HIGH INTENSITY DRUG TRAFFICKING AREA
FINANCIAL MANAGEMENT DATABASE PROJECT
INTRODUCTION:HIDTA Overview Congress established the High Intensity Drug Trafficking Area (HIDTA) Program to operate under the direction of the Office of National Drug Control Policy (ONDCP) by the Anti-Drug Abuse Act of 1988 (P. L.100-690, November 18, 1988) and the ONDCP Reauthorization Act of 1998.
Resources provided to the HIDTA Program have grown from $25 million in Fiscal Year 1990 to $206 million in FY 2001.
The FY 2001 HIDTA Program coordinated the efforts of a total of 941 local, 170 state and 35 Federal law enforcement agencies and 60 other agencies participating in 482 HIDTA-funded initiatives
INTRODUCTION:Project Background
The HIDTA Financial Management Database Project will give the HIDTA program a single national financial management system for all HIDTA locations.
Benefits include providing one set of financial records for all HIDTA participants, a standardized process for budget development and programming of funds, standardized reporting, ad-hoc reporting, and will provide better financial communication across the organization.
PROJECT ANALYSIS:
The Problem…
Each HIDTA office develops and manages its own budget separate from the national financial records.
The records maintained by the national HIDTA program office frequently differ from the records tracked by each individual HIDTA office.
32 HIDTA offices has each have a financial manager who spends at least 8 hours per week fixing discrepancies between local and national numbers.
PROJECT ANALYSIS:
The Objectives…
1. Reduce errors and improve the accuracy of HIDTA financial data.
2. Reduce the time and cost of reconciling HIDTA budgets by integrating all HIDTA financial records into one system.
3. Speed up the budgeting and reprogramming approval processes.
4. Improve financial reporting and managerial decision making capabilities.
PROJECT ANALYSIS:
In Scope…
All end-user interaction via web based interface
Custom HIDTA input form
Custom HIDTA reports – specific to program
Digital approval process equal to current process
Web-based remote management of product
Budgeting Process
Automated management of Grants Administration
PROJECT ANALYSIS:
Out of Scope…
Expenditure Tracking
Wide Area Network Design / Implementation
GroupWare
RETURN ON INVESTMENT:Expected Benefits
Return on Investment Analysis
Financial Management Costs Under Current System
# of personnel
Estimated Total Hours
per Month Each Hourl Rate
Total Cost per
MonthTotal Cost
per YearReconciling local and national figures 32 32 $45 $46,080 $552,960Other financial processes with curren system 32 48 $45 $69,120 $829,440
Total Annual Cost: $1,382,400
Financial Management Savings Under NEW System
Number of
personnel
Estimated Total Hours
per Month Each Hourl Rate
Total Cost per
MonthTotal Cost
per YearReconciling local and national figures 32 0 $45 $0 $0Other financial processes with curren system 32 12 $45 $17,280 $207,360
Total Annual Cost: $207,360
Total Annual Savings: $1,175,040
Financial Management Database Project Estimated Costs
Personnel Cost
PositionTotal Project
HoursHourly
Rate Total CostProject Manager 1016 $50 $50,800Project Team (5 people) 1300 $45 $58,500Contractors (2 people) 616 $250 $154,000Project IT Team (5 people) 1360 $45 $61,200Project Trainers (2 people) 160 $30 $4,800HIDTA Financial Managers (32 people) 1280 $45 $57,600
Total: $386,900
Materials CostItem Quantity Unit Cost Total CostCore Software (1000 users and support) 1 $500,000 $500,000System Server 4 $10,000 $40,000
Total: $540,000
Services CostItem Quantity Unit Cost Total CostTrain the Trainer (service per person) 3 $2,000 $6,000Estimated Travel CostsContractor Travel (weeks) - 2 people 20 $1,000 $20,000Travel to training (weeks) 32 people 32 $1,000 $32,000
Total: $58,000
Total Estimated Project Cost: $984,900
RISK MANAGEMENT:
Risk Assessment…
Users might not buy into the system after rollout
System software could be dropped by vendor
System software might not work as advertised
Could be more expensive to manage than planned
RISK MANAGEMENT:
Risk Control…
Training, support, and financial manager empowerment
Product is standards based and code is available
A third party could modify and/or support
Could contract with 3rd party for less expensive support
PROJECT IMPLEMENTATION:Timeline and Work Breakdown Structures…
Estimated 127 working days to complete entire project.
Core team of 15 people – 13 HIDTA, 2 contractors
Design phase 60 working days to complete.
Development phase 44 working days to complete.
Implementation phase 23 working days to complete
Task Name Duration Start Finish Predecessors
1 HIDTA Financial Management Database Project Summary 127 days 8/2/2004 8:00 1/25/2005 17:00
2 Design Phase 60 days 8/2/2004 8:00 10/22/2004 17:00
3 Develop System Design 60 days 8/2/2004 8:00 10/22/2004 17:00
4 Develop System Specs 60 days 8/2/2004 8:00 10/22/2004 17:00
5 Develop Training Plan 30 days 8/2/2004 8:00 9/10/2004 17:00
6 Develop System Security Plan 60 days 8/2/2004 8:00 10/22/2004 17:00
7 Development (Build) Phase 44 days 10/25/2004 8:00 12/23/2004 17:00
8 Build System Prototype 19 days 10/25/2004 8:00 11/18/2004 17:00
9 Install Server Hardware 2 days 10/25/2004 8:00 10/26/2004 17:00 3,4,6
10 Install Server Software 5 days 10/27/2004 8:00 11/2/2004 17:00 9
11 Load Sample Data 2 days 11/3/2004 8:00 11/4/2004 17:00 10
12 Configure System Software 10 days 11/5/2004 8:00 11/18/2004 17:00 11
13 Test system Prototype 10 days 11/19/2004 8:00 12/2/2004 17:00 12
14 Training 10 days 12/3/2004 8:00 12/16/2004 17:00
15 Train the Trainer training 5 days 12/3/2004 8:00 12/9/2004 17:00 13
16 Train all HIDTA Financial Managers 5 days 12/10/2004 8:00 12/16/2004 17:00 15
17 System Acceptance Test 5 days 12/17/2004 8:00 12/23/2004 17:00 16
18 Implementation Phase 23 days 12/24/2004 8:00 1/25/2005 17:00
19 Import Historical Data 3 days 12/24/2004 8:00 12/28/2004 17:00 17
20 Define/Build Production Input Forms 5 days 12/29/2004 8:00 1/4/2005 17:00 19
21 Define/Build Production Reports 5 days 12/29/2004 8:00 1/4/2005 17:00 19
22 Implement Security 2 days 12/24/2004 8:00 12/27/2004 17:00 17
23 Deploy at each HIDTA office 10 days 1/5/2005 8:00 1/18/2005 17:00 20,21
24 Develop Lessons Learned Report 5 days 1/19/2005 8:00 1/25/2005 17:00 23
25 Project Completion 0 days 1/25/2005 17:00 1/25/2005 17:00 24
ID
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
HIDTA Financial Management Database Project Summary 127 days
Design Phase 60 days
Develop System Design
Develop System Specs
5 Develop Training Plan
Develop System Security Plan
Development (Build) Phase 44 days
Build System Prototype 19 days
Install Server Hardware
Install Server Software
Load Sample Data
Configure System Software
Test system Prototype
Training 10 days
Train the Trainer training
Train all HIDTA Financial Managers
System Acceptance Test
Implementation Phase 23 days
Import Historical Data
Define/Build Production Input Forms
Define/Build Production Reports
22 Implement Security
Deploy at each HIDTA office
Develop Lessons Learned Report
Project Completion 1/25
28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 6 13 20Mar '04 Apr '04 May '04 Jun '04 Jul '04 Aug '04 Sep '04 Oct '04 Nov '04 Dec '04 Jan '05 Feb '05 Mar '05
Critical Path Gantt Chart
FINAL ANALYSIS:
Methods of Evaluation…
Project completed on time and on budget.
Documented use by all financial analysts.
Budget reconciliation time eliminated.
Reduce reprogramming processing time from 3 days to 1
Reduce budget approval process from 5 months to 3
HIGH INTENSITY DRUG TRAFFICKING AREA
FINANCIAL MANAGEMENT DATABASE PROJECT