Guarantee Case Law

Embed Size (px)

Citation preview

  • 7/31/2019 Guarantee Case Law

    1/20

    Guarantee

    Sub: Legal & Tax aspects of Business

    Submitted To:

    Prof. I.R.panjwan

    Submitted by:

    Jagdip Kaur Sandhu

    MMS-1 Div-c

    Roll no: 2011130

  • 7/31/2019 Guarantee Case Law

    2/20

    CONTENTS

    CHAPTER

    NUMBER

    PARTICULARS PAGE

    NUMBER

    1 Introduction 3

    2 Types of Guarantee 5

    3 Statutory analysis 6

    4 Judiciary analysisCase law:Ansal Engineering Projects Ltd. vs. Tehri Hydro

    DevelopmentHcl Technologies Limited vs Unique Identification

    Authority

    7-18

    5 Conclusion 19

    6 Bibliography 19

  • 7/31/2019 Guarantee Case Law

    3/20

    Contract of Guarantee

    1. Introduction:A contract of guarantee is a contract to perform the promise, or discharge the liability of a third

    person in case of his default

    The person who gives the guarantee is called the surety the person in respect of whose

    default the guarantee is given is called the principal debtor and the person to whom the

    guarantee is given is called the creditor. A guarantee may be either oral or written (Sec 126). It

    may be express or implied. To invoke contract of guarantee, default must be committed by the

    third person on whose behalf a person stands surety. The contract of guarantee is also known asthe contract of suretyship.

    Business owners know it is very difficult to borrow money for the business from a creditor

    without a personal guarantee even if the creditor has security against all of the business. If you

    sign the typical standard guarantee form used by creditors, you may be giving up rights designed

    to level the field. Some terms of the creditor guarantee are not in your best interest. .

    But what is a guarantee, what defences do you as a guarantor have and what are your rights? If

    you must pay under the guarantee, can you recover the money and how? Before you sign a

    guarantee, whether to support your business, or to help a relative or friend, you should know the

    answers to these questions. You should also consult a qualified lawyer to make sure the

    guarantee is not any broader than absolutely necessary.

    A guarantee is a contract between the guarantor (the person that gives the guarantee) and the

    creditor (typically the creditor that makes the loan). As a contract, it must meet the essential

    conditions required to form a valid and enforceable contract. There must be certainty of the

    terms of the guarantee: what is the extent of the guarantee, when can the creditor call for

    performance under the guarantee, and how can it be revoked.

    There must be some consideration for the guarantee as with all contracts. Usually this is the loan

    made to the business. It could also be an agreement to hold off taking some action that thecreditor is otherwise entitled to take, or allowing more time for the business to meet its

    obligations to the creditor under the existing arrangements. The amount or nature of the

    consideration does not matter as long as there is some consideration.

    The guarantee is normally in written and signed by the guarantor. But a guarantee can be

    enforceable even if it is not in writing; the guarantee could be implied from the conduct of the

    http://www.e-law.bc.ca/art_essential.htmlhttp://www.e-law.bc.ca/art_essential.htmlhttp://www.e-law.bc.ca/art_essential.htmlhttp://www.e-law.bc.ca/art_essential.htmlhttp://www.e-law.bc.ca/art_essential.html
  • 7/31/2019 Guarantee Case Law

    4/20

    parties such as a partial payment after a promise relied upon by the creditor to provide credit to

    the debtor.

    By giving the guarantee, the guarantor promises to carry out the obligations of the third party

    (the debtor) if the debtor fails to do so. If you guarantee a loan made to the black sheep of the

    family, then you agree that when the loan is not paid by the black sheep, you will make payment.The guarantee is usually of a loan. But, you can guarantee any type of obligation.

    In practice the creditor wants a "standard form" of guarantee where the guarantor waives various

    rights or defences available at common law. For example, at common law the creditor would

    normally be required to protect the security of the debtor; not allow the security to be lost or sold

    for less than fair value; not change or alter the terms of the loan with the debtor; not do anything

    that would materially alter the risk assumed by the guarantor; and not give up claims of the

    creditor against the debtor. If the creditor allows any this to happen, then the guarantor could be

    released from the guarantee. Most guarantees require the creditor to give up these defences orrights. With proper legal advice and some negotiation, you can retain many of these rights or at

    the very least limit the circumstances under which you give up your rights.

    Even if you have signed a standard form guarantee, certain defences may still be available to

    you. Do not assume that if you signed a guarantee no defences available against claims of the

    creditor. An essential requirement for a valid guarantee is mutual consent: both the creditor and

    the guarantor intended there be a guarantee. That is, when you signed the document, it must be

    clear you intended to give a guarantee. Sometimes you sign a document without realising that it

    contains a guarantee. Be forewarned however your signature will raise a presumption you

    intended to enter into the very same contract or agreement as set out in the document you signed.

    At times a person may feel there is no choice but to provide the guarantee; it is to help a family

    member with a new business, or your company needs the loan to continue an expansion

    programme. However, if you provide the guarantee because of what the law considers to be

    duress or undue influence, then the guarantee will not stand up in court. The creditor cannot

    always act only in its own best interest. Depending on the circumstances, the creditor may owe a

    fiduciary duty to the person asked to provide the guarantee. If this duty exists, and the creditor

    acts in breach of the duty, then the creditor cannot rely upon the guarantee.

    Another defence is "non est factum". Here the guarantor is really saying that the guarantee

    alleged is so fundamentally different from the agreement he thought he was making that he could

    not have intended to make the guarantee. But again if the document signed by you contains the

    guarantee; it will be difficult to raise such a defence. The appropriate facts to support such a

    defence might be found if the guarantor cannot for some reason read or understand the language.

    It may also be found if in signing a new or replacement guarantee the terms of the guarantee are

    changed without the knowledge of the guarantor.

  • 7/31/2019 Guarantee Case Law

    5/20

    If the creditor made any commitments to you about the guarantee, it is important that those

    commitments be in the guarantee. Many individuals have tried to argue that the creditor

    promised not to use the guarantee; or that the guarantee would only be used if some other person

    did not pay. Such commitments are not binding on the creditor unless they are in writing and,

    normally, contained in the guarantee document.

    If you pay the creditor, you have the right to recover that money from the debtor. You are also

    entitled to take an assignment of the creditor's rights against the principal debtor. Of course these

    rights have value only if the debtor has the means to pay you.

    Most creditors insist that the guarantor get independent legal advice from a solicitor before the

    guarantee is signed. This is to ensure that the creditor can enforce the guarantee if necessary.

    You should insist on getting independent legal advice from a solicitor qualified in business law

    to protect your rights.

    Illustrations

    A lends money to B and C promises A that in case B fails to pay money he will pay the money.

    Every contract of guarantee has three parties (1) principal debtor i.e. B (2) creditor i.e. A (3)

    surety i.e. C

    2. Types of guarantee:

    Continuing guarantee: A guarantee which extends to a series of transaction is called

    Continuing Guarantee.

    Illustration: A, in consideration that B will employ C in collecting the rents of Bs Zamindari,

    promises B to be responsible to the amount of Rs.5000, for the due collection and payment by C

    of those rents. This is a Continuing Guarantee.

    Revocation of continuing guarantee:1. By notice: (Sec.131) A continuing guarantee may at any time be revoked by the surety, as to

    future transactions, by notice to creditor

    2. By death of surety: (Sec.131) In the absence of any contract to the contrary, death of surety

    operates as revocation of continuing guarantee, so as far as regards future transactions.

    3. By discharge of surety: Continuing guarantee is also revoked when the surety is discharged in

    any of the following ways:

  • 7/31/2019 Guarantee Case Law

    6/20

    By variance in the terms of contract: (Sec 133) Any variance, made without the suretysconsent in the terms of the contract between the principal debtor and the creditor,

    discharges the surety as to transactions subsequent to the variance.

    By release or discharge of principal debtor: (Sec 134) The surety is discharged by anycontract between the creditor and the principal debtor, by which the principal debtor is

    released or by any act or omission of the creditor, the legal consequence of which is the

    discharge of the principal debtor.

    By creditor compounding with the principal debtor: A contract between the creditor s andthe principal debtor, by which the creditor makes a composition with, or promises to give

    time to, or not to sue the principal debtor discharge the surety unless the surety assents to

    such contract.

    By creditors act or omission impairing suretys eventual remedy: (Sec 139) If thecreditor does any act which is inconsistent with the rights of the surety, or omits to do any

    act which his duty to the surety requires him to do, and the eventual remedy of the surety

    himself against the principal debtor is thereby impaired, the surety is discharged. By creditor losing security against the principal debtor: (Sec 141) If the creditor loses

    or,without the consent of the surety, parts with the security he has against the principal

    debtor at the time when the contract of suretyship is entered into, the surety is discharged

    to the extent of the value of the security.

    By misrepresentation: (Sec 142) When a creditor misrepresents to the surety regardingthe material facts, the guarantee is invalid and therefore the surety is discharged.

    By concealment: (Sec 143) When a creditor obtains a guarantee by concealing or keepingsilent over the material facts, the surety is discharged as the guarantee is invalid.

    Failure of co-surety to join: (Sec 144) Failure on the part of some person to join thesurety who gave the guarantee on the express understanding that the creditor shall not act

    upon it until such another person has joined in it as co-surety, invalidates the guarantee

    and therefore discharges the surety.

    Invalid guarantees:Under the following circumstances, the contract of guarantee shall be invalid:

    By misrepresentation: (Sec 142) when a creditor misrepresents to the surety regarding thematerial facts, the guarantee is invalid and therefore the surety is discharged.

    By concealment: (Sec 143) When a creditor obtains a guarantee by concealing or keepingsilent over the material facts, the surety is discharged as the guarantee is invalid.

    Failure of co-surety to join: (Sec 144) Failure on the part of some person to join thesurety who gave the guarantee on the express understanding that the creditor shall not act

    upon it until such another person has joined in it as co-surety, invalidates the guarantee

    and therefore discharges the surety.

  • 7/31/2019 Guarantee Case Law

    7/20

    Essential elements absent: If the guarantee lacks one or more of the essential elements ofan ordinary contract, the guarantee will be invalid.

    3. Statutory analysis of Guarantee:

    1. There must be debt existing which should be recoverable.

    2. Three parties are involved:

    Principal Debtor, Creditor & Surety.3. Three contracts take place

    Between principal debtor & creditor Between creditor & surety. Between surety & principal debtor.

    4. There must be distinct promise, oral or written, by surety to pay debt in case of default

    committed by principal debtor.

    5. There must be some consideration

    6. The liability must be legally enforceable

    7. The contract of guarantee must have all the essentials of contract

    8. Liability of Surety is Contingent.

    9. In every Guarantee there is an implied indemnity given by principal debtor to surety.

    10. Guarantee will be all parties.

    11. Guarantee is to be stamped. (Maximum stamp duty Rs.10 lakhs)

    12. Guarantee is in possession of creditor.

    4. Judiciary analysis

    Case law:

    Ansal Engineering Projects Ltd. vs. Tehri Hydro Development ... on 31 July, 1996

  • 7/31/2019 Guarantee Case Law

    8/20

    Equivalent citations: 1996 VIAD SC 290, 1997 88 CompCas 149 SC

    Bench: K Ramaswamy, S Ahmed, G Pattanaik

    ORDER:

    1. This Special Leave Petition arises from the order of the learned Single Judge of the Delhi HighCourt dated January 17, 1996 made in Suit No. 990/95. The petitioner had sought for injunction

    under Section 41 read with Schedule II of the Arbitration Act, 1940 [for short, the 'Act'] to

    restrain the respondent from invoking the bank guarantee No. 33/1991 dated February 13, 1991

    to encash Rs. 57,9701- pursuant to the letter of invocation dated April 5, 1995. The facts

    mentioned therein are that petitioner had entered into contract on March 30, 1991 pursuant to a

    tender submitted by him to construct 108 residential quarters at Katharia, Bhagirath Puram,

    Tehri. The construction was to be completed within stipulated period but was not completed. In

    terms of the contract, the first respondent had terminated it. The petitioner availed of the remedy

    under Section 20 of the Act for appointment of an arbitrator for reference of the dispute in terms

    of the contract. Pending consideration thereof, he filed an application to restrain the respondent

    to encash the bank guarantee. The respondent after termination of the contract had issued a letter

    of invocation dated April 5, 1995 calling upon the UCO Bank to pay the aforesaid amount in

    terms of the bank guarantee. It was contended in the High Court that the amount due and payable

    by the petitioner should be determined in the suit. The bank guarantee could not be invoked till

    then and the payment thereof could not be made. The respondent had played fraud on the

    petitioner in entering into the contract and seeking extension of the time. There are exceptional

    circumstances which necessitated the petitioner to seek relief of injunction pendingdetermination of the amount due and payable by the petitioner. The High Court rejected the

    contentions and dismissed the petition. Thus, this special leave petition.

    2. Admittedly, the bank guarantee given by the UCO Bank on behalf of the petitioner reads as

    under:

    On production of a Bank Guarantee for the above principal amount and interest due thereon, we,

    UCO Bank, 5, Parliament Street, New Delhi (hereinafter referred to as "the Bank") at the request

    of Ansal Engineering Projects Limited Contractor (s) do hereby undertake to pay to theCorporation an amount not exceeding Rs. 57,57,970/- plus interest as aforesaid against any loss

    or damage caused to suffered or would be caused to or suffered by the Corporation by reason of

    any breach by the said Contractor (s) of any of the terms or conditions contained in the said

    Agreement.

  • 7/31/2019 Guarantee Case Law

    9/20

    We, UCO Bank, 5, Parliament Street, New Delhi do hereby undertake to pay the amount due and

    payable under this guarantee without any demur, merely on a demand from the Corporation

    stating that the amount claimed is due by way of loss or damage caused to or would be caused to

    or suffered by the Corporation by reason of breach by the said contractor (s) of any of the terms

    or conditions contained in the said Agreement or by reason of the Contractor (s) failure to

    perform the said Agreement. Any such demand made on the bank shall be conclusive as regards

    the amount due and payable by the bank under this guarantee. However, out liability under this

    guarantee shall be restricted to an amount not exceeding Rs. 57,57,9707/- plus interest due on the

    outstanding balance of mobilisation advance @ 18% p.a.

    We undertake to pay to the Corporation money so demanded notwithstanding any dispute or

    disputes raised by the Contractor (s)/Supplier (s) in any suit or proceeding pending before any

    Court or Tribunal relating thereto. Our Liability under this present being absolute and

    unequivocal.

    3. The letter of invocation of the respondent is thus:

    We hereby invoke subject Bank Guarantee and demand the amount detailed herein after as the

    amount claimed is due by way of loss and damage caused to or would be caused to or suffered

    by THDC/ourselves by reason of breach by Your customer of the terms and conditions contained

    in the said agreement and also by reason of your Customer's failure to perform the said

    agreement.

    THDC/We are limiting our claim against you to the extent of the principal amount of

    mobilization advance lying outstanding against your customer plus interest due on the

    outstanding balance of mobilization advance @ 18% per annum. You are as such, requested to

    pay the following amounts:

    (a) Outstanding amount of mobilization advance due and payable by M/s. Ansal Engineering

    Project Limited, in terms of the Bank Guarantee in question. Rs. 51,02,6587

    (b) Balance interest @ 18% per annum calculated on the outstanding mobilization advance upto

    30th October, 1994, Rs. 13,89,6257-.

    (c) Interest @ 18% per annum on the outstanding mobilization advance of Rs. 51,026587- w.e.f.

    31.10.1994 till the date of payment by you.

  • 7/31/2019 Guarantee Case Law

    10/20

    This notice of demand may be treated , as a fresh demand to pay the above noted amounts in

    terms of order dated 1.9.1994 passed by the Hon. High Court of Delhi at New Delhi in O.M.P.

    No. 39/1994 titled as M/s Ansal Engineering Projects . Ltd. versus Tehri Hydro Development

    Corporation Ltd. & Yourself. Photo copy of the said order is enclosed herewith for ready

    reference.

    4. It is settled law that bank guarantee is an independent and distinct contract between the bank

    and the beneficiary and is not qualified by the underlying transaction and the validity of the

    primary contract between the person at whose instance the bank guarantee was given and the

    beneficiary. Unless fraud or special equity exists, is (sic) pleaded and prima facie established by

    strong evidence as a triable issue, the beneficiary cannot be restrained from encasing the bank

    guarantee even if dispute between the beneficiary and the person at whose instance the bank

    guarantee was given by the Bank, had arisen in performance of the contract or execution of the

    works undertaken in furtherance thereof The Bank unconditionally and irrevocably promised to

    pay, on demand, the amount of liability undertaken in the guarantee without any demur or

    dispute in terms of the bank guarantee. The object behind is to inculcate respect for free flow of

    commence and trade and faith in the commercial banking transactions unhedged by pending

    disputes between the beneficiary and the contractor.

    5. It is equally settled law that in terms of the bank guarantee the beneficiary is entitled to invoke

    the bank guarantee and seek encashment of the amount specified in the bank guarantee. It does

    not depend upon the result of the decision in the dispute between the parties, in case of thebreach. The underlying object is that an irrevocable commitment either in the form of bank

    guarantee or letters of credit solemnly given by the bank must be honoured. The Court exercising

    its power cannot interfere with enforcement of bank guarantee/letters of credit except only in

    cases where fraud or special equity is prima facie made out in the case as triable issued by strong

    evidence so as to prevent irretrievable injustice to the parties. The trading operation would not be

    jettisoned and faith of the people in the efficacy of banking transactions would not be eroded or

    brought to disbelief. The question, therefore, is: whether the petitioner had made out any case of

    irreparable injury by proof of special equity or fraud so as to invoke the jurisdiction of the Court

    by way of injunction to restrain the first respondent from encashing the bank guarantee. The

    High Court held that the petitioner has not made out either. We have carefully scanned the

    reasons given by the High Court as well as the contentions raised by the parties. On the facts, we

    do not find that any case of fraud has been made out. The contention is that after promise to

    extend time for constructing the buildings and allotment of extra house and the term of bank

    guarantees was extended, the contract was terminated. It is not a case of fraud but one of acting

  • 7/31/2019 Guarantee Case Law

    11/20

    in terms of contract. It is next contended by Shri G. Nageshwara Rao, learned counsel for the

    petitioner that unless the amount due and payable is determined by a competent court or tribunal

    by mere invocation of bank guarantee or letter of credit pleading that the amount is due and

    payable by the petitioner, which was disputed, cannot be held to be due and payable in a case.

    The Court has yet to go into the question and until a finding after trial, a decision is given by a

    court or tribunal that amount is due and payable by the petitioner, it cannot be held to be due and

    payable. Therefore, the High Court committed manifest error of law in refusing to grant

    injunction as the petitioner has made out a prima facie strong case. We find no force in the

    contention. All the clauses of, the contract of the bank guarantee are to be read together. Bank

    guarantee/letters of credit is an independent contract between the bank and the beneficiary. It

    does not depend on the result of the dispute between the persons on whose behalf the bank

    guarantee was given by the bank and the beneficiary. Though the question was not elaborately

    discussed, it was in sum answered by this Court inHindustan Steel Workers Construction Ltd. v.G.S. Atwal & Co. (Engineers) Pvt. Ltd.. This Courthad held in Para 6 that the entire dispute was

    pending before the arbitrator. Whether, and if so, what is the amount due to the appellant was to

    be adjudicated in the arbitration proceedings. The order of the learned Single Judge proceeds on

    the basis that the amounts claimed were not and cannot be said to be due and the bank has

    violated the understanding between the respondent and the Bank in giving unconditional

    guarantee to the appellant. The learned Judge held that the bank had issued a guarantee in a

    standard form, covering a wider spectrum than agreed to between the respondent and the bank

    and it cannot be a reason to hold that the appellant is in any way fettered in invoking the

    unconditional bank guarantee. Similarly, the reasoning of the learned Single Judge that before

    invoking the performance guarantee the appellant should assess the quantum of loss and

    damages and mention the ascertained figure, cannot be put forward to restrain the appellant from

    invoking the unconditional guarantee. This reasoning would clearly indicate that the final

    adjudication is not a pre-condition to invoke the bank guarantee and that is not a ground to issue

    injunction restraining the beneficiary to enforce the bank guarantee.In Hindustan Steel Works

    Construction Ltd. v. Tarapore & Co. & Anr., it was Contended that a contractor had a

    counterclaim against the appellant; that disputes had been referred to the arbitrator and no

    amount was said to be due and payable by the contractor to the appellant till the arbitratordeclared the award. It was contended therein that those were exceptional circumstances

    justifying interference by restraining the appellant from enforcing the bank guarantee. The High

    Court had issued interim injunction from enforcing the bank guarantee. Interfering with and

    reversing the order of the High Court, this Court has held in para 23 that a bank must honour its

    commitment free from interference by the courts. The special circumstances or special equity

    pleaded in the case that there was a serious dispute on the question as to who has committed the

    http://indiankanoon.org/doc/708879/http://indiankanoon.org/doc/708879/http://indiankanoon.org/doc/708879/http://indiankanoon.org/doc/708879/http://indiankanoon.org/doc/1988070/http://indiankanoon.org/doc/1988070/http://indiankanoon.org/doc/1988070/http://indiankanoon.org/doc/1988070/http://indiankanoon.org/doc/1988070/http://indiankanoon.org/doc/1988070/http://indiankanoon.org/doc/708879/http://indiankanoon.org/doc/708879/
  • 7/31/2019 Guarantee Case Law

    12/20

    breach of the contract and that whether the amount is due and payable by the contractor to the

    appellant till the arbitrator declares the award, was not sufficient to make the case an exceptional

    one justifying interference by restraining the appellant from enforcing the bank guarantee. The

    order of injunction, therefore, was reserved with certain directions with which we are not

    concerned in this case.

    6. A conjoint reading of the bank guarantee and the letter of invocation demanding payment of

    amount due and payable by the petitioner would show that the first respondent had specified and

    quantified in terms of the bank guarantee a total sum with interest due thereon in a sum of Rs.

    57,57,970/- as on April 5, 1995. A demand in terms of clause (i) of the bank guarantee was

    made. The bank had irrevocably promised and undertaken to pay to the Corporation without any

    demur or damage an amount not exceeding Rs. 57,57,970/- plus interest's per terms and

    conditions contained in the bank guarantee untrammelled by the bi-lateral agreement between the

    petitioner and the first respondent-Corporation stating the amount claimed was due and payable

    on account of loss or damage caused to or likely to be caused to or by the Corporation by reason

    of any breach by the said contract or any of the terms and conditions contained in the said

    agreement notwithstanding any dispute or disputes raised under the contract in any suit or

    proceedings pending before any court or tribunal relating thereto. The liability of, the bank is

    absolute and unequivocal; it would thereby be clear that the bank is not concerned with the

    ultimate decision of a court and a tribunal in its finding after adjudication as to the amount due

    and payable by the petitioner to the first respondent. What would be material is the quantification

    of the liability in the letter of revocation. The bank should verify whether the amount claimed iswithin the terms of the bank guarantee or letter of credit. It is axiomatic that any payment by the

    bank, obviously be subject to the final decision of the court or the tribunal. At the stage of

    invocation of bank guarantee, the need for final adjudication and decision on the amount due and

    payable by the petitioner, would run contrary to the terms of the special contract in which the

    bank had undertaken to pay the amount due and payable by the contractor. Thus we hold that

    there is no question of making out any prima facie case much less strong evidence or special

    equity or exceptional circumstances for interference by way of injunction.

    7. The special leave petition is accordingly dismissed.

    Case law

    Hcl Technologies Limited vs Unique Identification Authority ... on 31 May, 2011

    THE HIGH COURT OF DELHI AT NEW DELHI

  • 7/31/2019 Guarantee Case Law

    13/20

    Judgment Reserved on: May 25, 2011 Judgment Pronounced on: May 31, 2011

    Advocates who appeared in this case:

    For the Plaintiff: Mr Neeraj Kishan Kaul, Sr. Adv with Mr Kartik Yadav, Adv.

    For the Defendant: Mr S.K. Dubey, Sr. Government Counsel, Mr Neeraj Chaudhari,

    CGSC and Mr Khalid Arshad and Mr Nitin Sharma, Advs. for D-1&2, Mr Rajiv Kapur,

    Adv. for D-3 CORAM:-

    HON'BLE MR JUSTICE V.K. JAIN

    1. Whether Reporters of local papers may be allowed to see the judgment?

    2. To be referred to the Reporter or not?

    3. Whether the judgment should be reported Yes in Digest?

    V.K. JAIN, J IA No. 8635/2011 (O. 39 R. 1&2 CPC)

    1. This is a suit for grant of perpetual injunction. Defendant

    No.2 - Unique Identification Authority of India (UIDAI) which is stated to be an office attached

    to the Planning Commission, to issue, a unique identification number to all Indian residents

    invited Expression of Interestfor appointment of Managed Service Provider(MSP) for

    Central ID Data Repository. Each participant in the tendering process was required to submit an

    Earnest Money Deposit(EMD) of Rs.2 crores in the form of bank guarantee in favour of

    defendant No.2. The EMD of unsuccessful applicants was to be returned to them within onemonth of issue of Request For Proposal(RFP) to the successful applicants. The EMD

    furnished by the successful applicants was to remain in force till RFP evaluation process was

    complete. The plaintiff, in compliance with the terms and conditions of the aforesaid tender

    submitted a bank guarantee of Rs.2 crores issued by defendant No.3 - State Bank of India. The

    bank guarantee was extended from time to time and is valid upto May 31, 2011. Vide letter dated

    May 9, 2011, the plaintiff withdrew from the biding process, without submitting a bid. It is

    alleged that defendant No.2, assuming the plaintiff to be a bidder, is seeking to encash the

    aforesaid bank guarantee and has informed the plaintiff that its request for returning the bank

    guarantee has not been accepted. It has accordingly been prayed that defendant No.2 be

    restrained from forfeiting the earnest money and be directed to return the earnest money amount

    of Rs.2 crores deposited by the plaintiff, vide bank guarantee dated 23.08.2010.

    2. This suit was listed for the first time on 23.05.2011 when an adjournment was taken by the

    plaintiff. When the matter was taken up on 24.05.2011, the plaintiff amended the plaint so as to

    implead Union of India as defendant No. 1 and State Bank of India as defendant No.3. The

    matter was adjourned to 25.05.2011 on the request of the plaintiff which was required to serve

  • 7/31/2019 Guarantee Case Law

    14/20

    advance copy of the plaint on the nominated counsel for Union of India. The arguments on IA

    8635/2011 filed by the plaintiff seeking ad interim injunction against invocation of bank

    guarantee and receipt of money from the bank were heard. The defendants did not get enough

    time to file written statement and has orally opposed the application.

    3. A perusal of the tender document dated 18.06.2010 filed by the plaintiff - Company wouldshow that the tendering process was divided into two sections. Defendant No.2 invited

    Expression of Interestfor selection of the Managed Service Providermaking it clear that the

    document was not to be construed as Tender/RFP. The second stage of tendering process

    comprised inviting techno-commercial bids by issuance of Request for Proposal to those EOI

    respondents, who were short-listed on the basis of pre-qualification criteria mentioned in the

    document.

    4. Clause 1 of EMD Form reads as under:-

    " THE CONDITIONS of this obligation are:

    1. If the Respondent, having been notified of the acceptance of its EOI by the Client during the

    period of validity of EOI

    (a) Withdraws his participation from the EOI during the period of validity of EOI document; or

    (b) Fails or refuses to participate in the subsequent tender process after having been short listed

    in accordance of the EOI Document. We undertake to pay to the Client upto the above amount

    upon receipt of its first written demand, without the Client having to substantiate its demand,

    provided that in its demand the Client will note that the amount claimed by it is due to it owing

    to the occurrence of one or both of the two conditions, specifying the occurred condition orconditions. This guarantee will remain in force upto and including 60 days after the period of

    EOI Response validity, and any demand in respect thereof should reach the Bank not later than

    the above date."

    5. Clause 6.1.6 reads as under:-

    "6.1.6 We understand that the bid security furnished by us may be forfeited:

    (a) If we withdraw our participation from the EOI during the period of validity of EOI document;

    or

    (b) In the case we do not participate in the subsequent Tender process after having been short

    listed"

    6. Clause 7 & 8 of Invitation to Bid read as under:-

  • 7/31/2019 Guarantee Case Law

    15/20

    "7. The Bidder is required to pay Rs.50,00,00,000/- (INR Fifty Crore Only) towards Bid Security

    in the form of a Bank Guarantee failing which the bid submitted by the bidder shall be rejected.

    The Bank Guarantee should be drawn in favour of "PAO, UIDAI" and payable at New Delhi.

    8. The bidders, in line with clause 3.2 of relevant expression of interest (EoI) for "Managed

    Services Provider(MSP) for CIDR dated 18th June, 2010 shall extend the validity of the EMD ofRs.2,00,00,000 (INR Two Crores only), submitted as part of EoI Response, so that the same is

    valid for 45 days beyond the validity of this RFP Bid as per Clause 5(f) above. This extension of

    EMD submitted at the time of EoI stage shall be submitted along with bid security of

    Rs.50,00,00,000/- (INR Fifty Crore Only)."

    7. Clause 12.7 of the Invitation to Bid reads as under:-

    "12.7 The bid security may be forfeited:

    a) If a Bidder withdraws its bid during the period of bid validity specified by the Bidder in the

    Bid; or

    b) In the case of a successful Bidder, if the Bidder fails;

    i. to sign the Contract in accordance with Clause 31; or

    ii. to furnish performance security in accordance with Clause 32."

    8. Clause 21.1 of the Invitation to Bid reads as under:-

    "21.1. The Bidder may modify or withdraw its bids after the bids' submission, provided that

    written notice of the modification or withdrawal is received by the Purchaser prior to the last dateprescribed for receipt of bids."

    9. Clause 32.1 of the tender document reads as under:-

    Within 15 days of the receipt of notification of award from the Purchaser, the successful Bidder

    shall furnish the performance security in accordance with the Conditions of Contract, in the form

    of a Contract Performance Bank Guarantee as per the format prescribed at Attachment 1 of

    Section III."

    10. Clause 32.2 of the tender document reads as under:-

    "32.2 Failure of the successful Bidder to comply with the requirement of Clause 31 or Clause

    32.1 shall constitute sufficient grounds for the annulment of the award and forfeiture of the bid

    security, in which event the Purchaser may award the Contract to the next best evaluated Bidder

    or call for new bids."

    11. Clauses 1 and 2 of Annexure-I; bid security form reads as under:-

  • 7/31/2019 Guarantee Case Law

    16/20

    "THE CONDITIONS of this obligation are:

    1. If the bidder, withdraws its Bid during the period of bid validity specified by the bidder on the

    Bid Form; or

    2. If the bidder, having been notified of the acceptance of its bid by the Purchaser during theperiod of bid validity,

    (a) Fails or refuses to execute the Contract, if required; or

    (b) Fails or refuses to furnish the Performance Security, in accordance with the instructions to

    bidders"

    12. A perusal of the bank guarantee executed by defendant No.3

    - State Bank of India, would show that it is in terms of the format provided in the tender

    document in this regard. To the extent it is relevant the bank guarantee reads as under:-

    THE CONDITIONS of this obligation are:

    1. If the Respondent, having been notified of the acceptance of its EOI by the Client during the

    period of validity of EOI

    (a) Withdraws his participation from the EOI during the period of EOI document; or

    (b) Fails or refuses to participate in the subsequent tender process after having been short listed

    in accordance of the EOI Document."

    13. It is an admitted position that on scrutiny of the Expression of Interestsubmitted by the

    plaintiff Company, it was short-listed for inviting techno-commercial bids by issuance of RFP. It

    is also an admitted case that no techno-commercial bid was actually submitted by the plaintiff -

    Company and it sought refund of the bank guarantee.

    Relying upon clause 6.1.6 , it was contended by the learned counsel for the plaintiff that there is

    no provision in the tender document for forfeiting the amount of EMD in case the short-listed

    respondent withdraws from the tendering process before submitting the techno-commercial bid.

    It was also contended by him, that this is also a case of special equity in favour of the plaintiff -

    Company since no loss has been caused to the defendants on account of withdrawal of the

    plaintiff from the tendering process without submitting the techno- commercial bid whereas

    irretrievable loss will be caused to the plaintiff, if the bank guarantee is allowed to be encashed.

    It was also submitted that being State, the defendant is expected to act fairly and reasonably in all

    its dealings including the commercial contracts. This is also his contention, that since the bank

    guarantee furnished by the plaintiff - Company expressly referred to the terms of the tender

    document, those terms have necessarily be read while interpreting the bank guarantee and the

  • 7/31/2019 Guarantee Case Law

    17/20

    bank guarantee cannot be invoked unless the terms and conditions of the tender document

    provide for the forfeiture of the EMD.

    14. In Hindustan Construction Co. Ltd. (supra), the applicants furnished guarantees which were

    to be returned to it on 7 th July, 2003 i.e. after one year of the maintenance periods. Therespondent, however, sought to invoke the bank guarantee on 7th July, 2003. On account of the

    threats and duress alleged to have been applied by the respondent by invoking the bank

    guarantees, the applicant, submitted an undertaking that the performance was not to be

    considered complete till such time advance ad hoc payments remained unadjusted and that the

    bank guarantee would be kept in force and could be invoked by the respondent without need to

    prove or show grounds for invocation. In view of this undertaking, encashment of the bank

    guarantee was put on hold by the respondent. This was also the case of the applicant that before

    the original time for completion of contract was to expire on 23 rd April, 1998, the respondent

    appointed a Consultant to examine the issue of extension of time, since the respondent had

    conveyed its difficulty in settling the claims by the applicant on the ground that their officers

    were not having the requisite experience and skill. On the recommendations of the Consultant,

    the petitioner was granted an interim extension of 25 months i.e. upto 30th June, 1997 and

    thereafter, an interim payment of Rs. 35.98 crores was also released to it by the respondent as

    partial compensation of additional cost arising from the prolongation of the work. Subsequently,

    the respondent unilaterally set up an Internal Claims Review Committee and sought to review the

    additional time and additional compensation awarded to the petitioner. This was alleged to be a

    mala fide act on the part of the respondent. The petitioner protested against it and soughtreference of the dispute to Dispute Review Board (DRB) which was constituted in terms of the

    contract. The Board granted certain extensions and related cost compensation to the applicants

    on cost of various items. It was also held that the applicants were entitled to Rs. 41 crores over

    and above the amount already paid and they were not liable for any liquidated damages.

    However, a part of the findings recorded by the Board was not accepted by the respondent who

    intended to invoke the arbitration clause. The applicants wrote to respondent requesting that no

    step should be taken for encashment of the bank guarantee until the points/issues were finally

    decided by the arbitral forum. The respondent intended to claim liquidated damages of Rs. 73.44

    crores in addition to claim of Rs. 35.98 crores which it had already paid to the applicant as ad

    hoc payments. The respondent threatened to invoke the bank guarantees amounting to Rs. 123.97

    crores. The case of the applicant was that the respondent could not be permitted to invoke the

    bank guarantee in an arbitrary method which was opposed to the specific terms of the contract as

    it would cause serious prejudice to its interest. It was also pointed out that the respondent itself

    had accepted the decision of the Board in regard to part of the extended period while the other

  • 7/31/2019 Guarantee Case Law

    18/20

    part was being questioned by it without any basis and justification. In a petition filed by the

    applicant under Section 9 of the Arbitration and Conciliation Act, the following four grounds

    were mainly taken:-

    (a) The invocation of bank guarantees by the respondents is intended to overreach theadjudicative process, provided under the terms of the agreement. This is a fraudulent attempt on

    the part of the respondent;

    (b) The invocation of bank guarantees is contrary to the terms of the bank guarantee;

    (c) The facts and circumstances of the case clearly demonstrate special equities in favor of the

    petitioners so as to justify grant of an injunction order; and

    (d) The petitioners shall suffer irretrievable injustice and injury in the event the bank guaranteesare permitted to be encashed.

    15. After considering various decisions on this subject, this Court inter alia observed as under:-

    "12. Originally, the only exception carved out to encashment of bank guarantee unconditionally

    was, fraud. However, subsequent judicial pronouncements have extended this scope by adding

    other class of cases which would fall in this exception - Cases of irretrievable injury, fraud,

    extraordinary special equities and invocation of bank guarantee being not in terms of the bank

    guarantee itself. It is very difficult to draw any straitjacket formula which would universallyapply to all the cases. The Court would have to examine each case in order to find out whether

    the case falls in any or more of the afore-stated classes."

    16. The legal propositions were formulated by the Court as under:

    On the analysis of the above law laid down by the Supreme Court in its different judgments, it is

    clear that injunction against encashment of bank guarantee is an exception and not the rule.

    Cases of such exceptions would have to be evidenced by documents and pleadings on record and

    compulsorily should fall within any of the following limited categories:-

    i) If there is a fraud in connection with the bank guarantee which would vitiate the very

    foundation of such guarantee and the beneficiary seeks to take advantage of such fraud.

    ii) The applicant, in the facts and circumstance of the case, clearly establishes a case of

    irretrievable injustice or irreparable damage.

  • 7/31/2019 Guarantee Case Law

    19/20

    iii) The applicant is able to establish exceptional or special equities of the kind which would

    prick the judicial conscience of the court.

    iv) When the bank guarantee is not invoked strictly in its terms and by the person empowered to

    invoke under the terms of the guarantee. In other words, the letter of invocation is in apparentviolation to the specific terms of the bank guarantee. The concept of irretrievable injustice, or

    damages, or special equities would come into play where the parties to a contract having been

    provided with internal adjudicative mechanism, attempts to frustrate results of such an internal

    adjudication by recourse to encashment of bank guarantee, particularly when under the terms and

    conditions of the contract, including the terms of the guarantee, such determination is 'final', of

    course subject to the limitations spelled out in such contracts. An attempt to over-reach the

    process of adjudication with intent to cause irreparable prejudice to the other side would be a

    circumstance which would influence the decision or tilt the special equities in favor of the

    applicant before the Court.

    5. Conclusion:

    "It is settled law that bank guarantee is an independent and distinct contract between the bank

    and the beneficiary and is not qualified by the underlying transaction and the validity of the

    primary contract between the person at whose instance the bank guarantee was given and the

    beneficiary. Unless fraud or special equity exists, is pleaded and prima facie established by

    strong evidence as friable issue, the beneficiary cannot be restrained from encashing the bank

    guarantee even if dispute between the beneficiary and the person at whose instance the bank

    guarantee was given by the bank, had arisen in performance of the contract or execution of the

    works undertaken in furtherance thereof....."

    6. Bibliography:

    Mulla: Indian Contract Act (volume 2)

    Business law for management: K.R.BULCHANDANI

    Indiankanoon.org

    http://www.e-law.bc.ca

    http://www.e-law.bc.ca/http://www.e-law.bc.ca/http://www.e-law.bc.ca/
  • 7/31/2019 Guarantee Case Law

    20/20