GROUND STORAGE RESERVOIR& PUMP STATION
PROJECT NEED
Population Growth DemandsSystem ResilienceMaintain High Level of ServiceFire ProtectionProvide Sustainable Supply of Safe, Clean and
Affordable Drinking Water
PROJECT SITE (FORMER MNDOT PROPERTY)
NEAR ORIGINAL EDEN PRAIRIE RAIL DEPOT
NEAR ORIGINAL EDEN PRAIRIE RAIL DEPOT
SITE LAYOUT
PUMP STATION
PUMP STATION
PUMP STATION
PUMP STATION
PUMP STATION
HIGHWAY 212 VIEW
BID RESULTS
Engineer’s Estimate: $8,600,000 Total Bid with Alternates: $7,957,353
Base Bid: $7,975,250Alternate 1 (Railroad Tracks): $32,300Alternate 2 (Mobile Lift): $10,500Alternate 3 (PVC Piping): -$60,697
Funding: WAC and Water Enterprise Bonds
PROJECT TIMELINE
Early Planning: 2015Site Selection and Hydraulic Analysis: 2016MNDOT Property Negotiations: 2017Site Acquisition: 2018/2019Design Completion: February 2019Bidding: May 2019Construction Complete: August 2020
QUESTIONS?
SITE SELECTION PROCESS• Hydraulic Performance• Proximity to Large Water Mains• Ease of Acquisition• Tax Roll Impact• Context Sensitive• Cost