisory GroupResidents, businesses,
institutions, commuters,environmental org’s
TechnicalAdvisory Committee
Technical Staff & Elected Officials from governmental and
regulatory agencies
PublicMeetingsOpen to All
interested parties
PublicHearingOpen to All
interested parties
TexasDepartment
of Transportation
Paris District
2nd Public Meeting
StudyProcess
Identify Need, Purpose, Goals, & Objectives
July 2010
Develop & Evaluate Universe of Alternatives
August 2010
Develop & Evaluate Conceptual Alternatives
September 2010
Recommendation for 3 Conceptual Alternatives
Oct. – Nov. 2010
Recommended Preferred Alignment Determination
Apr. - May 2011
Toll Feas, Financials, & Concept Alt Analysis Rpt
Jun. – Aug. 2011
Work Group Meetings
Work Group Meetings
TexasDepartment
of Transportation
Paris District
Detailed Analysis of 3 Conceptual Alternatives
Nov. – Dec. 2010
1st Public Meeting
Work Group Meetings
Work Group Meeting
Next Steps to Complete This
Study Phase
TexasDepartment
of Transportation
Paris District
Public Involvement Tools Advisory Group Meetings
Public Meetings / Hearing
Briefings & Presentations
Print & Broadcast Media
Web sitewww.txdot.govand search: Grayson Tollway Study
http://www.dot.state.tx.us/project_information/projects/paris/grayson_tollway/default.htm
TexasDepartment
of Transportation
Paris District
Typical Section – 2 lane with Passing
Ultimate 350’ – 400’ Right of Way Controlled Access Minimizes Initial Expense Phased for Future Expansion
TexasDepartment
of Transportation
Paris District
Typical Section - 4 Lane Tollway
Ultimate 350’ – 400’ Right of Way Controlled Access Frontage Road Locations TBD Allows for Inside Expansion to 6 Lanes
TexasDepartment
of Transportation
Paris District
The GCT
Corridor
StudyArea
Boundary
US 82
TexasDepartment
of Transportation
Paris District
Grayson Co. Thoroughfare Plan
FM 902
US 82
FM 120
Tollway
TexasDepartment
of Transportation
Paris District
Households & Growth (2035)
US 82
SH 56
FM 902
FM 121
FM 120
Dallas North Tollway
TexasDepartment
of Transportation
Paris District
No Build Scenarios
US 82
SH 56
US 82
SH 56
FM 902
FM 121
FM 120
FM 120
FM 121
20032035
FM 902
TexasDepartment
of Transportation
Paris District
Universe ofAlternatives
(Final)
TexasDepartment
of Transportation
Paris District
Comparing Alternatives
Engineering and Design Features Safety, Mobility, & Congestion Relief Social & Economic Impacts Environmental Impacts Cost Effectiveness & Affordability Other Features/Impacts
MajorNegative
Effect
SomeNegative
Effect
NoEffect,Neutral
SomePositiveEffect
MajorPositiveEffect
- - - o + ++
TexasDepartment
of Transportation
Paris District
ConceptualBuild
Alternatives
TexasDepartment
of Transportation
Paris District
NorthConceptualAlternatives
N1S
N4W
N2
TexasDepartment
of Transportation
Paris District
Public Meeting Survey - North
North Alternatives (best vs. worst)
05
10152025303540
N1N1NN1S N2
N2S N3 N4N4W N5 N6 N7 N8 N9
N10 N11 N12 N13
Alternatives
Vo
tes Best Alt.
Worst Alt
N1S N2 N4W
TexasDepartment
of Transportation
Paris District
South/MiddleConceptual
Alternatives
S1
S2EMod
S10
TexasDepartment
of Transportation
Paris District
Public Meeting Survey - South
South Alternatives (best vs. worst)
05
101520253035
S1
S1W S
2
S2E
S2W S
3
S4
S5
S6
S7
S8
S9
S10
S11
Alternatives
Vo
tes Best Alt.
Worst Alt
S1 S2-S2E-S2W S10
TexasDepartment
of Transportation
Paris District
Summary of Alternatives
NORTHERN ALTERNATIVES SUMMARY
ALTERNATIVECOST ROW PROPERTY REGIONAL
INTERIM ULTIMATE ACQ IMPACTS PLANS
N1S O O - - -
N2 - - - - - - -
NW4 Mod O - - - +
SOUTHERN ALTERNATIVES SUMMARY
ALTERNATIVECOST ROW PROPERTY REGIONAL
INTERIM ULTIMATE ACQ IMPACTS PLANS
S1 - - - - - - - + +S2E Mod O - - - + + + +
S10 - - - O - -
TexasDepartment
of Transportation
Paris District
CurrentStatus
TexasDepartment
of Transportation
Paris District
Grayson County Tollway Routing & Feasibility Study:from FM 121 (Gunter) to US 75 (Denison)Public MeetingJune 21, 2011
TexasDepartment
of Transportation
Paris District