NHSSCOTLAND PROJECT FACT FILE Health Facility Project Name Replacement Tain Health Centre Location Craighill Terrace Tain Ross-shire IV19 9EU Population served Just under 9,000 in Tain and surrounding areas Type of healthcare facility Health Centre Type of construction New Build Construction start date (estimated or actual) Estimated June 2013 Construction completion date Estimated June 2014 Gross floor area (m 2 ) 1,660 Project, design and construction cost Total Capex (excluding VAT) £4,045,839 Land Purchase £300,000 Equipment (estimated) £400,000 Cost per m 2 £2,437.25 (Capex only excludes VAT) Total bed numbers N/A Departmental information 2 GP Practices Dental Unit Community Accommodation Only significant equipment is dental chairs, X-ray, etc Client/owner NHS Highland http://www.nhshighland.scot.nhs.uk/

Health Facility Project Fact File - pcpd.scot.nhs.uk · Health Facility Project Name ... General Dental Services provided by salaried dental staff ... NHS Highland C 1 : 200 First

  • Upload
    ledieu

  • View
    215

  • Download
    1

Embed Size (px)

Citation preview

NHSSCOTLAND PROJECT FACT FILE

Health Facility Project Name

Replacement Tain Health Centre

Location

Craighill Terrace Tain Ross-shire IV19 9EU

Population served

Just under 9,000 in Tain and surrounding areas

Type of healthcare facility

Health Centre

Type of construction

New Build

Construction start date (estimated or actual)

Estimated June 2013

Construction completion date

Estimated June 2014

Gross floor area (m2)

1,660

Project, design and construction cost

Total Capex (excluding VAT) £4,045,839 Land Purchase £300,000 Equipment (estimated) £400,000

Cost per m2

£2,437.25 (Capex only excludes VAT)

Total bed numbers

N/A

Departmental information

2 GP Practices

Dental Unit

Community Accommodation

Only significant equipment is dental chairs, X-ray, etc

Client/owner

NHS Highland http://www.nhshighland.scot.nhs.uk/

Project Manager/Key contact(s)

John Bogle [email protected] 01955 880200

Capital procurement route

hub

Project management

The hub project management is being carried out by Sweett Group Contact Robert Dunlop [email protected] NHS Project Manager as above

Architects

Keppie

Contractor

Miller Construction

Services

General Medical Services provided by 2 GP practices General Dental Services provided by salaried dental staff Community Nursing, Midwifery, Health Visiting, Podiatry, Physiotherapy

Key facts

Tain Health Centre is being provided as part of a bundle of 3 health centres with NHS Grampian. It is the first bundled revenue project in Scotland and the first to cover 2 Board areas. The aspiration is to achieve BREEAM Excellent. The site occupies a position that will provide commanding views over the Dornoch Firth. A Care Home is to be built by others adjacent to the health centre and the opportunity is being taken to share services where possible and therefore reduce the costs for both parties. The new facility will replace the current Tain Health Centre which is cramped and no longer fir for purpose, it will also replace the current Tain Dental Clinic which is a converted residential property spread across the first and second floors of an old building with no disabled access.

51.0 m²Community Administration

45

(51.0 m²)

15.0 m²Community Lead

44

(15.0 m²)

9.0 m²Dental Reception

15

(9.0 m²)

19.1 m²Dental Support Office

16

(19.0 m²)

15.2 m²Dental Treatment 1

48

(15.0 m²)

15.2 m²Dental Treatment 2

49a

(15.0 m²)

15.1 m²Dental Treatment 3

49b

(15.0 m²)

18.4 m²Dental Treatment 4

49c

(17.0 m²)

11.8 m²Preventative & X-Ray

50

(12.0 m²)

19.7 m²LDU

51

(16.0 m²)

9.7 m²LDU DSR

61a

(7.0 m²)10.9 m²

Clinical Office54

(11.0 m²)

20.4 m²Dental Store

63b

(16.0 m²)

3.5 m²Compressor

65

(6.0 m²)

5.0 m²Disabled WC

09a

(4.5 m²)

23.8 m²Circ 8

72h

(0.0 m²)

15.3 m²Circ 9

72i

(0.0 m²)

7.1 m²Lift75a

(7.5 m²)

2.7 m²Patient WC

10e

(0.0 m²)

13.8 m²Stair74d

(15.0 m²)

14.0 m²Stair74e

(0.0 m²)

14.4 m²Stair74f

(15.0 m²)

9.0 m²DSR 2

61b

(9.0 m²)

2.9 m²Wheelchair Allowance

06b

(3.0 m²)

2.9 m²Patient WC

10f

(0.0 m²)

0.6 m²Elec69c

(1.5 m²)

0.6 m²HM73h

(0.0 m²)

14.7 m²Void

73

(0.0 m²)

35.4 m²Staff Rest

60a

(35.0 m²)

19.0 m²Female Changing

56

(19.5 m²)

3.3 m²Shower

59b

(3.3 m²)

2.7 m²Staff WC

58f

(2.2 m²)

2.7 m²Staff WC

58e

(2.2 m²)

3.1 m²Shower

59a

(3.3 m²)7.6 m²

Male Changing57

(7.5 m²)

7.5 m²Switch

69a

(7.5 m²)

36.8 m²Multi-Purpose Room

12

(36.0 m²)

2.1 m²Equipment Store

14

(2.0 m²) 3.9 m²Furniture Store

13

(4.0 m²)

0.5 m²HM73g

(0.0 m²)

0.8 m²HM73i

(0.0 m²)

6.1 m²Circ 10

72j

(0.0 m²)

22.3 m²Dental Waiting

04

(22.0 m²)

10.2 m²GP Office

23

(10.0 m²)

41.0 m²Circ 7

72g

(0.0 m²)

2.7 m²Staff WC

58d

(2.2 m²)

23.1 m²GP Waiting

03a

(45.0 m²)

9.6 m²Lobby

01

(0.0 m²)

16.6 m²GP Consulting 1

28

(16.5 m²)15.0 m²

GP Consulting 229a

(15.0 m²)15.0 m²

GP Consulting 429c

(15.0 m²)

14.9 m²GP Consulting 5

29d

(15.0 m²)15.0 m²

GP Consulting 629e

(15.0 m²)15.0 m²

GP Consulting 729f

(15.0 m²)

16.5 m²GP Consulting 8

31

(16.5 m²)15.0 m²

GP Consulting 932a

(15.0 m²)14.8 m²

GP Consulting 1032b

(15.0 m²)

15.1 m²GP Consulting 11

32c

(15.0 m²)

15.1 m²Treatment 1

30b

(15.0 m²)

40.9 m²Fearn Administration

20

(39.5 m²)

15.0 m²Practice Manager

22

(15.0 m²)

28.1 m²Tain Administration

24

(26.5 m²)

14.8 m²Practice Manager

26

(15.0 m²)

12.0 m²GP Office

27

(12.0 m²)

15.0 m²Treatment 3

33

(15.0 m²)

27.0 m²Circ 3

72c

(0.0 m²)

15.0 m²Treatment 2

30a

(15.0 m²) 15.0 m²GP Consulting 12

32d

(15.0 m²)

11.6 m²Clinical Store 1

36a

(11.5 m²)

9.9 m²IT Server

67

(10.0 m²)

4.8 m²Tain Reception

18

(4.5 m²)

4.8 m²Fearn Reception

17

(4.5 m²)

2.0 m²Stationary

38b

(2.0 m²)

2.7 m²Patient WC

10c

(2.5 m²)

2.7 m²Patient WC

10d

(2.5 m²)

9.5 m²Childrens Play

07a

(9.0 m²)

1.4 m²Info Point

08

(1.0 m²)

3.0 m²Stationary

38a

(3.0 m²)

56.8 m²Circ 1

72a

(335.3 m²)

3.4 m²Staff WC

58a

(2.2 m²)

9.9 m²Circ 5

72e

(0.0 m²)

40.0 m²Circ 4

72d

(0.0 m²)

15.3 m²Community Store

04c

(15.0 m²)

27.6 m²Circ 2

72b

(0.0 m²)

9.1 m²DSR 3

61c

(9.0 m²)

6.7 m²Disabled WC

09b

(4.5 m²)

2.7 m²Patient WC

10a

(2.5 m²)

2.8

Wheelc

hair A

llow

ance

06a

(3.0

m²)

2.7 m²Patient WC

10b

(2.5 m²)

15.0 m²GP Consulting 3

29b

(15.0 m²)

Departments

A - Entrance & Reception

B - Fearn GP Practice

C - Tain GP Practice

E - Community Unit

G - Services

H - Staff Facilities

J - Circulation

2.0 m²Pram Space

72k

(0.0 m²)

6.5 m²Lift75b

(7.5 m²)

22.0 m²GP Waiting

03b

(0.0 m²)

5.7 m²Baby Changing

11

(4.5 m²)

13.9 m²Stair74a

(15.0 m²)

14.5 m²Stair74c

(15.0 m²)

7.6 m²Clinical Store 2

36b

(7.5 m²)

2.7 m²Staff WC

58b

(0.0 m²)

0.4 m²HM73b

(0.0 m²)

0.5 m²HM73a

(0.0 m²)

0.7 m²Elec69b

(1.5 m²)

0.6 m²HM73e

(0.0 m²)

44.0 m²Physiotherapy Treatment

43

(44.0 m²)

15.0 m²Clinical Treatment 2

39b

(15.0 m²)

15.0 m²Clinical Treatment 1

39a

(15.0 m²)

17.5 m²Clinical Consulting 3

40c

(15.0 m²)

2.4 m²Staff WC

58c

(2.2 m²)

10.1 m²Clinical Interview 1

41a

(10.0 m²)

10.1 m²Clinical Interview 2

41b

(10.0 m²)

14.9 m²Clinical Consulting 2

40b

(15.0 m²)

14.9 m²Clinical Consulting 1

40a

(15.0 m²)

16.0 m²Podiatry Treatment

42

(16.0 m²)

8.6 m²Community Reception

45a

(8.5 m²)

12.7 m²Stair74b

(0.0 m²) 5.3 m²Community Waiting

05

(5.0 m²)

3.0 m²Tain Interview

18a

(0.0 m²)2.1 m²Fearn Interview

17a

(0.0 m²)

16.7

Wate

r S

erv

ices P

lant R

oom

76 ?

0.5 m²HM73c

(0.0 m²)

0.5 m²HM73d

(0.0 m²)

0.6 m²HM73f

(0.0 m²)

Access tounderstair store

Access tounderstair store

Access tounderstair store

Status

keppie

Project No.

Drawing No.

Drawing

Created ●

Rev

Date ● Scale ●

BELFAST ● EDINBURGH ● GLASGOW ● INVERNESS ● MANCHESTER ● PERTH

Checked ●

@A1

architecture ● interior design ● planning ● landscape ● urban design

www.keppiedesign.co.uk

INVERNESS

Copyright, Keppie Design, Ltd ©

Figured dimensions only are to be taken from this drawing.All dimensions are to be checked on site before any work is put inhand. IF IN DOUBT ASK.

CDM:Hazard Elimination & Risk Reduction has been undertaken andrecorded where appropriate, in accordance with the requirementsof "The Construction (Design and Management) Regulations 2007"and the "Industry Guidance for Designers"

Project

Client

Drawn: Chk'd: Date:

Revision

Drawn: Chk'd: Date:

Revision

Drawn: Chk'd: Date:

Revision

Drawn: Chk'd: Date:

Revision

Drawn: Chk'd: Date:

Revision

Dochfour Business CentreDochgarrochInvernessIV3 8GYTel: 01463 246 850

1 : 200

PL(20)001

209609

INFORMATION

LASS

14/03/12

Ground Floor Plan / First FloorPlan / Roof Plan

Tain Health Centre

Alba Community Partnerships /NHS Highland

C

1 : 200

First Floor Plan.

Room Schedule by Department

Number Room Name Area

BriefedArea

AreaSum

J - Circulation

01 Lobby 9.5 0.0 9.5

72a Circ 1 57.0 335.5 -278.5

72b Circ 2 27.5 0.0 27.5

72c Circ 3 27.0 0.0 27.0

72d Circ 4 40.0 0.0 40.0

72e Circ 5 10.0 0.0 10.0

72g Circ 7 41.0 0.0 41.0

72h Circ 8 24.0 0.0 24.0

72i Circ 9 15.5 0.0 15.5

72j Circ 10 6.0 0.0 6.0

72k Pram Space 2.0 0.0 2.0

74a Stair 14.0 15.0 -1.0

74b Stair 12.5 0.0 12.5

74c Stair 14.5 15.0 -0.5

74d Stair 14.0 15.0 -1.0

74e Stair 14.0 0.0 14.0

74f Stair 14.5 15.0 -0.5

75a Lift 7.0 7.5 -0.5

75b Lift 6.5 7.5 -1.0

356.0 410.5 -54.0

K - Other

73 Void 14.5 0.0 14.5

14.5 0.0 14.5

Grand total: 121 1482.5 1463.5 2.5

Room Schedule by Department

Number Room Name Area

BriefedArea

AreaSum

G - Services

61a LDU DSR 9.5 7.0 2.5

61b DSR 2 9.0 9.0 -0.0

61c DSR 3 9.0 9.0 0.0

65 Compressor 3.5 6.0 -2.5

67 IT Server 10.0 10.0 -0.0

69a Switch 7.5 7.5 0.0

69b Elec 0.5 1.5 -1.0

69c Elec 0.5 1.5 -1.0

73a HM 0.5 0.0 0.5

73b HM 0.5 0.0 0.5

73c HM 0.5 0.0 0.5

73d HM 0.5 0.0 0.5

73e HM 0.5 0.0 0.5

73f HM 0.5 0.0 0.5

73g HM 0.5 0.0 0.5

73h HM 0.5 0.0 0.5

73i HM 1.0 0.0 1.0

76 Water Services PlantRoom

16.5

71.5 51.5 3.5

H - Staff Facilities

56 Female Changing 19.0 19.5 -0.5

57 Male Changing 7.5 7.5 0.0

58a Staff WC 3.5 2.0 1.0

58b Staff WC 2.5 0.0 2.5

58c Staff WC 2.5 2.0 0.0

58d Staff WC 2.5 2.0 0.5

58e Staff WC 2.5 2.0 0.5

58f Staff WC 2.5 2.0 0.5

59a Shower 3.0 3.5 -0.0

59b Shower 3.5 3.5 -0.0

60a Staff Rest 35.5 35.0 0.5

85.0 79.5 5.5

Room Schedule by Department

Number Room Name Area

BriefedArea

AreaSum

E - Community Unit

04c Community Store 15.5 15.0 0.5

39a Clinical Treatment 1 15.0 15.0 -0.0

39b Clinical Treatment 2 15.0 15.0 -0.0

40a Clinical Consulting 1 15.0 15.0 -0.0

40b Clinical Consulting 2 15.0 15.0 -0.0

40c Clinical Consulting 3 17.5 15.0 2.5

41a Clinical Interview 1 10.0 10.0 0.0

41b Clinical Interview 2 10.0 10.0 0.0

42 Podiatry Treatment 16.0 16.0 -0.0

43 Physiotherapy Treatment 44.0 44.0 0.0

44 Community Lead 15.0 15.0 -0.0

45 Community Administration 51.0 51.0 -0.0

45a Community Reception 8.5 8.5 0.0

247.0 244.5 2.5

F - Dental

16 Dental Support Office 19.0 19.0 0.0

48 Dental Treatment 1 15.0 15.0 0.0

49a Dental Treatment 2 15.0 15.0 0.0

49b Dental Treatment 3 15.0 15.0 0.0

49c Dental Treatment 4 18.5 17.0 1.5

50 Preventative & X-Ray 12.0 12.0 -0.0

51 LDU 19.5 16.0 3.5

54 Clinical Office 11.0 11.0 -0.0

63b Dental Store 20.5 16.0 4.5

146.0 136.0 10.0

Room Schedule by Department

Number Room Name Area

BriefedArea

AreaSum

B - Fearn GP Practice

20 Fearn Administration 41.0 39.5 1.5

22 Practice Manager 15.0 15.0 0.0

23 GP Office 10.0 10.0 0.0

28 GP Consulting 1 16.5 16.5 0.0

29a GP Consulting 2 15.0 15.0 -0.0

29b GP Consulting 3 15.0 15.0 -0.0

29c GP Consulting 4 15.0 15.0 0.0

29d GP Consulting 5 15.0 15.0 -0.0

29e GP Consulting 6 15.0 15.0 -0.0

29f GP Consulting 7 15.0 15.0 -0.0

30a Treatment 2 15.0 15.0 -0.0

30b Treatment 1 15.0 15.0 0.0

36a Clinical Store 1 11.5 11.5 0.0

38a Stationary 3.0 3.0 0.0

217.0 215.5 1.5

C - Tain GP Practice

24 Tain Administration 28.0 26.5 1.5

26 Practice Manager 15.0 15.0 -0.0

27 GP Office 12.0 12.0 -0.0

31 GP Consulting 8 16.5 16.5 0.0

32a GP Consulting 9 15.0 15.0 -0.0

32b GP Consulting 10 15.0 15.0 -0.0

32c GP Consulting 11 15.0 15.0 0.0

32d GP Consulting 12 15.0 15.0 0.0

33 Treatment 3 15.0 15.0 0.0

36b Clinical Store 2 7.5 7.5 0.0

38b Stationary 2.0 2.0 0.0

156.0 154.5 1.5

Room Schedule by Department

Number Room Name Area

BriefedArea

AreaSum

A - Entrance & Reception

03a GP Waiting 23.0 45.0 -22.0

03b GP Waiting 22.0 0.0 22.0

04 Dental Waiting 22.5 22.0 0.5

05 Community Waiting 5.5 5.0 0.5

06a Wheelchair Allowance 3.0 3.0 -0.0

06b Wheelchair Allowance 3.0 3.0 -0.0

07a Childrens Play 9.5 9.0 0.5

08 Info Point 1.5 1.0 0.5

09a Disabled WC 5.0 4.5 0.5

09b Disabled WC 6.5 4.5 2.0

10a Patient WC 2.5 2.5 0.0

10b Patient WC 2.5 2.5 0.0

10c Patient WC 2.5 2.5 0.0

10d Patient WC 2.5 2.5 0.0

10e Patient WC 2.5 0.0 2.5

10f Patient WC 3.0 0.0 3.0

11 Baby Changing 5.5 4.5 1.0

12 Multi-Purpose Room 37.0 36.0 1.0

13 Furniture Store 4.0 4.0 -0.0

14 Equipment Store 2.0 2.0 0.0

15 Dental Reception 9.0 9.0 -0.0

17 Fearn Reception 5.0 4.5 0.5

17a Fearn Interview 2.0 0.0 2.0

18 Tain Reception 5.0 4.5 0.5

18a Tain Interview 3.0 0.0 3.0

189.5 171.5 18.0

Area Schedule (GIA)

Ground Floor GIA 959.5 m²

First Floor GIA 580.8 m²

1540.4 m²

1 : 200

Ground Floor Plan 1 : 200

Roof P lanLASS 19/02/12

A Client amendments to Dental. X-ray developing roomremoved / compressor room reduced / area added tostore

SS LA 06/06/12

B Client amendments to Dental.

SS LA 27/06/12

C Client amendments - stores added understairs.

SS AK 27/06/12

Ground Floor

0.0

First Floor

3300.0

Horizontal Larch Cladding Dark Gray roof tilesWhite render Dark Gray aluminiumfaced curtain wall

Timber Cladding

Ground Floor

0.0

First Floor

3300.0

Horizontal Larch Cladding Dark Gray roof tilesColoured render Dark Gray aluminiumfaced curtain wall

Timber Cladding

Ground Floor

0.0

First Floor

3300.0

Horizontal Larch Cladding Dark Gray roof tiles White render

Ground Floor

0.0

First Floor

3300.0

Horizontal Larch Cladding Dark Gray roof tilesWhite render Stone teature wall Horizontal Larch Cladding

Ground Floor

0.0

First Floor

3300.0

Horizontal Larch CladdingDark Gray roof tiles White renderDark Gray aluminiumfaced curtain wall

Ground Floor

0.0

First Floor

3300.0

Horizontal Larch CladdingDark Gray roof tiles

White render

Ground Floor

0.0

First Floor

3300.0

Wall head

6000.0

3000.0

Ground Floor

0.0

First Floor

3300.0

Wall head

6000.0

2700.0

Status

keppie

Project No.

Drawing No.

Drawing

Created ●

Rev

Date ● Scale ●

BELFAST ● EDINBURGH ● GLASGOW ● INVERNESS ● MANCHESTER ● PERTH

Checked ●

@A1

architecture ● interior design ● planning ● landscape ● urban design

www.keppiedesign.co.uk

INVERNESS

Copyright, Keppie Design, Ltd ©

Figured dimensions only are to be taken from this drawing.All dimensions are to be checked on site before any work is put inhand. IF IN DOUBT ASK.

CDM:Hazard Elimination & Risk Reduction has been undertaken andrecorded where appropriate, in accordance with the requirementsof "The Construction (Design and Management) Regulations 2007"and the "Industry Guidance for Designers"

Project

Client

Drawn: Chk'd: Date:

Revision

Drawn: Chk'd: Date:

Revision

Drawn: Chk'd: Date:

Revision

Drawn: Chk'd: Date:

Revision

Drawn: Chk'd: Date:

Revision

Dochfour Business CentreDochgarrochInvernessIV3 8GYTel: 01463 246 850

1 : 200

PL(25)001

209609

PLANNING

LASS

14/03/12

Elevations / Sections /Perspective

Tain Health Centre

Alba Community Partnerships /NHS Highland

-

1 : 200

East Elevation 2

1 : 200

Front Elevation (East Elevation)

1 : 200

North Elevation 1 : 200

South Elevation to Craighill Terrace

1 : 200

West Elevation 1

1 : 200

West Elevation 2

1 : 200

Section thru Community / Dental 1 : 200

Section thru GP wing

External MaterialsWallsWhite wet dash renderPainted smooth renderHorizontal larch claddingStone feature walls at entrance.Brick basecourse

RoofDark grey roof tiles to main buildingSingle ply roof over projection

Windows and DoorsDark grey aluminum faced timber windows or dark grey curtain walling to front entrance

Perspective view of Front Entrance