H10 dismounting & Blue tankL.Gatignon / EN-MEF

TD Meeting 8 July 2009

1. Situation on the “terrain”2. Political situation

Page 2: H10 dismounting & Blue tank

Most of these quadrupoles will be needed for K12++

Page 3: H10 dismounting & Blue tank

Dismounted week July 1st

Page 4: H10 dismounting & Blue tank

Space is sufficient for preparations for October 2009 run

Page 5: H10 dismounting & Blue tank
Page 6: H10 dismounting & Blue tank
Page 7: H10 dismounting & Blue tank
Page 8: H10 dismounting & Blue tank

Other Experiments (Cont’d)• NA62

– The SPSC is once more impressed by the amount of progress ’in real time’

– The RK measurement has been presented at KAON-09, based on 40% of the data, as promised

– They have performed a successful test of the RICH400 prototype this year (st=60 ps)

– Good progress on GTK, STRAWs and LAV– The SPSC notes the good progress with the R&D program and

congratulates NA62 with the preliminary result on RK.– Now that NA60 has announced at the May workshop that they are

investigating a new location, it seems appropriate to take a decision on the dismounting of the NA60 experiment and the H10 beam. EN/MEF is asked by the SPSC to submit a memo to the management (S.Bertolucci, S.Myers) requesting this decision.

LG&SM, 09/07/2009 8SPSC92 Summary for IEFC

From SPSC92 summary to IEFC Committee on 9 July 2009:

Page 9: H10 dismounting & Blue tank

List of incompatibilies H10/NA60 – K12/NA62

• Need several magnets from H10 beam line (QNRB are not abailable elsewhere)

• Would have to switch ~15 power supplies between H10 and K12 beam line or buy ad install extra power supplies (new buildin needed)

• H10 beam line interferes with taking out anti rings for interventions

• NA60 apparatus blocks material access to big NA62 detectors (RICH, “MAMUD”, …)

Page 10: H10 dismounting & Blue tank

Other relevant input

• NA60 apparatus is old and needs to be consolidated in a significant manner

• At the New Opportunities Workshop in May NA60 announced that they understand that ECN3 is no longer a realistic option and that they are studying options elsewhere e.g. in EHN1

• NA60 would compete for proton time if in ECN3 (also true if in the H8 beam, except if we would take protons from T6 (but then COMAPSS forced to run at -200 GeV/c)

Page 11: H10 dismounting & Blue tank

T4 target station:

P42

H8

H6T4

Page 12: H10 dismounting & Blue tank

M2

P62a

2a

T6 target station:

T6