Upload
bmgaris
View
644
Download
0
Embed Size (px)
Citation preview
HIBERNIA MANAGEMENT AND DEVELOPMENT COMPANY LTD
FLARE SYSTEM REVALIDATION STUDY
TECHNICAL NOTE
DOCUMENT NO : 8266-HIB-TN-C-0001
REVISION : B
DATE : October 2000
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
1
DOCUMENT REVISION RECORD
REV DATE DESCRIPTION PREPARED CHECKED APPROVED
Draft 21/07/00 Issued for IDC M. Goodman A. Robinson M. Goodman
A 23/08/00 Issued for Comment / Final M. Goodman A. Robinson M. Goodman
B 16/10/00 Final M. Goodman A. Robinson M. Goodman
RELIANCE NOTICE
This report is issued pursuant to an Agreement between Granherne (Holdings) Limited and/or its subsidiary or affiliate companies (“Granherne”) and HIBERNIA MANAGEMENT AND DEVELOPMENT COMPANY LTD which agreement sets forth the entire rights, obligations and liabilities of those parties with respect to the content and use of the report.
Reliance by any other party on the contents of the report shall be at its own risk. Granherne makes no warranty or representation, expressed or implied, to any other party with respect to the accuracy, completeness, or usefulness of the information contained in this report and assumes no liabilities with respect to any other party’s use of or damages resulting from such use of any information, conclusions or recommendations disclosed in this report.
Title:
FLARE SYSTEM REVALIDATION STUDY
QA Verified:
TECHNICAL NOTE Date:
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
2
CONTENTS
FRONT PAGE
DOCUMENT REVISION RECORD
CONTENTS
ABBREVIATIONS
HOLDS
1.0 INTRODUCTION
2.0 SUMMARY AND CONCLUSIONS
2.1 Introduction
2.2 Technical Audit of the Design Calculations
2.3 Challenge Process
2.4 As-Building the Flare System
2.5 Risk Management in Relation to Wind Condition and Flaring Events
2.6 Implications for Hibernia
2.6.1 Introduction
2.6.2 Capacity Opportunities
2.6.3 Impact on the Design Documentation
2.6.4 Future Work
3.0 DESIGN BASIS
3.1 Introduction
3.2 Safety Design Basis
3.2.1 Probabilistic Design Criteria
3.2.2 Deterministic Design Criteria
4.0 APPROACH
4.1 General
4.1.1 Flare System Revalidation Process
4.1.2 Legislative Obligations of HMDC’s Safety Design Philosophy
4.1.3 The Requirements of the Standards, Codes of Practice and Recommended
Practices
4.1.4 Ambiguities in the Recommended Practices
4.2 Calculation Audit
4.3 Challenge Process
4.4 Risk Management in Relation to Flaring Events and Wind Condition
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
3
5.0 TECHNICAL AUDIT OF THE DESIGN CALCULATIONS
5.1 Introduction
5.2 Results of the Technical Audit – Relief and Blowdown System Calculations
5.2.1 Technical Audit Issue Discussion – Relief and Blowdown System Calculations
5.3 Results of the Technical Audit – Relief Valve Sizing Calculations
5.3.1 Technical Audit Issue Discussion – Relief Valve Calculations
5.4 Technical Audit Conclusion Summary
6.0 CHALLENGE PROCESS
6.1 Introduction
6.1.1 The Principles of the Legislation
6.1.2 Relevant Canadian Legislation
6.1.3 Applying the Legislation
6.2 Jet Fire
6.2.1 Requirements of the relevant regulations, design codes and practices when
Hibernia was designed
6.2.2 How Jet Fire Was Actually Handled During Design
6.2.3 Current Requirements of the Design Codes and Practices
6.2.4 Current Best Industry Practice
6.2.5 The Effect of Applying Current Best Industry Practise to Hibernia
6.2.6 Jet Fire Conclusions
6.3 Blowdown (Depressuring) System Sizing
6.3.1 Requirements of the Codes, Guides, Standards and Recommended Practices
When Hibernia was Designed
6.3.2 How the System was Designed
6.3.3 Current Requirements of the Codes and Recommended Practices
6.3.4 Current Best Industry Practice
6.3.5 The Effect of Applying Current Industry Practice to Hibernia
6.4 Compressor Blowdown Stagger
6.4.1 Requirements of the Codes, Guides, Standards and Recommended Practices
When Hibernia was Designed
6.4.2 How the System was Designed
6.4.3 Current Requirements of the Codes and Recommended Practices
6.4.4 Current Best Industry Practice
6.4.5 The Effect of Applying Current Industry Practice to Hibernia
6.5 Two-Phase Relief
6.5.1 Requirements of the Codes, Guides, Standards and Recommended Practices
When Hibernia was Designed
6.5.2 How the System was Designed for Two-Phase Relief
6.5.3 Current Requirements Of The Codes And Recommended Practices
6.5.4 Current Best Practice
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
4
6.5.5 The Effect of Applying Best Industry Practice to Hibernia
6.6 Design Windspeed and Direction
6.6.1 Requirements of the Codes, Guides, Standards and Recommended Practices
when Hibernia was Designed
6.6.2 The Windspeed Used During Design
6.6.3 Current Requirements of the Codes and Recommended Practices
6.6.4 Current Best Practice
6.6.5 The Effect of Applying Best Industry Practice to Hibernia
6.7 Acceptable Flare Radiation Levels
6.7.2 The Radiation Levels Used in the Design
6.7.3 Current Requirements of the Codes and Recommended Practices
6.7.4 Current Best Practice
6.7.5 The Effect of Applying Best Industry Practice to Hibernia
6.8 Challenge Issues Resulting from the Technical Audit of the Design Calculations
6.9 Miscellaneous Issues
6.9.1 Insulation
7.0 AS-BUILDING THE FLARE SYSTEM
7.1 Introduction
7.2 As-built and Design Capacity
7.2.1 Case 1 - Design Blowdown Rate (as RABS Rev C1)
7.2.2 Case 2 - ‘As-Built’ - i.e. As Case 1 with Future Equipment Removed
7.2.3 Case 3 - As Case 2 with 3 min Stagger Removed
8.0 RISK MANAGEMENT IN RELATION TO FLARING EVENTS AND WIND CONDITION
8.1 Introduction
8.2 Potential Flare Envelope based on Total Blowdown Scenarios
8.2.1 Determination of Blowdown Load Basis
8.2.2 Determination of Continuous Load Basis
8.2.3 Determination of Allowable Thermal Radiation Impingement on the Platform
8.2.4 Other Calculation Criteria
8.3 Results
8.3.1 Emergency Relief - Platform Blowdown
8.3.2 Continuous Relief
8.4 Flare Envelope Conclusions
8.4.1 General
8.4.2 Emergency Relief - Platform Blowdown
8.4.3 Continuous Relief
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
5
9.0 IMPLICATIONS FOR HIBERNIA
9.1 Introduction
9.2 Flare System Capacity Opportunities
9.3 Impact on the Design Documentation
9.4 Optional Changes
9.5 Miscellaneous Requirements
9.5.1 Updating the Design Documentation
9.5.2 Implementation Projects
10.0 REFERENCES
APPENDIX I CALCULATION TECHNICAL AUDIT
APPENDIX II STAGE 2 PROPOSAL
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
6
ABBREVIATIONS
ALARP As low as reasonably practical
API American Petroleum Institute
ASME American Society of Mechanical Engineers
CSE Concept Safety Evaluation
CBA Cost Benefit Analysis
DAE Design Accidental Event
DIERS Design Institute for Emergency Relief Systems
DPRA Design Phase Risk Assessment of Potential Accidental Events
DPSEE Design Phase Safety and Environmental Evaluation
FRA Fire Risk Assessment
FSRS Flare System Revalidation Study (i.e. this study)
H&S Health and Safety
HEM Homogeneous Equilibrium Model
HSE Health and Safety Executive (UK government body)
HSW Health and Safety at Work
HTPT Hibernia Topsides Process Team
HVAC Heating Ventilation and Air Conditioning
MEP Mobil Engineering Practice
N North
NW North West
PFP Passive Fire Protection
PSHH Pressure Switch High High (a trip function)
QRA Quantified Risk Analysis
RABS Relief and Blowdown Study Report Doc. No. CM-E-C-R-M00-RP-3410 Rev C1
RAE Residual Accidental Event
TSR Temporary Safe Refuge
VLE Vapour Liquid Equilibrium
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
7
HOLDS
1. No holds.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
8
1.0 INTRODUCTION
The key Hibernia flare system design documents have remained unaltered since the
design phase. In certain areas, the key assumptions are now considered worthy of
review particularly to incorporate as-built system details and to assess the potential to
remove the Injection Compressor stagger. It has therefore been decided to revalidate
the key flare system design documents (principally the Relief and Blowdown Study
Report and the Flare System Calculation Volumes). Following from a series of
meetings during the period 9–10 May 2000, a scope of work for performing a staged
revalidation of the flare system was prepared.
The stages envisaged are described below:
Stage 1 – Flare System Revalidation Report
Stage 1 consists of the following activities:
Review the original documents in light of best practice to ensure a consistent and
clear design approach (including a technical audit of the existing flare system
design calculations). Analyse the results of any changes in design philosophy and
their impact on flare system design capacity.
Based on the above identify the changes required to update the Relief and
Blowdown Study Report.
Identify the available capacity in the system against a range of future projects
including the avoidance of Injection Compressor blowdown stagger.
Prepare a discussion document describing the background and requirement for any
changes to the key flare system documents.
Stage 2 – Modify the Key Hibernia Flare Design Documentation
Based on the results of Stage 1 update the key flare system design documentation.
This report covers Stage 1 of the revalidation process.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
9
2.0 SUMMARY AND CONCLUSIONS
2.1 Introduction
The key design documents relating to the flare system design have not been reviewed
for some time. In the intervening period codes of practice have changed, as-built
documentation and better analytical tools have become available and future
equipment, foreseen at the time of design, is no longer certain to be installed. This
report addresses these issues in order to revalidate the flare system design.
The results of the report are summarised in the following main sections:
Technical audit of the design calculations
Challenge process
As-building the flare system
Risk management in relation to wind condition and flaring events
Implications for Hibernia
These are described in turn below.
2.2 Technical Audit of the Design Calculations
The technical audit of the design calculations was undertaken primarily to identify
assumptions which were linked to the relief and blowdown system design basis and
because of some concern in HMDC that the calculations did not fully reflect the
design. In the event very few important assumptions were contained in design
calculations but it was clear that the calculations were not up to date and there were
some inconsistencies between the various flare system design documents. Also
design methods have improved which indicate certain assumptions are no longer
sufficiently conservative (for instance in the low temperature material selection
calculations).
Otherwise, as would be expected, some of the design bases on which the system was
founded have changed since the design phase and an exercise such as this is the
ideal way of capturing these changes (for instance the changes relating to the
maximum well rate).
One last aspect uncovered in the technical audit related to missing work (for instance
the LP flare network model which should have been run to calculate the back pressure
on relief valves which may be part of a coincident relief).
All these types of issue will require the design calculations to be revised and corrected.
A summary of the calculations that require revision can be found in Section 2.6.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
10
2.3 Challenge Process
The challenge process showed the problem of applying, often ambiguous, codes of
practice retrospectively. The process also showed that Hibernia has in general used a
conservative design basis which has resulted in a robust design when considering new
code requirements and current industry design approaches. Generally, this is
because newer approaches tend to interpret the codes without incorporating
unnecessary features, which reflects efforts to achieve low cost facilities. Only in one
area did we believe the design had not been sufficiently conservative and this area
was the use of compressor stagger to limit the LP flare system flowrate during
blowdown. However, to remove the stagger could present a considerable design
challenge because of the problem of increasing the pressure (and inventory) in the LP
separator when the blowdown valves opened. This is particularly undesirable if the
cause of the blowdown is a fire around the LP separator. The higher pressure and,
therefore, higher stress will increase the risk of premature failure. Consequently a
brief safety analysis which looked at the ability of the A train injection compressor
components (the equipment whose blowdown is delayed) to survive an adverse fire
was undertaken. The results demonstrated the equipment is unlikely to fail and,
therefore, the staggered system is safe in this situation.
Similarly, the challenge process also considered jet fire on lower pressure equipment.
Here it was found that thin walled vessels should be considered outside of the API
guidance (as suggested explicitly in the API recommended practices). In this case
applying modern practices relating to jet fire to this vessel suggests that as long as the
insulation remained intact the insulation will ensure the vessel survives a jet fire.
One other area, which would have been unknown to the original designers, are the
changes which have occurred to the recommended practices; here the only important
change relates to new API sizing method for calculating two-phase relief which will
need to be applied to the existing system.
The outcome of the challenge process is described in Section 2.6.
2.4 As-Building the Flare System
The removal of the allowances contained in the design for future equipment ‘frees-up’
approximately 30% of the HP flare capacity in the blowdown case. However there is
no impact at all on the LP flare capacity for this case as no future equipment was
planned to be connected to this system.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
11
2.5 Risk Management in Relation to Wind Condition and Flaring Events
We had expected to find some useful work regarding this aspect in the industry but
found none. Generally a picture emerged that the industry has no standard approach
to windspeed or the operational measures undertaken on a platform during high wind.
The outcome of such considerations is therefore undertaken on a case by case basis
relying mainly on the judgement of the asset owner. By applying a consistent
approach to the selection of design windspeed and the presence of personnel the
result changed the design case relatively little. The impact of the design windspeed
change, if pursued, is summarised in Section 2.6.
One aspect where consideration of wind condition would potentially have a beneficial
effect is related to continuous case flaring. In this case, because of the lower
allowable radiation levels, wind has a significant effect on what can be produced when
the compressors are unavailable. This suggests an allowable flare radiation envelope
should be developed such that the production rate can be set (maximised) dependent
on the measured (or expected) wind speed and direction.
2.6 Implications for Hibernia
2.6.1 Introduction
The implications for Hibernia effectively arise as two types.
Where analysis suggests that some aspects of the design are conservative
compared to the application of recommended and best practices, then this implies
some apparent spare capacity in the system. The use of such capacity is optional
dependent on future plans for the facility and economic benefit.
However, where analysis suggests that some aspects of the design are less
conservative than in the recommended or best practices, then this implies that the
system capacity is insufficient or marginal in these cases. In this case prudent
ownership requires that these issues are addressed and solutions provided.
2.6.2 Capacity Opportunities
The flare system revalidation analysis has identified a number of areas where a
capacity opportunity is available. Where the capacity opportunity is positive (i.e. the
apparent capacity, or capacity available in the flare system appears to rise) then
HMDC have the choice of adopting the new philosophy which can be used to allow
future platform modifications.
However, where the capacity opportunity is negative (i.e. the apparent capacity, or
capacity available in the flare system appears to fall) then HMDC should undertake
remedial measures to remove the possibility of exceeding the platform flare system
capacity.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
12
Both types of capacity opportunity are described below.
Changes that reduce the apparent capacity of the flare system
The new API method for calculating two-phase relief should be applied to the
relevant cases. At the same time, a new maximum design well rate together with
the number of wells which fail to shut in that need to be designed for will need to
become an explicit part of the RABS update. If the existing relief valves are to be
retained this may require some method for limiting the maximum well rate to an
acceptable value.
The missed design case of a failed open separation train spillover valve should be
calculated and measures sought to limit the peak rate experienced to within the
capacity of the flare system.
Changes which apparently increase the capacity of the flare systems
Remove the effect of future equipment.
Change the start pressure of the commencement of blowdown. A robust
interpretation of the codes of practice suggests in an automatically initiated
blowdown event the start point should be normal operating pressure. Some of the
Hibernia systems already follow this philosophy, however some (the compressor
systems) begin blowdown from the PSHH pressure (which is significantly in excess
of normal operating pressure). Changing this to be more consistent would free-up
capacity in the LP flare system. However, in doing so there is the disadvantage of
having to use more rigour when considering any changes in normal operating
pressures, which affect the blowdown and which the PSHH approach can avoid.
Increase the end pressure for blowdown for the thick walled vessels. The API
recommended practice has never required blowdown to 690 kPag for thick walled
vessels. Our calculations of vessel heat up confirm these conclusions. Therefore
blowdown to 690 kPag is excessive in this case. The end pressure should be 50%
of the design pressure unless there are good reasons otherwise. One such
situation is the inapplicability of this end pressure for the gas turbine driven HP gas
compressors. The blowdown end pressure for equipment in these systems is
determined by the requirements of the HP compressors seal oil system and the
requirement to be at or near atmospheric prior to the oil running out.
The effects of insulation. If the insulation is the right type and properly attached its
effects can properly be considered in the design calculations.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
13
Radiation levels. The Hibernia radiation levels did not truly reflect how the platform
was constructed. In particular the radiation requirement on the drilling derrick does
not reflect the shielding present, nor do the radiation levels on the escape ways
reflect international practice or Canadian regulations. The allowable radiation in
these levels should be raised to 9.5 kW/m2 and 6.3 kW/m2 respectively. This
allows considerably higher flaring rates before the radiation levels are breached.
Windspeed. Using a probabilistic method to select windspeed would lower the
design windspeed from 27 m/s to 24.2 m/s.
Gas blowby cases are over conservative. By taking a more realistic blowby case
the apparent capacity can be increased. This would pay benefits should the
separation train LCV valve coefficients (Cv) ever need to be raised.
The detailed analysis which forms the basis for the above can be found in sections
5.0, 6.0 and 9.0.
2.6.3 Impact on the Design Documentation
The following table summarises the changes that should be made to the design
calculations to improve their integrity and make them consistent and traceable.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
14
Table 2.1 Calculations Requiring Revision (System 34)
Number
34-
Title Number
34-
Description Action
005 / A Blowdown Section Inventory Calc (Provides input to blowdown simulations)
005/1 Are the blowdown volumes used sufficiently accurate?
Locate and review missing
calculations
005/3 Were the real settle out pressures ever
used?
Compare real settleout conditions
with design to ensure blowdown
rates are appropriate
006 / A Blowdown Summary 006/1 HP Blowdown calculation higher than
vendor aware of. Radiation level for
case is underestimated.
Update RABS.
006/2 Correct isentropic efficiency used? An optimistic isentropic efficiency
was used to calculate the
minimum system temperature.
Recalculate the temperatures.
See also 34.010/1.
010 / A Calculation of allowed
cooldown before
hydrate formation &
minimum
temperatures
achieved in flare gas
from critical blowdown
sections
010/1 Was the calculation methodology
sufficiently robust?
There are flaws in the method
used to calculate the minimum
temperatures in the system.
These should be corrected. Use
resultant more realistic figure to
implement alarms on high
pressure areas to avoid low
temperatures. Update RABS.
011 / A Review of HP flare
KO Drum size
011/1 A note on the front of calc 34-064 states
that Rev 7 of Design Basis gives max
well flow of 20,000 bpd + average well of
10,000 bpd, i.e. 30,000 bpd total. The
individual well design rate has changed.
What are the implications for the
platform?
Select number and design rate of
the well failure to shut in case.
Update RABS. Develop
operational procedure to cater for
time to fill HP flare KO vessel.
015 / A Calc to review options
for reducing HP to MP
Separator and MP to
LP Separator Blowby
Cases
015/1 Relief & Blowdown Study Report Rev C1
non-concurrent maximum allowable LP
and HP Flare loads are 110,874 kg/h
and 244,897 kg/h respectively. Rates
used in these calculations exceed
design.
Ensure design rates quoted are
consistent and reflect the installed
control valves. Update RABS.
022 / C HP Flare Network
Sizing (HP Separator
- Max Relief Case)
022/2 Effect of increased production /
production fluid GOR
Update RABS to mention link
between GOR and the compressor
capacity.
025 / C 3rd Stage
Compressor Max
Relief Case - Network
Analysis
025/2 Include in updated RABS cases which
are not catered for, i.e. consider relief
from both compressor trains
Check modifications to avoid
injection compressor RVs lifting
prevent coincident case. Update
RABS to explicitly mention the
cases which are not designed for.
033 / G Coalescer & LP
Separator Heaters
Simultaneous Fire
Relief - Network
Analysis
033/1 Assumption that the header is at zero
pressure (I.e. that this is a singular event
not coincident with any other releases)
Construct an LP flare network
model to calculate the back
pressure on relief valves when the
system is depressuring.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
15
Table 2.2 Calculations Requiring Revision (System 31)
Number Title Number Description Action
31.37 Relief Valve
Calculations - LP
Separator
31.37/1 Is it possible for the Test Separator
manifold to be connected to the LP
Separator when operating in high
pressure mode?
Ensure positive method of
ensuring isolation from HP system
exists. Update RABS to reflect
this.
The tables avoid repetition of the major issues which affect the capacity of the flare
system (see Section 2.6.2) and single issues that affect more than one item. The full
version of the tables can be found in sections 5.2.1 and 5.3.1.
Some minor changes which generally affect consistency are identified in Section 9.4.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
16
2.6.4 Future Work
It is difficult to be precise regarding the activities required in the longer term future as
these depend on the outcome of the recalculation work and the decisions made
therein. However, it is possible to summarise in general terms the shorter term
requirements of Stage 2:
Document Changes
Relief and Blowdown Study Report
Fairly extensive rewrite of the report.
Design Calculations
For each change prepare a calculation revision which revs up the existing
calculation (in other words building on the existing work). This would include:
- Calculations identified in this report requiring change.
- Flare radiation calculations (for windspeed and allowable radiation levels)
- Continuous radiation cases. Analysis of allowable production rate vs wind
speed and direction.
Blowdown inventory calculations (for removed inventory).
Reliability analysis of the system that controls the compressor stagger, to ensure
the system is sufficiently reliable to ensure the design integrity.
Implementation Projects
In this section there are some projects mentioned which will in all likelihood require
hardware changes to be made (resulting from the above there may be more).
Insulation conformance - The explicit ability of the platform to cope with a jet fire
hazard requires the insulation around the vessels to remain in place during jet
flame impingement. This may require the insulation strength to be improved.
Modifications to limit peak flaring rate during spillover valve failure.
Instrument modifications to warn operators when the requirement to blowdown
compressors is becoming imminent (to avoid low temperature problems).
In discussion with HMDC a detailed scope of work to undertake the above has been
developed. This is attached in Appendix 2.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
17
3.0 DESIGN BASIS
3.1 Introduction
The review focuses on those aspects and hazards that are directly relevant to the flare
system design. In particular these are flare radiation, jet and pool fire and, to a lesser
extent, explosion. This naturally excludes issues relating to blowout and iceberg
collisions as well as environmental issues.
However, before going into the main parts of the analysis, it is worth recapping the
safety basis and methodology followed by HMDC now and during the design phase.
This will need to be followed should any changes be made to design philosophies.
3.2 Safety Design Basis
As was convention at the time, the safety design progressed along two parallel routes.
The first was the use of probabilistic analysis to identify the acceptability of various
risks. The second was the deterministic design of the various safety systems
according to recognised codes and practices. Occasionally there was an interface
between the two processes when a risk was considered unacceptable. Where this
was apparent the design would be adjusted to mitigate the unacceptable risk.
These two processes are described in sections 3.2.1 and 3.2.2 below.
The problem of parallel processes is that some information can be lost across the
interface. More recently this has led to a concept called risk based design where the
key safety issues are resolved during the early conceptual design stages rather than
be left for implementation after the conceptual design is complete.
3.2.1 Probabilistic Design Criteria
By the time the FRA was commenced the HMDC Damage / Impairment Criteria had
been formalised. These were:
Criterion 1: Overall Platform Integrity
There must be no overall loss of integrity of the platform for at least 2 hours after the
initial event. Loss of integrity included:
Structural collapse of more than 50% of the platform topsides, or total collapse of
Module M30.
The 2 hours is judgementally used for a maximum time to evacuate by lifeboats (i.e.
time to respond to emergency, attempt to control, organise evacuation and abandon
platform)
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
18
Criterion 2: Integrity of Temporary Safe Refuge (TSR)
The TSR (i.e. living quarters) should remain a safe refuge for personnel for at least 2
hours. Loss of integrity may be due to:
Fire within the safe refuge;
Blast damage, in excess of major window breakage;
Collapse of any part of shelter area.
The time of 2 hours is derived and defined as for Criterion 1.
Criterion 3: Escape Routes
Escape routes from all parts of the platform to the TSR or other safe refuge should
remain passable for at least 30 minutes from the start of the incident. An escape route
may be made impassable by:
Thermal radiation over 12.5 kW/m2 to the outside of the escape route if protected by cladding;
Thermal radiation over 6.3 kW/m2 if unprotected;
Blockage due to blast damage;
Collapse of one or more modules;
Flooding over 1 m deep in the Utility Shaft.
The time of 30 minutes is intended to allow the escape of workers who had initially remained at their posts to shut-down the process operation or fight a growing fire. The criterion is violated if an incident results in either:
All escape routes from any module being impassable;
All routes from any one part of the platform to the TSR being impassable.
Since there is more than one escape route from any point, an incident must completely involve the total module to violate the criterion.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
19
Criterion 4: Means of Evacuation
The evacuation systems must remain effective for long enough to evacuate all
personnel. This requires at least one of the following to be true:
Helideck operable for at least 2 hours. Inoperability may result from one of the
following:
tilt over 15°
smoke due to oil fire and wind towards helideck
thermal radiation over 3.2 kW/m2
blast damage
unignited gas over helideck (due to likelihood of ignition)
collapse of M50 module.
Evacuation systems must be operable with at least 10% spare capacity (to allow for
launching partly loaded) and with passable escape routes, from TSR to evacuation
system, for at least 2 hours. Inoperability may result from:
tilt over 25° (preventing safe access)
thermal radiation over 12.5 kW/m2
blast damage (damaging launching gear and access walkways)
collapse of module M40 and M30.
The times are judgementally based on the proposed systems for the Hibernia platform.
The criterion is only violated if all the means of evacuation are unavailable.
In general the following approach was applied:
The Damage / Impairment Criteria set out above, give basic criteria which should not
be exceeded. It is not possible to ensure that no incidents will exceed the criteria.
The intent is that every reasonable and practical precaution is taken to ensure those
incidents that exceed the criteria are so unlikely that they can be considered as an
acceptable risk because the risk is negligible. These incidents are termed Residual
Accidental Events.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
20
Added to this were Hibernia’s three-tier framework of risk acceptability:
For any single incident that might affect the key safety systems (more accurately
safety functions from the above), the risk level for the three-tiers are:
Intolerable: greater than 10-4 per year.
ALARP region: 10-4 to 10-5 per year.
Lower bound of acceptability: less than 10-5 per year
Whilst it is inconceivable that any of the impairment criteria would change as a result
of the considerations in this report, change may affect the QRA upon which these
impairment criteria stand. Any changes considered, therefore, will require to be
confirmed through QRA.
3.2.2 Deterministic Design Criteria
A number of the final requirements for the design would stem from the above. This is
not surprising as some of the aspects of the impairment criteria actually have their
roots in the recognised international codes and practices, e.g.
Allowable Flare Radiation Levels:
Escape Ways
Not over 12.5 kW/m2 to the outside of the escape route if protected by cladding;
Not over 6.3 kW/m2 if escape way is unprotected
Helideck
Not over 3.2 kW/m2
The remaining requirements are part of the various design guides and codes of
practice. These are described in detail in Section 6.0
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
21
4.0 APPROACH
4.1 General
4.1.1 Flare System Revalidation Process
The flare revalidation process is summarised in the flowscheme overleaf. The stage
consisting of this report is Stage 1. The results of Stage 1 will form the basis for future
Stage 2 studies. The flowscheme indicates the potential range of projects this could
encompass.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
22
Figure 4.1 - Revalidation Process
Start
Technical audit of the existing
design calculations Challenge process Risk management
Prepare Flare System Revalidation
Report
Draft and Final Versions
Impact on
the design?
Update Relief and
Blowdown Study Report
(Rename “Flare System
Design Philosophy”)
Build flare network model
(for inclusion in the Flare
System Design
Philosophy) (Optional)
Stage 1
Major changes to flare
design calculations. As
build and replace the
design calculation volumes
Update Relief and
Blowdown Study Report.
(Rename “Flare System
Design Philosophy”)
Build flare network model
(for inclusion in the Flare
System Design Philosophy)
Prepare workscopes for the
modifications
Minor changes to flare
design calculations. Rev up
affected calculation
volumes
Update Relief and
Blowdown Study Report.
(Rename “Flare System
Design Philosophy”)
Build flare network model
(for inclusion in the Flare
System Design Philosophy)
(Optional)
End
Major impact Minor impact
Stage 2
Varies according
to outcome of
Stage 1
No Impact
HMDC Internal Audit /
Approval
HMDC Internal Audit /
Approval
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
23
4.1.2 Legislative Obligations of HMDC’s Safety Design Philosophy
HMDC’s legislative obligations to safety are encompassed in the Newfoundland
Offshore Petroleum Installations Regulations (Reference 1), an extract of which
follows:
43. (1) Every operator shall…submit to the Chief a concept safety analysis…that
considers all components and all activities associated with each phase in the life of the
production installation, including the construction, installation, operation and removal
phases…
(5)…
…(g) a definition of the situations and conditions and of the changes that would
necessitate an update of the concept safety analysis.
(8) The operator shall maintain and update the concept safety analysis referred to in
subsection (1) in accordance with the definition of situations, conditions and changes
referred to in paragraph (5)(g) to reflect operational experience, changes in activity or
advances in technology.
HMDC have met these requirements, initially through the preparation of the Concept
Safety Evaluation which has, over time, evolved into the Operational Plan which will be
issued in the near future.
The above very much parallels the type of approach the UK HSE require:
11. The employer…needs to review the risk assessment if there are developments
that suggest that it may no longer be valid (or that it can be improved). In most cases,
it is prudent to plan to review the risk assessments at regular intervals - the time
between reviews being dependent on the nature of the risks and the degree of change
likely in the work activity. Such reviews should form part of standard management
practice.
Management of health and safety at work - Approved Code of Practice (1992)
The study will be undertaken in this light.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
24
4.1.3 The Requirements of the Standards, Codes of Practice and Recommended
Practices
Where a particular design code is used its requirements are mandatory, e.g. the
requirements of ASME VIII for a vessel stamped accordingly. Recommended
practices are different in that their requirements are not mandatory in law unless they
are stated in the regulations; this is the case with Canadian requirements. For those
practices not in the regulations, common industry practice and deviation from those
would normally require Certifying Authority approval. In dispute, the applicability of the
use of the practice would be left to the courts to decide.
So, although recommended practices are not the same as design codes, their
requirements have become almost code like over time. Consider a situation where a
failure has occurred and its cause appears to be linked to a situation where a well
known, recommended practice was deviated from. There would in effect be an onus
to prove the requirement inferred in the practice was inappropriate at the time it was
being considered. Otherwise negligence would be very difficult to disprove. This proof
would be particularly hard to provide and would require thorough documentation
regarding the deviation to be kept for the life of the plant. This study will recognise this
reality and, therefore, design code, code of practice and recommended practices, so
long as they emanate from a recognised responsible body, are considered equivalent
in this study in terms of reliance.
4.1.4 Ambiguities in the Recommended Practices
The recommended practices are sometimes (some would say often) ambiguous in
their requirements and a study such as this tends demonstrate the problem. Therefore
interpretations of the practice’s actual intent often have to be made. This is one of the
designer’s challenges and a particular challenge of this report.
In the past, presumably to avoid the need for interpretation, owners of facilities have
removed the ambiguities by being prescriptive with their requirements. Thus, industry
practices, which often have little connection with the original design code intent, have
sometimes been established for expediency. The goal today is to apply the codes as
intended without unnecessary features that increase cost.
The methodology used in this study therefore lies in this latter approach to the
application of practices, to apply them as intended. Where there are differences
between the various methods of applying practices this will be highlighted in the
narrative.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
25
4.2 Calculation Audit
The calculation technical audit’s primary aim is to identify key assumptions or queries
contained outside the Relief and Blowdown Study Report. A secondary aspect is the
high level numerical and methodological check of the existing relief case calculations
to ensure their suitability to use as the basis for the revalidated Flare Design
Philosophy. This process will identify any areas that require detailed review to be
undertaken in future stages of the revalidation study.
The audit will use a tabular approach (compiled by calculation volume) to highlight the
assumptions or issues which require to be addressed during the challenge and risk
mitigation review processes in subsequent sections of the study.
Whilst addressing the calculations, secondary objectives such as consistency and
methodology have also been revisited and these results can also be found on the
detailed audit sheets.
4.3 Challenge Process
The challenge process is a sequential review of individual design parameters that had
an effect on the way the flare system was dimensioned.
The process looks first at the requirements of the design codes or practices to
place, in an historical context, the requirements for the design. The key codes and
practices applicable to this work are those referred to in the RABS, i.e.:
Canada Oil and Gas Installation Regulations
Petroleum Occupational Safety and Health Regulations - Offshore
Newfoundland
API RP 520
API RP 521
API RP 14C
Mobil EGS 661
ASME Section VIII, Division 1
Secondly, how the system was actually designed is considered. This aspect
captures the interpretations used when compared to the earlier activity.
Thirdly, the requirements of current codes and practices are then considered.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
26
Fourthly, current best practice is considered to challenge the existing design and
determine its suitability for application to Hibernia. Here the best practice applied
is Granherne’s own (there is no other convincing way for us to address this issue).
This is not to say that other companies do not apply the requirements differently.
Where possible some alternative applications will be mentioned where relevant.
Finally, the effect of these stages is considered and a recommendation made for
the way the requirements should be applied to Hibernia to give a consistent and
easily understood flare system design.
4.4 Risk Management in Relation to Flaring Events and Wind Condition
This issue stems from the technique used occasionally where the capacity of a flare
system has been increased when it has been realised that at the design windspeed no
personnel would be present on deck, thereby allowing higher incident radiation rates
on deck during these events. This would only be the case if a very high wind speed
were considered during design. A more pragmatic approach to design windspeed
selection would ensure that the coincident conditions were considered, i.e. a
realistically high windspeed.
Generally two cases are considered:
Emergency flaring
The methodology used to generate the results of the activity are based on multipliers
applied to the flowrates considered in the original flare boom length defining design
case, i.e. combined HP and LP blowdown. It should be appreciated that these
resultant rates cannot actually occur until the platform is actually modified to
incorporate the necessary inventory, in this case, in the same ratio (HP/LP) as design.
This is unlikely. The real effects, or real envelope, will therefore depend on the actual
modification made. The actual effect should be considered in detail during the
particular modification project’s design phase.
Continuous flaring
Continuous flaring differs from emergency flaring in that the acceptable radiation levels
are very much lower than for emergency events. Proportionally, the lower radiation
isopleths are more sensitive to wind than the high flow cases.
The methodology used in this study has taken a simulation from the recent
debottlenecking project (Case 3, a case which included Avalon production) and used
this to generate current normal operating input data to generate a new set of profiles.
The input data is adjusted up or down using simple multipliers to generate the
expected envelope.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
27
5.0 TECHNICAL AUDIT OF THE DESIGN CALCULATIONS
5.1 Introduction
The intent of this review is twofold:
To identify assumptions or items which have affected the design of the relief and
blowdown system including any issues which arise as a result of the review
(Section 5.2).
To revisit the relief valve calculations to perform a methodological and numerical
check to reconfirm the validity of the dimensioning design cases (Section 5.3).
5.2 Results of the Technical Audit – Relief and Blowdown System Calculations
In Appendix I the full results of the audit are given. The detailed tables that follow
identify a number of issues to be dealt with, either in Section 6.0, because they can be
challenged, or in this section if they are issues which concern the accuracy or
soundness of the design conclusions. For completeness, however, both sets of issues
are summarised below.
Table 5.3 Challenge Issues - Relief and Blowdown System Calculations
(System 34)
Calculation Issue
Number
34-
Title Rev Date Number
34-
Description
005 / A Blowdown Section Inventory Calc (Provides input to blowdown simulations)
06 18-May-93 005/2 Jet fire scenario not taken into account for
the design of the blowdown system
005/4 Were fire areas used for total blowdown
rate?
006 / A Blowdown Summary 05 19-May-93 006/2 Correct isentropic efficiency used?
006/3 Is design case too extreme?
042 / F Total LP Blowdown - Initial Conditions
- Network Analysis
02 18-Mar-93 042/2 Validity of staggering blowdown. Were the
systems sufficiently independent?
043 / F Injection Compressor 'A' Blowdown -
Initial Conditions - Network Analysis
02 18-Mar-93 See 34-042/2
044 / G Total LP Blowdown - After 3 mins
(stagger point) - Network Analysis
01 22-Mar-93 See 34-042/2
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
28
Table 5.4 Technical Audit Issues - Relief and Blowdown System Calculations
(System 34)
Calculation Issue
Number
34-
Title Rev Date Number
34-
Description
005 / A Blowdown Section Inventory Calc (Provides input to blowdown simulations)
06 18-May-93 005/1 Are the blowdown volumes used sufficiently accurate?
005/3 Were the real settle out pressures ever
used?
005/5 Are vessel weights used reasonable?
006 / A Blowdown Summary 05 19-May-93 006/1 HP Blowdown calculation higher than
vendor aware of. Radiation level for case is
underestimated.
006/4 Is constant rate blowdown a valid design
method, i.e. not according to API?
006/5 'As Built' settleout pressure
010 / A Calculation of allowed cooldown
before hydrate formation & minimum
temperatures achieved in flare gas
from critical blowdown sections
02 23-Mar-92 010/1 Was the calculation methodology
sufficiently robust?
010/2 Should 'troubleshooting' methanol injection
points be incorporated?
011 / A Review of HP flare KO Drum size 02 06-Feb-92 011/1 A note on the front of calc 34-064 states
that Rev 7 of Design Basis gives max well
flow of 20,000 bpd + average well of 10,000
bpd, i.e. 30,000 bpd total. The individual
well design rate has changed. What are the
implications for the platform?
012 / A Review of LP flare KO Drum size 03 10-Mar-92 See 34-011/1
015 / A Calc to review options for reducing HP
to MP Separator and MP to LP
Separator Blowby Cases
01 14-Aug-91 015/1 Relief & Blowdown Study Report Rev C1
non-concurrent maximum allowable LP and
HP Flare loads are 110,874 kg/h and
244,897 kg/h respectively. Rates used in
these calculations exceed design.
015/2 Is considering only one control valve fails
open for gas blowby case when 2 installed
in parallel realistic / allowable even with
provision of independent transmitters and
controllers?
060 / B Indicative Injection Compressor
Cooldown Calculation
01 29-May-92 See 34-010/1 and 34-010/2
061 / B Simplistic Steady State Preliminary
Review of the Annulus Rupture Relief
Flowrate
01 10-Sep-92 061/1 This case had the potential to be the
defining case for the HP flare system
(depending on installed choke valve CV)
What happened subsequently?
022 / C HP Flare Network Sizing (HP
Separator - Max Relief Case)
02 22-Mar-93 022/1 Calculated maximum pressure at PSV
discharge exceeds value on PSV datasheet
Rev C1
022/2 Effect of increased production / production
fluid GOR
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
29
Table 5.2 Technical Audit Issues - Relief and Blowdown System Calculations
(System 34) (Cont.)
Calculation Issue
Number
34-
Title Rev Date Number
34-
Description
023 / C HP Separator Max Spill-off Case -
Network Analysis
02 22-Mar-93 023/1 Calculated maximum pressure at spill-off
valve discharge exceeds value on control
valve datasheet Rev C1
023/2 Is case where valve fails fully open
considered?
See also 34-022/2
024 / C MP Separator Max Relief Case -
Network Analysis
02 24-Mar-93 024/1 Calculated maximum pressure at PSV
discharge exceeds value on PSV datasheet
Rev C2
025 / C 3rd Stage Compressor Max Relief
Case - Network Analysis
01 27-Jan-93 025/1 Calculated maximum pressure at PSV
discharge exceeds value on PSV datasheet
Rev C2 - Check for later revisions
025/2 Include in upated RABS cases which are
not catered for, i.e. consider relief from both
compressor trains
026 / C Injection Compressor Max Relief
Case - Network Analysis
01 27-Jan-93 026/1 Calculated maximum pressure at PSV
discharge exceeds value on PSV datasheet
Rev C2
See also 34-025/1& 34-025/2
027 / C MP Separator Max Spill-off Case -
Network Analysis
02 24-Mar-93 027/1 Was failed open control valve considered?
See also 34-022/2
028 / D West Test Separator Max Spill-off
Case - Network Analysis
02 24-Mar-93 028/1 Is case where valve fails fully open
considered.
See also 34-022/2
029 / D West Test Separator Max Relief Case
- Network Analysis
02 28-Jan-93 See 34-022/2
030 / D East Test Separator Max Spill-off
Case - Network Analysis
02 25-Mar-93 030/1 Is case where valve fails fully open
considered?
See also 34-022/2
031 / D East Test Separator Max Relief Case
- Network Analysis
02 25-Mar-93 See 34-022/2
34- / E 1st Stage Compressor Spill-off Case -
Network Analysis
01 29-Jan-93 34-/1 Calculated maximum pressure at spill-off
valve discharge exceeds value on control
valve datasheet Rev C1
34-/2 Is case where valve fails fully open
considered?
045 / E Total HP Blowdown Initial Conditions
(Checks blowdown line sizes for
individual system blowdowns)
01 22-Mar-93 045/1 There is no network analysis run with
common HP Blowdown at initial conditions
045/2 Consistency error in the number and flows
in the gas injection flowlines
039 / F LP Separator Max Spill-off Case -
Network Analysis
01 02-Mar-93 039/1 Is case where valve fails fully open
considered?
See also 34-022/2
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
30
Table 5.2 Technical Audit Issues - Relief and Blowdown System Calculations
(System 34) (Cont.)
Calculation Issue
Number
34-
Title Rev Date Number
34-
Description
042 / F Total LP Blowdown - Initial Conditions
- Network Analysis
02 18-Mar-93 042/1 Total blowdown rate (initial rate) used in
calc less than that in Relief & Blowdown
Study Report ( 89,601 kg/h)
033 / G Coalescer & LP Separator Heaters
Simultaneous Fire Relief - Network
Analysis
01 01-Feb-93 033/1 Assumption that the header is at zero
pressure (I.e. that this is a singular event
not coincident with any other releases)
036 / G Injection Stage Suction Scrubber PSV
- Network Analysis
01 10-Feb-93 036/1 Inconsistency on datasheet between
accumulation and 'Max Relieving Pressure'
(should be 10%)
037 / G HM & CM Expansion Drums
Simultaneous Fire Relief Case -
Network Analysis
02 01-Feb-93 037/1 Calculated back pressure (for 0152A/B)
greater than specified on datasheet - calc
considers this OK as less than 10% of set
pressure
See also 34-033/1
046 / G Fuel Gas Cooler / Heater tube rupture
relief line size check
01 02-Mar-93 046/1 ''As Built' P&IDs show bursting discs in this
service (calc considers PSVs) therefore
calc is no longer valid
050 / G 3rd Stage Suction Scrubber A (D-
3303A) PSV Discharge Line Size
Confirmation
01 02-Mar-93 050/1 Rev C2 PSV datasheet states set pressure
= 8200 kPa(g), 'As Built' P&ID shows set
pressure = 7000 kPa(g)
052 / G E-3301 Shell Side PSV Discharge
Line Size Confirmation
01 02-Mar-93 See 34-033/1
053 / G E-3303B Shell Side PSV Discharge
Line Size Confirmation
01 02-Mar-93 See 34-046/1
054 / G HP Manifold Relief - Network Analysis 01 02-Mar-93 054/1 Rev C2 PSV datasheet states set pressure
= 34,400 kPa(g), 'As Built' P&ID shows set
pressure = 34,100 kPa(g)
055 / G Simultaneous Fire Relief Case from Z-
3701 A/B, Z-3702 A/B & Z6202 A/B
(pig launchers and fuel gas package)
01 10-Feb-93 See 34-033/1
057 / G E-3701 Shell & Tube Side
Simultaneous Fire Relief Case - Line
Size Confirmation
01 12-Feb-93 057/1 Calculated back pressure exceeds that
specified on datasheet for both PSVs
See also 34-033/1
058 / G E-6201A/B Tube Side Fire Relief
Case
01 10-Feb-93 See also 34-033/1
059 / G Comparative Program check of
INPLANT Single Phase Simulation vs
ESI
01 23-Apr-93 059/1 Accuracy of calculations using ESI instead
of INPLANT
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
31
5.2.1 Technical Audit Issue Discussion – Relief and Blowdown System Calculations
The following describes the technical audit issues identified in Table 5.4. However,
first the general issues relating to the audit are described.
5.2.1.1 General Issues
A number of issues arose which affected many of the calculations in the flare system
calculation volumes. These are described below:
Flare network calculations - Whilst the flare network calculations were performed,
the results of the calculations were never carried over to the discipline (instrument)
data sheets (through which the equipment was purchased). In other words, the
control valves and relief valves were all sized with the wrong back pressure. In
most cases this has no effect because the relief valves are balanced and the
difference in back pressure is low or, for similar reasons, because we know the
control valves appear to be doing their respective duties (albeit probably a little
more open than planned). Where there is an effect this is noted as an issue below.
Fire zones were used in the calculations but Granherne, so far, have not had
access to documents describing them.
Vendor data didn’t make it through to the final calculations. This particularly
affected the settleout pressures for the compressors and the calculations of realistic
volumes in the system. Because of the aggregate nature of these changes we
suspect, but cannot be sure, there would be no material effect on the flare system
design.
5.2.1.2 Technical Audit Issues
Issue 34-005/1 - Are the blowdown volumes used sufficiently accurate?
The majority of the blowdown volume data is summarised and unchanged from an
earlier revision of the calculation that used the best available information at the time for
piping volumes. The separation train major vessel dimensions appear unchanged
from those used for the calculations however the ‘As Built’ dimensions of the E & W
Test Separators are greater and these vessels contribute a significant proportion of the
HP flare blowdown load. Any increase in HP flare blowdown load from this source can
be mitigated against the load incorporated for future equipment that remains
uninstalled.
No calculation was found to confirm compression train scrubber vessel dimensions
used for the blowdown/settleout calculations and therefore it was not possible to check
them against the ‘As Built’ vessels. This could have a significant effect on the LP flare
blowdown load. The missing calculation should be found and the calculation revised
to reflect the as built data.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
32
Issue 34-005/3 - Were the real settle out pressures ever used?
As stated above, the validity of the blowdown/settleout calculations for the
compression train could not be confirmed. The ‘As Built’ calculation of these values
could have a significant effect on the LP flare blowdown load. The missing
calculations should be found and reviewed. If necessary the blowdown calculations
should be rerun and the results incorporated in the RABS update,
Issue 34-005/5 - Are vessel weights used reasonable?
Blowdown section weights stated in the calculation are based on vendor data for
vessels. Weight of pipework associated with major vessels appears to have been
estimated only. For systems that contain only pipework (e.g. manifold systems) major
pipework weight is calculated from the best available information at the time. It is
considered that a more accurate calculation of system weights would be unlikely to
have a significant effect on the blowdown loads (because of aggregate effects).
Issue 34-006/1 - HP Blowdown calculation higher than vendor aware of.
Radiation level for case is underestimated
Revision 06 of this calculation identified a HP flare blowdown load 5.8% greater than
the load used by the vendor for the flare radiation calculations. This increase is not a
concern at present because, as stated above, there is a significant allowance included
in the total HP flare blowdown load for future equipment. However, the increased HP
flare blowdown load should be incorporated into the updated RABS.
Issue 34-006/4 - Is constant rate blowdown a valid design method, i.e. not
according to API?
A constant blowdown rate (i.e. not reducing with time) was used for two items of low
pressure equipment, the LP separator and the LP fuel gas KO drum. Though not
normally valid, as they operate at low pressure and thus will not contribute a significant
proportion of the total LP flare blowdown load the calculation is considered acceptable
(see also Section 6.3.5).
Issue 34-006/5 - 'As Built' settleout pressure
As Issue 34-005/3 above.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
33
Issue 34-010/1 – Was the calculation methodology sufficiently robust?
This calculation identified the minimum allowable temperatures that the process plant
could fall to during a process shutdown before potential problems could arise on
blowdown. The resulting cool-down temperatures were:
Hydrate Formation
Cooldown Temperature, oC 61.5
Resulting Blowdown Temperature, oC -30
Min Design Temp (-45 oC) Occurs in Flare
Cooldown Temperature, oC 50.0
Resulting Blowdown Temperature, oC -45
The simulations used to generate these numbers were checked and they revealed that
the resultant blowdown temperatures were calculated using adiabatic flashes and not
using a blowdown model. The adiabatic flash assumes isenthalpic expansion, i.e. the
isentropic coefficient is 0, and results in higher downstream temperatures.
A blowdown model was run for the ‘Min Design Temp (-45 oC) Occurs in Flare’ case,
depressurising from the same settle out pressure and a temperature of 50 oC and gave
the following results:
Min Design Temp (-45 oC) Occurs in Flare – Blowdown Model
Cooldown Temperature, oC 50.0
Resulting Blowdown Temperature, oC -59 (Isentropic Coefficient = 0.5)
Resulting Blowdown Temperature, oC -63 (Isentropic Coefficient = 0.7)
The results show that the temperature of the equipment must not be allowed to fall to
the level as originally calculated (50 oC) and more realistically blowdown should be
initiated at around 70 oC.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
34
This calculation does not give any conclusions on the allowable delay before
blowdown should be initiated, this is addressed in calculation 34-060 / B for the
Injection Compressor only. 060 / B concludes that for the original model basis there is
a huge spread of allowable delay periods depending upon environmental conditions
and whether insulation is installed. The results of calculation 060 / B are given below:
Cooldown temp at which hydrate formation occurs in LP flare system on section blowdown = 61.5 C
Hold time for cooldown temperature to reach 61.5 C, hr: 3.4 (No insulation, natural convection)
0.96 (No insulation, forced convection)
20 (1" insulation, natural convection)
28 (1.5" insulation, forced convection)
Cooldown temp at which minimum design temperature occurs in LP flare system on section blowdown = 50 C
Hold time for cooldown temperature to reach 50 C, hr: 4.5 (No insulation, natural convection)
1.28 (No insulation, forced convection)
28 (1" insulation, natural convection)
37 (1.5" insulation, forced convection)
Current platform design philosophy is to depressurise after 1-2 hours. Given this large
spread the difference on calculation of the minimum allowable cooldown may not have
a significant effect on the delay allowed before blowdown is initiated. As no firm
conclusions were made in this calculation and given the problems in the input data this
whole issue should be revisited and re-evaluated using ‘As Built’ / operating equipment
and environmental data due to the possible adverse effects on the platform should the
minimum temperatures defined above be achieved. Once the new calculations had
been completed alarms could be added to the affected equipment (e.g. the gas
injection manifold) which would warn that blowdown was necessary. Allowing the
temperature to fall below this point would lead to excessively low temperatures and the
potential for flare pipework failure through embrittlement.
Issue 34-010/2 - Should 'troubleshooting' methanol injection points be
incorporated?
They actually are installed. Therefore no further concern.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
35
Issue 34-011/1 – The individual well design rate has changed. What are the
implications for the platform?
The individual well rates have changed since design rendering the related calculations
obsolete. The new well rates need to be included in the RABS revision. Two aspects
will need to be addressed:
A final decision regarding the number of wells which fail to shut in, based on the
lower expected number of more prolific wells, which need to be designed for.
The maximum design well rate.
To follow from the above will require a modified procedure to be developed which
caters for the reduced time period available before the HP flare KO drum overfills
(which will happen in less than 10 minutes should relief occur at the higher well rates).
Issue 34-015/1 – Relief & Blowdown Study Report Rev C1 non-concurrent
maximum allowable LP and HP Flare loads are 110,874 kg/h
and 244,897 kg/h respectively. Rates used in these
calculations exceed design.
The maximum allowable independent LP and HP flare loads used in these calculations
to determine maximum allowable control valve CV for the blowby cases are greater
than the quoted figures in the Relief & Blowdown Study Report Rev C1 (i.e. 119,324
kg/h (LP) and 274,878 kg/h (HP) respectively). However the actual installed control
valve CVs are less than the calculated maximum. Therefore the system design rates
(244,897 and 110,874 kg/h) should not be exceeded. For consistency, the MP and LP
Separators relief valves should be checked against the installed control valve CVs.
Issue 34-015/2 - Is considering only one control valve fails open for the gas
blowby case when 2 are installed in parallel realistic / allowable
even with the provision of independent transmitters and
controllers?
This issue relates to the ability of only one of the LCVs to fail open. The level control
systems in question have independent transmitters and the equivalence in DCS terms
of duplicated controllers. This has been confirmed by HMDC studies. No further
action is required.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
36
Issue 34-061/1 - Annulus rupture case had the potential to be the defining case
for the HP flare system (depending on installed choke valve CV).
What happened subsequently?
The RABS states that gas lift to Hibernia wells is no longer required. If it becomes
necessary in the future then it will be provided by a method which will eliminate the
need to design for annulus rupture.
The situation with the Avalon wells is less clear. The RABS states that confirmation
was required during detailed design of the subsea facilities that annulus rupture need
not be considered as a relief case.
The need, or lack of, for design of the relief systems for annulus relief in both Hibernia
and Avalon wells should be confirmed.
Issue 34-022/1 – Calculated maximum pressure at PSV discharge exceeds value
on PSV datasheet Rev C1
Results of this calculation were taken into account on ‘As-Built’ PSV datasheet,
therefore no concern.
Issue 34-022/2 – Effect of increased production / production fluid GOR
The maximum associated gas capacity of the platform is governed by the capacity of
the compressors. This effectively set the required size of the HP separator relief
valves. Therefore even though the production GOR changes the relief valve should
have sufficient capacity whilst the compressors are able to take the gas. This link
should be made clear in the updated RABS.
Elsewhere in the system GOR has very little effect on the defining relief cases as
these are set by physical characteristics of installed valves, i.e. the gas blowby cases.
Should the physical characteristics of either of the above change, i.e. through
rewheeling a compressor stage, or through the use of larger control valve trims, the
calculations should be revisited.
Issue 34-023/1 – Calculated maximum pressure at spill-off valve discharge
exceeds value on control valve datasheet Rev C1
The difference in calculated and datasheet valve discharge pressure is small (146
kPa) and is insufficient to affect sizing. Furthermore, the installed CV is greater than
that required for the maximum flow (500 compared to 376 calculated for design
flowrate). Therefore the valve should be able to do its design duty.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
37
Issue 34-023/2 – Is case where valve fails fully open is considered?
It appears this case was not considered (or, at least, not in the calculations we have
seen). This comment appears to be true for all the spillover valve cases. The
consequences of failed open spillover valves should form a section in the updated
RABS.
Returning to this particular case, the normal operation of this valve directs
245,000 kg/h to the HP flare (when the compressors shut down). This is the same
flowrate as the design maximum for the HP flare. The calculated valve CV for this flow
is 376 and the control valve installed CV is 500 therefore if the valve were to be sent
wide open, for any reason, there would be an instantaneous flowrate of around
326,000 kg/h directed to the HP flare, which is well above the HP flare design figure.
We are also aware that this valve trim has recently been replaced with a 550 CV trim
making the potential overshoot worse. The consequences of this relief case, such as
thermal radiation impingement on the platform, together with remedial measures to
limit the peak should be investigated further.
Issue 34-024/1 - Calculated maximum pressure at (MP separator) PSV discharge
exceeds value on PSV datasheet Rev C2
Results of this calculation taken into account on ‘As-Built’ PSV datasheet, therefore no
concern.
Issue 34-025/1 - Calculated maximum pressure at (3rd stage compressor) PSV
discharge exceeds value on PSV datasheet Rev C2
‘As-Built’ PSV datasheet retains original back pressure of 500 kPa(g) max. However
the PSV set pressure is 25,500 kPa(g) and the minor increase in back pressure will
have no effect on the PSV capacity.
Issue 34-025/2 - Is relief from both compressor trains a valid case?
We are aware of events which have caused relief valves to lift on both compressors
simultaneously. A modification project was included to avoid this occurrence. The
project should be reviewed for its capability to prevent this case and a description
should be included in the updated RABS.
Issue 34-026/1 - Calculated maximum pressure at PSV discharge exceeds value
on PSV datasheet Rev C2
‘As-Built’ PSV datasheet retains original back pressure of 500 kPa(g) max. However
as the minimum PSV set pressure is 45,500 kPa(g) the minor increase in back
pressure will have no effect on the PSV capacity.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
38
Issue 34-027/1 – Was failed open MP spillover control valve considered?
The normal operation of this valve directs 94,500 kg/h to the HP flare. The calculated
valve CV for this flow is 522 and the control valve installed CV is 600 therefore if the
valve were to be sent wide open, for any reason, there would be an instantaneous
flowrate of somewhat less than 109,000 kg/h directed to the HP flare. This flowrate is
considerably lower than the HP flare design maximum so is tolerable. There may be
significant noise associated with this case.
Issue 34-028/1 – Is case where west test separator spillover valve fails fully open
considered?
The normal operation of this valve directs 58,800 kg/h to the HP flare. By inspection, if
the valve were to be sent wide open, for any reason, the instantaneous flow to the flare
would not exceed the HP flare design maximum so is tolerable. There may be
significant noise associated with this case.
Issue 34-030/1 – Is case where east test separator valve fails fully open
considered?
The normal operation of this valve directs 58,800 kg/h to the HP flare. By inspection, if
the valve were to be sent wide open, for any reason, the instantaneous flow to the flare
would not exceed the HP flare design maximum so is tolerable. There may be
significant noise associated with this case.
Issue 34-/1 – Calculated maximum pressure at 1st stage compressor spill-off
valve discharge exceeds value on control valve datasheet Rev C1
The difference in calculated and datasheet valve discharge pressure is small (50 kPa)
compared to the upstream pressure and the installed CV is greater than that required
for the maximum flow (320 compared to 231 calculated for design flowrate). The valve
will therefore easily pass the desired rate.
Issue 34-/2 – Is case where 1st stage compressor spillover valve fails fully open
considered?
The normal operation of this valve directs 59,800 kg/h to the HP flare. By inspection, if
the valve were to be sent wide open, for any reason, the instantaneous flow to the flare
would not exceed the HP flare design maximum rate. There may be significant noise
associated with this case.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
39
Issue 34-039/1 – Is case where LP separator spillover valve fails fully open
considered?
The normal operation of this valve directs 60,200 kg/h to the LP flare. The calculated
valve CV for this flow is 3097 and the control valve installed CV is 4145 therefore if the
valve were to be sent wide open, for any reason, there would be an instantaneous
flowrate of somewhat less than 80,600 kg/h directed to the LP flare. This flow is
considerably less than the LP flare design maximum flowrate. The case would be of
short duration as the LP separator pressure would immediately begin to fall, lowering
the rate experienced.
Issue 34-045/1 - There is no network analysis run with common HP Blowdown at
initial conditions
The calculations for total HP blowdown were all done on an individual basis only to
check that the velocity criterion was not exceeded in the laterals (a check for
excessive pressure drop was also made). No network analysis for total blowdown was
done. This was a valid approach at the time as it could be assumed that all blowdown
valves would be operating at sonic velocities and back-pressures that could restrict
flow would never be reached in the system. Given that HMDC are considering
modifications to the platform, the construction of a network model of the HP flare
system would be a useful exercise to determine the effects of any modifications
proposed.
Issue 34-045/2 - Consistency error in the blowdown flowrate from the gas
injection flowlines.
This calculation identifies 8 blowdown valves each with an initial blowdown rate of
2250 kg/h (the blowdown simulation gives actual rate is 2233 kg/h). The total
blowdown rate for all GI lines given in calc 34-006/A is 8932 kg/h indicating that the
HP flare system is designed to accommodate four GI wells. If more than four GI wells
are installed in the future, calculation 006 should be revisited.
Issue 34-042/1 – Total blowdown rate (initial rate) used in calc less than that in
Relief & Blowdown Study Report (89,601 kg/h)
This calculation uses 86,709 kg/h for total LP blowdown initial rate, less than that
stated in Relief & Blowdown Study Report (89,601 kg/h). The lower blowdown load is
in fact a more up to date figure as stated in calculation 34-006 / A Rev 06. The
decreased LP flare blowdown load should be incorporated into an updated Relief &
Blowdown Study Report.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
40
Issue 34-033/1 – Assumption that the header is at zero pressure (i.e. that this is a
singular event not coincident with any other releases)
To calculate the PSV back pressure for these valves, it is assumed that the header the
lateral relieves to is at zero pressure. This will not be true for systems which do not
blowdown. During a local fire the affecting these systems the blowdown system will be
activated. A back pressure only slightly higher than that calculated will be greater than
10% of the PSV set pressure of 700 kPa(g). API RP520 only allows a maximum back
pressure of 10% of set pressure for this type of valve (conventional). The valve
selection therefore needs to be reviewed and resized as necessary. This will require a
flare network model to be constructed.
In a number of areas this same inconsistency exists and the valve selection should be
reviewed similarly.
Issue 34-036/1 – Inconsistency on (injection compressor PSV) datasheet
between accumulation and 'Max Relieving Pressure' (should be
10%)
Rev C2 PSV-7326 datasheet 'Max Relieving Pressure' is 121% of set pressure
therefore inconsistent with stated 10% accumulation. The ‘As Built’ datasheet shows
accumulation at 10% therefore no concern.
Issue 34-037/1 – Calculated back pressure (for 0152A/B) greater than specified
on datasheet - calc considers this OK as less than 10% of set
pressure
The maximum calculated PSV back pressure is 84 kPa(g); higher than the ‘As Built’
datasheet, which shows 1-35 kPa(g), but less than 10% of the PSV set pressure of
1380 kPa(g). API RP520 allows a maximum back pressure of 10% of set pressure for
conventional valves therefore there is no concern.
Issue 34-046/1 – 'As Built' P&IDs show bursting discs installed in this service
(calc considers PSVs) therefore calc is no longer valid
There is no replacement calculation for the installed bursting discs. The bursting disk
calculations should be reviewed to identify implications for the flare system.
Issue 34-050/1 – Rev C2 PSV datasheet states set pressure = 8200 kPa(g), 'As
Built' P&ID shows set pressure = 7000 kPa(g)
‘As Built’ datasheet has 33-PSV-7200 set pressure of 8200 kPa(g). As the item of
equipment the PSV is protecting (D-3303A) has a design pressure of 8200 kPa(g) the
error is on the P&ID. The P&ID should be corrected at the next revision. This also
applies to 33-PSV-7226 protecting D-3303B.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
41
Issue 34-054/1 – Rev C2 (HP manifold) PSV datasheet states set pressure =
34,400 kPa(g), 'As Built' P&ID shows set pressure = 34,100
kPa(g)
The ‘As Built’ datasheet has 31-PSV-7042A/B set pressure of 34,100 kPa(g) therefore
the P&ID is probably correct and the design pressure revised downwards since the
Rev C2 PSV datasheet issued. No changes are therefore required.
Issue 34-057/1 – Calculated back pressure exceeds that specified on datasheet
for both (recirculation heater) PSVs
The maximum calculated back pressure for each PSV exceeds that stated on the ‘As
Built’ datasheet, which shows 1-35 kPa(g). However the calculated back pressure is
still less than 10% of each PSV set pressure. API RP520 allows a maximum back
pressure of 10% of set pressure for conventional valves therefore there is no concern.
Issue 34-059/1 – Accuracy of calculations using ESI instead of INPLANT
ESI has been used extensively in the flare calculations. This comparison calculation
between ESI and SIMSCI’s hydraulic simulator, INPLANT, showed that ESI gave
pressure drops 20% less than INPLANT. There appears that nothing was done to
recheck the calculations at the time. Assuming that INPLANT is more accurate (as it is
more rigorous) then a 20% difference on pressure drop calculation is significant. All
calculations using ESI should be revisited.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
42
5.3 Results of the Technical Audit – Relief Valve Sizing Calculations
In Appendix I the full results of the audit are given. The detailed tables that follow
identify a number of issues to be dealt with which concern the accuracy or soundness
of the design conclusions.
Table 5.5 Technical Audit Issues – Relief Valve Sizing Calculations
Calculation Issue
Number Title Rev Date Number Description
31.35 Relief Valve Calculations - HP Separator
C1 Nov-91 31.35/1 Does 2 phase relief case become the governing case if the calculation new calculation method given in API RP520, Seventh Edition used?
31.35/2 Flare network analysis for 2 phase case
(Calc 34-064 / G) used total load = 252,372
kg/h (40,000 bpd).
31.35/3 Relief & Blowdown Study Report Rev C1
states HP Separator Blocked Outlet
(Vapour) relief load is 244,897 kg/h.
31.35/4 The two phase calculation feed vapour /
liquid split was abnormally low.
31.35/5 Methodological problem in calculation
(compared to API RP520 Sixth Edition).
The wrong effective pressure was for the
V/L split and property conditions.
31.36 Relief Valve Calculations - MP Separator
C1 Nov-91 31.36/1 Does 2 phase relief case become the
governing case if the calculation new
calculation method given in API RP520,
Seventh Edition used?
31.36/2 Are 2 x 50% LCVs sufficiently independent?
31.36/3 Methodological problem in calculation
(compared to API RP520 Sixth Edition).
The wrong pressure was used to generate
the vapour amount and properties.
31.36/4 The two phase calculation feed vapour /
liquid split was abnormally low.
31.36/5 Calculation subsequently superseded but
no indication that calculation was
subsequently corrected.
31.36/6 The gas blowby cases are methodologically
flawed.
31.36/7 There is an error in the gas rate calculated
by the test separator gas blowby case.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
43
Table 5.3 Technical Audit Issues – Relief Valve Calculations (Cont.)
Calculation Issue
Number Title Rev Date Number Description
31.37 Relief Valve Calculations - LP
Separator
C0 27-Nov-91 31.37/1 Is it possible for the Test Separator
manifold to be connected to the LP
Separator when operating in high pressure
mode?
31.37/2 Are 2 x 50% LCVs sufficiently independent?
See also 31.36/6
31.38 Inlet Line Size Checking for Relief
Valves
05-Dec-91 31.38/1 Inlet line sizes should have been
recalculated using 'Final' relief data and
isometrics.
31.42 HP/MP/LP Separators PSV Inlet Line
Sizing
02-Jun-92 31.42/1 Pressure drop to HP Separator relief valves
has not been calculated using maximum
relieving capacity of valves
See also 31.43/1 & 31.43/2
31.43 Gas Blowby (Checking Capacity of
Downstream System for Gas Blowby
from HP to MP Separator and MP to
LP Separator)
22-Nov-92 31.43/1 This calculation considers both upstream
LCVs fail open simultaneously. This
scenario is not considered in the Relief &
Blowdown Study Report Rev C1 (or in any
other calculations reviewed), nor is the
platform designed for its affects.
31.43/2 This calculation considers both upstream
LCVs fail open simultaneously. This
scenario is not considered in the Relief &
Blowdown Study Report Rev C1 (or in any
other calculations reviewed), nor is the
platform designed for its affects.
31.43/3 The calculation identifies the failure of the
spillover valve (open) could lead to a relief
rate which is higher than the current design.
5.3.1 Technical Audit Issue Discussion – Relief Valve Calculations
The following describes the technical audit issues identified in Table 5.3. In this case
the issues are grouped by relief valve and then under broad issue headings.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
44
5.3.1.1 HP Separator Relief Valves
Two phase case
A series of issues raised by the technical audit can be grouped together under this
issue, i.e.
Issue 31.35/1 - Does two phase relief case become the governing case if the
calculation new calculation method given in API RP520, Seventh
Edition used?
Issue 31.35/2 - Flare network analysis for 2 phase case (Calc 34-064 / G) used
total load = 252,372 kg/h (40,000 bpd).
Issue 31.35/4 - The two phase calculation feed vapour / liquid split was
abnormally low.
Issue 31.35/5 - Methodological problem in calculation (compared to API RP520
Sixth Edition). The wrong pressure was used to generate the
vapour amount and properties.
The calculation of the relief valve area for the two-phase case underestimates the area
required. There was a combination of inconsistency, probably incorrect simulation
compositions and a flaw in methodology (compared to API RP 520 Sixth Edition) which
together would underestimate the orifice area required. However, because of the new
sizing method we are obliged now to use (see Section 6.5) and because of well rate
considerations these problems will naturally be corrected in the new calculation that
will be required.
So returning to 31.35/1, the most important of these considerations; the relief valve
orifice area required for the original two phase relief case based on the new Leung
omega API RP520 calculation method is 8.21 in2. This compares with the originally
(incorrectly) calculated value of 3.19 in2 for the same relief scenario. Obviously the
new method of calculation has a significant effect on required orifice area for relieving
two phase flow. In this particular case, the governing case for the relief valve was
blocked outlet – vapour relief only, which required a minimum orifice area of 9.38 in2
whereas the actual installed orifice area is 11.05 in2. On the face of it, therefore, no
hardware modifications are required.
However, we are aware that the maximum single well rate is now well in excess of the
originally considered 40 kbopd case (which represented one large and one medium
well failing to shut in). Therefore the relief case must be rigorously recalculated.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
45
Using the new sizing method the maximum safe well rate for a single well failing to
shut in is approximately 54 kbopd. Measures should be taken to limit the maximum
well rate to this value, and to less than this value if 2 wells failing to shut in becomes
the selected basis.
Vapour only case
Issue 31.35/3 - Relief & Blowdown Study Report Rev C1 states HP Separator
Blocked Outlet (Vapour) relief load is 244,897 kg/h.
The rate used in the calculation and to purchase the relief valve was 227,649 kg/h.
This appears to be confused in the RABS with the normal maximum associated gas
rate when the spillover valve is open during a compressor shut down. This
inconsistency should be corrected in the updated RABS.
5.3.1.2 MP Separator Relief Valves
Two phase case
Issue 31.36/1 - Does two phase relief case become the governing case if the new
calculation method given in API RP520, Seventh Edition is used?
Issue 31.36/3 - Methodological problem in calculation (compared to API RP520
Sixth Edition). The wrong pressure was used to generate the
vapour amount and properties.
Issue 31.36/4 - The two phase calculation feed vapour / liquid split was
abnormally low.
The same description as above (Section 5.3.1.1) is equally valid here (although the
orifice areas are different). This case must be calculated rigorously recalculated.
Issue 31.36/2 - Are 2 x 50% LCVs sufficiently independent?
This issue relates to the ability of only one of the LCVs to fail open. The level control
systems in question have independent transmitters and the equivalence in DCS terms
of duplicated controllers. This has been confirmed by HMDC studies. No further
action is required. See also below.
Issue 31.36/5 - Calculation subsequently superseded but no indication that
calculation was subsequently corrected.
The gas blowby rate was reduced in January 93 (because the valve CV was reduced
from 400 to 350). However the valve selection remained unchanged. The required
orifice area is therefore higher than it needed to be.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
46
Issue 31.36/6 - Are the gas blowby cases methodologically flawed?
It is arguable that the gas blowby cases are methodologically flawed. The reasons for
this are given below:
API RP520 does not allow credit for control valves in their normal position to move
to reduce the relief rate, although the requirements are rather vague. Thus there
may be a case for considering, irrespective of the control system, the worst case
as one valve failed open and one in its normal position. However, as there is also
a ESD/PSD between the systems we believe this would a very harsh case to
consider.
The 100% gas case is normally considered only in a shutdown situation (otherwise
a high component of the feed to the separator must pass with the gas to low
pressure system and be relieved). Therefore, in a shutdown situation (where the
liquid has dumped for some reason) a calculation method similar to settleout is
normally used, i.e. the volume of gas lost from the higher pressure side to raise the
pressure of the lower pressure side to the relief pressure is removed from the
effective relief driving force. Also in this case the failure open of one valve is more
likely to be acceptable because the likelihood of the both LCVs and the isolating
ESVs failing is very low
Should a LCV fail open during normal production then the blowby fluid is both
vapour and liquid (which will reduce the effective blowby volume rate) and also the
normal positions of the downstream control valves could be taken into account
thereby dramatically reducing the apparent relief rate.
The above assumes the QRA did not identify the possibility of both valves failing open
which we understand to be the case.
The net effect of the above is to suggest the relief rates designed for are higher than
they need be. A note could be added to the updated RABS to reflect this.
Issue 31.36/7 - There is an error in the gas rate calculated in the test separator
gas blowby case.
The calculation of the gas blowby rate from the test separators uses a subcritical
formula for the level control valve even though the calculation shows that the flow is
critical. By inspection, the error will not affect the sizing of the relief valve as relief rate
for this case is considerably less than for the governing case.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
47
5.3.1.3 LP Separator
Issue 31.37/1 - Is it possible for the Test Separator manifold to be connected to
the LP Separator when operating in high pressure mode?
The test separators are able to operate in two modes, high pressure and low pressure.
When operating in HP mode they are connected to the MP Separator and when in LP
mode to the LP Separator. This calculation considers that the test separators are in
LP mode but the reliability of the installed precautions / interlocks preventing
connection of the test separators in HP mode to the LP Separator is not apparent. As
the test separators can operate at 4240 kpa the potential gas blowby rate to the LP
Separator, if incorrectly lined up, would be significant. This relief scenario should be
investigated further.
Issue 31.37/2 - Are 2 x 50% LCVs sufficiently independent?
See Issue 31.36/2 above.
5.3.1.4 Miscellaneous
Issue 31.38/1 - Inlet line sizes should have been recalculated using 'Final' relief
data and isometrics.
This calculation was done with preliminary data and has obviously been revised as
many PSV inlet line sizes shown on the ‘As Built’ P&IDs are different to those
calculated here. The inlet line sizes should be checked against ‘As Built’ data and
isometrics.
Issue 31.42/1 - Pressure drop to HP Separator relief valves has not been
calculated using maximum relieving capacity of valves.
The relief valve inlet line size has been calculated using the calculated governing case
relief rate of 227,649 kg/h. API RP520 Part II states that the inlet line size should be
calculated using the ‘maximum rated capacity’ of the installed relief valve which in this
case is 262,161 kg/h. It is not expected that the inconsistency will have a significant
effect on the inlet line size as a margin of 20% was applied at the time. (See also
Issue 31.38/1 above).
Issue 31.43/1 and 2 - This calculation considers both upstream LCVs fail open
simultaneously. This scenario is not considered in the Relief &
Blowdown Study Report Rev C1 (or in any other calculations
reviewed), nor is the platform designed for its affects.
In view of the description in 31.36/6 this case does not appear feasible. The notes
attached to the calculations should have said so.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
48
Issue 31.43/3 - The calculation identifies the failure of the spillover valve (open)
could lead to a relief rate which is higher than the current design.
The calculation identifies that the LP Separator spillover valve, if it failed fully open,
could generate a flowrate of 121,035 kg/h in the LP flare. This is greater than the
current design LP flare capacity of 110,874 kg/h. The maximum flowrate which could
be sent to the LP flare system under this scenario should be investigated for the
current operation.
5.4 Technical Audit Conclusion Summary
In tabular form, the following summarises the actions required to be undertaken in
Stage 2.
Table 5.6 Technical Audit Conclusion Summary (System 34)
Number
34-
Title Number
34-
Description Action
005 / A Blowdown Section Inventory Calc (Provides input to blowdown simulations)
005/1 Are the blowdown volumes used sufficiently accurate?
Locate and review missing
calculations
005/2 Jet fire scenario not taken into account
for the design of the blowdown system
Incorporate jet fire calculations
and update RABS accordingly
005/3 Were the real settle out pressures ever
used?
Compare real settleout conditions
with design to ensure blowdown
rates are appropriate
005/4 Were fire areas used for total blowdown
rate?
No further action
005/5 Are vessel weights used reasonable? No further action
006 / A Blowdown Summary 006/1 HP Blowdown calculation higher than
vendor aware of. Radiation level for
case is underestimated.
Update RABS.
006/2 Correct isentropic efficiency used? An optimistic isentropic efficiency
was used to calculate the
minimum system temperature.
Recalculate the temperatures.
See also 34.010/1.
006/3 Is design case too extreme? Select start pressure basis and
update RABS.
006/4 Is constant rate blowdown a valid design
method, i.e. not according to API?
No further action unless staggered
blowdown becomes an issue
006/5 'As Built' settleout pressure See 005/3 above
010 / A Calculation of allowed
cooldown before
hydrate formation &
minimum
temperatures
achieved in flare gas
from critical blowdown
sections
010/1 Was the calculation methodology
sufficiently robust?
There are flaws in the method
used to calculate the minimum
temperatures in the system.
These should be corrected. Use
resultant more realistic figure to
implement alarms on high
pressure areas to avoid low
temperatures. Update RABS.
010/2 Should 'troubleshooting' methanol
injection points be incorporated?
No further action
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
49
Number
34-
Title Number
34-
Description Action
011 / A Review of HP flare
KO Drum size
011/1 A note on the front of calc 34-064 states
that Rev 7 of Design Basis gives max
well flow of 20,000 bpd + average well of
10,000 bpd, i.e. 30,000 bpd total. The
individual well design rate has changed.
What are the implications for the
platform?
Select number and design rate of
the well failure to shut in case.
Update RABS. Develop
operational procedure to cater for
time to fill HP flare KO vessel.
012 / A Review of LP flare KO
Drum size
See 34-011/1 See 34-011/1
015 / A Calc to review options
for reducing HP to MP
Separator and MP to
LP Separator Blowby
Cases
015/1 Relief & Blowdown Study Report Rev C1
non-concurrent maximum allowable LP
and HP Flare loads are 110,874 kg/h
and 244,897 kg/h respectively. Rates
used in these calculations exceed
design.
Ensure design rates quoted are
consistent and reflect the installed
control valves. Update RABS.
015/2 Is considering only one control valve
fails open for gas blowby case when 2
installed in parallel realistic / allowable
even with provision of independent
transmitters and controllers?
No further action required
060 / B Indicative Injection
Compressor
Cooldown Calculation
See 34-010/1 and 34-010/2 See 34-010/1 and 34-010/2
061 / B Simplistic Steady
State Preliminary
Review of the Annulus
Rupture Relief
Flowrate
061/1 This case had the potential to be the
defining case for the HP flare system
(depending on installed choke valve CV)
What happened subsequently?
No further action required
022 / C HP Flare Network
Sizing (HP Separator
- Max Relief Case)
022/1 Calculated maximum pressure at PSV
discharge exceeds value on PSV
datasheet Rev C1
No further action required
022/2 Effect of increased production /
production fluid GOR
Update RABS to mention link
between GOR and the compressor
capacity.
023 / C HP Separator Max
Spill-off Case -
Network Analysis
023/1 Calculated maximum pressure at spill-off
valve discharge exceeds value on
control valve datasheet Rev C1
No further action required.
023/2 Is case where valve fails fully open
considered?
Recalculate case. Assess
measures for reducing the peak
load during failure. Implement
modification project.
See also 34-022/2 See also 34-022/2
024 / C MP Separator Max
Relief Case - Network
Analysis
024/1 Calculated maximum pressure at PSV
discharge exceeds value on PSV
datasheet Rev C2
No further action required.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
50
Number
34-
Title Number
34-
Description Action
025 / C 3rd Stage
Compressor Max
Relief Case - Network
Analysis
025/1 Calculated maximum pressure at PSV
discharge exceeds value on PSV
datasheet Rev C2 - Check for later
revisions
No further action required.
025/2 Include in updated RABS cases which
are not catered for, i.e. consider relief
from both compressor trains
Check modifications to avoid
injection compressor RVs lifting
prevent coincident case. Update
RABS to explicitly mention the
cases which are not designed for.
026 / C Injection Compressor
Max Relief Case -
Network Analysis
026/1 Calculated maximum pressure at PSV
discharge exceeds value on PSV
datasheet Rev C2
No further action required.
See also 34-025/1& 34-025/2 See also 34-025/1& 34-025/2
027 / C MP Separator Max
Spill-off Case -
Network Analysis
027/1 Was failed open control valve
considered?
Recalculate case. Assess
measures for reducing the peak
load during failure if necessary.
See also 34-022/2
028 / D West Test Separator
Max Spill-off Case -
Network Analysis
028/1 Is case where valve fails fully open
considered.
No further action required.
See also 34-022/2 See also 34-022/2
029 / D West Test Separator
Max Relief Case -
Network Analysis
See 34-022/2 See 34-022/2
030 / D East Test Separator
Max Spill-off Case -
Network Analysis
030/1 Is case where valve fails fully open is
considered?
No further action required.
See also 34-022/2 See also 34-022/2
031 / D East Test Separator
Max Relief Case -
Network Analysis
See 34-022/2 See 34-022/2
34- / E 1st Stage Compressor
Spill-off Case -
Network Analysis
34-/1 Calculated maximum pressure at spill-off
valve discharge exceeds value on
control valve datasheet Rev C1
No further action required.
34-/2 Is case where valve fails fully open
considered?
No further action required.
045 / E Total HP Blowdown
Initial Conditions
(Checks blowdown
line sizes for
individual system
blowdowns)
045/1 There is no network analysis run with
common HP Blowdown at initial
conditions
Consider constructing a HP flare
network model to assess future
modification projects against.
045/2 Consistency error in the number and
flows in the gas injection flowlines
Add a note to the RABS clarifying
the injection manifold rate basis.
039 / F LP Separator Max
Spill-off Case -
Network Analysis
039/1 Is case where valve fails fully open
considered?
Recalculate case. Assess
measures for reducing the peak
load if necessary.
See also 34-022/2 See also 34-022/2
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
51
Number
34-
Title Number
34-
Description Action
042 / F Total LP Blowdown -
Initial Conditions -
Network Analysis
042/1 Total blowdown rate (initial rate) used in
calc less than that in Relief & Blowdown
Study Report ( 89,601 kg/h)
Update RABS
042/2 Validity of staggering blowdown. Were
the systems sufficiently independent?
Perform safety analysis to
satisfactory standard to show the
vessels will not fail during jet fire
(including the A injection
compressor and components).
043 / F Injection Compressor
'A' Blowdown - Initial
Conditions - Network
Analysis
See 34-042/2 See 34-042/2
033 / G Coalescer & LP
Separator Heaters
Simultaneous Fire
Relief - Network
Analysis
033/1 Assumption that the header is at zero
pressure (I.e. that this is a singular event
not coincident with any other releases)
Construct a LP flare network
model to calculate the back
pressure on relief valves when the
system is depressuring.
036 / G Injection Stage
Suction Scrubber PSV
- Network Analysis
036/1 Inconsistency on datasheet between
accumulation and 'Max Relieving
Pressure' (should be 10%)
No further action required.
037 / G HM & CM Expansion
Drums Simultaneous
Fire Relief Case -
Network Analysis
037/1 Calculated back pressure (for 0152A/B)
greater than specified on datasheet -
calc considers this OK as less than 10%
of set pressure
See also 34-033/1
No further action required.
044 / G Total LP Blowdown -
After 3 mins (stagger
point) - Network
Analysis
See 34-042/2 See 34-042/2
046 / G Fuel Gas Cooler /
Heater tube rupture
relief line size check
046/1 ''As Built' P&IDs show bursting discs in
this service (calc considers PSVs)
therefore calc is no longer valid
There is no replacement
calculation for the installed
bursting discs. The bursting disk
calculations should be reviewed to
identify implications for the flare
system.
050 / G 3rd Stage Suction
Scrubber A (D-3303A)
PSV Discharge Line
Size Confirmation
050/1 Rev C2 PSV datasheet states set
pressure = 8200 kPa(g), 'As Built' P&ID
shows set pressure = 7000 kPa(g)
P&ID set pressure error?
052 / G E-3301 Shell Side
PSV Discharge Line
Size Confirmation
See 34-033/1 See 34-033/1
053 / G E-3303B Shell Side
PSV Discharge Line
Size Confirmation
See 34-046/1 See 34-046/1
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
52
Number
34-
Title Number
34-
Description Action
054 / G HP Manifold Relief -
Network Analysis
054/1 Rev C2 PSV datasheet states set
pressure = 34,400 kPa(g), 'As Built'
P&ID shows set pressure = 34,100
kPa(g)
No further action required.
055 / G Simultaneous Fire
Relief Case from Z-
3701 A/B, Z-3702 A/B
& Z6202 A/B (pig
launchers and fuel
gas package)
See 34-033/1 See 34-033/1
057 / G E-3701 Shell & Tube
Side Simultaneous
Fire Relief Case - Line
Size Confirmation
057/1 Calculated back pressure exceeds that
specified on datasheet for both PSVs
See also 34-033/1
See 34-033/1
058 / G E-6201A/B Tube Side
Fire Relief Case
See also 34-033/1 See 34-033/1
059 / G Comparative Program
check of INPLANT
Single Phase
Simulation vs ESI
059/1 Accuracy of calculations using ESI
instead of INPLANT
Revisit ESI calculations and
replace as necessary
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
53
Table 5.7 Technical Audit Conclusion Summary (System 31)
Number Title Number Description Action
31.35 Relief Valve Calculations - HP Separator
31.35/1 Does 2 phase relief case become
the governing case if the calculation
new calculation method given in API
RP520, Seventh Edition used?
Replace two phase sizing case
with new method. Use finalised
maximum well design rates.
Implement modification project as
necessary.
31.35/2 Flare network analysis for 2 phase
case (Calc 34-064 / G) used total
load = 252,372 kg/h (40,000 bpd).
See 31.35/1
31.35/3 Relief & Blowdown Study Report
Rev C1 states HP Separator
Blocked Outlet (Vapour) relief load is
244,897 kg/h.
Correct inconsistency in RABS
update.
31.35/4 The two phase calculation feed
vapour / liquid split was abnormally
low.
See 31.35/1
31.35/5 Methodological problem in
calculation (compared to API RP520
Sixth Edition). The wrong effective
pressure was for the V/L split and
property conditions.
See 31.35/1
31.36 Relief Valve Calculations - MP Separator
31.36/1 Does 2 phase relief case become
the governing case if the calculation
new calculation method given in API
RP520, Seventh Edition used?
See 31.35/1
31.36/2 Are 2 x 50% LCVs sufficiently
independent?
No further action required.
31.36/3 Methodological problem in
calculation (compared to API RP520
Sixth Edition). The wrong pressure
was used to generate the vapour
amount and properties.
See 31.35/1
31.36/4 The two phase calculation feed
vapour / liquid split was abnormally
low.
See 31.35/1
31.36/5 Calculation subsequently
superseded but no indication that
calculation was subsequently
corrected.
No further action required.
31.36/6 Are the gas blowby cases are
methodologically flawed?
Add note to RABS update
31.36/7 There is an error in the gas rate
calculated by the test separator gas
blowby case.
No further action required.
31.37 Relief Valve
Calculations - LP
Separator
31.37/1 Is it possible for the Test Separator
manifold to be connected to the LP
Separator when operating in high
pressure mode?
Ensure positive method of
ensuring isolation from HP system
exists. Update RABS to reflect
this.
31.37/2 Are 2 x 50% LCVs sufficiently
independent?
See 31.36/2
See also 31.36/6 See also 31.36/6
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
54
Number Title Number Description Action
31.38 Inlet Line Size
Checking for Relief
Valves
31.38/1 Inlet line sizes should have been
recalculated using 'Final' relief data
and isometrics.
Check / redo inlet line sizing
calculations as necessary.
31.42 HP/MP/LP Separators
PSV Inlet Line Sizing
31.42/1 Pressure drop to HP Separator relief
valves has not been calculated using
maximum relieving capacity of
valves
See 31.38/1
See also 31.43/1 & 31.43/2 See also 31.43/1 & 31.43/2
31.43 Gas Blowby
(Checking Capacity of
Downstream System
for Gas Blowby from
HP to MP Separator
and MP to LP
Separator)
31.43/1&2 This calculation considers both
upstream LCVs fail open
simultaneously. This scenario is not
considered in the Relief & Blowdown
Study Report Rev C1 (or in any
other calculations reviewed), nor is
the platform designed for its affects.
No further action required.
31.43/3 The calculation identifies the failure
of the spillover valve (open) could
lead to a relief rate which is higher
than the current design.
Recalculate case. Assess
measures for reducing the peak
load during failure. Implement
modification project. Same action
as 34.039/1.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
55
6.0 CHALLENGE PROCESS
6.1 Introduction
Before commencing the challenge process the key legislative aspects are introduced
6.1.1 The Principles of the Legislation
The general requirements of HSW legislation are neatly summarised in the following
extract. Here we use an interpretation supplied by a representative of the relevant UK
government department. We believe the requirements of Canadian HSW legislation to
be very similar:
As a duty holder under HSW legislation, you have a continuing duty to ensure the H&S
of employees and other persons who may be affected by the way in which you
undertake your business. The legislative regime sets a goal for duty holders to do all
that is reasonably practicable. In some areas technological change is so fast that
standards of compliance which would have been acceptable 10 years ago, are no
longer satisfactory. However the advantage of goal setting is that it keeps pace with
technological change, but also allows you to develop solutions which are better
aligned with the risks in your workplace.
So you will always, and continuously, have to keep an eye on new codes, standards,
good industry practice, etc., to ensure you are doing enough to satisfy the law. Where
it is reasonably practicable to do so, changes should be made. Nevertheless HSE
would accept that for existing installations it may be less reasonably practicable to
make a change, than is the case for a new installation - it is a judgement call which the
law requires you to make (and be able to justify, if or when challenged).
This sets the general principles by which retrospective change can be considered on
Hibernia. This advice clearly states that new codes and practices should be applied to
the facility unless it can be shown to be unreasonable.
6.1.2 Relevant Canadian Legislation
The relevant legislative regulations for Hibernia are those issued under the Canada -
Newfoundland Atlantic Accord Implementation Act. The key regulations which have
relevance for the flare system are as follows:
Newfoundland Offshore Petroleum Installations Regulations
During the design phase the relevant version of the regulations was the 1991 draft.
These were revised once again in draft form in 1993. The regulations were finally
registered on the 21 February, 1995.
During this time there was no substantive change to the documents in relation to
the design of the flare system.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
56
The key extracts from the 1995 regulations are given below:
Gas Release System
17. (1) In this section, “gas release system” means a system for releasing gas and
combustible liquid from an installation and includes a flare system, a pressure relief
system, a depressurizing system and a cold vent system.
(2) Every gas release system shall be designed and located, taking into account
the amounts of combustibles to be released, the prevailing winds, the location of
other equipment and facilities…, so that when the system is in operating it will not
damage the installation…, or injure any person.
(3) Every gas release system shall be designed and installed in accordance with
(a) American Petroleum Institute RP 520, Recommended Practice for the Design
and Installation of Pressure-Relieving Systems in Refineries;
(b) American Petroleum Institute RP 521, Guide for Pressure -Relieving and
Depressuring Systems;
(c) American Petroleum Institute Standard 526, Flanged Steel Safety-Relief
Valves;
(d) American Petroleum Institute Standard 527, Seat Tightness of Pressure Relief
Valves; and
(e) American Petroleum Institute Standard 2000, Venting Atmospheric and Low-
Pressure Storage Tanks.
(4) Every gas release system shall be designed and constructed to ensure that
oxygen cannot enter the system during normal operation.
(5)…
(7) With the exception of water, any liquid that cannot be safely and reliably burned
at the flare tip of a gas release system shall be removed from the gas before it
enters the flare…
(9) Every gas release system shall be designed and installed so that, taking into
account the prevailing wind conditions, the maximum radiation on areas where
personnel may be located , from the automatically ignited flame of a flare or vent,
will be
(a) 6.3 kW/m2, where the period of exposure will not be greater than one minute;
(b) 4.72 kW/m2, where the period of exposure will be greater than one minute but
not greater than one hour; and
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
57
(c) 1.9 kW/m2, where the period of exposure will be greater than one hour.
The remainder of the regulations describe requirements relating to ventilation, the
selection of electrical components, escape routes, emergency control systems etc.
Petroleum Occupational Safety and Health Regulations - Newfoundland, Draft
November 1989.
These regulations are referenced in the RABS. Their only influence on the flare
system design appears to be to ensure the sound levels are acceptable:
i.e.
85 dB but no more than 90 dB for 8 hours exposure
102 dB but no more than 104 dB for 1 hours exposure
etc.
The other regulations covering certificates of fitness, drilling, and diving have no
significant influence on the design of the flare system.
6.1.3 Applying the Legislation
With the legislation in mind, the remainder of this section is organised to deal first with
the larger issues, which may affect a number of design characteristics of the flare
system. Subsequently the lesser aspects are dealt with sequentially as required.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
58
6.2 Jet Fire
6.2.1 Requirements of the relevant regulations, design codes and practices when
Hibernia was designed
6.2.1.1 Canadian Legislation
We are unaware of any explicit references in Canadian legislation regarding this
particular hazard.
6.2.1.2 Mobil Engineering Guide (EGS 661-1990)
We have been unable to source a copy of the 1990 version of the above so instead
are required to interpret between the 1985 version and the Draft 1991 version. In this
case no interpretation is required, as both versions are silent on the subject of jet
flame and the design requirements to mitigate against its effects. The guides,
however, do mention the maximum time allowed for depressuring is 2 minutes per
3 mm of vessel wall thickness, but shall not be less than 6 minutes. Where
depressuring is impractical the use of water sprays or insulation (both applied to Mobil
specification) can be considered. Some of these latter methods could be read to take
some account of extreme fires (for example jet fire).
6.2.1.3 API 521 (Third Edition, November 1990)
The third edition is silent on the issue of jet fire impingement on vessels.
6.2.2 How Jet Fire Was Actually Handled During Design
This is a summary of how jet fire was handled in the design phase. The entire subject
of its consideration was based in the probabilistic safety related design path. Out of
necessity it is an abridged version as the component parts are numerously described
in the various project documentation. Here the aim is to capture the essence of the
process and its effect on the way Hibernia was designed.
This is described below.
6.2.2.1 Legislative Requirements
The Canadian draft Production and Conservation Regulations required the submission
and maintenance of a Safety Plan for the Hibernia facilities. Part of the Safety Plan
would comprise the Concept Safety Evaluation. This document would form the basis
for all the risk and hazard related studies on the Hibernia Project.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
59
6.2.2.2 Concept Safety Evaluation (CSE)
The Concept Safety Evaluation (Reference 2) was the first attempt to identify and
quantify the major hazards connected with the Hibernia facility. The study also began
to define the terms Design Accidental Event (DAE) and Residual Accidental Event
(RAE) which would be used for the rest of the project. The definitions would, however,
gradually change over time but for the moment it is understood a DAE would only
affect those in the immediate vicinity of the accident whereas a RAE would potentially
affect the platform population.
Of key interest to the Flare Revalidation Study were the aspects identified regarding jet
fire.
The study explicitly recognised the potential for vessel rupture caused by short
duration jet fires in Module M10.
Deluge was considered ineffective in preventing escalation due to jet fire.
The times given for failure from jet fire impingement on various thicknesses of steel
were:
Table 6.8 Failure Times for Structures Engulfed in Jet and Pool Fires
Structure Jet Fire* (min) Pool Fire+ (min)
60mm Thickness Steel 12 30
25mm Thickness Steel 5 13
12mm Thickness Steel 2.5 6
5mm Thickness Steel 1 2.5
H120 Firewall 60 120
13mm Thickness Steel Tube Coated with Chartek Type III** >60
* Based on a jet fire radiation of 300 kW/m2
+ Based on a pool fire radiation of 150 kW/m2
** Based on research and field trials by Shell Thornton
(CSE Table 6.1)
The CSE also recognised the Key Safety Functions defined as follows:
the platform’s primary structure
the escape routes from the central parts of the platform to the Temporary Safe
Refuge
the Temporary Safe Refuge (TSR), including the central control room
the availability of the evacuation systems.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
60
Added to this were Hibernia’s three-tier framework of risk acceptability:
For any single incident that might affect the key safety systems (more accurately
functions from the above), the risk level for the three-tiers are:
Intolerable: greater than 10-4 per year.
ALARP region: 10-4 to 10-5 per year.
Lower bound of acceptability: less than 10-5 per year
The CSE went on then to assess the risk to the Key Safety Functions using
consequence analysis and event trees.
The CSE demonstrated to a reasonable extent that the effects of jet fire and explosion
did not jeopardise the structural integrity of the platform or the availability of the
evacuation systems. In this it is implicit in the CSE that jet fire was considered a RAE
and more of a risk to structural impairment than explosion.
The CSE also indicated that jet fire impingement may cause rapid failure of
unprotected structures even if deluge systems are operating. This might be because
the intense heating raises the surface temperature above 100°C, prior to application of
water, preventing the formation of a protective liquid film.
To confirm the above the CSE made various recommendations for future work which
included the requirement to conduct a Fire Risk Assessment to review the impact of
fire on structural integrity of the H120 walls and the flare boom and the potential for
escalation in Module M10.
6.2.2.3 Fire Risk Assessment (FRA)
By the time the FRA (Reference 3) was commenced the HMDC Damage / Impairment
Criteria had been formalised. These can be found in Section 3.2.1:
Also outlined in the FRA were the details of the blowdown system. The system
considered was, in principle, the same as the system outlined in the Relief and
Blowdown Study Report and subsequently built (see Table 6.17 for more detail).
The FRA looked at the duration and flame lengths of jet fires with and without
blowdown. This is summarised below:
Table 6.9 HP Separator Jet Flame Length With and Without Blowdown
Hole Size Without Blowdown (m) With Blowdown (at the end of the 15
minutes) (m)
5 mm 9 5
50 mm 53 29
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
61
Wherever the possibility of a jet fire impinging on a structural member was identified
the FRA recommended the use of PFP and firewalls to ensure the impairment criteria
were satisfied. These aspects were studied in the Structural Passive Fire Protection
Analysis (Reference 7).
The analysis undertaken in the FRA identified the potential for escalation should a jet
fire impinge on a vessel, e.g.
“Fire water deluge will act to keep the equipment cool, but a jet fire impinging directly
on a vessel may cause localised heating and loss of wall strength…”
(FRA page 56)
“Operation of the blowdown system should not be viewed as evidence of satisfactory
vessel response, and may not prevent failure if the vessel is subject to high heat loads
such as jet flame impingement...”
(FRA page 57)
“A HP separator incident could escalate to the LP separator and vice versa. The
vessels will be provided with local deluge protection which will provide adequate
protection for incident thermal radiation…”
(Emphasis added. FRA page 70)
The emphasis is added to contrast against protection from jet flame impingement.
This was more clearly outlined in the team review (part of the consequence analysis):
“The LP separator is likely to fail due to jet flame impingement…”
(FRA page B.15)
This led to the recommendation to install kerbs to prevent spread of liquid spills or pool
fires.
Generally the problem of jet fire impingement on vessels was implicitly mentioned on a
number of levels in Module M10. Other jet fire consequence analyses identified the
problems of jet flame impingement on firewalls, the crude oil coolers, the flare boom
and the hydraulic panel on level 5.
One of the key conclusions of the FRA was less clear:
“The FRA considered a number of potential fire scenarios. In each scenario, except
possibly a large blowout, the active systems (isolation, blowdown, F&G detection and
protection) will limit the consequences and should prevent escalation.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
62
Even if the active systems fail to operate, then the passive fire protection should
ensure that the Damage / Impairment Criteria are met…”
(FRA page 119)
The recommendations were to be studied further.
6.2.2.4 FRA Update
The FRA Update (Reference 4) revisited the key aspects of the FRA in relation to jet
fire and began to soften the conclusions. Some of the statements are included below:
“The KO drums are provided with deluge. This may not provide complete protection
against jet flame impingement…, but the duration would be short and failure is
unlikely…”
(FRA Update page 20)
“A jet flame from the gas scrubbers could impinge the MP separator, but it is unlikely
that it would be of sufficient duration to cause failure, provided the blowdown system
operates…”
(FRA Update page 21)
A leak from either the HP or LP Separators could cause either a jet flame or a pool
fire…Escalation to the HP and LP Separator is unlikely provided that the deluge
operates and the vessels are blown down…”
(FRA Update page 21)
A related aspect considered in the FRA Update was the use of PFP and particularly
Lloyds who stated no credit should be taken for any active fire systems when
considering the ability of PFP systems.
The study ended with the main FRA conclusions being considered valid.
6.2.2.5 Design Phase Risk Assessment of Potential Accidental Events (DPRA)
The DPRA (Reference 5) focused on the different types of accidental events. The
concept of contained events being DAE and uncontained events being RAE was
formally introduced.
The report also contained discussion of how the design was optimised so as to
prevent DAEs escalating into RAEs and impairing the main safety functions. The
document formalised the selection and differentiation between DAE and RAE. This is
shown below:
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
63
Figure 6.2 Method for Determining the Acceptability of DAEs and RAEs
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
64
The report was not completely clear as to which events were RAE or DAE. However
the following outlines our understanding:
Some hydrocarbon release events (assumed to be explosion, blowout and smoke)
are RAEs.
Otherwise, most fire hazards are DAEs. This includes jet fire impingement on main
structural members as this was mitigated against using PFP. Only in a few cases is
there potential for the fire scenarios to cause a RAE. These were identified as:
Fire damage to deck plate at el 114.000 allows fire damage to the underdeck
and collapse of structures within 2 hours.
Spread of fire from one wellhead to the another exceeds the capability of the fire
protection systems.
Failure of the isolation and blowdown systems to contain the inventory of
produced hydrocarbons and failure of the fire fighting systems to prevent
escalation for both topsides and utility shaft hydrocarbon releases. These are
“worst case” scenarios where virtually all the emergency systems have failed to
operate as intended. (An Emergency Systems Report would be prepared to look
into the possibility of these failures).
Smoke and heat effects could cause impairment of the Temporary Safe Refuge
(TSR) if the worst case circumstances occurred, e.g. the wind blows towards the
TSR, HVAC systems fails to detect smoke / gas or shutdown and doors and
penetrations are open.
Blowout combined with worst case weather conditions, causes impairment of the
TSR and evacuation systems.
Large fire on a hydrocarbon deck in the Utility shaft causing significant spalling of
the concrete walls and failure of the reinforcing bars.
All the above were subjected to further study and CBA (whose requirement that the
mitigation measure be undertaken if the cost was less than 10 times the yearly loss) to
show the risks were ALARP.
In the case of the failure of the safety systems the RAE was considered a DAE after
further study:
“In exceptional circumstances, individual components might be impaired. However,
the system’s redundancy was found to be adequate to perform the intended function”
(Reference 8)
“The Explosion Overpressure Risk Assessment… further assessed the effects of
explosions on the vent and blowdown systems and the structural design basis (one of
the main safety functions). Both were found to be acceptable.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
65
“Thus it is concluded that the basis for the selection of DAE and RAEs, and the
assumptions relating to the adequacy of emergency systems preventing DAEs into
RAEs, are valid.
DPRA page 42
The remainder of the report explains the other types of event which are RAE. These
are summarised in the table overleaf:
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
66
Table 6.10 Summary of Risks of Impairment (as they relate to this study)
RESIDUAL ACCIDENTAL
EVENT
RISK OF IMPAIRMENT OF MAIN SAFETY FUNCTION
(per year)
CSE Estimate Detailed Design Risk
Hydrocarbon Fire Hazards:
Damage to Underdeck
Spread to Wellheads
Heat Impairment of TSR
Crude Oil Fire in Utility Shaft
-
-
-
-
2 x 10-6
1.5 x 10-6
1 x 10-6
3 x 10-7
Sub-total for Hydrocarbon Fire Hazards - 4.8 x 10-6
Explosion Hazards
M10
M20
-
-
-
1 x 10-6
1 x 10-6
Sub-total for Explosion Hazards - 2 x 10-6
Blowout 1 x 10-4 1.5 x 10-5
Smoke 1.7 x 10-4 (in QRA of TSR
Integrity report)2.1 x 10-5
Dropped Objects - -
Flooding of Utility Shaft - <1 x 10-6
External Events:
Iceberg Collision
Ship Collision
Helicopter Crash
Earthquake
Wave Slam
5 x 10-7
5 x 10-7
1 x 10-6
(Note 2)
-
5 x 10-7
5 x 10-7
Negligible (Note 1)
(Note 2)
5 x 10-5 (Note 3)
Sub-total for External Events 2 x 10-6 1 x 10-6
TOTAL 2.7 x 10-4 1.5 x 10-5
Notes
Note 1: Negligible risk of impairing main safety functions. Risk to occupants of helicopter could be 2.6 x 10-4 per year.
Individual risk will be lower (approximately half) because the same individual is not on every helicopter flight.
Note 2: Earthquake design return period is 2000 years (5 x 10-4 per year) but this does not lead to structural failure
nor pollution. Risk associated with hydrocarbon events caused by earthquake will be significantly less than
other causes.
Note 3: Risk of damaging one essential generator. Risk to main safety functions will be negligible.
Jet fires are mentioned no further in the document.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
67
6.2.2.6 Design Phase Safety and Environmental Evaluation (DPSEE)
The preceding documents were summarised in the DPSEE (Reference 6). There
were no fundamental changes of relevance to the analysis herein.
It is relevant to mention the process areas in M10 where jet fire impingement was
explicitly considered and the mitigating reasons given:
Flare system - It was identified that the LP and HP flare KO drums would be
susceptible to jet fire. However this hazard was considered mitigated against by
the use of deluge and because the system was open to the flare.
Crude cooler - The loss of crude oil cooler inventory was identified and protection
provided using remedial means of isolation.
The remaining M10 areas were no longer mentioned in relation to jet fire.
6.2.2.7 Conclusions
Clearly, jet fire was considered extensively during the design. Indeed the platform is in
some respects designed to resist its effects, i.e. the PFP on the structural members
and the flare boom. Within this is the assumption that the jet fire can last significant
periods of time. Also implicit in the work is the ineffectiveness of deluge on protecting
the affected equipment against jet fire impingement. On the other hand, and of most
relevance to this report, there is no indication that jet fire was ever considered in the
blowdown system design.
In the event the issue seems to have been finally lost when the emergency systems
redundancy was deemed sufficient to perform the intended function, which was to
prevent escalation of a DAE to an RAE through loss of inventory (jet fire is not explicit
but appears to be the cause of the concern). The flaw in the argument is none of the
systems were actually included in the analysis of jet fire escalation or could be shown
to prevent escaltion (although all would be helpful in the situation).
This leaves the platform with the case where a jet fire impinges on a vessel
(particularly the LP separator) with no explicit protection to avoid escalation to at least
a DAE explosion event.
Because of the flaw mentioned above, the FRA did not look at the potential for jet fire
escalation to a RAE so no acceptability criteria were ever established. Potentially
therefore there was a missed RAE event in the analysis.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
68
It would be wrong to read this description believing that Hibernia has some design
deficiency. Generally this was the case with all facilities at the time, as the design
codes contained no guidance on how to cope with the jet fire hazard. In fact Hibernia
is much better than most facilities in this regard as will become evident in the following
sections.
6.2.3 Current Requirements of the Design Codes and Practices
6.2.3.1 Mobil (MP 70-P-06, July 1998)
The MEP remains silent on the issue of jet fire and its requirements have not
materially changed since the versions used during design.
6.2.3.2 API 521 (Fourth Edition, March 1997)
The requirements of the API codes has not changed in relation to jet fire since the
design phase and there still is no explicit requirement to design for jet fire events.
API’s position seems to be that jet fire is a low probability event whose effects are
analogous to explosion. These consequences are beyond the ability of a blowdown
system to contain. API were contacted to confirm whether this is the case. They have
responded the issue will be addressed once again during the API 521 revision planned
to commence during 2001. Granherne are pressing API to provide a response within
the timescale of this study.
6.2.4 Current Best Industry Practice
Once a hazard is identified it does not really matter that the codes of practice are silent
on the requirements to mitigate the hazard and this is the situation the industry finds
itself in with regard to jet fires. We fully expect future versions of API 521 to consider
in more detail the effects of jet fire and we know of at least two other organisations
performing research on the subject (Shell and a Joint Industry Project).
Current industry practice is tending towards incorporating jet fire into the analysis of
new facilities. Granherne know of at least 3 recent projects that were designed with
the assumption of jet fire impingement on equipment was a design criteria.
However, in the absence of prescriptive methods, the way the available research is
used will vary by company although the key aspects are likely to be similar.
Granherne’s approach would follow the following lines:
In terms of methodology the process follows early work by Gayton and Murphy
(Reference 11), who proposed the following methodology:
For each item of equipment define the type of fire (pool, jet, partial engulfment,
total engulfment) likely to affect it.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
69
Calculate rate of heat input appropriate to that type of fire.
Calculate the rate of temperature rise of the vessel wall.
Estimate the time to rupture.
If the time to rupture does not meet safety criteria, then design changes may be
necessary to improve the vessel protection.
The sense of the above is self-evident.
Not all vessels will need fire protection. Current studies by Granherne use a more
sophisticated approach than the simple table presented in the QRA, but essentially they
confirm the reasonableness of the early work if only by default. If it can be shown that the
risk of escalation given blowdown is low, then fire protection may be shown not to be
necessary.
Figure 6.3 - Output from a 1-D Heat Up ProgramRESULTS OF HEATUP CALCULATIONS
0.0
100.0
200.0
300.0
400.0
500.0
600.0
700.0
0.0 1.3 2.5 3.8 5.0 6.3 7.5 8.8 10.0 11.3 12.5 13.8 15.0 16.3 17.5 18.8 20.0 21.3 22.5 23.8 25.0 26.3 27.5 28.8 30.0time (min)
he
at
flu
x (
kW
/m2
), t
em
pe
ratu
re l
iqu
id &
va
po
ur
sp
ac
e (
de
g C
)
0.0
20.0
40.0
60.0
80.0
100.0
pre
ss
ure
(b
ara
), s
tre
ss
(%
yie
ld2
0),
yie
ld (
%y
ield
20
)
Heat Input
Liq. Temp
Gas Temp
Press. Bar
% Yield Stress 20C - Applied
% Yield Stress 20C- Strength
The industry is supporting more detailed analysis of fires offshore and performing
experiments to determine how fires behave in confined spaces. These have shown that
fires actually fill the upper space in a module. Also the heating fluxes are considerably
lower than the 300 kW/m2 originally used for analysis. This is because on a platform the
rate of burning is dependent on the ventilation whereas the original figures were from
research in the open air. Although there remains the potential for flame impingement and
engulfment, the implications are that the airflows around the vessel are not so severe,
and deluge systems will still be able to cool the skin. On the other hand, high level
pipework may be more at risk (although pipework is normally considered more robust).
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
70
One last aspect where change is evolving is in the benefit taken for insulation surrounding
a vessel. As long as it does not catch fire (which is normally the case), and is clad in
steel (rather than aluminium) and the fastening system is secure, the insulation is very
effective at protecting the vessel wall from flame impingement.
Means are now available to calculate the interactions between flame and vessel (and
insulation, if appropriate) in 3D. Whilst confirming the general conclusions of the earlier
modelling, the detail shows effects such as shadowing, liquid level and the lack of heat
removal laterally through the skin.
Figure 6.4 - Temperatures in a Half Filled Vessel Subject to Fire Load - from Heat
Up 3D
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
71
The results of these calculations feed into the design requirements for the system.
Therefore, current thinking is not so different than in the Hibernia QRA reports in terms
the dependency of the effects of heat on wall thickness, in that thin walled vessels are
likely to fail in less than 15 minutes. Wall thickness is also related to design pressure,
and the flare drums and associated pipework are vulnerable, being low pressure
systems having thin walls. This is why the flare system is specifically mentioned in the
Hibernia safety work. The problem with the early Hibernia work is these effects were
not carried through (in terms of analysis and engineering) to all the areas that were
likely to be affected.
Blowdown, active fire protection and passive fire protection are complementary means
of reducing the risk (loss) from vessel escalation. Primarily this is an asset protection
scheme, since the immediate fatalities in the area will occur before escalation, and
others are likely to be protected in the TSR. The TSR will limit the impact to the
personnel from escalation.
Using this method, the link between the blowdown and other means of protection
would then be explicit in the quantified risk assessment (QRA). This does not appear
to be the case in the Hibernia QRA.
6.2.5 The Effect of Applying Current Best Industry Practise to Hibernia
In this section the effect of applying best industry practise in relation to jet fire is
reviewed. As has been seen, the issue of jet fire causes 3 related aspects to be
considered:
The analysis of jet fire impingement on Hibernia vessels, i.e. what are the
consequences of jet fire impingement on various vessels?
Dependent on the outcome of this will affect the following considerations.
Should anything be done regarding final blowdown pressure and blowdown
duration?
Should the use of other mitigating means be used?
This would have the following effects on Hibernia.
6.2.5.1 Analysis of jet fire impingement on Hibernia vessels
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
72
There are a number of pressure levels on Hibernia. Within these pressure levels there
is the potential for leak, leak ignition, jet fire and then the potential for escalation.
Usually the worst case scenarios involve the vessels, as these contain the large
system inventories. The worst case scenario is also usually considered to be a leak
from one of the flanges in the pipework around the vessel impinging on the vessel
itself. This means that short jet fire lengths are still severe in effect. One exception to
this is where there is the possibility of a jet fire from a high pressure system impinging
on a low pressure, thin walled vessel. On Hibernia there is such a case which can be
caused by a jet fire somewhere around the HP separator impinging on the LP
separator.
To analyse the situation the following generic case was selected.
The heating of a vessel engulfed by flame was assessed using the package 3-D Heat
Up, a Granherne-developed heat transfer program. The program 3-D Heat Up treats a
source of heat as a flame as a set of discrete emitting “plates” and the receiver also as
a 3-D shape made up of a number of quadrilaterals. The program allows the user to
include details of any insulation on the surface of the vessel. The user can place the
receiving vessel anywhere with respect to the flame, and for the purpose of this study
the vessel was assumed to be engulfed entirely (which would only result from a very
large leak size), as this was the worst case. The diagram below shows a cross section
of the location of the flame.
Table 6.11 Schematic Arrangement of Flame and Vessel
0
10
20
30
40
50
60
70
0 10 20 30 40 50 60 70 80 90 100
(m)
(m)
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
73
Jet Flame
Vessel
The heat flux within the flame has been found to depend on the wind speed, since
greater wind speeds imply more mixing and this will generate more burning and higher
fluxes. The heat up was therefore assessed for 3 different wind speeds, 2, 5 and 10
m/s, which were calculated to create fluxes of 120, 160 and 180 kW/m2, respectively.
These were thought to be typical of vessels in areas of the platform where ventilation
control of the combustion process was expected. Higher localised fluxes have been
reported in flames in the open (e.g. up to 300 kW/m2), but are not thought to be
applicable in confined spaces. The program has a component that assesses the
residual stresses at elevated temperatures.
The heat response was modelled for the vessels overleaf:
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
74
Table 6.12 Hibernia Vessel Parameters Summary
Area /
Equipment
Pressure
(kPaA)
Wall thickness
(incl. cladding
where appropriate)
Gas molecular
weight
Insulation
thickness
HP Separator 4240 60.2 21 50mm (steel
supports)
MP Separator 1240 31.6 26 50mm (steel
supports)
LP Separator 210 17.3 48 50mm (steel
supports)
1st Stage
Suction Cooler
210 15.9* 48 Personnel
protection
1st Stage
Suction
Scrubber
160 15.9 36 Insulation height
(High level =
1130 mm)
2nd Stage
Suction Cooler
1125 12.7* 36 Personnel
protection
2nd Stage
Suction
Scrubber
1070 31.8 22 Insulation height
(High level =
780 mm)
3rd Stage
Suction Cooler
3900 41* 22 Personnel
protection
3rd Stage
Suction
Scrubber
3800 50.8 22 Insulation height
(High level =
800 mm)
Injection Stage
Suction Cooler
17120 102* 22 Personnel
protection
Injection Stage
Suction
Scrubber
16940 101.6 22 Insulation height
(High level =
450 mm)
*Cooler head cylinder thickness.
The heat up was then calculated for each of the vessels for two cases, with and
without insulation. Each of the vessels was assumed to be oriented horizontally, but
the results have been checked against vessels oriented vertically (particularly for the
compressor scrubbers). The results of the analysis were charted. The temperatures
do not predict absolutely the potential for vessel failure, since a depressured vessel
will have reduced stresses.
Sample results for an insulated vessel are shown in the figure. These show the
temperatures in the vessel, depicting it as an “unpeeled” skin:
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
75
Figure 6.5 Sample Output from 3-D Heat Up for Horizontal Vessel Elements
1
4
7
10
13
16 1
9
S1S2S3S4S5S6S7S8S9
S1
0
S11S1
2
S1
3
S1
4
S1
5
S1
6
265
270
275
280
285
290
295
290-295
285-290
280-285
275-280
270-275
265-270
This plot distorts the vessel somewhat, as points at the end, which is dished, are
closer to each other physically than is represented. As can be seen, the temperatures
on the gas side of the vessel are higher than those on the liquid side. This is because
the liquid conducts heat better than the gas, and also because the liquid is a bigger
heat sink. The kink at the far dished end is due to the modelling of conduction through
skin between points that are close together.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
76
Bottom, liquid side of vessel
Top, gas side of vessel
Dished end of vessel
Dished end of vesselTemp (K)
The results for each of the three separator vessels, for 3 different heat loads, with and
without insulation are shown below:
Table 6.13 Heat Up Calculation - Separator Peak Vessel Temperatures (K)
Case 180 kW/m2 160 kW/m2 120 kW/m2
60 mm with insulation
(HP Separator)
358 357 355
60 mm no insulation
(HP Separator)
825 786 696
32 mm with insulation
(MP Separator)
372 370 366
32 mm no insulation
(MP Separator)
1063 1024 903
17 mm with insulation
(LP Separator)
397 392 382
17 mm no insulation
(LP Separator)
1287 1269 1078
For the compressor train components runs were performed only at the highest heat flux
(180 kW/m2).
Table 6.14 Heat Up Calculation - Compressor Components Temperatures (K)
Area / Equipment Temperature
without insulation
Temperature
with insulation
1st Stage Suction Cooler 1353 383
1st Stage Suction Scrubber 1313 343
2nd Stage Suction Cooler 1460 449
2nd Stage Suction Scrubber 1039 335
3rd Stage Suction Cooler 1070 448
3rd Stage Suction Scrubber 863 323
Injection Stage Suction Cooler 747 433
Injection Stage Suction Scrubber 628 313
It can be seen from the above that the temperatures of the MP and LP separators and
compressor components up to the 3rd stage suction cooler are well above 500oC if
there is no insulation around the vessels. The highest temperatures are recorded on
the gas side of the vessel, where there is no liquid to act as a heat sink.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
77
When the effect of such temperatures on the stresses within the vessels is analysed, it
is found that the vessels are vulnerable to differing degrees. The program identifies
the residual strength left in the vessel at the final temperature, after 15 minutes of
heating. This residual strength takes into account the potential for blowdown of the
vessel to 50% of the design pressure. Thus it is defined as the ratio of the applied
stresses to the vessel at the end of the blowdown period and the residual strength
remaining in vessel at the elevated temperature.
Typical results of the model are shown below:
Figure 6.6 - Sample Result of 3-D Heat Up Calculation for Stresses
(As a percent of Yield Stress at Temperature)1 4 7
10
13
16
19
S1
S100
100
200
300
400
500
600
Str
es
se
s (
% o
f re
ma
inin
g s
tre
ng
th
Vessel Cell No
500-600
400-500
300-400
200-300
100-200
0-100
Once more the greatest effects are seen on the gas side, which is where temperatures
are highest. In the case above failure would occur as the stresses are 5 times the
remaining (residual) strength.
Information can be extracted from the stress results in several formats, such as time to
failure, highest stress and so on. The result format used below shows the ratio of the
applied stress and the percentage of residual strength remaining at time t = 15
minutes.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
78
Table 6.15 - Vessel Stress Analysis - Separators
Vessel Stresses at t = 15 minutes as a Percent of Yield Stress at Elevated Temperature
Case 180
kW/m2
160
kW/m2
120
kW/m2
Remarks
60 mm with insulation
(HP Separator)
31 31 31 Vessel remains intact
60 mm no insulation
(HP Separator)
38 34 32 Vessel remains intact
32 mm with insulation
(MP Separator)
30 30 30 Vessel remains intact
32 mm no insulation
(MP Separator)
145 111 52 Vessel can fail at
higher fluxes
17 mm with insulation
(LP Separator)
29 29 29 Vessel remains intact
17 mm no insulation
(LP Separator)
600 511 204 Vessel fails
The results above show that the HP separator does not heat up significantly even
when the effects of the insulation are not included. Consequently the vessel stress as
a percentage of yield stress at the temperature is low. The integrity of the MP and LP
separators, however, is only guaranteed by the insulation. The heat input is much
lower in the insulated case, and given the modest temperature rises in such cases, it
can be said that there will be no threat to the vessels.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
79
Table 6.16 Vessel Stress Analysis - Compressor Components
Vessel Stresses at t = 15 minutes as a Percent of Yield Stress at Elevated Temperature
Area / Equipment 180 kW/m2 without
insulation
Remarks
1st Stage Suction Cooler 141 Equipment fails
1st Stage Suction Scrubber 141 Vessel fails
2nd Stage Suction Cooler 720 Equipment fails
2nd Stage Suction Scrubber 145 Vessel fails
3rd Stage Suction Cooler 82 Equipment
remains intact
3rd Stage Suction Scrubber 49 Vessel remains
intact
Injection Stage Suction Cooler <40 Equipment
remains intact
Injection Stage Suction Scrubber <40 Vessel remains
intact
The results show that the lower pressure vessel’s integrity is only ensured by
insulation. The higher pressure equipment, on the other hand, has wall thicknesses
sufficient to survive a jet fire without insulation. By inspection, this suggests that the
current system where the A train injection compressor is blowdown 3 minutes after the
other systems is acceptable (i.e. the vessels should not fail) even if the A train injection
compressor components are engulfed in a jet fire.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
80
Also implicit in the ability of the vessel to survive the fire is the necessity for the
staggering system to function as designed. Some concern has been expressed that
the reliability of the system (software, electronics, ESD/PSD and pneumatics) has not
been conclusively demonstrated. Of the failures that could occur, the failure of the
blowdown system to initiate at all is the most serious with the potential, during a fire, to
allow vessel failure and / or escalation through jet fire or explosion. Even outside a fire
situation, the potential for explosion is seriously increased once the contents of the
compressor system begins to vent into the module through the seals as the seal oil
runs out. Of much less concern would be the failure of the staggering system to pause
the A train injection compressor blowdown. In this case the worst event which would
be likely would be abnormally high radiation rates on the platform (dependent on the
wind condition). However, even this benign failure has the potential to escalate if the
initiating cause is an incident involving the LP separator. In this case the coincident
blowdown would add inventory to the area as the back pressure on the LP separator
would be abnormally high. There appears to be good reason, therefore, to perform a
reliability analysis to confirm the system’s ability to function as required.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
81
6.2.6 Jet Fire Conclusions
The integrity of the insulation thus is a key issue for the protection of the lower
pressure equipment, namely:
MP separator
LP Separator
1st Stage Suction Cooler
1st Stage Suction Scrubber
2nd Stage Suction Cooler
2nd Stage Suction Scrubber
All of this equipment is insulated in one form or another.
If the insulation remains intact on the vessel under conditions of jet flame engulfment,
and resists the physical impulse from the momentum of the gas jet, then it is likely that
the vessels will not fail. On the other hand, such integrity does not seem to have been
designed into the vessel, and so some upgrading of the protection may be necessary.
The above does not take credit for the presence of deluge. There is still some debate
in the industry on the ability of deluge to mitigate the effects of jet fire, which relate to
how quickly it is applied after the jet fire event has commenced. If the vessel is too
hot, the deluge has difficulty establishing a cooling skin. However, there are a number
of research projects underway which should eventually define the available credit to
take for deluge. For the moment it is sufficient to state that a system with deluge is
much improved over one without.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
82
6.3 Blowdown (Depressuring) System Sizing
6.3.1 Requirements of the Codes, Guides, Standards and Recommended Practices
When Hibernia was Designed
6.3.1.1 Mobil Engineering Guide (EGS 661-1990)
As mentioned previously, we have been unable to source a copy of the 1990 version
of the above so instead are required to interpret between the 1985 version and the
Draft 1991 version. Using this approach we can estimate the following requirements
at the design stage. Our interpretation of the requirements of the Mobil guide at the
time is:
Vessels shall be depressured to 690 kPag (100 psig) or to 50% of the design
pressure, whichever is smaller. The maximum time allowed to depressure a system is
2 minutes per 3 mm (1/8 in) of vessel wall thickness. Depressuring time of less than
6 minutes need not be used regardless of vessel wall thickness. Depressuring time
shall not exceed 15 minutes, except with Mobil approval.
Vapour depressuring may not be practical when the vessel design pressure is less
than 690 kPag, as piping and valves may become unreasonably large, or when vapour
depressuring load governs the size of the pressure relief and flare headers. When
vapour depressuring is not practical, vessels may be insulated to reduce the vapour
depressuring load or may be protected by other means such as water sprays.
Start pressure for the blowdown was specified as the maximum operating pressure,
which presumably was equivalent to the pressure trip setting.
These latter forms of protection could also be used in lieu of depressuring if designed
according to Mobil guidelines.
Excursions from these requirements required approval from Mobil.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
83
6.3.1.2 API 521 (Third Edition, November 1990)
During 1991/2 (when these aspects of the design were being finalised) the relevant
version of API 521 was the third edition 1990. This code required the following in
regard to depressuring system sizing.
These systems should have adequate venting capacity to permit reduction of the
vessel stress to a level at which stress rupture is not of immediate concern. For sizing
criteria this generally involves reducing the equipment pressure from initial conditions
to a level equivalent to 50% of the vessel’s design gauge pressure within
approximately 15 minutes. This criterion is based on the vessel wall temperature
versus stress to rupture and applies generally to vessels with wall thicknesses of
approximately 1 inch (25 millimeters) or more. The required percentage depressuring
rate depends on the metallurgy of the vessel, the thickness and initial temperature of
the vessel wall…
Some operating companies limit the application of vapor depressuring to facilities to
facilities that operate at 250 pounds per square inch gauge (1724 kilopascals gauge)
and above, where the equipment and the volume of the contents are significant. Other
companies provide depressuring on all equipment that processes light hydrocarbons,
and they set the depressured level at 100 pounds per square inch gauge (690
kilopascals) or 50% of the design pressure whichever is the lower. The 100 pounds
per square inch gauge (690 kilopascals) level is intended to permit somewhat more
rapid control in which the source of a fire is the leakage of flammable materials from
the equipment to be depressured. On the other hand, in some cases involving
relatively high-pressure vessels that contain relatively large inventories of light
hydrocarbons, depressuring below the 50-percent level within 15 minutes may not be
practical. However, in certain designs this provides an ample margin of safety with
regard to vessel safety from overheating…
API allows the blowdown to commence with the start pressure at initial conditions.
6.3.2 How the System was Designed
The RABS describes the following project philosophy:
1. Blowdown sections will be depressured from their normal operating pressure to
690 kPag (100 psig) or 50% of the vessels design pressure, whichever is lower.
The maximum time allowed to depressure a vessel/system shall be 2 minutes per
3mm (1/8 in) of vessel wall thickness. Depressuring time of less than 6 minutes
will not be used regardless of vessel wall thickness. Depressuring time shall not
exceed 15 minutes.
(Emphasis added) RABS page 8
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
84
The emphasis is added to highlight the start pressure considered.
Clearly the Mobil requirements were followed except in the case of the start pressure
for blowdown. Here the RABS suggests the blowdown commences at normal
pressure, whereas the Mobil requirement was from maximum operating pressure.
This issue is confused further by the fact that the calculations for the compressor
system appears to be based on the pressure trip settings suggesting the RABS
contains a typographic error and the design did indeed follow the Mobil guide.
However, the RABS goes on:
2. As a seal oil systems are to be used on the turbine-driven compressors. A more
stringent depressuring design basis then the basis detailed in 1) is required for
blowdown sections which include a compressor.
In order to avoid gas escape along the compressor shaft, compressor sections are
to be depressurised from their initial settle-out conditions to a pressure less than
the static head exerted by the height of the seal oil rundown capacity. This
capacity is defined as the seal oil reservoir volume between the liquid level trip
switch and an empty reservoir. This volume will be sized to allow for an interval of
15 minutes to depressure all of the compressors to 110 kPa (abs).
In order to minimise the peak initial total LP Blowdown flowrate it was agreed that a
staggered compressor blowdown should be used….
The motor-driven gas compressor (K-33-1) is now to utilise a dry gas seal
arrangement instead of a seal oil system. However as the depressuring rate from
this section is low (less than 5% of the peak initial blowdown flowrate) the same
depressuring basis as defined above for the turbine-driven compressor blowdown
sections has been used for this blowdown section.
RABS pages 8 and 9
Due to the selection of the compressor seals, the atmospheric end pressure could not
be avoided unless the system was significantly modified. Otherwise the remaining gas
in the system would spill through the seals into the module when the seal oil ran out.
Of course, more blowdown isolation valves would have avoided the requirement to
depressure the entire compressor system to atmospheric.
The issue of staggering is described in more detail in Section 6.4.
The RABS goes on further:
3. For the production manifolds (HP, MP and test manifolds) and gas injection
manifold it has been agreed that a specific exception to the basis detailed in 1) will
be taken.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
85
The reason for this decision is that these sections have very high design pressures
(34400 kPag for the HP, MP, and test manifolds and 45500 kPag for the gas
injection manifold) and contain only pipework. (Note: Manifold pipe wall
thicknesses are in excess of 1 inch.) Therefore, it seems highly conservative to
depressure to 690 kPag in 15 minutes and gives high peak blowdown flowrates
from these sections which form a significant portion of the total HP blowdown
Flowrate.
It was agreed that the application of the philosophy basis identified in 1) was not
intended for this type of high pressure blowdown section. API RP 521 advises that
for high pressure sections including vessels with wall thicknesses of 1 inch or
more, the depressuring basis can be to reduce the pressure from initial conditions
to 50% of the design pressure within approximately 15 minutes. API RP 521 also
notes that on certain high pressure/inventory blowdown sections the depressuring
basis may be reviewed more critically to provide both a practical and safe basis.
The depressuring basis used for the manifolds is as follows:
i) The gas injection manifold will be depressured to 50% of the design
pressure within approximately 15 minutes.
ii) As the initial pressure of the HP, MP and test manifolds is already below
50% of their design pressure they will be depressured to 50% of their
appropriate downstream separators design pressure within approximately
15 minutes.
iii) As the future gas lift manifold wall thickness will probably be less than 1
inch and the current peak blowdown flowrate from this section is not
excessive, this section will still be depressured in accordance with the
basis detailed in 1).
RABS pages 8 to 10
So, virtually every interpretation of API RP 521 that could have been taken made
eventually was. This probably resulted from the ambiguity the recommended practice
contained at the time. Notice also the start pressure of the manifold blowdown which
is again the normal pressure, further highlighting the inconsistency of approach.
Nonetheless, in our view, all of the above interpretations were acceptable as they are
generally conservative. Whether the approach could be described as consistent is
another matter. This issue is described further in Section 6.3.5.
The RABS would also have benefited from a mention of who agreed these issues and
the forum and documentation they were agreed in as the audit trail appears to go dead
after this time.
This result of this approach is shown on the table overleaf.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
86
Table 6.17 Blowdown Section Summary
Blowdown
Section No.
Description/Major Equipment Blowdown Start
Pressure (kPa (abs))
Blowdown Final
Pressure (kPa (abs))
Blowdown
Time (mins)
To
Flare
1 Test Manifold #1 4241 2751 15 HP
2 Test Manifold #2 4241 2751 15 HP
3 Well Clean-up Test Manifold 4241 2751 15 HP
4 HP Production Manifolds 4241 2751 15 HP
5 MP Production Manifolds 1241 1101 15 HP
6 Test Separator #1 (D-3105) 4241 791 15 HP
7 Test Separator #2 (D-3107) 4241 791 15 HP
8 Well Clean-up Test Separator
(D-3106)
4241 791 15 HP
9 HP Separator (D-3101) 4241 791 15 HP
10 MP Separator (D-3102) 1241 791 15 HP
11 1st Stage Compressor and
Suction Scrubber
(K-3301 and D-3301)
316 110 15 LP
12 2nd Stage Compressor and
Suction Scrubber A
(K-3302A and D-3302A)
2046 110 15 LP
13 2nd Stage Compressor and
Suction Scrubber B
(K-3302B and D-3302B)
2046 110 15 LP
14 3rd Stage Compressor and
Suction Scrubber A
(K-3303A and D-3303A)
6122 110 15 LP
15 3rd Stage Compressor and
Suction Scrubber B
(K-3303B and D-3303B)
6122 110 15 LP
16 Injection Compressor and
Suction Scrubber A
(K-3304A and D-3304A)
24115 110 12
Note 3
LP
17 Injection Compressor and
Suction Scrubber B
(K-3304B and D-3304B)
24115 110 15 LP
18 Gas Injection Manifold 45601 22851 15 HP
19 Gas Lift Manifold (Note 2) 13801 791 15 HP
20 HP Fuel Gas KO Drum and Fuel
Gas Filter Separators (D-6201,
Z-6201A/B, and Z-6202A/B)
3201 791 12 HP
21 HP Fuel Gas Cooler (E-6201) 3201 791 15 HP
22 Offgas Manifold 4241/1241 791 15 HP
23 LP Fuel Gas KO Drum (D-6202) 621 601 6 LP
24 LP Separator (D3103) 211 Note 1 Note 1 LP
25 Lift Gas Dehydrator and Suction
and Discharge Scrubbers
(C-3801, D-3801, and D-3802)
(Note 2)
17300/13700 791 15 HP
Note 1: The LP Separator operating pressure is already below the level which it should be depressured to. Therefore, only a nominal
blowdown capacity has been taken for this section.
Note 2: The Lift Gas Dehydrator and Gas Lift Manifold are future items.
Note 3: Injection Compressor “A” blowdown is staggered on a 3-minute time delay after other blowdown sections. Therefore, the
blowdown time for this section is only 12 minutes.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
87
6.3.3 Current Requirements of the Codes and Recommended Practices
6.3.3.1 Mobil “Pressure Relief and Vapor Depressuring Systems” MP 70-P-06, July 1998
This Mobil Engineering Practice (MEP) supersedes the earlier engineering guides.
The key requirements concerned with the design of the blowdown system are given
below:
1. Vessels shall be depressured to 690 kPag (100 psig) or to 50% of the design
pressure, whichever is less. The maximum time allowed to depressure a system is
2 minutes per 3 mm (1/8 in) of vessel wall thickness. Depressuring time of less
than 6 minutes need not be used regardless of vessel wall thickness.
Depressuring time shall not exceed 15 minutes, except with Mobil approval.
2. Vapour depressuring may be impractical when the vessel design pressure is less
than 690 kPag (100 psig), because valves and piping may become unreasonably
large and costly. It is also impractical when the vapour depressuring load governs
the size of the pressure relief and flare headers. When vapour depressuring is not
practical, vessels may be insulated (see MP 70-P-05) to reduce the vapour
depressuring load or they may be protected by other means, such as water sprays
(see MP 70-P-01). The use of either of these alternatives requires Mobil approval.
The Mobil practice also gives guidance on blowdown start pressure:
7.2. Depressuring Flowrate
To calculate the vapor flowrate that is needed to accomplish depressuring, the
maximum expected operating pressure of the vessels under consideration shall be
used as the initial pressure and the pressure specified in Section 7.1.1 as the final
pressure.
The practice refers to the API 521 method with regard to depressuring system sizing
for pool fire and the option of controlling the blowdown peak rate by using controlled
blowdown (i.e. reducing the peak rate by control). The remainder of the document in
relation to depressuring is linked to compositional effects that should be considered
during the unsteady state calculations.
Comparisons with the earlier versions of the Mobil practices suggest there has been
no change that would affect the design of the blowdown system.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
88
6.3.3.2 API 521 Fourth Edition, March 1997
The relevant part of the Fourth Edition, in relation to the design of the blowdown
system, is given below:
3.19.1 GENERAL
...A vapor depressuring system should have adequate capacity to permit reduction of
the vessel to a level where stress rupture is not of immediate concern. For sizing, this
generally involves reducing the equipment pressure from initial conditions to a level
equivalent to 50% of the vessel design pressure within approximately 15 minutes.
This criteria is based on the vessel wall temperature versus stress to rupture and
applies generally to vessels with wall thicknesses of approximately 1 inch (25mm) or
more. Vessels with thinner walls generally require somewhat greater depressuring
rate...
Where fire is controlling, it may be appropriate to limit the application of vapor
depressuring to facilities that operate at 250 pounds per square inch gauge (1724
kilopascals gauge) and above, where the size of the equipment and volume of the
contents are significant. An alternative is to provide depressuring on all equipment
that processes light hydrocarbons and set the depressured rate to achieve 100 pounds
per square inch gauge (690 kilopascals gauge) or 50% of the vessel design pressure,
whichever is lower, in 15 minutes..." API 521 pages 24 and 25.
There are two issues which derive from the above (and comparison with the earlier
version used during design):
1. The subtle change in the form of words regarding the relevant pressure levels.
As time has passed the requirement of API 521 has hardened and now represents
the clearest idea of the API’s design intent. The practice’s intent can be read as
follows:
To protect against stress rupture:
Systems with design pressure above 1724 kPag should be depressured to
50% of the design pressure.
Systems with design pressure below 1724 kPag need not be depressured.
However, if it is chosen to do so, the final pressure should be 690 kPag or 50%
of the design pressure, whichever is less.
Vessels with wall thicknesses below 1 inch should be considered separately.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
89
API were contacted regarding this issue to confirm the above. API were reluctant
to commit to a final response until the meeting of the API 521 Task Force in
October 2000. Granherne are pressing them for a more rapid comment.
2. In this context, what is the meaning of “immediate concern”?
Immediate concern in this instance is 15 minutes. However this hides the fact that
once the stress level in a vessel is reduced by half, the time taken in an API 521
pool fire to heat the (1 inch and over) steel to a temperature at which stress rupture
is likely of the order of hours. The remainder of the blowdown should have been
completed by the time the vessel fails (assuming sufficient fuel to keep the fire
going this long). Based on this scenario the depressuring requirement can be
seen to be very conservative as is evidenced by the fact that some facilities are
allowed to do without depressuring facilities.
Again the start pressure for the blowdown is referred to as initial conditions.
6.3.4 Current Best Industry Practice
Granherne would apply API requirements as they were intended, i.e:
Systems with design pressure above 1724 kPag should be depressured to
50% of the design pressure (unless there are good reasons otherwise, for
example, the equipment in the HP compression systems which requires a
lower end pressure due to seal oil considerations – see Section 6.3.5 below).
Systems with design pressure below 1724 kPag need not be depressured.
However, if it is chosen to do so, the final pressure should be 690 kPag or 50%
of the design pressure, whichever is less.
Vessels with wall thicknesses below 1 inch should be considered separately.
The above approach would always lead to the minimum sized flare system, indeed it
has the effect of focussing on the most susceptible equipment, thereby applying a high
level of safety.
In passing we should also mention that the API is ambiguous with respect to pipework
engulfed in fire, implying that it does not always need to be depressured. Presumably,
this is because pipework is considered durable in a fire compared to vessels and the
consequences of failure are less than for vessels probably leading to more, fairly
minor, jet fires as the flanges fail. Onshore, this sometimes allows the high pressure
inlet pipework not to be depressured at all (because it is usually located in an area
where fire is unlikely). Offshore this approach is not normally possible and we would
select the depressuring approach from the above. Because of recent accidents where
pipework has catastrophically failed, Granherne expect pipework systems to become
the next target in jet fire analysis and eventually become part of a common
methodology.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
90
The start pressure we believe most logical to apply is from initial conditions in cases
where the blowdown is automatically initiated on fire. The probability of coincidence of
high pressure in the system (i.e. just below the PSHH) and fire can be shown to be
very low. The requirement to start at the maximum operating pressure stems from the
era when fire and gas detection systems were unreliable and, as a consequence, did
not initiate automatically. This meant that the fire had the possibility to heat the
system, raising the system’s pressure, prior to manual operator intervention.
Using this approach care would be needed to adjust the calculations should the
pressure profile in the system change significantly.
In passing it should also be noted that some companies adjust the blowdown time
period to remove the stress on all vessels so that they do not rupture in the event of jet
fire impingement. This would normally be required if the vessels were not protected.
This is a particularly expensive way of catering for the jet fire hazard.
Regarding the time to depressure the vessels. The 15 minutes is selected such that
the temperature reached when the stress is halved leaves the vessel not prone to
rupture. Once this satisfactory situation is reached, the vessel continues to
depressure and the period before escalation should lengthen. In other words, if the
initiation of blowdown is timely the period for evacuation should be significantly in
excess of 15 minutes (although it cannot be guaranteed).
6.3.5 The Effect of Applying Current Industry Practice to Hibernia
Application of the above design practice requirement would significantly reduce the
load on the HP flare as the HP and MP separators could be depressured more slowly.
The target would instead move to ensuring the stress level in the LP separator fell as
quickly as possible as this is the most likely vessel to fail. The existing design case
includes only a nominal depressuring rate (at the time, the clause in the API regarding
thin walled vessels was less than clear). Satisfying the jet fire calculations in Section
6.2.5 should be the target of the revised calculations.
The above would certainly simplify the slightly conflicting requirements of the RABS.
However, it would have very little effect on the ultimate capacity of the system as most
high pressure parts blowdown to the LP flare because of the HP compressors seal oil
system and the requirement to be at atmospheric prior to the oil running out.
Retrofitting dry gas seals to the compressors, or adjusting the sectioning would be the
only ways to significantly increase the latent capacity of the LP flare.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
91
Returning to the conflicting requirements in the RABS; it was either acceptable, or it
was not, to blowdown to 50% of the design pressure. If it was (as we believe it was) it
should have been applied to the entire system except where it could be shown
inappropriate, moving the focus to these cases. This was not done, which leaves the
impression of some ‘fitting’ of the requirements to the selected flare boom length.
Nevertheless, this approach, whilst inconsistent, is generally conservative compared to
the intent of the API and therefore a capacity opportunity exists within the system. To
take advantage of the opportunity would require some hardware changes to limit the
blowdown rate to be compatible with the 50% of design end pressure.
As blowdown on Hibernia is initiated automatically there is also a good case for
reducing the severity of the calculated load on the LP flare system by reducing the
start pressure for the compressor blowdown, thus reducing the inventory removed
from the system. This, too, would have the effect of making some spare capacity in
the system. If this were to be implemented no hardware changes would be required;
the new peak rate with the existing system components would be calculated (which
would be less than at the higher pressure), thereby taking up less of the available
system capacity. Without making hardware changes the blowdown would reach the
end pressure in a little less time than 15 minutes.
Prior to agreeing any of the above the permission of Mobil for a deviation to the MEP
would need to be sought.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
92
6.4 Compressor Blowdown Stagger
6.4.1 Requirements of the Codes, Guides, Standards and Recommended Practices
When Hibernia was Designed
6.4.1.1 Canadian Legislation
There are no requirements specific to this issue as far as we are aware.
6.4.1.2 Mobil Requirements (EGS 661-1990)
As mentioned previously, we have been unable to source a copy of the 1990 version
of the above so instead are required to interpret between the 1985 version and the
Draft 1991 version. Using this approach we can estimate the following requirements
at the design stage. Our interpretation of the requirements of the Mobil guide at the
time is:
The Mobil guide allowed the control of the depressuring rate so as not to exceed the
maximum allowable rate in the flare system, i.e.:
Vapor depressuring valves may restrict the initial depressuring to the capacity of the
closed pressure relief system and flare.
EGS 661-1985
Whilst not explicit this seems to indicate that the use of staggering to achieve this was
acceptable.
6.4.1.3 API (Third Edition, November 1990)
The third edition is silent on the issue of staggering.
6.4.2 How the System was Designed
Because of the wet seal oil system the compressors were required to depressure to
the LP flare system. The end pressure was required to be atmospheric. This placed a
large load on the LP flare and by 1992 it was realised that LP flare system was unable
to cope with the peak rate (the radiation levels on the platform were too high). The A
train injection compressor stage blowdown was therefore delayed 3 minutes to reduce
the peak rate experienced.
(See Appendix I, calculation 34-006/A Rev 05 for the summary of the loads from the
various areas).
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
93
6.4.3 Current Requirements of the Codes and Recommended Practices
The material requirements of either the current Mobil guide or API 521 has not
changed regarding the acceptability of staggering.
6.4.4 Current Best Industry Practice
The concept of staggering or sequentially depressuring plant has been around the
industry for many years. Whilst not explicitly allowed by the Mobil guide or API
recommended practice nor is it forbidden.
Used most carefully, staggered blowdown is usually reserved for situations where
plant is sufficiently independent that total plant blowdown is not desirable. A good
example of such a situation is a refinery where there are a number of self contained
plant areas, sufficiently independent, and sufficiently far apart that blowdown for a
plant fire in one area would only be desirable in that area.
This is the normal test for the acceptability for staggered blowdown:
The systems should be sufficiently separate such that common mode failure is not
a concern (this would normally require separate PLC control systems and
instrument air supplies).
The systems should be in separate fire areas.
We have seen these requirements in another Operator’s design guidelines the logic
being self-evident.
Generally these requirements defy the application of staggered blowdown to offshore
facilities and in Hibernia’s case neither of these criteria are achieved.
6.4.5 The Effect of Applying Current Industry Practice to Hibernia
From the above there is clearly concern regarding the staggering of the A injection
compressor blowdown. The case where there is a jet fire around the A train injection
stage (including scrubbers etc.) causing a blowdown of the remaining plant, which is
not on fire is anomalous. In Section 7.2.3 the required blowdown rates required to
avoid stagger are described.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
94
6.5 Two-Phase Relief
6.5.1 Requirements of the Codes, Guides, Standards and Recommended Practices
When Hibernia was Designed
6.5.1.1 Canadian Legislation
There are no requirements specific to this issue as far as we are aware.
6.5.1.2 Mobil Requirements (EGS 661-1990)
As mentioned previously, we have been unable to source a copy of the 1990 version
of the above so instead are required to interpret between the 1985 version and the
Draft 1991 version. Using this approach we can estimate the following requirements
at the design stage. Our interpretations of the requirements of the Mobil guide at the
time are:
Pressure relief valves shall be sized in accordance with API RP and API STD 526.
Pressure relief valves handling vapour and liquid should be sized according to the two-
phase flowrate from the vessel. Refer to API RP 521 for guidance in determining
vapor and liquid loads from various types of equipment.
EPG 60-B-05 September 1991 page 13
6.5.1.3 API
API RP 14C requires a pressure vessel to have a relief valve sized for full inflow. API
521 requires designers to size the relief valve for closed outlets. The codes are
ambiguous on how such an event will occur. Elsewhere, API 521 (vaguely) refers to
the following:
“The probability of two unrelated failures occurring simultaneously is remote and
normally does not need to be designed for.”
API 521 Third Edition p. 6
To protect a vessel or system from overpressure when all outlets are blocked, the
capacity of the relief device must be at least as great as the capacity of the sources of
pressure. If all outlets are not blocked the capacity of the unblocked outlets may
properly be considered.
API 521 Third Edition p. 8
API 520 also contained various methods for sizing relief valves including a method for
sizing for two-phase relief. The two-phase sizing method relied on calculating the
required orifice required for vapour relief and liquid relief and adding them together.
The API said the following of the method:
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
95
A reasonable, conservative method of sizing for two-phase liquid/Vapour relief is as
follows:
a) Determine the amount of liquid that flashes by an isenthalpic (adiabatic)
expansion from the relieving condition either to the critical downstream pressure for
the flashed vapour or to the back pressure, whichever is greater.
b) Calculate individually the orifice area required to pass the flashed vapor
component, using Equations 2-7 as appropriate, according to service, type of valve,
and whether the back pressure is greater or less than the critical downstream
pressure.
c) Calculate individually the orifice area required to pass the unflashed liquid
component using Equation 9. The pressure drop (P1-P2) is the inlet relieving pressure
minus the back pressure.
d) Add the individual areas calculated for the vapor and liquid components to obtain
the total orifice area, A, that is required.
e) Select a pressure relief valve that has an effective discharge area equal or greater
than the total calculated orifice area…
API RP 520 Sixth Edition page 37
6.5.2 How the System was Designed for Two-Phase Relief
HP Separator
Combining the requirements described above (and effectively ignoring the full flow
requirement of API RP 14C) gave rise to the following relief valve sizing case.
The HP separator relief valve is dimensioned by the full associated gas rate at design
oil production rate. The most credible scenario that might lead to such a case would
be blockage of the HP separator vapour outlet. This could occur due to maloperation
of an isolation valve or the failure of the pressure control valve in the vapour outlet.
Once this occurred the pressure in the vessel would quickly rise and should cause an
ESD trip. However as is the case with all relief valve sizing cases this trip is assumed
to fail and the relief valve sized for the resulting case.
From a methodological standpoint this is supportable.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
96
The two-phase sizing case was selected to consist of a maximum well and an average
well representing the case where two wells fail to shut in (there is a similar case for the
test separator which should be read in this light). Here we partly return to an API
RP14C type case. There is no description in the RABS of how this case might occur
(to us it appears to require the failure of at least 5 ESVs and a high pressure trip). The
calculation method used to find the required area was the additive method contained
in API RP 520 (Fifth Edition). The calculation showed a very much lower required
area than the full associated gas case (3.2 in2 compared to 9.38 in2 for the full
associated gas case).
The HP flare KO vessel was sized to accommodate the resulting liquids from this case
for a 10 minute relief event.
Test Separator
The test separator relief valve follows the above except the sizing case is the two-
phase sizing case.
6.5.3 Current Requirements Of The Codes And Recommended Practices
6.5.3.1 Mobil Requirements (MP 70-P-06)
The Mobil MEP now requires the following:
Pressure relief valves shall be sized in accordance with API RP 520 PT 1 or local
codes, whichever is the more stringent.
MP 70-P-06 page 20
The relevant edition of the API is the Sixth Edition Errata; 1994. This edition retains
the API additive calculation method.
6.5.3.2 API 520 (Seventh Edition, January 2000)
The API has been extensively rewritten with respect to sizing for two-phase
liquid/vapor relief:
3.10.2 A recommended method for sizing pressure relief devices in two-phase
service is presented in Appendix D. The user should be aware that there are currently
no pressure relief devices with certified capacities for two-phase flow since there are
no methods for certification.
Page 55
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
97
In Appendix D it goes on to state:
D.1.1 The method for two-phase sizing presented in this Appendix is one of
several techniques currently in use and newer methods are continuing to evolve as
time goes on. It is recommended that the particular method to be used for a two-
phase application be fully understood. It should be noted that the methods presented
in this Appendix have not been validated by test, nor is there any recognized
procedure for certifying the capacity of pressure relief valves in two-phase flow
service.
A series of equations based on the Leung omega method are presented. Finally an
alternative method is also mentioned:
D.1.4 A more rigorous approach using vapor/liquid equilibrium (VLE) models
incorporated into a computerized analytical method based on HEM can be considered.
Appendix D page 69
6.5.4 Current Best Practice
The issue of the new calculation method has caused concern in the industry. The
history of the change stems from some work prepared by DIERS. This group found
that the API method undersized relief valves in two-phase relief cases undergoing
froth reactions. This led to a certain amount of lobbying to have the DIERS method
incorporated in the API. Other groups (presumably aware the DIERS model would not
be appropriate for the oil and gas industry) began to work on models which had the
capacity to predict two-phase relief flows through orifices. These models have been
tested and appear to indicate the API method undersizes orifices in two-phase flow.
Granherne take a pragmatic view of this situation based around the following
arguments:
The earlier API method defines an effective orifice area, which is used to select the
next larger orifice size for installation. The best evidence which recommends this
method is API do not know of a single overpressure failure event to have occurred
since the method was first incorporated into an API code in July 1990 (although the
method has been around much longer than this). Usually a loss event is the
precursor to changing a recommended practice or design code.
Leung omega and HEM methods size the (sharp edged) orifice required to pass
the flow. As valves are not available in all sizes (only the API STD 526
designations) a designer would have to select the next larger size. The valve is
implicitly oversized.
The later Leung omega and HEM work are based around real orifices rather than
the API type of effective orifice area which contains a number of correction factors
which mean an API orifice is bigger than at first sight it seems.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
98
Both the new methods are homogeneous and do not account for phase slip (i.e.
the flow through the orifice is sufficiently slow through the orifice to allow the
phases to remain in thermodynamic equilibrium) and therefore must be
approximations. The additive API method is non-homogeneous and has phase
slip inherent in the method, albeit fortuitously.
However, Granherne recognise the valuable research undertaken to date and expect it
to become the basis of relief valve sizing in the future. We expect the sizing method to
adjust as the research is applied to API 526 relief valves when the comparisons will be
much clearer (maybe to the extent that the resulting valve selections are not so
different from the additive method which, for the moment, they are).
None of this, however, protects HMDC (or their advisors) from the difficulties
mentioned in Section 4.1.3 and the requirement to prove the new recommended
practice is not appropriate if it is proposed not to incorporate it. Clearly, it is feasible to
procure a larger relief valve if the calculation check suggests it is necessary. A QRA
will not, in this case, show any improvement in risk profile for the facility. Yet, by
inspection, a valve that is larger than the existing will cope better if the underlying
basis is true and thereby reduce risk in some unquantifiable manner.
Granherne will therefore apply the new requirements to new projects as a matter of
course.
6.5.5 The Effect of Applying Best Industry Practice to Hibernia
Applying the Leung omega or HEM method has no effect on the sizing selection for
the HP separator. Based on the 40 kbopd original two-phase sizing cases, the full
associated vapour case is still the defining case. The Test separator, however, is a
different matter. It seems that to cater for the new sizing method the valve size should
increase.
The sizing will also depend on the final philosophy selected for the number of wells
which fail to shut-in. HMDC have performed some work on this aspect, including
taking account of the future number of wells and their corresponding rate, which will
need to be incorporated in the updated RABS.
This project can be undertaken when feasible. We also believe that no restrictions to
production need apply in the time it takes to procure the new valves, as it is arguable
that the system is safe by experience.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
99
6.6 Design Windspeed and Direction
6.6.1 Requirements of the Codes, Guides, Standards and Recommended Practices
when Hibernia was Designed
6.6.1.1 Canadian Legislation
There are no requirements specific to this issue as far as we are aware.
6.6.1.2 Mobil Engineering Guide (EGS 661-1990)
As mentioned previously, we have been unable to source a copy of the 1990 version
of the above so instead are required to interpret between the 1985 version and the
Draft 1991 version. Using this approach we can estimate the following requirements
at the design stage.
The 1985 version used a design windspeed equivalent to 93 km/h (57.8 mph or
84.8 fps or 25.8 m/s) if the discharge tip speed was 0.5 Mach. Otherwise MRDC Loss
Prevention Engineering were to be consulted.
By 1991 this was at the point of changing to:
Radiant heat intensities at a design reference point on the platform shall not exceed
the values in Table 2 with the wind in an adverse direction and at maximum
emergency discharge rates. The design wind speed for determining radiant heat
intensities shall be 12.4 km/h (Corrected to 32.2 km/h) (20 mph). The reference point
will be selected, subject to Mobil approval, as the nearest point on the platform that
cannot be readily shielded. Radiant heat intensities shall also be calculated at 67
percent and 133 percent of design wind speed and at other critical points on the
platform to determine what precautions must be taken for flaring during adverse wind
conditions.
Draft EPG 60-B-05 September 1991
6.6.1.3 API 521 (Third Edition, November 1990)
The API is silent on the issue of windspeed to use when designing flare stacks/booms.
The only reference anywhere in the document that refers specifically to particular
windspeed is in Appendix C that uses two definitions of windspeed to size a flare
stack.
Design wind velocity is 20 mph (or 29.3 feet per second). (8.9 m/s)
Normal average windspeed is 20 mph (29.3 feet per second) (8.9 m/s)
There is no suggestion (or otherwise) that these figures should be used for flare
system design.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
100
6.6.2 The Windspeed Used During Design
The system was designed on the basis contained in the RABS and subsequent
documentation. This is summarised in the following:
a) Windspeed
From the Project Environmental Data Summary (PEDS) the maximum 1 hour
mean wind speed at 140 m above sea level (i.e. at the flare tip location) is
34.2 m/s based on a 1-year return period. The expected frequency shown in
PEDS, is however, less than 0.1% and only quantifiable in directions that would
not adversely affect flare radiation levels.
Therefore, for the purposes of the radiation calculations, a wind speed of 27 m/s
(60 mph), blowing directly towards the platform, will be considered as the worst
case in accordance with the agreed composite specification basis.
RABS page 22
No basis for this figure was given.
6.6.3 Current Requirements of the Codes and Recommended Practices
6.6.3.1 Mobil “Pressure Relief and Vapor Depressuring Systems” MP 70-P-06, July 1998
The reference to design windspeed is lost in the new document. It may now be linked
to the GKN Birwelco software recommended for the flare sizing task.
6.6.3.2 API 521 (Fourth Edition, March 1997)
The API remains silent on the methodology for selecting design windspeed and retains
the 20 mph level for the calculation examples.
6.6.4 Current Best Practice
The selection of design windspeed for flare design is usually prescriptively applied by
the Operators. This has arisen probably because there is so little guidance elsewhere
in the national or international codes. A quick survey of projects that Granherne have
been involved with indicates design windspeeds from 10 to 27 m/s (22 to 60 mph) for
offshore locations, none of which appear to have been set by using a constant
methodology.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
101
However, if Granherne were to choose a design windspeed it would be selected on a
probabilistic basis. In a fairly arbitrary sense (as we have not quantified the effect on a
number of facilities of using this method), we too would choose a windspeed based on
the maximum 1 hour mean wind speed at the flare tip location with a probability of
0.1% based on a 1-year return period (i.e. in a similar way to the RABS). The reason
for selecting this yearly approach is because it seems reasonable. However, we
would not necessarily limit the direction to directly onto the platform if a slight deviation
produced a significantly higher windspeed. This would be the absolute maximum we
would consider. If the resultant windspeed were higher than 27 m/s (60 mph) we
would limit consideration to this level and the flare boom would be dimensioned on this
case. This windspeed is derived from Granherne experience of the usual limit placed
on helideck operations. Beyond this level it is no longer safe to be on deck (see also
Section 8.0).
In saying the above, Granherne would also have sympathy for any situation where a
less onerous windspeed were selected; the codes could be interpreted to allow it.
6.6.5 The Effect of Applying Best Industry Practice to Hibernia
In the event, Granherne’s current best practice would have had a very minor effect on
the flare boom length or (as is the case now the platform is constructed) the design
rates allowable.
Review of the Project Environmental Specification enables the following comparison to
be made:
Table 6.18 Comparison of Design Windspeed Criteria with Granherne Best
Practice
RABS (m/s) Granherne (m/s)
Most Adverse Direction (directly
onto the platform)
Not identified 24.2
Most Adverse Windspeed in an
on platform direction
34.2 from NW (not analysed) 34.2 from NW (analysed and not
as extreme as above)
Design figure 27 24.2
The windspeeds are very similar to the RABS criteria. The effect of using these
windspeeds is demonstrated in Section 8.0.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
102
6.7 Acceptable Flare Radiation Levels
6.7.1.1 Canada Oil and Gas Installations Regulations (January 1991, Draft)
Recapping the requirements:
(9) Every gas release system shall be designed and installed so that, taking into
account the prevailing wind conditions, the maximum radiation on areas where
personnel may be located, from the automatically ignited flame of a flare or vent,
will be
(a) 6.3 kW/m2, where the period of exposure will not be greater than one minute;
(b) 4.72 kW/m2, where the period of exposure will be greater than one minute but
not greater than one hour; and
(c) 1.9 kW/m2, where the period of exposure will be greater than one hour.
6.7.1.2 Mobil Engineering Guide (EGS 661-1990)
As mentioned previously, we have been unable to source a copy of the 1990 version
of the above so instead are required to interpret between the 1985 version and the
Draft 1991 version. Using this approach we can estimate the following requirements
at the design stage.
The 1985 version used the criteria given in Table 6.10 in the calculation of flare stack
height.
Table 6.19 Allowable Radiant Heat Intensities Excluding Solar Radiation (1985)
Heat Intensities
Allowed, K
W/m2
Location
1580 Areas where personnel must remain at their posts
2365 Storage tanks containing volatile material, and control rooms
4730 Areas where escape of personnel is possible in several minutes
6300 Open areas where refinery personnel can be exposed up to one minute
with appropriate clothing
9465 Areas where protection or shielding from the radiant heat is available to
refinery personnel in six seconds or less (except for control rooms or for
non-combustible equipment and facilities)
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
103
By 1991 this was at the point of changing to:
The flare stack location shall be determined by allowable radiant heat intensities at
various critical points on offshore platforms or processing facilities. It shall be
calculated in accordance with API RP 521 and as modified by this guide.
The modifications to API RP 521 the 1991 guide refers to are given in Table 6.11
below.
Table 6.20 Allowable Radiant Heat Intensities (1991)
Heat Intensities
Allowed, K
W/m2
Condition(1)
1580 For continuous flaring operations in areas where personnel must remain at
their work stations without shielding but with appropriate clothing
1580 Emergency flaring for several minutes(2) - personnel without appropriate
clothing
790 Continuous flaring(2) - personnel expected to wear appropriate clothing
3155 Emergency flaring up to one minute(2) - personnel without appropriate
clothing
Notes
1. In areas where personnel can be exposed to higher radiation intensities, heat shielding must be
provided and also for equipment and structure as necessary.
2. In areas where personnel are not expected to wear appropriate clothing (i.e. coveralls, boots,
gloves, hard hats) allowable radiation levels have been reduced by a factor of two.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
104
API RP 521 (Third Edition, November 1990) recommends the following:
Table 6.21 Recommended Design Flare Radiation Levels Excluding Solar
Radiation (API RP 521)
Permissible Design
Level (K)
KW/m2
Location
15.77 Heat intensity on structures and in areas where operators are not likely to be
performing duties and where shelter from radiant heat is available (for example,
behind equipment).
9.46 Value of K at design flare release to any location to which people have access (for
example, at grade below the flare or a service platform of a nearby tower);
exposure should be limited to a few seconds, sufficient for escape only.
6.31 Heat intensity in areas where emergency actions lasting up to 1 minute may be
required by personnel without shielding but with appropriate clothing.
4.73 Heat intensity in areas where emergency actions lasting several minutes may be
required by personnel without shielding but with appropriate clothing.
1.58 Value of K at design flare release to any location where personnel are continuously
exposed.
6.7.2 The Radiation Levels Used in the Design
The design used the following radiation levels, derived from Draft Canadian
Legislation, as outlined by the RABS:
Table 6.22 Radiation Flux Limits Excluding Solar Radiation
Permissible Design
Level (K)
KW/m2
Conditions
6.3 Heat intensity in areas where emergency actions lasting up to 1 minute may be
required by personnel without shielding but with appropriate clothing.
4.72 Heat intensity in areas where emergency actions lasting up to several minutes may
be required by personnel without shielding but with appropriate clothing.
1.9 Value of allowable radiation level at design flare release at any location where
personnel are continuously exposed, i.e. helideck
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
105
In addition the following statement is included in the RABS:
In addition to the above radiation limitations HTPT advised that the maximum radiation
level experienced on the platform escape routes is not to exceed 1000 Btu/ft2 h (3.16
W/m2) for periods over 1 minute of exposure.
RABS page 22
The design calculations for the worst emergency flaring case (total platform blowdown)
and a flare boom length of 115m resulted in the following radiation levels:
Approximately 3.16 kW/m2 at the north side M10 weather deck
Approximately 6.30 kW/m2 at the drilling derrick crown block
Approximately 4.72 kW/m2 at the drilling derrick finger board
6.7.3 Current Requirements of the Codes and Recommended Practices
6.7.3.1 Mobil “Pressure Relief and Vapor Depressuring Systems” MP 70-P-06, July 1998
The new document has the following recommendations on thermal radiation levels.
Table 6.23 Allowable Radiant Heat Intensities in W/m2 Excluding Solar Radiation
Appropriate Clothing* Without Appropriate Clothing*
Continuous Release 1105 790
Emergency Releases
Travel time to Shelter
6 Sec 9465 3150
1 Min 6300 3150
3 Min 4730 1580
No Shelter Available 1580 790
Equipment Only
Exposure15770
Volatile Liquids Tanks,
API Separators, CCB
2365
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
106
6.7.3.2 API 521 (Fourth Edition, March 1997)
The recommendations on flare thermal radiation levels in the new addition of API
RP521 remain the same as the previous version.
6.7.4 Current Best Practice
We have mentioned earlier in this report that best practice is subjective to some
extent. Where issues are not subjective are in matters of law. Once a requirement
passes into law, as have the Canadian regulations, by meeting those requirements, an
owner has effectively discharged their responsibilities. As is also customary in matters
of precedence, national regulations always supercede recommended practices.
Normally there is actually little difference between the two requirements and this is
where we find ourselves in the Hibernia context. This is demonstrated in the following
table:
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
107
Table 6.24 Summary of Flare Radiation Requirements for Hibernia
Canadian Regulations
Impairment Criteria
Equivalent API RP521
Remarks
Maximum radiation on areas where the period of exposure will be greater than one hour
1.9 N/A 1.58 Apply Canadian regulations.
Helideck operable for at least 2 hours. Inoperability may result from…thermal radiation over 3.2 kW/m2
(Impairment Criterion 4)
Silent 3.2 Not specifically mentioned
Not used as a normal radiation level.
Maximum radiation on areas where the period of exposure will be greater than one minute but not greater than one hour
4.72 N/A 4.73 Apply Canadian regulations.
Maximum radiation on areas where the period of exposure will not be greater than one minute
And,
Escape routes from all parts of the platform to the TSR… to remain passable for 30 minutes…An escape route may be made impassable by:
Thermal radiation over 6.3 kW/m2
if unprotected:
(Impairment Criterion 3)
6.3 6.3 6.3 Apply Canadian regulations.
Maximum radiation on areas where the period of exposure will not be greater than a few seconds
(In this case the area in question is normally accessible)
Silent N/A 9.5 Apply API requirements in absence of Canadian regulation.
The actual wording of API 521 is:
Value of K at design flare release to any location to which people have access (for example, at grade below the flare or a service platform of a nearby tower); exposure should be limited to a few seconds, sufficient for escape only. (Note 1)
Escape routes from all parts of the platform to the TSR… to remain passable for 30 minutes…An escape route may be made impassable by:
Thermal radiation over 12.5 kW/m2 to the outside of the escape route if protected by cladding:
(Impairment Criterion 3)
Silent 12.5 Not specifically mentioned
Not used as a normal radiation level.
Maximum radiation on areas where shelter is present.
(In this case the area in question is not normally accessible)
Silent N/A 15.8 Not used as a normal radiation level.
The actual wording of API 521 is:
Heat intensity on structures and in areas where operators are not likely to be performing duties and where shelter from radiant heat is available (for example, behind equipment). (Note 1)
Notes:
1_) On towers and elevated structures where rapid escape is not possible, ladders must be provided on
the side away from the flare, so the structure can provide some shielding when K is greater than …
6.3 kilowatts per square meter.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
108
The allowable radiation levels on Hibernia will have to be selected from within these
requirements.
6.7.5 The Effect of Applying Best Industry Practice to Hibernia
The application of Canadian regulations and interpretation of the guidelines in API
RP521 where the Canadian requirements are silent (replicated in Table 6.24) for the
Hibernia platform gives the following allowable thermal radiation levels at various parts
of the platform:
Crown Block 9460 W/m2
The crown block falls into the category an area to personnel have access (i.e. a
service platform of a nearby tower); where exposure can be limited to a few seconds,
sufficient for escape only.
It could even be argued that a more extreme limit at this point could be used: The
Damage / Impairment criterion No. 3 indicates that a value of 12500 W/m2 may be
appropriate for the area under consideration. The criterion is specifically aimed at
escape routes protected by cladding but could equally be applied to the drilling derrick
which is partially enclosed and offers any operator working in the area the opportunity
to shelter behind a clad structure for the duration of the emergency. A reference for
the figure of 12500 W/m2 cannot be found in the guides and practices referenced
above although a somewhat worse value of 15800 W/m2 can be found in the API
which is allowed only in an area where shielding exists. These requirements are
included for information only.
In the original design it appears an unnecessarily conservative approach, which did
not recognise the presence of shielding, was applied to this area which limited the
radiation level to 6300 kW/m2.
Weather Deck 6300 W/m2
The weather deck and monkey board falls into the category of an area where
emergency actions lasting up to one minute may be required by personnel without
shielding but with appropriate clothing. It is expected that personnel on the weather
deck would be appropriately clothed and in the event of an emergency blowdown
would be able to leave either leave the deck in a minute or less or alternatively find
shelter in the same time period.
In the original design, values of 3200 and 4720 kW/m2 respectively were applied to
these areas. The former resulted from the HTPT note attached to the table which
outlined the explicit design requirements and, from the above, is a radiation level
allowable for 2 hours in an emergency. The latter neither recognises the escape
ability from the monkey board nor the shielding. Both cases therefore appear
unnecessarily conservative.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
109
Helideck 3200 W/m2
The helideck does not really fall into any specific category as defined in the guides and
practices reference above but it could be argued that it loosely falls into the category of
an area where personnel are continuously exposed during an emergency (for up to
two hours) and therefore the value of 3200 W/m2 is chosen. This corresponds with the
Damage / Impairment criterion No. 4 which indicates that a value of 3200 W/m2 is
appropriate for the helideck which is based on Canadian regulations.
Weather Deck (Continuous flaring) 1900 W/m2
For a true (non-emergency) continuous release, e.g. production flaring, a figure of
1900 kW/m2 should be used (again in accordance with Canadian regulations).
Of the above, the most important radiation level is likely to be the continuous flaring
case as it will be the most persistent (occasionally). The other radiation levels are only
approached during a platform blowdown and therefore are short duration (only
seconds) and will only be felt if a coincident severe adverse wind occurs during the
event.
Using this radiation level and location as the design case ensures that the helideck will
experience very much lower radiant rates during continuous flaring.
The radiation levels used in the flare operating envelope calculations, described fully in
Section 8.0 below, have used the above thermal radiation limits to determine the
allowable maximum flaring capacity for the ‘As Built’ flare for two windspeeds.
The results of these calculations are discussed in detail in Section 8.0 but the principle
conclusion is that if the best practice radiation levels are applied as defined above then
the flare system capacity would be approximately 200% of the current design load in
terms of thermal radiation only. The effect on hydraulics in the system for this capacity
increase has not been studied at this time.
This section should be read in conjunction with Section 8.4.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
110
6.8 Challenge Issues Resulting from the Technical Audit of the Design Calculations
Issue 34-005/2 - Jet fire scenario was not taken into account for in the design of
the blowdown system.
This issue is addressed in Section 6.2.
Issue 34-005/4 - Were fire areas used for total blowdown rate?
A simple approach to blowdown was used where the entire all equipment to be
depressured was assumed to be on fire. This is equivalent to the entire M10 module
being on fire, something which is very unlikely and if it occurs will be catastrophic.
More conventionally the platform is separated into fire areas. In this case the
blowdown valves are sized to cater for the fire case. However, the combined case is
not normally the sum of all the areas on fire and some effort is instead focussed at the
selection of a realistic worst case. The worst case is represented by the fire occurring
in the area which adds most to platform load coincident with the resultant rates from
the blowdown valves for the non-fire areas are added. These latter rates are less than
the rate that would be experienced in a fire case and the overall blowdown load is
more accurately represented. In this case we have been unable to locate fire area
drawings which forces the M10 fire case to remain the design case.
Issue 34-006/2 - Is correct isentropic efficiency used?
The isentropic efficiency specified when performing blowdown simulations affects both
the downstream blowdown temperature of gas and equipment but also the upstream
vessel wall temperature. An isentropic efficiency of 1 simulates perfectly isentropic
expansion of the gas and gives the worst case (i.e. lowest) temperatures. An
isentropic efficiency of 0 simulates perfectly isenthalpic expansion of the gas and gives
the best case (i.e. highest) temperatures. For blowdown of a vessel or system where
the feed to the vessel has been stopped the expansion of the gas is somewhere
between isentropic and isenthalpic. The selection of the isentropic efficiency is usually
based on project philosophy and experience.
The blowdown simulations performed for these calculations used an efficiency of 0.5.
There is no indication in the calculations or simulation outputs for the basis of this
selection. The selection of an efficiency of 1 is unrealistic, but a more usual figure to
use is 0.7 minimum which would lead to lower blowdown temperatures.
The impact of lower blowdown temperatures is twofold. The first concerns the
materials of construction of the flare system itself. The flare system appears from the
‘As Built’ P&IDs to constructed of LTCS with a minimum design temperature of -45oC.
The second impact is in areas of the process where hydrates can form.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
111
From the calculations reviewed problems of both hydrate formation and flare design
temperature only occur if blowdown is initiated after a delay with of the plant
maintained at pressure during the upset. Calculation 34-010 / A and 34-060 / B
address this problem but the calculations do not give any specific conclusions on the
allowable delay. Calculation 060 / B concludes that for the settleout pressures used
there is a huge spread of allowable delay periods depending upon environmental
conditions and whether insulation is installed. Current platform design philosophy is to
depressurise after 1-2 hours. If lower blowdown temperatures are expected then this
philosophy may have to be reviewed. See Issue 34-010/1 for further details.
Precautions against hydrate formation can be taken and these are discussed further
below.
For more discussion regarding this see the related discussion in Section 5.2.1.2 item
34.010/1.
Issue 34-006/3 - Is design case too extreme?
This concern relates to the high start pressure used for the blowdown calculations.
See Section 6.3 for the recommended solution.
Issue 34-042/2 - Validity of staggering blowdown. Were the systems sufficiently
independent?
This aspect is covered in Section 6.4.
6.9 Miscellaneous Issues
6.9.1 Insulation
The presence of satisfactory insulation on the vessels will allow substantially reduced
depressuring rates compared to those used during design. This aspect should be
checked in detail when the insulation on the vessels is reviewed.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
112
7.0 AS-BUILDING THE FLARE SYSTEM
7.1 Introduction
The Hibernia platform was built incorporating features for future equipment; this
included future capacity built into the flare system. As some of these projects are no
longer foreseen this section looks to remove their effect from the currently installed
flaring cases. This, in effect, will result in a system whose design cases are “as-built”.
The difference between the design capacity and the “as-built” capacity is the capacity
available for future projects, including those that were originally foreseen.
7.2 As-built and Design Capacity
The following table summarises the initial relieving capacity by area considered during
the design phase as well as the results of removing the requirements for future
equipment and potentially the 3 minute stagger on the injection compressor ‘A’
blowdown.
Table 7.25 As Built and Design Capacity
Case Scenario LP Flare Load
kg/h
HP Flare Load
kg/h
1 Design Blowdown Rate as per Relief &
Blowdown Study Report Rev C1
89,601 133,616
2 ‘As Built’ i.e. As Case 1 with Future Equipment
Removed
89,601 94,843
3 As Case 2 with 3 min Stagger Removed 126,291 94,843
The table below summarises the effect on thermal radiation impingement at various
points on the platform for the cases described in Table 7.1 with the original design
wind speed of 27 m/s blowing in a northerly direction.
Table 7.2 Thermal Radiation Impingement on Platform Areas
Case Crown Block
W/m2
Weather Deck
W/m2
Helideck
W/m2
1 6152 2911 1034
2 5623 2700 860
3 8838 3146 1314
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
113
The capacity of the flare system is essentially decided by the allowable thermal
radiation impingement on the platform. The different levels of thermal radiation and
their limitations on working and escape routes are discussed in Section 6.7. Based on
the original design radiation levels:
Crown Block 6300 W/m2
Weather Deck 3200 W/m2
Helideck 1900 W/m2
Then the following deductions can be made from the resulting thermal radiation
impingement on the platform for the 3 flare operating cases described in Table 7.1.
7.2.1 Case 1 - Design Blowdown Rate (as RABS Rev C1)
The results for this case indicate that the thermal radiation impingement at the crown
block is close to the limiting value of 6300 W/m2. This is what we would expect as the
flare stack lengths was effectively sized for this flaring scenario. The thermal radiation
impingement at the weather deck and helideck are within the limits stated above
7.2.2 Case 2 - ‘As-Built’ - i.e. As Case 1 with Future Equipment Removed
The results for this case indicate, as expected, that removing the load assigned for
‘future’ equipment from the HP flare gives some margin for increased flare load
generated by future projects / platform modifications. The margin is available for
thermal radiation at all platform areas discussed but, by inspection, the limit is
expected to occur at the crown block. It should be noted that any projects which
generate extra coincident LP blowdown load on the flare will have a greater effect on
thermal radiation impingement than that for HP blowdown due to the nature of the flare
systems. Therefore capacity, in terms of mass flowrate, liberated from the HP flare is
not necessarily available in full for the LP flare system.
7.2.3 Case 3 - As Case 2 with 3 min Stagger Removed
This case investigates the effect on the ‘As Built’ flare (i.e. with loads from ‘future’
equipment removed) of removing the 3 minute stagger between blowdown initialisation
and the blowdown of the Injection Compressor ‘A’ system. This is potentially a
modification that HMDC would consider making in the future. It can be seen from the
results, however, that though the thermal radiation levels at the weather deck and the
helideck are acceptable, the level at the crown block is greater than the current design
limit based on the criteria above. This would likely be acceptable if the shielding
around the drilling derrick structure was taken into account.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
114
8.0 RISK MANAGEMENT IN RELATION TO FLARING EVENTS AND
WIND CONDITION
8.1 Introduction
In Section 6.6 the issue of design windspeed was discussed. In this section we look at
the various windspeeds to show the effect it has on the radiation envelope on
Hibernia.
The selected windspeeds are:
The most adverse windspeed (with a probability of 0.1% and a return period of 1
year) in a direction which could influence the radiation levels on the platform. In
this case the windspeed = 34.2 m/s from the NW.
The most adverse windspeed (with a probability of 0.1% and a return period of 1
year) directly onto the platform. In this case the windspeed = 24.2 m/s from the N.
The original design windspeed from the RABS. In this case the windspeed =
27 m/s.
The results are shown below:
8.2 Potential Flare Envelope based on Total Blowdown Scenarios
8.2.1 Determination of Blowdown Load Basis
A basis for constructing an operating envelope for this study had to be developed with
no specific modification projects in mind. The task is complicated by the fact that there
are two flare systems, the LP flare and the HP flare. An increase in flare load has a
different consequence depending upon the particular flare affected, due to the different
nature of the flares. The HP flare utilises a sonic tip and therefore has a flame that
burns much more efficiently and is stiffer than the flame developed by the pipe flare tip
on the LP network.
Given the above, the only sensible approach to preparing an operating envelope was
to base it on multiples of the radiation case defining case, i.e. total platform blowdown
giving coincident LP and HP flare release as defined in the Relief and Blowdown Study
Report. The relieving loads on each flare for the design flare capacity case are given
as Case 1 in Table 7.1 above.
Flaresim calculations were performed for flare loads ranging from 50% to 500% of the
design case to enable an envelope to be defined. In reality, the systems would be
hydraulically limited long before these higher rates were achieved. The relief rate for
each flare was maintained in the same proportion as the design case and fluid
properties also remained constant for all capacities considered.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
115
8.2.2 Determination of Continuous Load Basis
The Relief and Blowdown Study Report identified that the worst case continuous
flaring occurs when there is a relief load on both the HP and LP flare systems. This
occurs either at start up or when the compression train is lost for any reason.
To determine the continuous relief load, we considered the loss of HP and LP
compression at 100% production causing the associated gas from the to spill-off to the
HP and LP flares, from the HP and MP separators and LP separator respectively. To
generate the input data we used a simulation taken from the recent debottlenecking
project (Case 3, a case which included Avalon production) with a total production of
200 kbopd (taken in this instance as 100% capacity) and used this to calculate spill-off
rates to each flare system if the compression train is disconnected. At 100%
production, therefore, the flare loads are 359.2 Te/h (MW 21.3) to the HP flare and
50.4 Te/h (MW 45.0) to the LP flare. Note that in this case the HP flare rate exceeds
current capacity.
Flaresim calculations were performed for flare loads ranging from 30% to 100% of the
above determined rates to enable an envelope to be defined. In reality, the systems
would be hydraulically limited before these higher rates were achieved. The relief rate
for each flare was maintained in the same proportion as the 100% case and fluid
properties also remained constant for all capacities considered.
8.2.3 Determination of Allowable Thermal Radiation Impingement on the Platform
The flare capacity envelope for any area on the platform is very much dependent on
the maximum allowable thermal radiation impingement at that particular area. For this
study the following limiting thermal radiation impingement levels were used to
generate the operating envelopes:
Crown Block 9500 / 12500 W/m2
Weather Deck 6300 W/m2
Helideck 3200 W/m2
Continuous *1900 W/m2
* API suggests a lower figure (1580 kW/m2) is appropriate. In this case, because of Canadian regulations,
this is ignored.
For the areas with two thermal radiation levels given, the lower figure refers to the
‘Best Practice’ value as identified in Section 6.7.5 above and the upper figure is the
allowable thermal radiation level in accordance with the Impairment / Damage criteria
which is included for information. The reasoning behind the choice of limiting thermal
radiation levels and their effect on personnel and structures are discussed in detail in
section 6.7 above.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
116
8.2.4 Other Calculation Criteria
Relief gas compositions for the total platform blowdown design case were taken from
the Kaldair Design Data Dossier (Reference 13) and used to generate the fluid
properties used in the Flaresim simulations.
Windspeeds used for the calculations are 27 m/s (original design) and 24.5 m/s
(determined from environmental data). Both these wind are blowing in a Northerly
direction, i.e. directly back onto the platform from the direction of the flare boom. The
reasoning behind the choice of windspeeds is discussed in detail in section 6.6 above.
Also considered was the 34.2 m/s NW wind considered in the RABS. The results of
the analysis indicated very similar results as the 24.5 m/s windspeed.
8.3 Results
8.3.1 Emergency Relief - Platform Blowdown
The results of the study are presented in graphical form in figures 8.1 to 8.10 below.
The curves on each graph represent the distance of the isopleth from the flare tip
varies with blowdown rate. The isopleth under consideration depends upon the area
of the platform under consideration as described above. The distance of isopleth to
flare tip is measured in the direction of the platform area under consideration. For
example, Figure 8.1 shows the distance of the 12500 W/m2 from the flare tip in the
direction of the crown block. The Horizontal line represents the actual distance of
crown block from the flare tip. Where the two intersect gives the blowdown rate, as a
percentage of design, which would result in thermal radiation of 12500 W/m2 impinging
on the crown block.
For information, although not applicable to emergency relief, the radiation distance to
the 1900 kW/m2 level is also given. This would be the type of figure that would be
considered allowable around the TSR.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
117
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
118
Figure 8.1 Envelope of Operability for Crown Block with Limiting Thermal Radiation 12500 W/m2 with Northerly Wind 24.5 m/s
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
0% 50% 100% 150% 200% 250% 300% 350% 400% 450% 500% 550% 600%
% Design Case Blowdown Rate
Dis
tan
ce f
rom
Fla
re T
ip
Crow n Block Minimum Distance from Tip
12500 W/m2 Isopleth Distance from Tip
Figure 8.2 Envelope of Operability for Crown Block with Limiting Thermal Radiation 9500 W/m2 with Northerly Wind 24.5 m/s
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
160.0
0% 50% 100% 150% 200% 250% 300% 350% 400% 450% 500% 550% 600%
% Design Case Blowdown Rate
Dis
tan
ce f
rom
Fla
re T
ip
Crow n Block Minimum Distance from Tip
9500 W/m2 Isopleth Distance from Tip
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
119
Figure 8.3 Envelope of Operability for Weather Deck with Limiting Thermal Radiation 6300 W/m2 with Northerly Wind 24.5 m/s
0.0
20.0
40.0
60.0
80.0
100.0
120.0
0% 50% 100% 150% 200% 250% 300% 350% 400% 450% 500% 550% 600%
% Design Case Blowdown Rate
Dis
tan
ce f
rom
Fla
re T
ip
6300 W/m2 Isopleth Distance from Tip
Weather Deck Minimum Distance from Tip
Figure 8.4 Envelope of Operability for Helideck with Limiting Thermal Radiation 3200 W/m2 with Northerly Wind 24.5 m/s
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
160.0
180.0
200.0
0% 50% 100% 150% 200% 250% 300% 350% 400% 450% 500% 550% 600%
% Design Case Blowdown Rate
Dis
tan
ce f
rom
Fla
re T
ip
3200 W/m2 Isopleth Distance from TipHelideck Minimum Distance from Tip
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
120
Figure 8.5 Envelope of Operability for Helideck with Limiting Thermal Radiation 1900 W/m2 with Northerly Wind 24.5 m/s
0.0
50.0
100.0
150.0
200.0
250.0
0% 50% 100% 150% 200% 250% 300% 350% 400% 450% 500% 550% 600%
% Design Case Blowdown Rate
Dis
tan
ce f
rom
Fla
re T
ip
1900 W/m2 Isopleth Distance from Tip
Helideck Minimum Distance from Tip
Figure 8.6 Envelope of Operability for Crown Block with Limiting Thermal Radiation 12500 W/m2 with Northerly Wind 27.0 m/s
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
0% 50% 100% 150% 200% 250% 300% 350% 400% 450% 500% 550% 600%
% Design Case Blowdown Rate
Dis
tan
ce f
rom
Fla
re T
ip
Crow n Block Minimum Distance from Tip
12500 W/m2 Isopleth Distance from Tip
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
121
Figure 8.8 Envelope of Operability for Weather Deck with Limiting Thermal Radiation 6300 W/m2 with Northerly Wind 27.0 m/s
0.0
20.0
40.0
60.0
80.0
100.0
120.0
0% 50% 100% 150% 200% 250% 300% 350% 400% 450% 500% 550% 600%
% Design Case Blowdown Rate
Dis
tan
ce f
rom
Fla
re T
ip
Weather Deck Minimum Distance from Tip
6300 W/m2 Isopleth Distance from Tip
Figure 8.7 Envelope of Operability for Crown Block with Limiting Thermal Radiation 9500 W/m2 with Northerly Wind 27.0 m/s
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
160.0
0% 50% 100% 150% 200% 250% 300% 350% 400% 450% 500% 550% 600%
% Design Case Blowdown Rate
Dis
tan
ce f
rom
Fla
re T
ip
Crow n Block Minimum Distance from Tip
9500 W/m2 Isopleth Distance from Tip
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
122
Figure 8.9 Envelope of Operability for Helideck with Limiting Thermal Radiation 3200 W/m2 with Northerly Wind 27.0 m/s
0.0
20.0
40.0
60.0
80.0
100.0
120.0
140.0
160.0
180.0
200.0
0% 50% 100% 150% 200% 250% 300% 350% 400% 450% 500% 550% 600%
% Design Case Blowdown Rate
Dis
tan
ce f
rom
Fla
re T
ip
Helideck Minimum Distance from Tip
3200 W/m2 Isopleth Distance from Tip
Figure 8.10 Envelope of Operability for Helideck with Limiting Thermal Radiation 1900 W/m2 with Northerly Wind 27.0 m/s
0.0
50.0
100.0
150.0
200.0
250.0
0% 50% 100% 150% 200% 250% 300% 350% 400% 450% 500% 550% 600%
% Design Case Blowdown Rate
Dis
tan
ce f
rom
Fla
re T
ip
Helideck Minimum Distance from Tip
1900 W/m2 Isopleth Distance from Tip
8.3.2 Continuous Relief
The results of the continuous flare relief study are presented in graphical form in
figures 8.11 and 8.12 below. The curves on each graph represent the distance of the
1900 W/m2 isopleth from the flare tip varying with continuous relief rate. The distance
of isopleth to flare tip is measured in the direction of the platform area under
consideration, in this case only the weather deck is considered. The horizontal line
represents the actual distance of weather deck from the flare tip. Where the two
intersect gives the continuous relief rate, as a percentage of design, which would
result in thermal radiation of 1900 W/m2 impinging on the weather deck.
The figures in parentheses on the x axis represent the combined LP and HP flare
mass flowrate under consideration e.g. the mass of gas flared if the platform is
operating at 100% capacity (considered to be 200 kbopd) is 409.6 Te/h with a pseudo
molecular weight of 22.8. Note that the mass flowrates stated become invalid if the
ratio of HP to LP flare load differs from that considered here (see Section 8.2.2 above
for further details).
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
123
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
124
Figure 8.11 Envelope of Operability for Weather Deck with Limiting Thermal Radiation 1900 W/m2 (Continuous)
with Northerly Wind 24.5 m/s
0.0
20.0
40.0
60.0
80.0
100.0
120.0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 110%
% Design Case Continuous Flaring Rate (Total Flare Mass Rate, Te/h)
Dis
tan
ce f
rom
Fla
re T
ip, m
1900 W/m2 Isopleth Distance from Tip
Weather Deck Minimum Distance from Tip
Figure 8.12 Envelope of Operability for Weather Deck with Limiting Thermal Radiation 1900 W/m2 (Continuous)
with Northerly Wind 27.0 m/s
0.0
20.0
40.0
60.0
80.0
100.0
120.0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 110%
% Design Case Continuous Flaring Rate (Total Flare Mass Rate, Te/h)
Dis
tan
ce f
rom
Fla
re T
ip, m
1900 W/m2 Isopleth Distance from Tip
Weather Deck Minimum Distance from Tip
(122.9) (163.8) (204.8) (245.8) (286.7) (327.7) (368.7) (409.6)(81.9)(41.0)(0) (450.6)
(122.9) (163.8) (204.8) (245.8) (286.7) (327.7) (368.7) (409.6)(81.9)(41.0)(0) (450.6)
8.4 Flare Envelope Conclusions
8.4.1 General
An immediate and obvious conclusion which can be drawn from the results of this
study is that a wind speed of 27 m/s gives higher thermal radiation levels on the
platform than the 24.5 m/s wind speed for the relief cases considered here.
However if we analyse the results given for the wind speed of 24.5 m/s, the Granherne
best practice wind speed as defined in Section 6.6, figures 8.1 to 8.5 and 8.11 above,
the following conclusions can be drawn for each flaring scenario:
8.4.2 Emergency Relief - Platform Blowdown
Maximum allowable thermal radiation at the crown block - 9500 W/m2
For this case the thermal radiation on the crown block is the limiting factor. An initial
blowdown rate of approximately 150% of the design rate can be tolerated before the
limit of 9500 W/m2 is limit is exceeded in this area.
The other cases considered are less onerous, with the 3200 W/m2 isopleth impinging
on the Helideck at around 350% of the design blowdown rate and the 6300 W/m2
isopleth impinging on the weather deck at around 370% of the design blowdown rate.
The above suggests considerable capacity is inherent in the system dependent on the
final basis selected. However, caution should be exercised as this apparent capacity
will change dependent on the detail of the project which actually utilises the apparent
capacity. In other words the absolute capacity will only be confirmed once the LP and
HP rates are fully defined and detailed calculations are performed for the modification
under consideration.
8.4.3 Continuous Relief
For this case the maximum allowable thermal radiation of 1900 W/m2 at the weather
deck is considered to be the limiting factor. For a northerly wind blowing at 24.5 m/s, a
platform production rate of 62% of the design rate (considered to be 200 kbopd) can
be tolerated before the limit of 1900 W/m2 is limit is exceeded in this area.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
125
Here is an area where consideration of wind condition may provide useful economic
benefits. If the regulators allow it, which may depend on flare quota considerations,
the actual production rate when the compressors were unavailable could be set based
on the measured windspeed and direction for the period in question. In other words
when the windspeed was low or in a beneficial direction the flaring rate could be set at
100% of production. Should this prove attractive to HMDC a set of envelopes for a
range of wind speeds and directions could be prepared which could be used in an
operational procedure to select production rate dependent on wind condition.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
126
9.0 IMPLICATIONS FOR HIBERNIA
9.1 Introduction
In the foregoing sections the various aspects relating the RABS have been analysed.
The intent of this section is to combine the analysis into a form that can be used to
make decisions regarding potential capacity opportunities that exist in the flare system,
as well as identify the issues that will require resolution irrespective of the exercise of
any choices. Generally the potential changes fall into 3 categories:
Capacity opportunities resulting from the application of more modern design
practices (not all of these opportunities add apparent capacity).
Areas where the design documentation should be revised to increase the integrity
and traceability in the design.
Optional changes which can be considered to be related to house keeping.
Therefore this section is separated into three main sections; Firstly an outline of the
capacity opportunities is given including the apparent capacity effects the changes
would have; Secondly, a list and description of the important changes required to
ensure the integrity and traceability of the system design documentation is given;
Lastly, optional changes are described which will aid the future maintenance and
understanding of the design in future years.
Finally, a list of items that do not easily fall into the previous sections is included for
completeness.
In Appendix 2 a proposed scope of work is included which defines, in more
prescriptive terms, the work required to revalidate the flare system design assuming
HMDC decide to implement the changes described in this section in their entirety.
9.2 Flare System Capacity Opportunities
The following summarises the capacity opportunities available in the flare system with
respect to new codes and best practices.
8266-HIB-TN-C-0001 Page of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
127
Table 9.26 Effect of Changing Flare System Design Philosophy on the Apparent Design Capacity (Total Blowdown)
Issue Description /
concern
Case Meets current
code req's?
Safety Cost Failure potential Flare system
capacity*
Recommendation
Jet Fire Described in Section
6.2. Are vessels
sufficiently protected
from the effects of jet
fire?
Original design did not
purposefully include
mitigating measures
Design
Safety analysis not carried
through to engineering.
Codes do not
require
measures to be
included for jet
fire (API
currently
working to
change this)
N/A Rapid escalation. None Adopt best practice.
Ensure insulation
integrity on lower
pressure systems
during jet flame impulse
momentum.
Best practice
Detailed 3D analysis and
prevention measures to
ensure vessel will not fail in
a jet fire
Rapid escalation prevented
unless insulation fails.
Reducing
blowdown
start
pressure
Described in Section
6.3. Compressors
blowdown from PSHH
setting. Rest of
system depressures
from normal pressure.
Design Exceeds code
requirement
+ N/A N/A No effect on HP flare.
LP flare capacity
available is increased
by ~ 17,000 kg/h
compared to the
original blowdown case
89,601 kg/h
HMDC have declined
this change for now,
preferring the more
conservative design
approach (which avoids
changes to blowdown
calculations should
compressor operating
conditions change
significantly). The
capacity opportunity will
be described in an
appendix in the updated
RABS.
Best practice
As blowdown initiates
automatically, design
system with normal start
pressure
In the unlikely event that there
was a fire coincident with a shut
in situation (that was not caused
by trip) the blowdown rate would
be higher than anticipated and if
the wind were adverse could
lead to higher than planned
radiation levels on the platform.
Reducing
the
Described in Section
6.3 Certain vessels
Design Exceeds RP 521
requirements in
N/A N/A No significant effect on
LP flare because the
Best practice would
require all blowdown
8266-HIB-TN-C-0001 Page 128 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
Issue Description /
concern
Case Meets current
code req's?
Safety Cost Failure potential Flare system
capacity*
Recommendation
blowdown
end
pressure
(i.e. with wall
thicknesses over 1”)
can be depressured to
50% of the design
pressure rather than
690 kPag.
Various components are
depressured to either
690 kPag or 50% of the
design pressure
some instances. HP compressor seal oil
system requires the
compressor and
components to
depressure to
atmospheric pressure.
HP flare capacity
available is increased
by ~ 70% compared to
the original blowdown
case 133,316 kg/h
(reduces to
~40,000 kg/h)
calculations to be re-run
and new orifice plates in
the affected blowdown
section. For the
moment best practice is
declined. An appendix
to the updated RABS
will be created to
identify the capacity
opportunity in case it is
required in the future.
Best practice
Systems with design pressure above 1724 kPag should be depressured to 50% of
the design pressure. Systems with design
pressure below
1724 kPag need not be
depressured. However, if
it is chosen to do so, the
final pressure should be
690 kPag or 50% of the
design pressure,
whichever is less.
Vessels with wall
thicknesses below 1 inch
should be considered
separately.
More closely
follows the intent
of RP 521
+ N/A
Blowdown
stagger
Described in Section
6.4. Stagger not
sufficiently
independent and
equipment is in same
fire zone. Fire may
affect A train injection
compressor, yet
blowdown will be held.
Design Ambiguous
(although the
recommended
practices allow
controlled
blowdown)
1. Stagger fails closed would
lead to escalation.
2. Stagger fails open at
initiation leads to high radiation
levels.
3. Jet fire analysis suggests
injection compressor vessels
should not fail.
33,974 kg/h of load is
added to the LP flare
blowdown case.
(compared to
89,601 kg/h original LP
flare blowdown design
case. New rate is
therefore
Decline best practice.
The A train injection
compressor
components are not at
risk due to their
thickness.
QRA the software
reliability.
8266-HIB-TN-C-0001 Page 129 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
Issue Description /
concern
Case Meets current
code req's?
Safety Cost Failure potential Flare system
capacity*
Recommendation
123,575 kg/h).Best practice avoids stagger
unless the systems can be
made sufficiently
independent
+ 1. Difficult problem relating to
back pressure on LP separator
to overcome.
2. Otherwise, very reliable.
Higher radiation levels designed
for.
Design
windspeed
and direction
Described in Section
6.6. The design
windspeed is higher
than absolutely
necessary.
Design = 27 m/s from North No code
requirements.
N/A If windspeed is higher and
design release is occurring the
radiation levels on the platform
will be exceeded.
HP and LP flare
apparent capacity is
increased by
approximately 7% (i.e.
by 9,000 kg/h and
6,000 kg/h
respectively).
Best practice declined.
For continuous flaring
case a risk mitigation
procedure could be
developed to increase
the flaring rate when the
compressors were down
dependent on the
measured wind
condition.
Best practice = 24.5 m/s
from North
34.2 m/s from North West
No code
requirements
If windspeed is higher and
design release is occurring, the
radiation levels for emergency
on the platform will be exceeded
somewhat. It is highly unlikely
that anyone would be on deck
without the necessary protection
in such a case.
Acceptable
flare
radiation
levels
Described in Section
6.7. The requirements
in the RABS are over
conservative.
Design
6.3 kW/m2 at crown block and 3.2 kW/m2 at escape ways
Over
conservative
N/A N/A HP and LP flare capacity is increased by approximately 50% before new radiation levels are approached during blowdown (i.e. by 60,000 kg/h and 45,000 kg/h for the HP and LP flares respectively).
Adopt and describe best practice in flare documentation. The practice will remove inconsistency compared to Canadian regulations and international standards. Hydraulic considerations may not allow the full use of new capacity.
Best practice - Radiation levels raised to:
9.5 kW/m2 at crown block (shielded)
6.3 kW/m2 at any escape way (no shielding)
3.2 kW/m2 at the helideck
1.9 kW/m2 continuous at the weather deck
(and meets
Canadian
regulations)
N/A
8266-HIB-TN-C-0001 Page 130 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
Issue Description /
concern
Case Meets current
code req's?
Safety Cost Failure potential Flare system
capacity*
Recommendation
Incorporate
the effects of
vessel
insulation on
the vapour
rates
Described in Section
6.9.1.
Design
No credit taken for insulation on vessels in blowdown calculations
Over
conservative
N/A N/A HP and LP flare capacity is increased by approximately 5% during blowdown case (i.e. by 6,000 kg/h and 4,000 kg/h for the HP and LP flares respectively).
Best practice would require all blowdown calculations to be re-run. For the moment best practice is declined. A note will be incorporated in the revised flare documents to note the capacity opportunity in case it is required in the future.
Best practice
Credit taken for insulation
N/A
Remove the
effect of
future
equipment
Described in Section
7.0.
N/A N/A N/A N/A N/A HP flare capacity is increased by approximately 38,000 kg/h during blowdown. LP flare system capacity unchanged.
Incorporate the revised data in the updated RABS. Identify the “spare” capacity for future projects in a suitable section.
N/A N/A N/A Negl. N/A
= acceptable - + = most acceptable
= least expensive - = most expensive
* by making change to best practice
8266-HIB-TN-C-0001 Page 131 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
Care needs to be exercised when considering Table 9.26 as the values are not
additive. What the table does show however is the significant spare capacity in the HP
flare when considering the blowdown cases. The LP flare is very different. The
changes that affect capacity alone (rather than implied through radiation calculations)
are insufficient to offset the large change required to remove the blowdown stagger.
Therefore this change would force the design rate of the system to be increased and
would therefore require detailed hydraulic analysis to be undertaken. The difficult
aspect will be the superimposed back pressure on the LP separator. If this is too high
there will be the undesirable consequence of raising the pressure in the LP separator
when the blowdown valve opens. This would have the effect of increasing inventory
and reducing the time to failure of the LP separator if exposed to fire. Some mitigating
measures would likely be required in this instance. Given this and the apparent
inherent capability of the injection compressor components to survive the pause period
before blowdown commences, suggests that the stagger in the system should be
retained.
For the relief cases other than blowdown, two out of three of the capacity opportunities
(i.e. relief cases which were overestimated during design) are negative. The worst of
the problems relates to the spillover valve failure cases as these have the potential to
significantly exceed the HP flare system design rate. This is shown on Table 9.27.
which follows.
8266-HIB-TN-C-0001 Page 132 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
Table 9.27 Effect of Changing Flare System Design Philosophy on the Apparent Design Capacity (Relief Cases)
Issue Description /
concern
Case Meets current
code req’s?
Safety Cos
t
Failure potential Flare system capacity* Recommendation
Two-phase
relief (See
Section 5.3
and 6.5)
New sizing
method
increases valve
size required for
this case
Design - Old additive API method No longer N/A If the design case is the
sizing case the vessel can
be overpressured.
The design rate which can
be accommodated in the
existing valves reduces
dramatically. For
comparison max single well
rate for HP separator is ~
54 kbopd.
Adopt best practice.
This issue requires the
maximum well rate and
maximum number of
wells to be redefined as
they are likely to
compromise the RV size
on the HP separator.
The test separator RVs
are being replaced.
Best practice - New API method
Valve size may be to high
and valve will chatter.
Missed relief
cases (See
Section 5.2)
Failure of
spillover valves
(open) exceeds
flare system
capacity.
Design - missed a valid relief case No. N/A If valve fails open the flare
system design rate is
significantly exceeded.
Flare system capacity was
not dimensioned for the
dimensioning case.
Adopt best practice and
use measures to limit
peak load.
Best practice - Design for any single
valve failure.
N/A
Blowby
cases
methodology
flawed (See
Section
5.3.1)
Blowby cases
are over
conservative.
This would
prevent the
installation of
larger LCVs if
this proved
necessary.
Design - Over conservative case
assumed.
N/A Valve is likely to chatter if
faced with the blowby
case.
As there will be no desire to
change the existing valve,
there will be a latent capacity
in the system which can be
used for future upgrades.
The capacity change
available (which would
translate to an increase in
separator LCV size) is
approximately 20%.
Add note to RABS
update to describe the
spare capacity.
Best practice:
Use settleout pressure for
shutdown case
Take account of downstream
control valve positions and fluid
properties in production case.
N/A A valve, properly sized for
the case in question, will
not chatter when faced
with the design case.
= acceptable - + = most acceptable
= least expensive - = most expensive
* by making change to best practice
8266-HIB-TN-C-0001 Page 133 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
In the above tables the issues which add capacity are optional. In other words these
are issues that HMDC can adopt or decline at will. The issues which have a negative
capacity effect, for obvious reasons, will require some work to resolve.
9.3 Impact on the Design Documentation
The outcome of the technical audit indicates the following aspects of the design will
need to be revisited / revised. The table is a significantly shortened version of the
table presented in Section 5.4 and represents the most important changes that should
be considered. Repetitive items (including those in tables 9.1 and 9.2) and issues
requiring simple comment in the RABS update are omitted. The table should be read
in this light.
8266-HIB-TN-C-0001 Page 134 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
Table 9.28 Calculations Requiring Revision (System 34)
Number
34-
Title Number
34-
Description Action
005 / A Blowdown Section Inventory Calc (Provides input to blowdown simulations)
005/1 Are the blowdown volumes used sufficiently accurate?
Locate and review missing
calculations
005/3 Were the real settle out pressures ever
used?
Compare real settleout conditions
with design to ensure blowdown
rates are appropriate
006 / A Blowdown Summary 006/1 HP Blowdown calculation higher than
vendor aware of. Radiation level for
case is underestimated.
Update RABS.
006/2 Correct isentropic efficiency used? An optimistic isentropic efficiency
was used to calculate the
minimum system temperature.
Recalculate the temperatures.
See also 34.010/1.
010 / A Calculation of allowed
cooldown before
hydrate formation &
minimum
temperatures
achieved in flare gas
from critical blowdown
sections
010/1 Was the calculation methodology
sufficiently robust?
There are flaws in the method
used to calculate the minimum
temperatures in the system.
These should be corrected. Use
resultant more realistic figure to
implement alarms on high
pressure areas to avoid low
temperatures. Update RABS.
011 / A Review of HP flare
KO Drum size
011/1 A note on the front of calc 34-064 states
that Rev 7 of Design Basis gives max
well flow of 20,000 bpd + average well of
10,000 bpd, i.e. 30,000 bpd total. The
individual well design rate has changed.
What are the implications for the
platform?
Select number and design rate of
the well failure to shut in case.
Update RABS. Develop
operational procedure to cater for
time to fill HP flare KO vessel.
015 / A Calc to review options
for reducing HP to MP
Separator and MP to
LP Separator Blowby
Cases
015/1 Relief & Blowdown Study Report Rev C1
non-concurrent maximum allowable LP
and HP Flare loads are 110,874 kg/h
and 244,897 kg/h respectively. Rates
used in these calculations exceed
design.
Ensure design rates quoted are
consistent and reflect the installed
control valves. Update RABS.
022 / C HP Flare Network
Sizing (HP Separator
- Max Relief Case)
022/2 Effect of increased production /
production fluid GOR
Update RABS to mention link
between GOR and the compressor
capacity.
025 / C 3rd Stage
Compressor Max
Relief Case - Network
Analysis
025/2 Include in updated RABS cases which
are not catered for, i.e. consider relief
from both compressor trains
Check modifications to avoid
injection compressor RVs lifting
prevent coincident case. Update
RABS to explicitly mention the
cases which are not designed for.
033 / G Coalescer & LP
Separator Heaters
Simultaneous Fire
Relief - Network
Analysis
033/1 Assumption that the header is at zero
pressure (I.e. that this is a singular event
not coincident with any other releases)
Construct an LP flare network
model to calculate the back
pressure on relief valves when the
system is depressuring.
8266-HIB-TN-C-0001 Page 135 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
Table 9.29 Calculations Requiring Revision (System 31)
Number Title Number Description Action
31.37 Relief Valve
Calculations - LP
Separator
31.37/1 Is it possible for the Test Separator
manifold to be connected to the LP
Separator when operating in high
pressure mode?
Ensure positive method of
ensuring isolation from HP system
exists. Update RABS to reflect
this.
In Granherne’s opinion none of the above items are optional.
9.4 Optional Changes
The following changes could be considered to increase the integrity and traceability of
the design work.
Table 9.30 Technical Audit Optional Changes (System 34)
Number
34-
Title Number
34-
Description Action
045 / E Total HP Blowdown
Initial Conditions
(Checks blowdown
line sizes for
individual system
blowdowns)
045/1 There is no network analysis run with
common HP Blowdown at initial
conditions
Consider constructing a HP flare
network model to assess future
modification projects against.
045/2 Consistency error in the number and
flows in the gas injection flowlines
Add a note to the RABS clarifying
the injection manifold rate basis.
046 / G Fuel Gas Cooler /
Heater tube rupture
relief line size check
046/1 ''As Built' P&IDs show bursting discs in
this service (calc considers PSVs)
therefore calc is no longer valid
There is no replacement
calculation for the installed
bursting discs. The bursting disk
calculations should be reviewed to
identify implications for the flare
system.
050 / G 3rd Stage Suction
Scrubber A (D-3303A)
PSV Discharge Line
Size Confirmation
050/1 Rev C2 PSV datasheet states set
pressure = 8200 kPa(g), 'As Built' P&ID
shows set pressure = 7000 kPa(g)
P&ID set pressure error?
059 / G Comparative Program
check of INPLANT
Single Phase
Simulation vs ESI
059/1 Accuracy of calculations using ESI
instead of INPLANT
Revisit ESI calculations and
replace as necessary
8266-HIB-TN-C-0001 Page 136 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
Table 9.31 Technical Audit Optional Changes (System 31)
Number Title Number Description Action
31.36 Relief Valve Calculations - MP Separator
31.36/6 Are the gas blowby cases are
methodologically flawed?
Add note to RABS update
31.38 Inlet Line Size
Checking for Relief
Valves
31.38/1 Inlet line sizes should have been
recalculated using 'Final' relief data
and isometrics.
Check / redo inlet line sizing
calculations as necessary.
These items are optional as the inconsistencies are minor.
The other area that could be improved is the overall level of as built of the design
calculations. Generally the calculations were never revised for key design data late in
the project. This included the calculation of inventory and the use of vendor supplied
settleout pressures. The latter item becomes more important if the changes above are
pursued. When the relief valve and control valve data sheets were prepared
superseded design data was also used. Our initial analysis of these combined effects
suggests that they are benign. For example we expect, but cannot be sure, that the
inventory assumptions will actually be conservative; Our analysis of the valve
calculations shows that in some cases the valves may have ended up being slightly
smaller than desired but if this were a problem it would have shown up by now.
This type of inconsistency is relatively common; there is never the perfect design
project. HMDC will need to decide whether they can accept the inconsistencies.
9.5 Miscellaneous Requirements
9.5.1 Updating the Design Documentation
The above changes generally point to a requirement to rerun some of the key flare
system design calculations. Whether or not this uncovers areas where hardware
changes will need to be made will have to be seen; nevertheless there will still be the
requirement to update the design volumes and make the calculation changes
traceable. This will be in addition to making the new calculated information obvious in
the updated RABS.
8266-HIB-TN-C-0001 Page 137 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
The following summarises the type of changes to the design documentation that will
be necessary:
Relief and Blowdown Study Report
Fairly extensive rewrite of the report.
Design Calculations
For each change prepare a calculation revision which revs up the existing
calculation (in other words building on the existing work). This would include:
- Calculations identified above.
- Flare radiation calculations (for windspeed and allowable radiation levels)
- Continuous radiation cases. Analysis of allowable production rate vs wind
speed.
Blowdown inventory calculations (for removed inventory)
Reliability analysis of the system that controls the compressor stagger, to ensure
the system is sufficiently reliable to ensure the design integrity.
9.5.2 Implementation Projects
In this section there are some projects mentioned which will in all likelihood require
hardware changes to be made (resulting from the above there may be more).
Insulation conformance - The explicit ability of the platform to cope with a jet fire
hazard requires the insulation around the vessels to remain in place during jet
flame impingement. This may require the insulation strength to be improved.
Modifications to limit peak flaring rate during spillover valve failure.
Instrument modifications to warn operators when the requirement to blowdown
compressors is becoming imminent (to avoid low temperature problems).
8266-HIB-TN-C-0001 Page 138 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
10.0 REFERENCES
1. Canada-Newfoundland Atlantic Accord Implementation Act - Newfoundland
Offshore Petroleum Installations Regulations, February 21,1995.
2. Concept Safety Evaluation, Cremer and Warner, October 1991.
3. Fire Risk Analysis, Cremer and Warner, May 1992.
4. Fire Risk Analysis Update, Cremer and Warner, February 1993.
5. Design Phase Risk Assessment, Caldwell Consulting, May 1995.
6. Design Phase Safety and Environmental Assessment, Doc No. CM-E-F-R-M00-
RP-104 Rev C0, May 1995.
7. Structural Passive Fire Protection Analysis, Aker Engineering, 21 February 1993.
8. Review of Emergency Systems for the Proposed Hibernia Platform, Cremer and
Warner, Report No. 93432, 15th March 1994. HMDC Doc No: CM-Y-F-R-M00-RP-
008.000 Rev 001.
9. Deleted.
10. Deleted.
11. Gayton P.W. and Murphy, S.N. (1995) Depressurisation System Design, IChemE
workshop, “The Safe Disposal of Unwanted Hydrocarbons”, Aberdeen 1995.
12. Deleted.
13. Kaldair Design Data Dossier, Doc. No. CM-Z-M-Z-210-ZM-1083-002.0, December
1995.
8266-HIB-TN-C-0001 Page 139 of 139 Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc October 2000
APPENDIX I
CALCULATION TECHNICAL AUDIT
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 1 of 42 October 2000
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 2 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-005 / A Blowdown Section Inventory Calc 06 18-May-93
(Provides input to blowdown simulations)
Audit Tasks Methodology X see /2&4 Consistency As Built X see /1,3&5
Key Assumptions
Blowdown volumes calculated using piping isometrics available at that time. Not as built.
Included between 10 - 20% margin for small bore pipework.
Future Gas Dehydration Unit blowdown section included
Future MP Manifold blowdown section included
Future Gas Lift Manifold blowdown section included
Not all BD volumes recalculated using final piping isometrics
Vessel weights estimated?
Blowdown of GT driven compressors must be to atm conditions in 15 mins (seal oil system rundown time),
therefore based on estimated settle out pressure + 5% contingency on section vol. The vessels were assumed on fire.
1st Stage Compressor uses dry gas seals therefore not as critical as above
PIDs at Rev C2, Isometrics at Rev B
Key Results
Results Summarised in table below
Section Total Volume Liquid Charge Wetted Area Section Weight Initial Pressure1 Initial Temp1
m3 m3 m2Tonnes kPa(a)
oC
HP Separator 186.81 72.70 98.40 165.00 - -
MP Separator 340.60 78.07 121.80 175.00 - -
West Test Separator 48.53 11.30 30.60 45.00 - -
Future Test Separator 33.50 6.96 29.04 36.00 - -
East Test Separator 49.05 9.66 28.11 46.50 - -
HP Manifold 54.50 (2) 200.00 234.91 - -
MP Manifold 43.45 (2) 125.00 193.13 - -
Test Manifolds 2.70 (2) 50.00 11.69 - -
HP Offgas Manifold 16.97 - - 32.00 - -
MP Offgas Manifold 17.60 - - 23.87 - -
Gas Injection Manifold 4.00 - - 40.00 - -
Gas Injection Flowline 1.50 - - 40.00 - -
Future Gas Lift Manifold 1.70 - - 17.21 - -
Future Gas Dehydration Unit
8.38 - - 50.00 - -
2.55 - - 10.00 - -
1st Stage Gas Compressor 55.62 5.00 10.80 35.00 316 91.0
2nd Stage Gas Compressor 24.92 (2) 10.20 45.00 2,046 80.0
3rd Stage Gas Compressor 19.18 (2) 6.60 75.00 6,122 86.8
4th Stage Gas Compressor 9.15 - 100.00 24,115 117.0
Notes
1. Values only given for compressor sections where settle out conditions calculated
2. Not required as input as auto calculated by blowdown program
Issues
34-005/1 Are the blowdown volumes used sufficiently accurate?
34-005/2 Jet fire scenario not taken into account for the design of the blowdown system
34-005/3 Were the real settle out pressures ever used?
34-005/4 Were fire areas used for total blowdown rate?
34-005/5 Are vessel weights used reasonable?
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
Gas Dehydrator, Inlet Cooler & Scrubber
Gas Dehydrator Discharge Cooler & Scrubber
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 3 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-005 / A Blowdown Section Inventory Calc 05 08-May-92
(Provides input to blowdown simulations)
Audit Tasks Methodology Consistency As Built X see Rev 06
Key Assumptions
See 34-005 Rev 6 and 34-006 for final data used in blowdown analysis.
Key Results
See 34-005 Rev 6 and 34-006 for final volumes used.
Issues
See 34-005 Rev 6 and 34-006.
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 4 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-006 / A Blowdown Summary 05 19-May-93
Audit Tasks Methodology X See /2-4 Consistency X See /1 As Built X See /5
Key Assumptions
Blowdown model isentropic efficiency set at 0.5
Blowdown from PSHH to LP flare and from normal operating pressure to HP flare.
Assumes heat input from fire.
Constant rate blowdown from LP Separator and FG Separator (500 and 250 kg/h respectively).
Uses estimated settleout pressures?
Key Results
Rev 04 calculated peak values remain the basis for flare spec (Rev 05 calc provides final summary of BD loads)
Rev 05 calculated values not incorporated into Relief & Blowdown Study Report Rev C2
Total LP Blowdown Flows
- Minor changes for peak total LP BD flows between rev 04 & 05 (though individual flowrates have changed)
- Basis for spec of total LP BD load to vendor considers blowdown of GT driven compressors from PSHH settle out conditions
in all stages for both trains. This case is considered of low probability
- Sensitivity check on blowdown from compressor settleout pressure. Depressuring from normal operating pressure
increases apparent system capacity by 19%
- Total peak BD flow (staggered from PSHH settle out conditions) for this calc rev 86,709 kg/h [89,601 kg/h in Relief & Blowdown
Study Report] - Detailed in table below
Total HP Blowdown Flows
- Total peak HP BD load increase by 5.8 % since rev 04 calc
- Includes for future / possible future equipment including: MP Manifolds / Future Test Separator & Manifolds / System
Gas Lift Manifolds / Gas Dehydration
- Future Gas Dehydration unit is significant (20%) proportion of total HP BD load. The volume used in BD calc is approx double
expected value
- Total peak BD flow this calc rev 141,335 kg/h [133,616 kg/h in Relief & Blowdown Study Report] - Detailed in table below
Design Case Blowdown Summary Table - Initial Blowdown Rates (time = 0)
System Initial Blowdown Rate, kg/h System Initial Blowdown Rate, kg/h
Inj Comp 'A' 0 Test Manifolds 588
Inj Comp 'B' 36,690 HP Manifold 3,239
3rd Stage Comp 'A' 15,917 MP Manifold (future) 999
3rd Stage Comp 'B' 15,917 Test Separator E & W 23,559
2nd Stage Comp 'A' 7,325 Test Separator (future) 8,262
2nd Stage Comp 'B' 7,325 HP Separator 41,311
1st Stage Comp 2,785 MP Separator 8,284
LP Separator 500 GI Manifold 4,154
LP FG KO Drum 250 GL Manifold (future) 3,075
FG Cooler 681
HP FG KO Drum 6,093
Offgas Manifolds 4,096
Dehydration System (future) 28,062
GI Flowlines 8,932
Total 86,709 Total 141,335
1. Blowdown from PSHH Settleout conditions, 3 minute time delay on Inj Comp 'A' blowdown
Issues
34-006/1 HP Blowdown calculation higher than vendor aware of. Radiation level for case is underestimated.
34-006/2 Correct isentropic efficiency used?
34-006/3 Is design case too extreme?
34-006/4 Is constant rate blowdown a valid design method, i.e. not according to API?
34-006/5 'As Built' settleout pressure
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
Blowdown to HP FlareBlowdown to LP Flare1
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 5 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-006 / A Blowdown Summary for RFD Flare Report 04 14-Feb-92
Audit Tasks Methodology X see Rev 05 Consistency As Built X see Rev 05
Key Assumptions
Superseded by Rev 5
Key Results
Total LP Blowdown Flows
- Total peak LP Flare BD flow for this calc rev as per Relief & Blowdown Study Report Rev C1, i.e. 89,601 kg/h (taking into account
3 minute stagger on Inj Compressor 'A' blowdown) - Detailed in table below
Total HP Blowdown Flows
- Total peak HP Flare BD flow for this calc rev as per Relief & Blowdown Study Report, i.e. 133,611 kg/h - Detailed in table below
Design Case Blowdown Summary Table - Initial Blowdown Rates (time = 0)
System Initial Blowdown Rate, kg/h System Initial Blowdown Rate, kg/h
Inj Comp 'A' Test Manifolds
Inj Comp 'B' HP Manifold
3rd Stage Comp 'A' MP Manifold (future)
3rd Stage Comp 'B' Test Separator E & W
2nd Stage Comp 'A' Test Separator (future)
2nd Stage Comp 'B' HP Separator
1st Stage Comp MP Separator
LP Separator GI Manifold
LP FG KO Drum GL Manifold (future)
FG Cooler
HP FG KO Drum
Offgas Manifolds
Glycol Column (future)
Glycol Discharge Scrubber (fut)
Total 89,601 Total 133,616
1. Blowdown from PSHH Settleout conditions, 3 minute time delay on Inj Comp 'A' blowdown
Issues
See 34-006 Rev 5
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-008 / A Flare gas LHV calc for RFD flare report 03 13-Apr-92
Audit Tasks Methodology Consistency As Built Key Assumptions
N/A. Based on design compositions.
Key Results
LHV in Flare Data Sheet
Issues
None
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
Blowdown to LP Flare1 Blowdown to HP Flare
8,484
8,484
0
33,974
250
4,188
5,250
3,589
20,098
4,047
50,244
8,840
17,562
17,562
1,117
21,969
6,093
2,832
3,075
617
1,657
2,785
500
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 6 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-009 / A Metal Surface Temperature Calcs for AFD Flare Report 03 20-Apr-92
Audit Tasks Methodology Consistency As Built Key Assumptions
Metal temperature model derived from Kern's Process Heat Transfer and Kent's Mechanical Engineers Handbook.
Ambient Air Temp = 20C
Emissivity = 0.7
Windspeed = 0 / 27 m/s
Pipe Flame Buoyancy = 3.0 m/s
Sonic Flame Buoyancy = 4.6 m/s
Stack Length = 115m
HP Flare Tip angle 45 deg to Horizontal
LP Flare Tip angle 90 deg to Horizontal
Windspeed = 0 / 27 m/s
Calorific Value = 47 MJ/kg
Key Results
Metal Temperatures at the following point locations considered (m):
North East Elevation Worst Case Temp, oC
Top Weather Deck 75 0 30 70.3
Crown Block 55 10 93 109.0
Finger Board 58 6 69 93.2
Platform Crane 84 42 49 87.0
Boom Base 75 0 0 55.8
30m up Flare Boom 90 0 26 72.7
50m up Flare Boom 100 0 43 91.8
70m up Flare Boom 110 0 61 127.2
90m up Flare Boom 120 0 78 198.0
105m up Flare Boom 128 0 91 335.4
110m up Flare Boom 130 0 95 420.5
112.5m up Flare Boom 131 0 97 482.7
Issues
None.
Temperatures are for information and paint selection. Not dimensioning design criteria.
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-009 / A Metal Surface Temperature Calcs for AFD Flare Report 02 16-Jan-92
Audit Tasks Methodology Consistency As Built Key Assumptions
As Rev 03 of this calculation
Key Results
Superseded by Rev 03 of this calculation
Issues
As Rev 03 of this calculation
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 7 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-010 / A Calculation of allowed cooldown before hydrate formation & minimum 02 23-Mar-92
temperatures achieved in flare gas from critical blowdown sections
Audit Tasks Methodology Consistency As Built X See /1
Key Assumptions
Ref. Process simulations: HIBBD126A.LIS, 126B, 127, 137, 138, 139, 159, 160, 162
Key Results
1. Injection Compressor Blowdown Section
Initial settle out conditions = 22,669 kPa(a), Temp = 108.2 C
Hydrates form if gas cools to 61 C before blowdown commences
2. 3rd Stage Compressor Blowdown Section
Initial settle out conditions = 7,348 kPa(a), Temp = 92.0 C
Hydrates form if gas cools to 20 C before blowdown commences
3. 2nd Stage Compressor Blowdown Section
Initial settle out conditions = 2,237 kPa(a), Temp = 69.2 C
Hydrates form if gas cools to 25 C before blowdown commences
4. Inlet Gas Manifold Blowdown Section
Initial conditions = 40,000 kPa(a), Temp = 156 C
Hydrates form if gas cools to 67.5 C before blowdown commences
Issues
34-010/1 Was the calculation methodology sufficiently robust?
34-010/2 Should 'troubleshooting' methanol injection points be incorporated?
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-011 / A Review of HP flare KO Drum size 03 09-Mar-92
Audit Tasks Methodology Consistency As Built Key Assumptions
Max HP relief case = 244,897 kg/h, MW = 20.65, dP(tip) = 500 kPa, T = 59.0 C, z = 0.98, k=1.24 (as per R & BD Study Report Rev C1)
Calc'd KO Drum operating pressure (739 kPa(a)) based on estimated pipe equivalent length (drum to tip)
Droplet size 400m
Drum sizing to API 521
Vol liquid required to hold = 37.18 m3 (for basis see 34-011 Rev 02)
Key Results
HP Flare KO Drum reduced to 2.8m Dia x 7.5m T/T
Issues
None
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 8 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-011 / A Review of HP flare KO Drum size 02 06-Feb-92
Audit Tasks Methodology Consistency X See /1 As Built X (See 34-011 Rev 03)
Key Assumptions
Liquid volume sizing basis: 10 mins relief of 1 well at max flow and 1 well at average flow (i.e. 10 mins at 40,000 bpd)
Overall sizing basis: Drum at maximum liquid level + Max HP flare relief load (274,878 kg/h, MW = 21.8, T = 83.7 C
z = 0.98, P = 743 kPa(a))
Key Results
HP Flare KO Drum reduced to 2.8m Dia x 8.0m T/T (Superseded by Calc 34-011 Rev 03)
Issues
34-011/1 A note on the front of calc 34-064 states that Rev 7 of Design Basis gives max well flow of 20,000 bpd + average
well of 10,000 bpd, i.e. 30,000 bpd total. The individual well design rate has changed. What are the implications
for the platform?
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-012 / A Review of LP flare KO Drum size 03 10-Mar-92
Audit Tasks Methodology Consistency As Built Key Assumptions
Max LP relief case = 110,874 kg/h, MW = 25.37, dP(tip) = 10 kPa, T = 67.5 C, z = 1.0, k=1.19 (as per R & BD Study Report Rev C1)
Calc'd KO Drum operating pressure (147.7 kPa(a)) based on estimated pipe equivalent length (drum to tip)
Droplet size 400m
Drum sizing to API 521
Liquid transfer from HP Flare KO Drum = 37.13 m3
Key Results
LP Flare KO Drum reduced to 2.8m Dia x 8.0m T/T
Issues
See 34-011/1
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-013 / A Preliminary calc of HP Flare tip delta P vs flowrate 01 11-Jun-91
Audit Tasks Methodology Consistency As Built Key Assumptions
Superseded by vendor (Kaldair) supplied curve
Vendor data based on HP flowrate of 244,897 kg/h, MW=20.65, T=59 C
Key Results
Superseded by vendor (Kaldair) supplied curve
Issues
None
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 9 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-014 / A HP Flare Drum Pump Calculations 02 02-Jul-91
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare Drum size is 2.8m Dia x 8.5m T/T
Total drum volume is 58.05m3
Pump capacity designed to Mobil E&P661 (Empty half drum volume in 2 hours)
Key Results
15m3/h pump capacity
Issues
None however 'As-Built' HP Flare Drum size reduced to 2.8m Dia x 8.0m T/T
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-015 / A Calc to review options for reducing HP to MP Separator and 01 14-Aug-91
MP to LP Separator Blowby Cases
Audit Tasks Methodology X See /2 Consistency X See /1 As Built (See Note)
Key Assumptions
Maximum allowable LP Flare flowrate = 119,324 kg/h (Higher than design rate stated in R & BD Study Report Rev C1)
Maximum allowable HP Flare flowrate = 274,878 kg/h (Higher than design rate stated in R & BD Study Report Rev C1)
Uses Masoneillan sub-critical flow correlation except for HP to MP case with 2 off control valves (critical flow)
Key Results
For MP to LP Separator blowby relief rate not to exceed maximum allowable LP Flare load:
Calculates min LP Sep design pressure of 9.2 barg with single valve Cv=1300 , or
Original LP Sep design pressure (7 barg) but 2 off control valves (with independent transmitters and controllers) Cv=700 each
For HP to MP Separator blowby relief rate not to exceed maximum allowable HP Flare load:
Calculates min MP Sep design pressure of 33.5 barg with single valve Cv=750, or
Original MP Sep design pressure (20 barg) but 2 off control valves (with independent transmitters and controllers) Cv=375 each
Issues
34-015/1 Relief & Blowdown Study Report Rev C1 non-concurrent maximum allowable LP and HP Flare loads are
110,874 kg/h and 244, 897 kg/h respectively. Rates used in these calculations exceed design.
34-015/2 Is considering only one control valve fails open for gas blowby case when 2 installed in parallel
realistic / allowable even with provision of independent transmitters and controllers?
Note: Actual installed control valve CVs (PID for HP Separator, Rev E2, states max control valve CV=350, datasheet states CV=330)
(PID for MP Separator, Rev E3, states max control valve CV=650, datasheet states CV=600)
Audited by AJR Date 16-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 10 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-016 / A Flare purge flowrate calc 03 18-Feb-93
Audit Tasks Methodology Consistency As Built Key Assumptions
Sweep velocity 0.2 m/s
Sweep gas MW = 20.21
Sweep gas Temp = 10 C or 37 C
Lines Swept HP LP
16"-VH-34153 14"-VL-35299
12"-VH-34278 20"-VL-35263
14"-VH-34208 14"-VL-35261
16"-VH-34156 14"-VL-35241
14"-VH-34157
14"-VH-34151
Key Results
Purge gas mass flowrates for flowmeter specification
Issues
None
Audited by AJR Date 19-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-017 / A Calculation of flare gas Peak Velocity at the Flare Gas Flowmeter Location 01 21-Nov-91
Audit Tasks Methodology Consistency X (Out of date max flows)
As Built
Key Assumptions
Max HP Flare Gas Rate = 274,878 kg/h (giving vel = 91.73 m/s) [18" N.B. Line]
Max LP Flare Gas Rate = 119,324 kg/h (giving vel = 89.23 m/s) [24" N.B. Line]
Max LP Flare Gas Rate (new design value) = 131,473 kg/h (giving vel = 92.23 m/s) [24" N.B. Line]
Key Results
Maximum gas velocities as given above
Issues
None as calc was only developed to assist ESIN with flowmeter evaluation
Audited by AJR Date 19-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 11 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-018 / A Comparison of Flare Vendor Radiation Levels 02 30-Jan-92
Audit Tasks Methodology Consistency As Built Key Assumptions
Windspeed = 0 or 27 m/s
Flame Emissivity Values:
Birwelco calculations include for solar radiation
Boom Length assumed 123 m
Flare Tip angle 45 deg
Key Results
Radiation levels at key points on the platform for the different flaring cases.
Issues
None.
This calculation was used for selection only. Calculation was eventually superseded by the flare vendor's 'As Built' data package.
See also calculation 34-062
Audited by AJR Date 19-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-019 / B Line sizing calculations for lines discharging to HP & LP Flare systems 01 30-Jan-92
(i.e. Relief, Blowdown & Spill-off valves)
Audit Tasks Methodology Consistency N / A As Built N / A
Key Assumptions
Preliminary line sizing calculation for input into deck level flare headers and lines upstream of blowdown valves only
Lines where velocity is greater than 0.35 Mach identified as requiring angled entry into flare header
Key Results
Calc is superseded by Network Analysis runs.
Issues
None
Audited by AJR Date 19-Jun-00 Checked by MFG Date 15-Aug-00
Case HP Flare LP Flare
Kaldair Birw elco Kaldair Birw elco
1 0.1 0.121 0 .18 0.148
2 0.1 0.107 - -
3 0.1 0.122 - -
4 - - 0.2 0.3
5 0.1 0.124 0.2 0.3
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 12 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-020 / B LP Flare KO Drum Level Valve Calculation 01 30-Jan-92
Audit Tasks Methodology Consistency As Built (See Issues)
Key Assumptions
Masoneillan sub-critical flow formulae
Installed CV (LV-0009) = 65 (P&ID shows valve number to be LV-0109)
4" liquid outlet line
Key Results
Line size and installed control valve CV are adequate
As a result of calc LP Flare KO Drum heater duty revised to 30kW
LSLL set point revised to ensure drum heater element is always covered
Issues
None for this calc (See 34-021 below). Control valve datasheet confirms actual 'As-Built' CV=70
Audited by AJR Date 19-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-021 / B Gas blowby calc from LP Flare KO Drum to open Hazardous Drains Tank (F-5201) 01 06-Feb-92
& Calc of F-5201 Req'd Vent Line Size (Result of HAZOP comment)
Audit Tasks Methodology Consistency As Built (See Issues)
Key Assumptions
LP Flare KO Drum at its maximum pressure (i.e.135 kPa(a) )
Masoneillan sub-critical flow formulae
Installed CV (LV-0009) = 65 (P&ID shows valve number to be LV-0109)
Key Results
Built-up back pressure at F-5201 approximately 1.1 kPa(g). (Design pressure on 'As-built' P&ID = Static head + 3 kPa(g).
Static head calculated to be 20 kPa based on tank water full to overflow level)
Issues
None. Actual 'As-Built' control valve CV=70 however calculation results will not change significantly.
Vessel number is 'F-5210 on 'As-Built' P&IDs.
Audited by AJR Date 19-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 13 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-060 / B Indicative Injection Compressor Cooldown Calculation 01 29-May-92
Audit Tasks Methodology Consistency As Built (See Issues)
Key Assumptions
Internal B&R program 'ColdSpot' used, system (incl compressor, scrubber etc) converted to single pseudo pipesize for calc purposes
Injection Compressor settle out conditions P=22669 kPa(a), T=108.2C
HT coefficients based on either natural convection + ambient temp of -10C or forced convection (wind speed 30ft/s)
Min flare temp = -45C
Key Results
Cooldown temp at which hydrate formation occurs in LP flare system on section blowdown = 61.5 C
Hold time for cooldown temperature to reach 61.5 C, hours: 3.4 (No insulation, natural convection)
0.96 (No insulation, forced convection)
20 (1" insulation, natural convection)
28 (1.5" insulation, forced convection)
Cooldown temp at which minimum design temperature occurs in LP flare system on section blowdown = 50 C
Hold time for cooldown temperature to reach 50 C, hours: 4.5 (No insulation, natural convection)
1.28 (No insulation, forced convection)
28 (1" insulation, natural convection)
37 (1.5" insulation, forced convection)
Results support philosophy that compressor sections will not remain isolated at pressure for periods in excess of 1-2 hours
Issues
See 34-010/1 and 34-010/2
Audited by AJR Date 19-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-061 / B Simplistic Steady State Preliminary Review of the Annulus Rupture Relief Flowrate 01 10-Sep-92
Audit Tasks Methodology Consistency As Built X See /1
Key Assumptions
Based on 4" choke valve with max CV = 174
Two possible sources of Lift Gas
- 3rd Stage Compressor (P=18,237 kPa(a), T=177.4 C, MW=21.86, z=0.937)
- Future Lift Gas Dehydrator (P=13,700 kPa(a), T=38 C, MW=22.09, z=0.66)
Lift gas supplied at 13,000 kpa(a) downstream of choke valve
Relief flow based on Masoneillan critical flow formulae
Critical flow factor = 0.82
Key Results
Relief flowrate based on 3rd Stage Compressor 228.6 MMSCFD
Relief flowrate based on Future Lift Gas Dehydrator 319.6 MMSCFD
Max HP flare design load 237.85 MMSCFD
Installed choke valve CV must be around 120 if lift gas supplied from Future Lift Gas Dehydrator to avoid exceeding flare design load
Issues
34-061/1 Annulus rupture case had the potential to be the defining case for the HP flare system (depending on installed
choke valve CV). What happened subsequently?
Audited by AJR Date 19-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 14 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-062 / B Sensitivity review of max emergency radiation levels on total blowdown case 01 21-May-93
if injection compressor 'A' staggered blowdown mechanism fails
Audit Tasks Methodology Consistency As Built Key Assumptions
Calc for indicative only, design values by flare vendor
Wind speed = 27 m/s
3 cases considered, total platform blowdown with:
1 - Turbine driven compressors at PSHH settle out conditions, staggered blowdown (3 mins)
2 - Turbine driven compressors at normal settle out conditions, staggered blowdown (3 mins)
3 - Turbine driven compressors at normal settle out conditions, staggering mechanism fails
HP tip at 45o angle
Stack length = 115 m
Key Results
Case 1 Case 2 Case 3
Location
Crown Block 7112 (2254) 6029 (1911) 8104 (2569)
Finger Board 5094 (1615) 4490 (1423) 5644 (1789)
Weather Deck 3013 (955) 2718 (861) 3284 (1041)
Reconfirms requirement for staggered blowdown to meet radiation specs however increased radiation
deemed acceptable for short periods
Issues
None. Case 2 results were superseded by vendor calculations. The vendor calculations confirm the staggering requirement.
The calculations used earlier tip orientations, however as the Case1 and Case 3 calculations are indicative only this is
not considered significant.
Audited by AJR Date 19-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-063 / B Summary of Tube Rupture Relief Flare Line Liquid Velocity 01 01-Jun-93
(Calcs to Provide Information Requested by Piping Stress)
Audit Tasks Methodology Consistency As Built Key Assumptions
No details of method of tube rupture flowrate given in this calc
Key Results
Fluid velocities (for stress calculation purposes)
Issues
None
Audited by AJR Date 19-Jun-00 Checked by MFG Date 15-Aug-00
Radiation Levels, W/m2 (Btu/ft2/h)
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 15 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-022 / C HP Flare Network Sizing 02 22-Mar-93
(HP Separator - Max Relief Case)
Audit Tasks Methodology Consistency X See /1 As Built X See /2
Key Assumptions
HP Flare system iso rev A4
HP Separator Blocked Outlet (227,649 kg/h total load)
PSV Datasheet at Rev C1 indicates multiple PSVs with staggered set pressures on HP Separator relief valves. 3 x 50% PSVs,
(2 operating + 1 standby). 2 are set at vessel DP + 1 set at 105% DP
Blocked outlet relief is 100% vapour (no liquid or 2 phase relief)
Tip P estimated from Kaldair supplied graph
Maximum pressure at PSV discharge (Normal + Built-up back pressure) = 851 kPa(a)
Key Results
Maximum pressure at PSV discharge for this case = 943 kPa(a)
Maximum Mach No. in system = 0.25
Calculated tip P = 415 kPa
Issues
34-022/1 Calculated maximum pressure at PSV discharge exceeds value on PSV datasheet Rev C1
34-022/2 Effect of increased production / production fluid GOR
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-023 / C HP Separator Max Spill-off Case - Network Analysis 02 22-Mar-93
Audit Tasks Methodology X See /2 Consistency X See /1 As Built Key Assumptions
HP Flare system iso rev A4
HP Separator Max Spill-off (244,897 kg/h total load)
Max spill-off relief is 100% vapour (no liquid or 2 phase relief)
Tip P estimated from Kaldair supplied graph
Maximum pressure at spill-off valve discharge = 1001 kPa(a)
Key Results
Maximum pressure at spill-off valve discharge for this case = 1147 kPa(a)
Maximum Mach No. in system = 0.25
Calculated tip P = 483 kPa
Issues
34-023/1 Calculated maximum pressure at spill-off valve discharge exceeds value on control valve datasheet Rev C1
34-023/2 Is case where valve fails fully open considered?
See also 34-022/2
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 16 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-024 / C MP Separator Max Relief Case - Network Analysis 02 24-Mar-93
Audit Tasks Methodology Consistency X See /1 As Built X See below
Key Assumptions
HP Flare system iso rev A4
MP Separator Max Relief is gas blowby @ 249,332 kg/h (total load)
Based on 2 x 50% installed control valves CV = 450 each (not purchased at relief valve data sheet issue date)
PSV Datasheet at Rev C2 indicates multiple PSVs with staggered set pressures on MP Separator. 3 x 50% PSVs,
(2 operating + 1 standby). 2 are set at vessel DP + 1 set at 105% DP. Note that PSV datasheet on HOLD at Rev C2.
Relief is 100% vapour (no liquid or 2 phase relief)
Tip P estimated from Kaldair supplied graph
Maximum pressure at PSV discharge (Normal + Built-up back pressure) = 851 kPa(a)
Key Results
Maximum pressure at PSV discharge for this case = 1097 kPa(a)
Maximum Mach No. in system = 0.30
Calculated tip P = 483 kPa
Issues
34-024/1 Calculated maximum pressure at PSV discharge exceeds value on PSV datasheet Rev C2
'As Built' P&ID shows 2 x 50% LVs (LV-7327/7332) + note stating max installed control valves CV = 350 each - therefore no
further action required. (Control valve datasheet states CV=330)
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-025 / C 3rd Stage Compressor Max Relief Case - Network Analysis 01 27-Jan-93
Audit Tasks Methodology X See /2 Consistency X See /1 As Built Key Assumptions
HP Flare system iso rev A1
3rd Stage Compressor blocked outlet relief is 134,720 kg/h for K-3303A and 134,720 kg/h for K-3303B. Relief from
one train at a time only considered
Staggered set pressures on 3rd Stage Compressor relief valves (3 x 33.3% PSVs 1st set at DP, 2nd at 103% DP & 3rd at 105% DP)
Tip P estimated from Kaldair supplied graph
Maximum pressure at PSV discharge (Normal) = 1 to 500 kPa(g), (Built-up back pressure not considered)
Key Results
Maximum pressure at PSV discharge for this case = 754 kPa(a)
Maximum Mach No. in system = 0.33
Calculated tip P = 259 kPa
Issues
34-025/1 Calculated maximum pressure at PSV discharge exceeds value on PSV datasheet Rev C2 - Check for later revisions
34-025/2 Is relief from both compression trains a valid case?
HP flare isometric out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID).
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 17 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-026 / C Injection Compressor Max Relief Case - Network Analysis 01 27-Jan-93
Audit Tasks Methodology Consistency X See /1 As Built Key Assumptions
HP Flare system iso rev A1
Injection Compressor K-3304B blocked outlet relief is 155,273 kg/h
Relief from one train at a time only considered
Staggered set pressures on Injection Compressor relief valves (4 x 25% PSVs 1st set at DP, 2nd at 102% DP,
3rd at 104% DP & 4th at 105% DP)
Tip P estimated from Kaldair supplied graph
Maximum pressure at PSV discharge (Normal) = 1 to 500 kPa(g), (Built-up back pressure not considered)
Key Results
Maximum pressure at PSV discharge for this case = 726 kPa(a)
Maximum Mach No. in system = 0.28
Calculated tip P = 268 kPa
Issues
34-026/1 Calculated maximum pressure at PSV discharge exceeds value on PSV datasheet Rev C2
See also 34-025/2
HP flare isometric out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID).
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-027 / C MP Separator Max Spill-off Case - Network Analysis 02 24-Mar-93
Audit Tasks Methodology X See /1 Consistency As Built Key Assumptions
HP Flare system iso rev A4
MP Separator Max Spill-off (94,453 kg/h total load)
Max spill-off relief is 100% vapour (no liquid or 2 phase relief)
Tip P estimated from Kaldair supplied graph
Maximum pressure at spill-off valve discharge = 551 kPa(a)
Key Results
Maximum pressure at spill-off valve discharge for this case = 470 kPa(a)
Maximum Mach No. in system = 0.42
Calculated tip P = 103 kPa
Issues
34-027/1 Was failed open control valve considered?
See also 34-022/2
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 18 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-028 / D West Test Separator Max Spill-off Case - Network Analysis 02 24-Mar-93
Audit Tasks Methodology X See /1 Consistency As Built Key Assumptions
HP Flare system iso rev A3
West Test Separator Max Spill-off (58,803 kg/h total load)
Max spill-off relief is 100% vapour (no liquid or 2 phase relief)
Tip P estimated from Kaldair supplied graph
Maximum pressure at spill-off valve discharge = 551 kPa(a)
Key Results
Maximum pressure at spill-off valve discharge for this case = 290 kPa(a)
Maximum Mach No. in system = 0.41
Calculated tip P = 32 kPa
Issues
34-028/1 Is case where valve fails fully open considered.
See also 34-022/2
HP flare isometric out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-029 / D West Test Separator Max Relief Case - Network Analysis 02 28-Jan-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system iso rev A4
West Test Separator max relief case is Blocked Outlet (189,279 kg/h total load). Equivalent to relief of full 30,000 bopd flowrate
1 x 100% PSV set at vessel DP
Relief is 2-phase
Tip P estimated from Kaldair supplied graph
Maximum pressure at PSV discharge (Normal) = 1 to 500 kPa(g)
Key Results
Maximum pressure at PSV discharge for this case = 394 kPa(a)
Maximum Mach No. in system = 0.42
Calculated tip P = 32 kPa
Satisfactory 2-phase flow regime (annular)
Issues
None
See also 34-022/2
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 19 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-030 / D East Test Separator Max Spill-off Case - Network Analysis 02 25-Mar-93
Audit Tasks Methodology X See /1 Consistency As Built Key Assumptions
HP Flare system iso rev A4
East Test Separator Max Spill-off (58,803 kg/h total load)
Max spill-off relief is 100% vapour (no liquid or 2 phase relief)
Tip P estimated from Kaldair supplied graph
Maximum pressure at spill-off valve discharge = 551 kPa(a)
Key Results
Maximum pressure at spill-off valve discharge for this case = 298 kPa(a)
Maximum Mach No. in system = 0.38
Calculated tip P = 50 kPa
Issues
34-030/1 Is case where valve fails fully open considered?
See also 34-022/2
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-031 / D East Test Separator Max Relief Case - Network Analysis 02 25-Mar-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system iso rev A4
East Test Separator max relief case is Blocked Outlet (189,279 kg/h total load). Equivalent to relief of full 30,000 bopd flowrate
1 x 100% PSV set at vessel DP
Relief is 2-phase
Tip P estimated from Kaldair supplied graph
Maximum pressure at PSV discharge (Normal) = 1 to 500 kPa(g), (Built-up back pressure not considered)
Key Results
Maximum pressure at PSV discharge for this case = 456 kPa(a)
Maximum Mach No. in system = 0.37
Calculated tip P = 32 kPa
Satisfactory 2-phase flow regime (annular)
Issues
None
See also 34-022/2
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 20 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-032 / D 1st Stage Compressor Max Relief Case - Network Analysis 01 28-Jan-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system iso rev A1
1st Stage Compressor K-3301 blocked outlet relief is 72,801 kg/h
1 x 100% PSV set at 90% DP + 1 x 100% standby PSV set at 90% DP
Tip P estimated from Kaldair supplied graph
Maximum pressure at PSV discharge (Normal) = 1 to 500 kPa(g)
Key Results
Maximum pressure at PSV discharge for this case = 326 kPa(a)
Maximum Mach No. in system = 0.34
Calculated tip P = 24 kPa
Issues
None
PSV set pressure is 90% downstream system design pressure to avoid tube rupture relief case on E-3302A/B
HP flare isometric out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID).
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34- / E 1st Stage Compressor Spill-off Case - Network Analysis 01 29-Jan-93
(No calc No.)
Audit Tasks Methodology X See /2 Consistency X See /1 As Built Key Assumptions
HP Flare system iso rev A1
Max Spill-off = 59,841 kg/h (normal design flowrate)
Tip P estimated from Kaldair supplied graph
Maximum pressure at spill-off valve discharge = 201 kPa(a)
Key Results
Maximum pressure at spill-off valve discharge for this case = 251 kPa(a)
Maximum Mach No. in system = 0.33
Calculated tip P = 18 kPa
Issues
34-/1 Calculated maximum pressure at spill-off valve discharge exceeds value on control valve datasheet Rev C1
34-/2 Is case where valve fails fully open considered?
HP flare isometric out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID).
Calculation probably part of 34-032
Audited by AJR Date 20-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 21 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-045 / E Total HP Blowdown Initial Conditions 01 22-Mar-93
(Checks blowdown line sizes for individual system blowdowns)
Audit Tasks Methodology X See /1 Consistency X See /2 As Built Key Assumptions
HP Flare system iso rev A3
HP flare headers and sub-headers are not sized by blowdown case
Laterals are sized by individual section blowdown but sizing is velocity governed and not pressure governed
Blowdown simulations HIBBD155/156/109/110/111/112/164/114/115/104/105/185/184/106/113/165/107.LIS
Max velocity = 0.8 Mach
Individual blowdown lines 50m equivalent length
Considers pressure at end of lateral (i.e. header pressure) is atmospheric except for high flows where a header P is calculated
Compositions from blowdown simulations referenced above
ESI compressible flow analysis sufficient (network analysis using INPLANT not required)
Process data sheet for blowdown valves tagged on back of calc CM-E-C-K-M00-DS-0016 Rev D1, 11-Mar-93
Two types of blowdown valve:
- full bore ball valves (with downstream orifice installed)
- Angle type choke valves (or proprietary designed high pressure drop valves)
Key Results
Velocities in laterals found to be acceptable for given line sizes (i.e. less than Mach 0.8) except for lines from
'Dehydration' section (line size increased from 6" to 8") and 'Future Test Separator' section (line size increased from 3" to 6")
Issues
34-045/1 There is no network analysis run with common HP Blowdown at initial conditions
34-045/2 Consistency error in the blowdown flowrate from the gas injection flowlines (HP blowdown rates are identical to
those given in calc 34.006 except for GI flowlines where this calc uses 8 off BD valves at 2250 kg/h each and
calc 34.006 uses a combined figure of 8932 kg/h)
Other items to note are:
All line sizes are per 'As Built' P&IDs. Future 'Dehydration' section and 'Future Test Separator' section line sizes on latest P&IDs
(not 'As Built') have not been updated with results of this calc
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-038 / F LP Separator Max Relief Case - Network Analysis 01 02-Mar-93
Audit Tasks Methodology Consistency As Built Key Assumptions
LP Flare system isometric No Rev Given
LP Separator Max Relief is gas blowby @ 110,874 kg/h (total load)
Based on 2 x 50% installed control valves CV = 700 each (not purchased at relief valve data sheet issue date)
PSV Datasheet at Rev C2 indicates multiple PSVs with staggered set pressures on LP Separator. 3 x 50% PSVs,
(1 operating + 1 standby are set at vessel DP + 1 operating set at 104.3% DP). Note that PSV datasheet on HOLD at Rev C2.
Relief is 100% vapour (no liquid or 2 phase relief)
No tip P (pipe flare)
Maximum pressure at PSV discharge (Normal + Built-up back pressure) = 191 kPa(a)
Key Results
Maximum pressure at PSV discharge for this case = 268 kPa(a)
Maximum Mach No. in system = 0.45
Issues
None
Calculated maximum pressure at PSV discharge exceeds value on PSV datasheet Rev C2. However installed PSVs are
balanced so this will not affect the rating.
'As Built' P&ID shows 2 x 50% LVs (LV-7360/7367) + note stating max installed control valves CV = 650 each. Actual installed
valve CV=600 therefore no further action required.
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID).
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 22 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-039 / F LP Separator Max Spill-off Case - Network Analysis 01 02-Mar-93
Audit Tasks Methodology X See /1 Consistency As Built Key Assumptions
LP Flare system isometric No Rev Given
Max Spill-off = 60,147 kg/h
No tip P (pipe flare)
Maximum pressure at spill-off valve discharge = 139 kPa(a)
Key Results
Maximum pressure at spill-off valve discharge for this case = 143 kPa(a)
Maximum Mach No. in system = 0.22
Issues
34-039/1 Is case where valve fails fully open considered?
See also 34-022/2
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID).
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-040 / F Produced Water Surge Drum Gas Breakthrough Case - Network Analysis 01 02-Mar-93
(From LP Separator)
Audit Tasks Methodology Consistency As Built Key Assumptions
LP Flare system isometric No Rev Given
Produced Water Surge Drum Gas Breakthrough from LP Separator = 493 kg/h
Based on max CV of installed control valve (no datasheet in calc)
Relief is 100% vapour (no liquid or 2 phase relief)
No tip P (pipe flare)
Key Results
Maximum Mach No. in system is negligible
Produced Water Surge Drum will not be overpressured for this case
Issues
None
Installed valve CV not stated in calc so impossible to check against P&ID however rate is so low as to be negligible for this study.
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 23 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-041 / F Produced Water Degassing Drum Gas Breakthrough Case - Network Analysis 01 02-Mar-93
(From MP Separator)
Audit Tasks Methodology Consistency As Built X See below
Key Assumptions
LP Flare system isometric No Rev Given
Produced Water Degassing Drum Gas Breakthrough from MP Separator = 54,938 kg/h
Based on max CV of installed control valve (no datasheet in calc)
Calc uses operating pressure of upstream vessel and max superimposed LP Flare backpressure of 142 kPa(a) downstream
Relief is 100% vapour (no liquid or 2 phase relief)
No tip P (pipe flare)
Key Results
Maximum Mach No. in system = 0.23
Produced Water Degassing Drum will not be overpressured for this case
Issues
None
Installed valve CV not stated in calc but resulting flowrate suggests a CV of 300 used. Actual installed CV = 330
which does not affect the results of the calculation significantly.
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-042 / F Total LP Blowdown - Initial Conditions - Network Analysis 02 18-Mar-93
Audit Tasks Methodology X See /2 Consistency X See /1 As Built Key Assumptions
LP Flare system isometric Rev A3
Blowdown simulations HIBBD200/202/203/154.LIS
Total blowdown rate (initial rate) = 86,707 kg/h
Staggered flow - 3 minute time delay on Inj 'A' Compressor / Scrubber
Compositions from blowdown simulations referenced above
No tip P (pipe flare)
Process data sheet for blowdown valves with calc CM-E-C-K-M00-DS-0016 Rev D1, 11-Mar-93
Key Results
Maximum Mach No. in system = 0.44
Blowdown Valve Rev D1 Datasheet
backpressure
Network Analysis
Backpressure
33-ESV- kPa(a) kPa(a)
7279 201 266
7350 201 - No initial flow (staggered valve)
7372 201 231
7153 201 173
7177 201 203
7253 201 254
Additional valves on summary sheet not identified and no supporting blowdown valve datasheet attached
Issues
34-042/1 Total blowdown rate (initial rate) used in calc less than that in Relief & Blowdown Study Report ( 89,601 kg/h)
34-042/2 Validity of staggering blowdown. Were the systems sufficiently independent?
Some calculated backpressures greater than specified on blowdown valve Rev D1 datasheet. Not significant as still below
critical pressure ratio.
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 24 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-043 / F Injection Compressor 'A' Blowdown - Initial Conditions - Network Analysis 02 18-Mar-93
Audit Tasks Methodology Consistency X See below As Built Key Assumptions
LP Flare system isometric Rev A3
Blowdown simulations HIBBD201.LIS
Injection Compressor 'A' blowdown rate (initial rate) = 45,133 kg/h
No other equipment blows down at same time as Injection Compressor 'A'
Compositions from blowdown simulations referenced above
No tip P (pipe flare)
Process data sheet for blowdown valves with calc CM-E-C-K-M00-DS-0016 Rev D1, 11-Mar-93
Key Results
Maximum Mach No. in system = 0.48
Blowdown Valve Rev D1 Datasheet
backpressure
Network Analysis
Backpressure
33-ESV- kPa(a) kPa(a)
7350 201 275
Issues
None
Calculation was prepared to identify the maximum velocity in the header (and consequently set the downstream pressure at
atmospheric for the worst case). Therefore network or back pressure results should not be used. The effect of the increase
in back pressure on the 'A' compressor blowdown valve is insignificant (no effect on critical pressure ratio).
See also 34-042/2
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-033 / G Coalescer & LP Separator Heaters Simultaneous Fire Relief - Network Analysis 01 01-Feb-93
Audit Tasks Methodology X See /1 Consistency As Built Key Assumptions
LP Flare system isometric Rev A1
Considers pressure at end of sub-header (i.e. main header pressure) is atmospheric
Maximum allowable built-up back pressure at PSV discharge must be < 10% of set pressure (i.e. conventional valves)
PSV Relief Case Rate Configuration
31-PSV-
7378A/B Fire 40,771 kg/h 1 x 100% operation + 1 x 100% Standby
7428A/B Fire 7,214 kg/h 1 x 100% operation + 1 x 100% Standby
7437A/B Fire 7,214 kg/h 1 x 100% operation + 1 x 100% Standby
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.60
Line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
31-PSV- kPa(a) kPa(a)
7378A/B 102-136 161
7428A/B 102-136 152
7437A/B 102-136 152
Issues
34-033/1 Assumption that the header is at zero pressure (i.e. that this is a singular event not coincident with any other releases)
Calculated backpressure greater than specified on datasheet - calc considers this OK as less than 10% of set pressure
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
Equipment Protected
LP Separator Heaters
Coalescer A
Coalescer B
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 25 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-035 / G 3rd Stage Suction Scrubber PSV - Network Analysis 01 10-Feb-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system isometric Rev A1
Considers pressure at end of sub-header (i.e. main header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
Maximum allowable built-up back pressure at PSV discharge must be < 10% of set pressure i.e. conventional valves
- (suitability of conventional valves to be confirmed by inst / vendor - datasheet at rev C2, 11-Nov-92)
Relief Case Rate Configuration
Backflow 9,121 kg/h 1 x 100% operation
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.61
Line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
33-PSV- kPa(a) kPa(a)
7226 102-601 214.5
Issues
None
Basis for backflow calculation not given (probably NRV failure)
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-036 / G Injection Stage Suction Scrubber PSV - Network Analysis 01 10-Feb-93
Audit Tasks Methodology Consistency X See /1 As Built Key Assumptions
HP Flare system isometric Rev A1
Considers pressure at end of sub-header (i.e. main header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
Maximum allowable built-up back pressure at PSV discharge must be < 10% of set pressure i.e. conventional valves - lots of margin
- (suitability of conventional valves to be confirmed by inst / vendor - datasheet at rev C2, 11-Nov-92)
Relief Case Rate Configuration
Backflow 23,334 kg/h 1 x 100% operation
PSV datasheet States 10% accumulation but 'Max Relieving Pressure' given is 121% of set pressure
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.56
Line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
33-PSV- kPa(a) kPa(a)
7326 102-601 174
Issues
34-036/1 Inconsistency on datasheet between accumulation and 'Max Relieving Pressure' (should be 10%)
Basis for backflow calculation not given (probably NRV failure)
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
PSV Equipment Protected
33-PSV-7326 Inj Stage Suction Scrubber B
33-PSV-7226 3rd Stage Suction Scrubber B
PSV Equipment Protected
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 26 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-037 / G HM & CM Expansion Drums Simultaneous Fire Relief Case - Network Analysis 02 01-Feb-93
Audit Tasks Methodology Consistency X See /1 As Built Key Assumptions
LP Flare system isometric Rev A3
Considers pressure at end of sub-header (i.e. main header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
Maximum allowable built-up back pressure at PSV discharge must be < 10% of set pressure (i.e. conventional valves)
Equipment Relief Case Rate Configuration
Protected
CM Exp'n Drum Fire 1,055 kg/h 1 x 100% operation + 1 x 100% Standby
HM Exp'n Drum Fire 27,628 kg/h 1 x 100% operation + 1 x 100% Standby
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.45
Line size increase for common line from 6" to 8". Other line sizes sufficient
Datasheet backpressure
Calculated Backpressure*
kPa(a) kPa(a) * incorporating line size increase
102-136 136
102-136 185
Issues
34-037/1 Calculated backpressure (for 0152A/B) greater than specified on datasheet - calc considers
this OK as less than 10% of set pressure
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
PSV
64-PSV-0118A/B
63-PSV-0152A/B
64-PSV-0118A/B
63-PSV-0152A/B
Relief Valve
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 27 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-044 / G Total LP Blowdown - After 3 mins (stagger point) - Network Analysis 01 22-Mar-93
Audit Tasks Methodology Consistency As Built Key Assumptions
LP Flare system isometric Rev A3
Blowdown simulations HIBBD200/202/203/154.LIS
Total blowdown rate after 3 mins (stagger point) = 85,504 kg/h
Staggered flow - 3 minute time delay on Inj 'A' Compressor / Scrubber
Compositions from blowdown simulations referenced above
No tip P (pipe flare)
Key Results
Calculation undertaken to check velocities were acceptable. Maximum Mach No. in system = 0.36 therefore line sizes sufficient
Blowdown Valve Rev D1 Datasheet
backpressure
Network Analysis
Backpressure
33-ESV- kPa(a) kPa(a)
7279 201 176
7350 201 253
7372 201 157
7153 201 193
7177 201 157
7253 201 209
Additional valves on summary sheet not identified and no supporting blowdown valve datasheet attached
Issues
None
Total blowdown rate (initial rate) referenced in calc less than that in Relief & Blowdown Study Report ( 89,601 kg/h) but not
sufficient to effect sizing
Some calculated backpressures greater than specified on blowdown valve Rev D1 datasheet but not sufficient to affect sizing
See also 34-042/2
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-046 / G Fuel Gas Cooler / Heater tube rupture relief line size check 01 02-Mar-93
Audit Tasks Methodology N/A Consistency N/A As Built X See /1
Issues
34-046/1 'As Built' P&IDs show bursting discs in this service (calc considers PSVs) therefore calc is no longer valid
Audited by AJR Date 21-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 28 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-047 / G Simultaneous Fire Relief Case from E-6202 & Z-6201 A/B 01 02-Mar-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system isometric No Rev Given
Considers pressure at end of sub-header (i.e. main header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
62-PSV-0040A/B stated to be conventional valves yet 'Normal Back Pressure' is 1-500 kPa(g) (i.e. > 10% set pressure)
- others are balanced for similar 'Normal Back Pressure'
PSV Relief Case Rate Configuration
62-PSV-
0040A/B Fire 1,346 kg/h 1 x 100% operation + 1 x 100% Standby
0081 Fire 1,814 kg/h 1 x 100% operation
0092 Fire 1,814 kg/h 1 x 100% operation
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.56
Header 3"-VH-34205 increased in size (shown as 3"-VH-34326 & 4"-VH-34327 on 'As Built' P&ID). Original size gave
mach no. = 0.97
Other line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure*
62-PSV- kPa(a) kPa(a) * incorporating line size increase
0040A/B 102-601 153
0081 102-601 156
0092 102-601 160
Issues
None
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 22-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-048 / G 2nd Stage Suction Scrubber A (D-3302A) PSV Discharge Line Size Confirmation 01 02-Mar-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system isometric No Rev Given
Considers pressure at end of sub-header (i.e. main header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
33-PSV-7099 balanced valve - suitability of balanced valve to be confirmed by inst / vendor - datasheet at rev C2, 11-Nov-92
Relief Case Rate Configuration
Backflow 5,080 kg/h 1 x 100% operation
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.53
Line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
33-PSV- kPa(a) kPa(a)
7099 102-601 157
Issues
None
Basis for backflow calculation not given (probably NRV failure)
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 22-Jun-00 Checked by MFG Date 15-Aug-00
Z-6201B
PSV Equipment Protected
33-PSV-7099 D-3302A
Equipment Protected
E-6202 (Tube side)
Z-6201A
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 29 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-049 / G Inj Stage Suction Scrubber A (D-3304A) PSV Discharge Line Size Confirmation 01 02-Mar-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system isometric No Rev Given
Considers pressure at end of sub-header (i.e. main header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
33-PSV-7301 conventional valve - suitability of conventional valve to be confirmed by inst / vendor - datasheet at rev C2, 11-Nov-92
Relief Case Rate Configuration
Backflow 23,334 kg/h 1 x 100% operation
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.59
Line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
33-PSV- kPa(a) kPa(a)
7301 102-601 188
Issues
None
Basis for backflow calculation not given (probably NRV failure)
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 22-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-050 / G 3rd Stage Suction Scrubber A (D-3303A) PSV Discharge Line Size Confirmation 01 02-Mar-93
Audit Tasks Methodology Consistency As Built X See /1
Key Assumptions
HP Flare system isometric No Rev Given
Considers pressure at end of sub-header (i.e. main header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
33-PSV-7200 conventional valve - suitability of conventional valve to be confirmed by inst / vendor - datasheet at rev C2, 11-Nov-92
Relief Case Rate Configuration
Backflow 13,233 kg/h 1 x 100% operation
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.60
Line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
33-PSV- kPa(a) kPa(a)
7200 102-601 229
Issues
34-050/1 Rev C2 PSV datasheet states set pressure = 8200 kPa(g), 'As Built' P&ID shows set pressure = 7000 kPa(g)
Basis for backflow calculation not given (probably NRV failure)
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 22-Jun-00 Checked by MFG Date 15-Aug-00
33-PSV-7301 D-3304A
PSV Equipment Protected
PSV Equipment Protected
33-PSV-7200 D-3303A
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 30 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-051 / G HP Fuel gas KO Drum (D-6201) PSV Discharge Line Size Confirmation 01 02-Mar-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system isometric No Rev Given
Considers pressure at end of PSV discharge line (i.e. sub-header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
62-PSV-0024A/B balanced valves
PSV Relief Case Rate Configuration
62-PSV-
0024A/B Fire 10,895 kg/h 1 x 100% operation + 1 x 100% Standby
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.49
Line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
62-PSV- kPa(a) kPa(a)
0024A/B 102-601 210
Issues
See 34-033/1
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 22-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-052 / G E-3301 Shell Side PSV Discharge Line Size Confirmation 01 02-Mar-93
Audit Tasks Methodology Consistency As Built Key Assumptions
LP Flare system isometric No Rev Given
Considers pressure at end of PSV discharge line (i.e. sub-header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
33-PSV-0094 conventional valve - suitability of conventional valve to be confirmed by inst / vendor - datasheet at rev C2, 20-Nov-92
Relief Case Rate Configuration
Fire 1,182 kg/h 1 x 100% operation
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.27
Line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
33-PSV- kPa(a) kPa(a)
0094 102-136 115
Issues
None
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 22-Jun-00 Checked by MFG Date 15-Aug-00
33-PSV-0094 E-3301
PSV Equipment Protected
Equipment Protected
D-6201
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 31 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-053 / G E-3303B Shell Side PSV Discharge Line Size Confirmation 01 02-Mar-93
Audit Tasks Methodology N/A Consistency N/A As Built X See below
Issues
None
'As Built' P&IDs show bursting discs installed in this service (calc considers PSVs) therefore calc is no longer valid
See also 34-046/1
Audited by AJR Date 22-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-054 / G HP Manifold Relief - Network Analysis 01 02-Mar-93
Audit Tasks Methodology Consistency As Built X See /1
Key Assumptions
HP Flare system isometric No Rev Given
Conventional valve
Calculation takes into account total system pressure drop but still assumes that this is a singular event not coincident
with any other releases
PSV Relief Case Rate Configuration
31-PSV-
7042A/B Fire 74,585 kg/h 1 x 100% operation + 1 x 100% Standby
Tip P estimated from Kaldair supplied graph
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.68
Line sizes sufficient
Calculated tip P = 33 kPa
Relief Valve Datasheet backpressure
Calculated Backpressure
31-PSV- kPa(a) kPa(a)
7042A/B 102-601 226
Issues
34-054/1 Rev C2 PSV datasheet states set pressure = 34,400 kPa(g), 'As Built' P&ID shows set pressure = 34,100 kPa(g)
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 22-Jun-00 Checked by MFG Date 15-Aug-00
Equipment Protected
HP Manifold
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 32 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-055 / G Simultaneous Fire Relief Case from Z-3701 A/B, Z-3702 A/B & Z-6202 A/B 01 10-Feb-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system isometric No Rev Given
Balanced valves
Calculation takes into account total system pressure drop but still assumes that this is a singular event not coincident
with any other releases
Relief Case Rate Configuration
Fire 17,345 kg/h 1 x 100% operation
Fire 12,688 kg/h 1 x 100% operation
Fire 17,345 kg/h 1 x 100% operation
Fire 12,688 kg/h 1 x 100% operation
Fire 1,814 kg/h 1 x 100% operation
Fire 1,814 kg/h 1 x 100% operation
Tip P estimated from Kaldair supplied graph
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.39
Line sizes sufficient
Calculated tip P = 50 kPa
Relief Valve Datasheet backpressure
Calculated Backpressure
37-PSV- kPa(a) kPa(a)
1021 102-601 344
1043 102-601 307
1063 102-601 336
1001 102-601 313
62-PSV-
0111 102-601 285
0122 102-601 282
Issues
See 34-033/1
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 23-Jun-00 Checked by MFG Date 15-Aug-00
37-PSV-1043
Z-3702A
Z-3701B
62-PSV-0122
Z-6202A
37-PSV-1063
Z-6202B
Z-3702B
62-PSV-0111
Z-3701A37-PSV-1001
PSV Equipment Protected
37-PSV-1021
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 33 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-056 / G Individual HP Separator Blowdown Case - Line Size Confirmation 01 10-Feb-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system isometric No Rev Given
Total blowdown rate (initial rate) = 41,311 kg/h
Tip P estimated from Kaldair supplied graph
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.66
Line sizes sufficient
Calculated tip P = 33 kPa
Blowdown Valve Rev D1 Datasheet
backpressure
Calculated Backpressure
31-ESV- kPa(a) kPa(a)
7318 551 402
Issues
None
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 23-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-057 / G E-3701 Shell & Tube Side Simultaneous Fire Relief Case - Line Size Confirmation 01 12-Feb-93
Audit Tasks Methodology Consistency X See /1 As Built Key Assumptions
LP Flare system isometric No Rev Given
Considers pressure at end of sub-header (i.e. main header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
Conventional valvesEquipment Protected Set Pressure Relief Case Rate Configuration
E-3701 (SS) 1380 kPag Fire 15,804 kg/h 1 x 100% operation
E-3701 (TS) 780 kPag Fire 2,135 kg/h 1 x 100% operation
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.48
Calculation considers that line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
37-PSV- kPa(a) kPa(a)
1482 102-136 197
1497 102-136 161
Issues
34-057/1 Calculated backpressure exceeds that specified on datasheet for both PSVs
See also 34-033/1
Possible that LP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 23-Jun-00 Checked by MFG Date 15-Aug-00
37-PSV-1497
PSV
37-PSV-1482
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 34 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-058 / G E-6201A/B Tube Side Fire Relief Case - Line Size Confirmation 01 10-Feb-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system isometric No Rev Given
Considers pressure at end of PSV discharge line (i.e. sub-header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
Conventional valves
PSV Relief Case Rate Configuration
62-PSV-
0001A/B Fire 828 kg/h 1 x 100% operation + 1 x 100% Standby
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.22
Line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
62-PSV- kPa(a) kPa(a)
0001A/B 102-601 112
Issues
See 34-033/1
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 23-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-059 / G Comparative Program check of INPLANT Single Phase Simulation vs ESI 01 23-Apr-93
Audit Tasks Methodology X See /1 Consistency As Built Key Assumptions
HP Separator Max Spill-off Case
Key Results
Pressure Drop given by ESI run ~20% less than INPLANT
Velocity given by ESI run 5% max less than INPLANT
Mach Nos. given by ESI run ~10% max less than INPLANT
Probably due to estimated average fluid properties used in ESI runs
Issues
34-059/1 Accuracy of calculations using ESI instead of INPLANT
Audited by AJR Date 23-Jun-00 Checked by MFG Date 15-Aug-00
E-6201A/B (Tube side)
Equipment Protected
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 35 of 42 October 2000
Calculation Description Rev DateNumber /
Calculation Book
34-034 / G 2nd Stage Suction Scrubber B PSV - Network Analysis 02 26-Mar-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system isometric Rev A3
Considers pressure at end of sub-header (i.e. main header pressure) is atmospheric (i.e. that this is a singular event not
coincident with any other releases)
33-PSV-7124 balanced valve - suitability of balanced valve to be confirmed by inst / vendor - datasheet at rev C2, 11-Nov-92
Relief Case Rate Configuration
Backflow 5,080 kg/h 1 x 100% operation
ESI compressible flow analysis sufficient
Key Results
Maximum Mach No. in system = 0.51
Line sizes sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
33-PSV- kPa(a) kPa(a)
7124 102-601 162
Issues
None
Basis for backflow calculation not given (probably NRV failure)
Possible that HP flare isometric was out of date when calc was made however unlikely to effect results significantly (line sizes
used are correct compared to 'As Built' P&ID)
Audited by AJR Date 23-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-064 / G HP Separator Max 2-Phase Relief - Network Analysis 01 07-Jun-93
Audit Tasks Methodology Consistency As Built Key Assumptions
HP Flare system isometric Rev A4
HP Separator Blocked Outlet via PSV-7308A. Total load = 252,372 kg/h (based on 1 max well (30,000 bpd)
+ 1 average well (10,000 bpd) flowing)
Note at front of calc states that Rev 7 of Design Basis gives max well flow of 20,000 bpd + average well i.e. 30,000 bpd total
- calc considers 40,000 bpd flowrate anyway
INPLANT separator module not working therefore calc considers 2-phase flow to flare tip
No PSV datasheets included in calculation. Datasheet for PSV-7308 included in Calc 34-022 is for vapour relief only.
Tip P estimated from Kaldair supplied graph based on 64,273 kg/h vapour
Key Results
Maximum Mach No. in system = 0.31
Line sizes appear sufficient
Relief Valve Datasheet backpressure
Calculated Backpressure
31-PSV- kPa(a) kPa(a)
7308 102-851 646
Issues
None
See also PSV calculation technical audit
Audited by AJR Date 23-Jun-00 Checked by MFG Date 15-Aug-00
33-PSV-7124 D-3302B
PSV Equipment Protected
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 36 of 42 October 2000
Book H General
Book H contains a number of 'Check Print' copies of calculations reviewed in earlier volumes. There are nosignificant comments to record. In addition there a number of un-numbered calculation (all superseded). These 'Check Prints' and un-numbered calculations have not been reviewed in detail.
Calculation Description Rev DateNumber /
Calculation Book
34-001 / H Combined LP/HP KO Drum Sizing (Preliminary) No Rev 31-Jan-91
Audit Tasks Methodology N/A Consistency N/A As Built N/A
Calculation superseded. Not reviewed in detail
Audited by AJR Date 26-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-002 / H HP KO Drum Sizing (Check) No Rev 04-Feb-91
Audit Tasks Methodology N/A Consistency N/A As Built N/A
Calculation superseded. Not reviewed in detail
Audited by AJR Date 26-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-003 / H Flare Boom Length Calculations (Preliminary) No Rev 01-Mar-91
Audit Tasks Methodology N/A Consistency N/A As Built N/A
Calculation superseded. Not reviewed in detail
Audited by AJR Date 26-Jun-00 Checked by MFG Date 15-Aug-00
Calculation Description Rev DateNumber /
Calculation Book
34-004 / H Flare System - Material Balance for Flare UFD 0 25-Mar-91
Audit Tasks Methodology N/A Consistency N/A As Built N/A
Calculation superseded. Not reviewed in detail
Audited by AJR Date 26-Jun-00 Checked by MFG Date 15-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 37 of 42 October 2000
Calculation Description Rev DateNumber
31.35 Relief Valve Calculations - HP Separator C1 Nov '91
Audit Tasks Methodology X see /1,4&5 Consistency X see /2&3 As Built X See below
Four Cases Considered; Fire, Blocked Outlet - Vapour Flow Only, Blocked Outlet - 2 Phase Flow (2 wells flowing),
Gas Blowby From Injection Compressor Suction Scrubber
Key Assumptions
Fire Case
Vessel dimensions: 3.7m x 18.8m T/T
No credit taken for vessel insulation
Blocked Outlet Case - Vapour Flow Only
Flow based 100% Hibernia normal case
Blocked Outlet Case - 2 Phase Flow (2 wells flowing)
2 wells flowing - 1 maximum well and 1 average well (total mass flowrate 207,848 kg/h)
Uses superseded API RP520 method of calculating separate orifice areas for liquid and vapour flow then adding together
Gas Blowby From Injection Compressor Suction Scrubber
Upstream pressure 138 bara
Valve CV = 16 max
Key Results
Results Summarised in table below
Case Relief Orifice Area
Flowrate Required
kg/h in2
Fire Case 38,835 1.55
Blocked Outlet Case - Vapour 227,649 9.38 Governing Case
Blocked Outlet Case - 2 Phase 207,848 3.19
Gas Blowby 34,192 Not Calc'd
Installed PSV orifice area from 'As Built' datasheet 9.6 in2.
Issues
31.35/1 Does 2 phase relief case become the governing case if the calculation new calculation method given
in API RP520, Seventh Edition used?
31.35/2 Flare network analysis for 2 phase case (Calc 34-064 / G) used total load = 252,372 kg/h (40,000 bpd).
31.35/3 Relief & Blowdown Study Report Rev C1 states HP Separator Blocked Outlet (Vapour) relief load is 244,897 kg/h.
31.35/4 The two phase calculation feed vapour / liquid split was abnormally low.
31.35/5 Methodological error in calculation (compared to API RP520 Sixth Edition). The wrong effective pressure was
for the V/L split and property conditions.
A note on the front of calc 34-064 / G states that Rev 7 of Design Basis gives max well flow of 20,000 bpd
+ average well i.e. 30,000 bpd total
HP Separator dimensions used in calc not 'As Built' (3.46m x 17.28m T/T) but this case is not governing therefore of no concern.
Actual installed control valve CV = 0.8 for blowby case.
Audited by AJR Date 07-Aug-00 Checked by MFG Date 16-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 38 of 42 October 2000
Calculation Description Rev DateNumber
31.36 Relief Valve Calculations - MP Separator C1 Nov '91
Audit Tasks Methodology X see /1-4,6-8 Consistency X see /5 As Built X See below
Six Cases Considered; Fire, Blocked Outlet - Vapour Flow Only, Blocked Outlet - 2 Phase Flow (2 wells flowing),
Gas Blowby From HP Separator, Gas Blowby From Test Separators (Individually), Gas Blowby From 3rd Stage Suction Scrubber
Key Assumptions
Fire Case
Vessel dimensions: 4.5m x 23.5m T/T
No credit taken for vessel insulation
Blocked Outlet Case - Vapour Flow Only
Flow based 50% Hibernia, 50% Avalon case
Blocked Outlet Case - 2 Phase Flow (2 wells flowing)
2 wells flowing - 1 maximum well and 1 average well (50% Hibernia, 50% Avalon case)
Uses superseded API RP520 method of calculating separate orifice areas for liquid and vapour flow then adding together
Gas Blowby From HP Separator
Control valve upstream pressure 42.26 bara
Valve CV = 350 max (Revised CV in 1993. Originally 450)
Two LCVs in parallel installed but only one valve fails at any one time
Gas Blowby From Test Separator
Control valve upstream pressure 41.95 bara
Valve CV = 195 max
Gas Blowby From 3rd Stage Suction Scrubber
Control valve upstream pressure 40.70 bara
Valve CV = 16 max
Key Results
Results Summarised in table below
Case Relief Orifice Area
Flowrate Required
kg/h in2
Fire Case 27,241 2.30
Blocked Outlet Case - Vapour 75,227 8.50
Blocked Outlet Case - 2 Phase 88,590 2.22
Gas Blowby - HP Separator 249,332* 30.52* Governing Case
Gas Blowby - Test Separator 115,086 Not Calc'd
Gas Blowby - 3rd Stage Scrubber 10,107 Not Calc'd
* Based on original CV of 450
Installed PSV orifice area from 'As Built' datasheet = 2 x 16 in2 operating.
Issues
31.36/1 Does 2 phase relief case become the governing case if the calculation new calculation method given
in API RP520, Seventh Edition used?
31.36/2 Are 2 x 50% LCVs sufficiently independent?
31.36/3 Methodological error in calculation (compared to AIP RP520 Sixth Edition). The wrong effective pressure was
for the V/L split and property conditions.
31.36/4 The two phase calculation feed vapour / liquid split was abnormally low.
31.36/5 Calculation subsequently superseded but no indication that calculation was subsequently corrected.
31.36/6 The gas blowby cases are methodologically flawed.
31.36/7 The wrong control valve sizing equation is used in the calculation leading to an incorrect relief rate calculated
for the gas blowby from test separator case.
Actual installed HP Separator level control valve CV = 330 for blowby case.
Actual installed 3rd Stage Scrubber level control valve CV = 4.0.
MP Separator dimensions used in calc not 'As Built' (4.1m x 23.5m T/T) but this case is not governing therefore of no concern.
Audited by AJR Date 07-Aug-00 Checked by MFG Date 16-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 39 of 42 October 2000
Calculation Description Rev DateNumber
31.37 Relief Valve Calculations - LP Separator C0 27-Nov-91
Audit Tasks Methodology X see /1&2 Consistency As Built Four Cases Considered; Fire, Gas Blowby From MP Separator, Gas Blowby From Test Separators (Individually),
Gas Blowby From 2nd Stage Suction Scrubber
Key Assumptions
Fire Case
Vessel dimensions: 4.2m x 23.2m T/T
No credit taken for vessel insulation
Gas Blowby From MP Separator
Control valve upstream pressure 12.35 bara
Valve CV = 700 max
Two LCVs in parallel installed but only one valve fails at any one time
Gas Blowby From Test Separator
Control valve upstream pressure 12.04 bara
Valve CV = 195 max
Gas Blowby From 2nd Stage Suction Scrubber
Control valve upstream pressure 11.00 bara
Valve CV = 16 max
Key Results
Results Summarised in table below
Case Relief Orifice Area
Flowrate Required
kg/h in2
Fire Case 14,195 3.28
Gas Blowby - MP Separator 110,874 28.80 Governing Case
Gas Blowby - Test Separator 24,853 Not Calc'd
Gas Blowby - 2nd Stage Scrubber 2,384 Not Calc'd
Installed PSV orifice area from 'As Built' datasheet = 2 x 16 in2 operating.
Issues
31.37/1 Is it possible for the Test Separator manifold to be connected to the LP Separator when operating in high pressure
mode?
31.37/2 Are 2 x 50% LCVs sufficiently independent?
See also 31.36/6
Actual installed MP Separator level control valve CV = 600 for blowby case.
Actual installed 2nd Stage Scrubber level control valve CV = 24.0. No concern as this is not a major relief case.
Audited by AJR Date 07-Aug-00 Checked by MFG Date 16-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 40 of 42 October 2000
Calculation Description Rev DateNumber
31.38 Inlet Line Size Checking for Relief Valves 05-Dec-91
Audit Tasks Methodology X see below Consistency X see /1 As Built X see /1
Key Assumptions
Inlet line equivalent length 100m
Preliminary data used for relief loads and selected orifice areas
Key Results
Relief valve inlet line sizes
Issues
31.38/1 Inlet line sizes should have been recalculated using 'Final' relief data and isometrics.
This calculation has obviously been revised as many PSV inlet line sizes are different to those calculated here.
The data used for this calculation is nearly all out of date. Some relief valve tag numbers have changed and all PSV relieving
capacities and maximum relieving capacities are different on the 'As Built' PSV datasheets. Some PSV set pressures are
also different.
Audited by AJR Date 07-Aug-00 Checked by MFG Date 16-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 41 of 42 October 2000
Calculation Description Rev DateNumber
31.41 Relief Valve Calculations - Oil Separation & Export C1 20-May-92
Audit Tasks Methodology Consistency See below As Built See belowEquipment Considered: E-3103 A/B LP Separator Heaters (HM Side)Key AssumptionsOnly fire case consideredExchanger dimensions: 1.75m OD x 7.431m OL (channel length = 1.1m)Wetted area calc takes into account 15m of 12" pipingPSV set pressure 1380 kPagShell is liquid fullLatent heat of vaporisation = 50 Btu/lbKey ResultsRelief flowrate = 40771 kg/h Required orifice area = 2.36 in2IssuesNone. 'As Built' exchanger has slightly different dimensions (1.175m OD x 7.641m OL) to those used in the calculation but considered insignificant.smaller diameter. Installed orifice area = 2.85 in2.Equipment Considered: D-3104 A/B CoalescersKey AssumptionsOnly fire case consideredCoalescer dimensions: 3.05m ID x 9.75 T/TWetted area calc takes based on LSHHPSV set pressure 700 kPagLatent heat of vaporisation = 415 Btu/lb (as per LP Separator)Key ResultsRelief flowrate = 7214 kg/h Required orifice area = 1.61 in2IssuesNone. Installed orifice area = 2.85 in2.Equipment Considered: E-3104 A/B Crude Product Coolers (HC & CM Side)Key AssumptionsOnly fire case consideredExchanger dimensions: 2.61m x 4.4m x 1.18mHC side PSV set pressure 700 kPagCM side PSV set pressure 1500 kPagWetted area calc for HC side uses 50% total surface areaWetted area calc for CM side uses 50% total surface areaLatent heat of vaporisation (HC) = 415 Btu/lb (as per LP Separator)Latent heat of vaporisation (CM) = 817.3 Btu/lb (treated as water)Key ResultsHC Side: Relief flowrate = 1827 kg/h Required orifice area = 0.41 in2CM Side: Relief flowrate = 928 kg/h Required orifice area = 0.15 in2IssuesNone. 'As Built' exchanger has slightly different dimensions (2.877m x 4.4m x 1.359m) to those used in the calculation but considered insignificant. Installed orifice area, HC side = 0.503 in2, CM side = 0.196 in2.Equipment Considered: E-3701 A/B Crude Recirculation Heater (HC & HM Side)Key AssumptionsOnly fire case consideredExchanger dimensions: 0.813m OD x 4.82m OL (channel length = 1.299m)Wetted area calc takes into account 20m for each sideShell is liquid fullHC side PSV set pressure 740 kPagHM side PSV set pressure 1460 kPagWetted area calc for HC (tube) side uses channel surface areaWetted area calc for HM (shell) side uses shell surface areaLatent heat of vaporisation (HC) = 182.1 Btu/lbLatent heat of vaporisation (HM) =50 Btu/lbKey ResultsHC Side: Relief flowrate = 4866 kg/h Required orifice area = 0.33 in2HM Side: Relief flowrate = 15804 kg/h Required orifice area = 1.13 in2IssuesNone. However, HC Side 'As Built' PSV datasheet has relief load = 2135 kg/hr and installed orifice area of 0.785 in2. This isequivalent to using the same properties in this calc as used for the Coalescer and LP Separator calculation (I.e. latent heat of vap. = 415 Btu/lb anf MW= 37.68).There is an error in the calculation as the orifice area req'd calc uses a flowrate in kg/h instead of lb/h. Resulting true requiredorifice area req'd should be = 0.74in2. As the installed orifice area is greater than the true required as given above there is no concern.Equipment Considered: Z-3701 A/B / Z-3702 A/B Crude Oil Pig Launcher / ReceiverKey AssumptionsOnly fire case consideredDimensions Launcher: 547.7 / 706mm ID x 7200mm OL
Receiver: 547.7 / 706mm ID x 11400mm OL Wetted area calc takes into account 15m of 12" pipingPSV set pressure 4500 kPagEquipment is liquid fullLatent heat of vaporisation = 50 Btu/lbKey ResultsLauncher: Relief flowrate = 12688 kg/h Required orifice area = 0.48 in2Receiver: Relief flowrate = 17345 kg/h Required orifice area = 0.66 in2IssuesNone. 'As Built' equipment has slightly different dimensions to those used in the calculation but considered insignificant.Installed orifice area = 0.785 in2 for both pieces of equiment.
Audited by AJR Date 07-Aug-00 Checked by MFG Date 16-Aug-00
8266-HIB-TN-C-0001 Appendix I Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 42 of 42 October 2000
Calculation Description Rev DateNumber
31.43 Gas Blowby (Checking Capacity of Downstream System for Gas Blowby 22-Nov-92
from HP to MP Separator and MP to LP Separator)
Audit Tasks Methodology X see /1-3 Consistency See below As Built See below
Gas Blowby From HP to MP Separator
Key Assumptions
MP Separator PSVs orifice area is 2 x 16 in2 operating.
MP Separator spill off valve CV = 600
MP Separator spill off valve capacity during blowby case is 94,500 kg/h
Both 50% upstream LCVs fail at the same time
Key Results
Total relief capacity of PSVs and spill-off valve operating together is 365,594 kg/h
If HP Separator level control valves have a CV of 329.8 each, the total relief load if both valves fail open (365,594 kg/h) can
be handled by the installed PSVs and spill off valve operating together.
Issues
31.43/1 This calculation considers both upstream LCVs fail open simultaneously. This scenario is not considered in the
Relief & Blowdown Study Report Rev C1 (or in any other calculations reviewed), nor is the platform designed
for its affects.
Note that the 'As Built' HP Separator LCVs CV = 330 each , 'As Built' spill-off valve CV = 600 and 'As Built' MP Separator PSVs
orifice area is 2 x 16 in2 operating.
The maximum relief load given above (365,594 kg/h) is not considered in the Relief & Blowdown Study Report Rev C1 as
the governing HP flare relief case (HP Separator blocked outlet @ 244,897 kg/h) and is not considered in the flare hydraulic calculations
Gas Blowby From MP to LP Separator
Key Assumptions
LP Separator PSVs orifice area is 2 x 16 in2 operating.
LP Separator spill off valve CV = 4145
LP Separator spill off valve capacity during blowby case is 86,713 kg/h
Both 50% upstream LCVs fail at the same time
Key Results
Total relief capacity of PSVs and spill-off valve operating together is 194,875 kg/h
If MP Separator level control valves have a CV of 550 each, the total relief load if both valves fail open (194,875 kg/h) can
be handled by the installed PSVs and spill off valve operating together.
Issues
31.43/2 This calculation considers both upstream LCVs fail open simultaneously. This scenario is not considered in the
Relief & Blowdown Study Report Rev C1 (or in any other calculations reviewed), nor is the platform designed
for its affects.
31.43/3 The calculation identifies the failure of the spillover valve (open) could lead to a relief rate which is higher than
the current design.
Note that the 'As Built' LP Separator LCVs CV = 600 each , 'As Built' spill-off valve CV = 4145 and 'As Built' MP Separator PSVs
orifice area is 2 x 16 in2 operating. 'As Built' total relief load if calculated using the same method as given here will be higher
than 194,875 kg/h as the installed LCV CV = 600 (not 550).
The maximum relief load given above (194,875 kg/h) is not considered in the Relief & Blowdown Study Report Rev C1 as
the governing LP flare relief case (MP to LP Separator gas blowby @ 110,874 kg/h) and is not considered in the
flare hydraulic calculations
Audited by AJR Date 07-Aug-00 Checked by MFG Date 16-Aug-00
APPENDIX II
STAGE 2 PROPOSAL
Flare System Revalidation Study - Stage 2 Proposal Rev C (27 pages)
8266-HIB-TN-C-0001 Appendix II Revision: B/tt/file_convert/55276c7749795994178b46d5/document.doc Page 1 of 1 October 2000