16
1

Hampshire Strategy Day - event.wwtonline.co.uk

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

1

Background

▪ Next to former Vosper Thorneycroft site

▪ Area of regeneration

▪ Built 1966

▪ Compliance issues

2

Pre-existing layout

3

PSTs

Inlet Works

Storm Tank

Sludge TankASP

FSTs

LLPS

Site Issues

• Main issues

• How to achieve performance on constrained site

• How to maintain performance on constrained site

• How to be a good neighbour in revitalised area

• Approach to answering these issues

• Integrated team

• Compliance planning

• Stakeholder engagement

Process Drivers

• New Total Nitrogen Permit

• UWWTR - 15 mg/l Annual Average (70% Removal)

• WRA - 15mg/l Annual Average

• Adherence with existing Permit from Historic Limitation

• FFT 427 l/s

• Inlet Screen performance

• Catchment Population Growth to 73000 pe

• Historic Odour Nuisance - new limits set to 1.5 ouE/m3 at nearest property

• Pre-requisite planning condition for regeneration and site

5

Process solution

6

Crude Sewer

Storm Screen

Inlet Screens

Terminal PS

FOGG Plant

Lamellas

UFS

BNR

MBR

Sludge Tanks

Centrifuges

Storm Tank

Odour Control Scrubbers

LLPS

Architectural Solution

Construction Sequence - 1

8

Construction Sequence - 2

9

Construction Sequence - 3

10

Construction Sequence - 4

11

Innovations

12

Membrane Technology

13

Membrane Technology

• Hollow fibre ultrafiltration MBR. Air and chemicals

are used for cyclical cleaning of the filters.

▪ Pore sizes (0.03 µm) small enough to retain

Bacteria & Viruses as well as solids.

• Treatment performance is already significantly

outperforming the Permit Conditions

• ~5 mg/l BOD vs. Target 25 mg/l

• ~5mg/l SS vs. Target 60 mg/l

• ~15mg/l Nitrogen vs. Target 15 mg/l or 75%

removal

• Nitrogen removal on target for meeting standards

once optimised following sludge plant

commissioning

14

UWWTR 24h composite samples (24 samples per year)

DateBIOCHEMICAL OXYGEN

DEMAND

(HOMOGENISED)

CHEMICAL OXYGEN

DEMAND (LOW LEVEL)

(HOM)

TOTAL NITROGEN

SOLIDS (SUSPENDED

AT 105C)

(HOMOGENISED)

11/07/2018 07:15 5.78 2.

20/07/2018 06:45 3.9 44.8 37.5 3.5

10/08/2018 06:45 6.3 43.9 49.7 3.

17/08/2018 06:32 3.69 38.1 31.8 2.

11/09/2018 06:46 3.22 33.2 18.3 2.

24/09/2018 10:15 1. 23.8 11.1 2.5

05/10/2018 07:24 3.43 26.3 14.4 2.

26/10/2018 09:01 2.46 23.2 13.9 2.

13/11/2018 06:55 2.12 14.4 11.2 2.

27/11/2018 11:22 1. 7.34 9.85 2.

04/12/2018 12:25 2.15 11.8 13.4 2.

08/12/2018 07:42 2.52 11.6 13.1 2.

13/12/2018 07:37 1. 19.7 17.7 2.

Summary

▪ Use of BNR and MBR at Woolston has enabled us to achieve high performance already before

completion on very constrained site.

▪ Digital engineering / BIM key to success in planning complex temporary and permanent works.

▪ Without stakeholder support the project would have been unbuildable and vastly more

expensive solutions would have been required.

15

END