Gypsum to Gypsum (GtoG): The European Life+ project that aims to transform the gypsum waste market De Guzmán Báez, A.; Jiménez Rivero, A.; García Navarro, J.; Rodríguez Quijano, M. RESEARCH GROUP SUSTAINABILITY IN CONSTRUCTION AND INDUSTRY WORLD CONGRESS AND EXPO ON RECYCLING JULY 20-22, 2015 TRYP BARCELONA APOLO HOTEL

Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

Gypsum to Gypsum ( GtoG): The European L i fe+

pro ject that a ims to t ransform the gypsum w aste

market

De Guzmán Báez, A.; Jiménez Rivero, A.; García Navarro, J.;

Rodríguez Quijano, M.

RESEARCH G RO UP SUSTAI NAB I L I T Y I N CO NST RUCT I ON

AND I NDUST RY

W O RL D CO NG RESS AND EXPO O N RECYCL I NG

J U LY 2 0 - 2 2 , 2 0 1 5

T R Y P B A R C E L O N A A P O L O H O T E L

Page 2: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

2 /14 World Congress and Expo on Recycling

1. PROJECT INFORMATION

2. MAIN OBJECTIVES

3. WORK PLAN

4. IMPACT

TABLE OF CONTENTS

Page 3: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

Project information - Main objectives – Work Plan - Impact

3 / 14 World Congress and Expo on Recycling

LIFE11 ENV/BE/001039

LIFE+ Environment Policy & Governance in 2011:

EU's financial instrument supporting environmental, nature conservation

and climate action projects throughout the EU

Duration: 36 months (01.01.2013 – 31.12.2015)

Budget: 3,566,250.00 €

EU Contribution (50%): 1,783,123.00 €

PROJECT INFORMATION

Page 4: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

Project information - Main objectives – Work Plan - Impact

4 / 14 World Congress and Expo on Recycling

Coordination:

Promoted by the Gypsum European Industry, in order to enhance general awareness at an

European level about the benefits to the environment as well as the improvement of social aspect

related with construction .

17 partners involved in the value chain:

Demolition companies, Gypsum Industry, Gypsum Recyclers,

Consultant and Research centers.

PROJECT INFORMATION: CONSORTIUM

Page 5: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

Project information - Main objectives – Work Plan - Impact

5 / 14 World Congress and Expo on Recycling

Plasterboard manufacturers

Project coordination

Deconstruction companies

Deconstruction consultants

Recycling companies

Research centers

PROJECT INFORMATION: CONSORTIUM

Page 6: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

6 / 14 World Congress and Expo on Recycling

Project information - Main objectives – Work Plan - Impact

OVERALL AIM OF THE GtoG PROJECT

To transform the gypsum demolition waste market

To reach higher recycling rates of gypsum waste, thereby helping to achieve a

resource efficient economy.

Closed-loop recycling for gypsum products will only happen if:

Deconstruction techniques are applied for all demolition or refurbishment

projects;

Sorting of waste is done at source - avoiding C&D mixed waste;

Processing is carried out according to clear standards;

Reincorporation of the recycled materials in the production process is

carried out with innovative techniques.

Page 7: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

7 / 14 World Congress and Expo on Recycling

Project information - Main objectives – Work Plan - Impact

GtoG PROJECT SPECIFIC OBJECTIVES

To demonstrate the feasibility and advantages of deconstruction versus

demolition.

To qualify gypsum waste.

To reincorporate up to 30% of recycled gypsum (both pre and post-

consumer).

To develop European criteria for recycled gypsum to establish the EoW

status.

To reassess the percentage of recycled gypsum in the GPP for wall

panels (currently, 5%).

To assess the carbon footprint and methods to mitigate it.

Page 8: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

8 / 14 World Congress and Expo on Recycling

Project information - Main objectives – Work Plan - Impact

Deconstruction of

gypsum-based systems Gypsum waste

processing

(recycling)

Recycled

Gypsum

Deconstruction Gypsum waste characterisation

Gypsum waste processing

Manufacturing of plasterboard with recycled content

Page 9: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

9 /14 World Congress and Expo on Recycling

Project information - Main objectives – Work Plan - Impact

A. Preparatory Actions:

• A.1. Value Chain analysis in terms of deconstruction methodologies, economics of logistic and recycling

B. Implementation Actions:

• B.1. Eco-efficiency of deconstruction/segregation: Technical/Economic/market feasibility

• B.2. Valorisation of deconstruction waste.

• B.3. Towards sustainable lightweight systems

C. Monitoring Actions:

• C.1. Monitoring of the impact in the value chain (cradle to cradle approach)

D. Communication and Dissemination Actions:

• D.1 Communication and dissemination.

E. Project Management and Monitoring of the project progress:

• E.1 Coordination and monitoring

• E.2. After Life Communication Plan

WORK PLAN

Page 10: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

10 /14 World Congress and Expo on Recycling

Project information - Main objectives – Work Plan - Impact

ACTION A – PREPARATORY ACTIONS

Analysis of current practices:

- Deconstruction practices

- Recycling

- Plasterboard manufacturing practices

DELIVERABLES

DA1. Report: Inventory of current practices (September 2013)

DA2. Report: Inventory of best practices (December 2015)

Technical-Economic-Legislative-Environmental criteria

Page 11: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

11 /14 World Congress and Expo on Recycling

Project information - Main objectives – Work Plan - Impact

ACTION B – IMPLEMENTATION

European pilot projects (deconstruction – recycling – reincorporation of

the recycled gypsum) in BE, FR, UK and DE.

1. Pre-deconstruction audit and deconstruction of gypsum-based

construction systems.

2. Waste Acceptance criteria - Gypsum waste processing according to

– Recycled gypsum quality criteria

3. Demonstrate, at industrial level, the optimized value chain (up to

30% recycled gypsum content in new plasterboard)

DELIVERABLES

DB1: EU Handbook: best practices in deconstruction (March 2015)

DB2: EU manual for best practices in audit (March 2015)

DB3: Guidance on gypsum waste acceptance criteria (June 2015)

DB4: Report: Production process parameters (July 2015)

Page 12: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

12 /14 World Congress and Expo on Recycling

Project information - Main objectives – Work Plan - Impact

ACTION C - MONITORING OF THE IMPACT

OF THE PROJECT ACTIONS

- Definition of Best Practice Indicators

- Monitoring of deconstruction-recycling-reincorporation practices

(validating the effectiveness of the indicators applied in the pilot

projects)

- Road map and proposal of procedures for the implementation of a

sustainable value chain.

DELIVERABLES

DC1. Report: Best practice indicators for deconstruction, recycling and

reincorporation (July 2015)

DC2. Report: Specifications for recycled gypsum end-of-waste

DC3. Technical handbook and outline roadmap

Page 13: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

13 /14 World Congress and Expo on Recycling

Project information - Main objectives – Work Plan - Impact

SOCIO-ECONOMIC EXPECTED IMPACTS

- Makeover of the demolition industry;

- Influence the local authorities behaviour to encourage

deconstruction of buildings;

- Increase sustainability credentials of gypsum products in the local

economy;

- Push towards collection of plasterboard waste in the local areas;

- Improve the conditions for the uptake of a gypsum recycling

market.

Page 14: Gypsum to Gypsum (GtoG): The European Life+ project that aims … · 2017-02-02 · World Congress and Expo on Recycling 7 / 14 Project information - Main objectives – Work Plan

http://gypsumtogypsum.org/

An a d e G u zmán Báez a n a . d e g u z m a n @ u p m . e s

h t t p : / / b l o g s . u p m . e s / g i s c i / e n / h o m e /

THANK YOU VERY MUCH