Copyright 2012 Tokyo Electric Power Company All Rights Reserved 1
TEPCO Media Correspondence following the Fukushima Nuclear Accident
Kazuhiro HasegawaGeneral Manager
Corporate Communications DepartmentTokyo Electric Power Company
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 2
The Power Plants immediately after the Earthquake
Hirono TPS [3,800MW]Hirono TPS [3,800MW]
Kashiwazaki-Kariwa Nuclear PS [8,210MW]
Fukushima Daiichi Nuclear PS [4,700MW]Fukushima Daiichi Nuclear PS [4,700MW]
PS shut down due to the earthquake
PS not shut down due to the earthquakePS restored after the shut down due to the earthquake
Fukushima Daini Nuclear PS [4,400MW]Fukushima Daini Nuclear PS [4,400MW]
Hitachinaka TPS [1,000MW]Hitachinaka TPS [1,000MW]
Kashima TPS [4,400MW]Kashima TPS [4,400MW]
52,000MW
31,000MW
Beforethe earthquake
Shortly afterthe earthquake
Decreased supply capacitydue to the earthquake
On March 11, 2011, our power plants near the coast of Pacific Ocean were severely damaged by the Earthquake.
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 3
After the Earthquake
After the earthquake, TEPCO had to simultaneously handle media activities for both Fukushima Daiichi accident and the planned blackouts.
Source: TEPCO, March 15, 2011
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 4
Emergency Control Room (HQ and Fukushima Daiichi) Immediately after the earthquake, we set up the emergency control room
and started communicating with Fukushima Daiichi NPS. The communication team received info concerning the accident in this
room. Fukushima Daiichi TEPCO HQ
Interconnected via aTV Conference System
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 5
External Organizational Structure & Info Flow
TEPCO
HQ
1F*
Off-site Center
FukushimaPref.
GoJ
Cabinet Office
NISA
Actual
Office of PM
NISA
HQ
1F*
Off-site Center
FukushimaPref.
Tokyo
Fukushima
Planned
Did not function
On the day of the earthquake, we established our communication organization.
Though the Off-site Center was responsible for managing media correspondence activities in an integrated fashion, it did not function as planned.
*1F: Fukushima Daiichi NPS
TEPCO
GoJ
Cabinet Office
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 6
Media Correspondence Activities
Media Correspondence Result (March 11, 2011-March 31, 2012) Remarks
Press Releases
• Total: 3,902 Nuclear power station: 3,597, power
supply/demand: 124, compensation: 29, others: 152
• About 10/ Day
Press Conference
TEPCO
• Total: 877 Nuclear power station:833, power
supply/demand: 30, compensation: 5, management: 9
• Total: 966 (Approx. 2.5/ Day)
Joint • Total: 89 (April 25-December 16)
Phone Inquiries Answered • Total: Approx. 19,000 • About 50/ Day
Site Tour • Total: 4 (Fukushima Daiichi)
Web Page
• The website includes not only press releases, but also explanatory videos, pictures, documents, plant related parameters, monitoring results, and live press conferences.
• Twitter: TEPCO_English• YouTube: OfficialTEPCOen
We have been engaged in media correspondence activities day and night, such as press conferences, answering phone inquiries, and updating our homepage.
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 7
Press Releases
After the Earthquake, TEPCO issued approximately 3,900 press releases that mainly dealt with the accident.
0
50
100
150
200
250
300
350
400
450
Num
ber
of P
ress
Rel
ease
s
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 8
0
500
1000
1500
2000
2500
3000
Num
ber
of p
hone
-cal
ls
Telephone Correspondence
Immediately after the earthquake, TEPCO received a tremendous number of media telephone calls from not only within Japan but also from all over the world.
There was a variety of questions regarding Fukushima Daiichi NPS, electricity demand and supply, TEPCO management, compensation, etc.
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 9
Press Conference Since March 11, 2011, TEPCO has held 877 press conferences. From April 25 to December 16, 2011, 89 GoJ-TEPCO joint press conferences
were held.
0
20
40
60
80
100
120
140
Num
ber
of c
onfe
renc
es
2011 2012
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 10
TEPCO’s Website TEPCO’s website covers information on the accident, compensation
payouts, and power supply, etc. In principle, TEPCO provides English translations for all press releases. The website includes not only press releases, but also explanatory videos,
pictures, documents, plant related parameters, monitoring results, and live press conferences.
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 11
Fukushima Daiichi Press Tours TEPCO has held four press tours to Fukushima Daiichi. 2011: November 11 (J-Village) and 12 (1F) 2012: February 20, February 28, and May 26
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 12
Lessons Learned from my point of view
Were we well prepared? Off-site Center did not work as expected before Never thought of planned blackouts Personnel Issues
Have we disclosed everything? Tried to disclose everything but slow A matter of trust
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 13
Thank you for your attention.
Kazuhiro HasegawaGeneral Manager
Corporate Communications DepartmentTokyo Electric Power CompanyEmail: [email protected]
Copyright 2012 Tokyo Electric Power Company All Rights Reserved 14
【 Ref. 】 Internal Organizational Structure TEPCO established internal functional teams, such as the communication
team (documentation and Q&A preparation), the media correspondence team and the media telecommunications team.
Communication Team• Prepares explanatory documents and Q&As• Situated in the HQ Emergency Control Room• Covers ONLY Fukushima Daiichi Matters
Media Correspondence Team• Manages press conferences and interviews• Covers ONLY Fukushima Daiichi Matters
Departments in chargeFukushima Daiichi NPS
Communication Team• Covers issues outside of
Fukushima Daiichi matters• Prepares explanatory
documents and Q&As• Also manages press
conferences and interviews• Situated in TEPCO HQ
Info Source
Documentation
Media Contact
Nuclear Related MattersOther Matters
(Compensation, Power Supply, Tariff, Business Plan, Finance, etc.)
Media Telecommunications Team• Answers phone inquiries • Covers all matters
Nuclear Related Departments
Fukushima Daiichi Stabilization Center