Hans INGVARSSON, edited by Martin Steward for CEDR TGR 22 Jan 09
ERA-NET ROAD
CEDR TGR meeting 22nd of January 2009, Brussels
ENR Work Package 6 - Progress Report
New trans-national research formulation and implementation
Work Package Progress and Risk Report 2
First Joint Funded Research Programme
50 000 € per country in 3 years, in total 1.65 M €
• Austria (PEB Chair)• Denmark• Finland• Germany• Ireland• Norway• Poland• Spain• Sweden (PL)• The Netherlands• United Kingdom
Work Package Progress and Risk Report 3
SRO 3 PEB Progress
• Selected Project Proposals (Project Costs incl. VAT) - RIMAROCC (Sweden, France, the Netherlands and Norway) 366 000
Euro - IRWIN (Finland and Sweden) 320 000 Euro - P2R2C2 (UK, Finland, Norway and Slovenia) 214 000 Euro - SWAMP (Denmark and Sweden) 289 000 Euro
1 189 000 Euro• Evaluation Principles
- Excellence- Transparency- Fairness and Impartiality- Confidentiality- Efficiency and Speed
• Selection Criteria- Competence (10 %)- Experience (10 %)- Content (50 %)- Management (20 %)- Quality Price Ratio (10 %)
Work Package Progress and Risk Report 4
WP 6 – Task 2
ENR1 WP 6 Interregnum Programme (Task 2):
Make Second Joint Programme/Call in Spring 2009
Actions to undertake:
1. Review SROs and hold further workshop if necessary.
2. Develop 2nd call, using same methodology as SRO3 call.
3. Complete in Spring 2009, to coincide with start of ENR2.
Work Package Progress and Risk Report 5
CA & DoRN (SRO1)
Work Package Progress and Risk Report 6
SRO 1 Commitments
Participating countries:• Austria• Belgium (Flanders)• Finland• Germany• Ireland• Norway• Slovenia• Sweden• The Netherlands• United Kingdom
Perhaps:• Denmark• SwitzerlandNo wish to participate:• France• Poland
To date no response:• Belgium (Wallonia)• Hungary• Lithuania
Work Package Progress and Risk Report 7
SRO 1 Commitments
Participating countries:• Austria• Belgium (Flanders)• Finland• Germany• Ireland• Norway• Slovenia• Sweden• The Netherlands• United Kingdom
PEB Chair (offer):• Austria• Sweden
Programme Leader (offer)
• Austria
Work Package Progress and Risk Report 8
PEB (SRO 1)
Country PEB Member Deputy PEB Member
Austria Christian Pecharda (PL)
Günter Breyer
Belgium (Flanders) Armand Rouffaert ?
Finland Saara Toivonen Mikko Räsänen
Germany Roland Weber Stefan Matena
Ireland Harry Cullen Albert Daly
Norway Jon Krokeborg Randi Eggen
Slovenia Tomaž Pavčič Bojan Leben
Sweden Claes Tingvall (Chair)
Per Strömgren
The Netherlands Herman Moning Karin Holthuis
United Kingdom Sandra Brown Graham Harper
Work Package Progress and Risk Report 9
WP 6 Progress (Milestones)
Milestones:
1. SRO chosen for further ellaboration (Cracow 4 September 2009).2. SRO workshop undertaken (Copenhagen 18 -19 November 2009).3. Task Force set up (Ljubljana 18 December 2009).4. Description of Research Needs (DoRN) exists (5 January 2009).5. SRO 1 PEB set up (Brussels 20 January 2009)6. Kick Off Meeting undertaken (in Malmö on 3rd of February 2009)7. Second Joint Call launched (to be done 1st half of February 2009).8. CA’s (with appended DoRN’s) signed by all participating NRAs at latest at
the end of March 2009.9. Second Joint Call closed (1st half of April 2009)10. Selection of approved project proposals (to be finalized in MidMay 2009).11. Evaluate project proposals/applications (end of April and beginning of May
2009).12. Contract Negotiations will take place during June 2009.13. Start of approved projects is foreseen in July 2009 by signing Project
Contracts.
Hans Ingvarsson (WP6 Leader)
ERA-NET ROAD (WP 6)
Interregnum Mission
Almost Completed !