Himeji Number 2 Goes Commercial

Embed Size (px)

Citation preview

  • 7/24/2019 Himeji Number 2 Goes Commercial

    1/13

    Himeji No.2 goes commercial

    The new M501J gas turbine combined cycle units at Himeji No.2 havesuccessfully started commercial operation and are demonstrating world-

    class levels of efficiency.

    Aerial view of Himeji No.2. The power station is the largest thermal power plant owned by Kansai

    Electric.

    Five years ago the Kansai Electric Power Company (Kansai Electric) started a large-

    scale project to replace Himeji No.2 Thermal Power Station with what it claimed would

    be the worlds most efficient combined cycle plant featuring Mitsubishi Hitachi Power

    Systems (MHPS) 501J gas turbines.

    The last unit of this environment friendly project, which targeted reduction of greenhouse

    gas emissions while securing a competitive power supply for the Kansai area, began

    commercial operation earlier this year.

  • 7/24/2019 Himeji Number 2 Goes Commercial

    2/13

    The new combined cycle plant:

    Has recorded an electrical efficiency over 60 %

    Enables about 30% CO2 and 85% NOx reduction compared with the original plant

    Will deliver savings in the order of $520 million per year compared with the old plant.

    With the high price of gas in Japan typically being four to five times that in the US

    high efficiency has long been a pursuit of Japanese companies. Accordingly, when

    Kansai Electric, took the decision to replace the Himeji No.2 Thermal Power Station, it

    opted for state-of-the-art technology.

    Although Kansai Electric could not foresee future events, the decision to opt for the most

    efficient technology proved to be visionary. Since the disaster at Fukushima, which

    forced the closure of the countrys entire nuclear fleet, Japan has had to rely on thermal

    generation and expensive imported fuel. This had made Himeji 2 an even more

    important asset in Kansai Electrics generating portfolio.

    MHPS installed the first 501J at its T-Point station, which is its validation plant. MHPS

    owns T-Point and sells the power output to Kansai Electric. Prior to Japans nuclear

    shutdown, this plant used to predominantly operate in cycling mode, meeting peak

    demand for Kansai. Since Fukushima, however, it has been running more continuously

    to help ease the tight supply in the region.

    Plant configuration

    Himeji No.2 power station is the largest thermal power plant owned by Kansai Electric.

    The original plant, built in 1963, was composed of six conventional units with a total

    output of 2550 MW. These units were originally commissioned and operated with crude

  • 7/24/2019 Himeji Number 2 Goes Commercial

    3/13

    or heavy oil but were later converted to natural gas. Two of the original units are still in

    operation.

    The new Himeji No.2 Thermal Power Station is a state-of-the-art combined cycle plant

    comprised of six single-shaft blocks rated 486.5 MW each (at an ambient of 4C) for a

    total capacity of 2919 MW. Each block consists of one M501J gas turbine rigidly

    coupled to a SRT-50 single reheat steam turbine.

    Because the gas and steam turbine are linked in a single shaft arrangement without a

    clutch, the gas turbine and steam turbine are ramped up at the same time.

    All six combined cycle blocks have started commercial operation with high reliability

    and, according to MHPS, are demonstrating superior performance with a net efficiency

    in excess of 60%.

    High efficiency GT

    The main contributor to this high efficiency is the M501J gas turbine and its high turbine

    inlet temperature.

    The M501J gas turbine has been designed with a turbine inlet temperature of 1600C

    (2912F) by integrating the proven component technologies used in the 1400C F-series

    and the 1500C G series turbines. The M501J also benefited from the development of

    key technologies for the national 1700C-class gas turbine project.

    The turbine has been carefully developed over a number of years. Operating tests of the

    first M501J gas turbine started in February 2011 at Machinery Works T-Point

    demonstration combined-cycle power plant in Takasago. The tests proceeded as

    scheduled with the first spin-up on February 2nd followed by first ignition soon after. The

  • 7/24/2019 Himeji Number 2 Goes Commercial

    4/13

    inlet temperature reached 1600C on the seventh start-up. The unit went commercial on

    July 1, 2011.

    The design of the M501J gas turbine is based on proven F- and G-series features:

    The compressor shaft-end drive connected to the generator reduces the thermal

    expansion and eliminates the need for a flexible coupling.

    The rotor has a two-bearing structure to support the compressor and turbine ends.

    An axial flow exhaust structure is used to optimize the combined-cycle plant layout.

    The rotor structure has bolt-connected disks with the torque pin in the compressor

    rotor and a disc with curved coupling in the turbine rotor to ensure reliable torque

    transmission.

    The M501J turbine section is an axial-flow, four-stage, high-load, high-performance

    turbine.

    Row-1 to row-4 rotating blades and rows 1-3 stationary vanes are air-cooled. Unlike the

    row-4 blades in the G-series turbine, which are uncooled, those in the J-series turbine

    are cooled to cope with the higher inlet temperature. As with the F- and G-series gas

    turbines MGA1400 (Mitsubishi Gas Turbine Alloy) is used for the rotating blades, while

    the vanes are made of MGA2400. The rows 1-3 blades are made of DS (directionalsolidified) superalloy.

  • 7/24/2019 Himeji Number 2 Goes Commercial

    5/13

    Exterior view of the new plant. The power station is a state-of-the-art combined cycle plant

    composed of six single-shaft blocks each rated at 486. !".

    The cooling structure was improved for the F-series and again for the G-series turbine,

    and the J-series uses high-performance film cooling and advanced thermal barrier

  • 7/24/2019 Himeji Number 2 Goes Commercial

    6/13

    coating (TBC) developed in the national project, aimed at developing a 1700C

    machine.

    The M501J compressor is designed as an axial flow type with a pressure ratio of 23:1; it

    was based on the technology used in the H-series compressor, which has a pressure

    ratio of 25:1. Three-dimensional (3D) advanced design techniques were used to

    improve the performance and reduce the shockwave loss in the initial stages and

    frictional loss in the intermediate and final stages.

    In addition, bleeding was used in the low-, middle-, and high-pressure stages during

    compressor start-up to suppress rotating stall on start-up, and the partial-load

    performance of the combined cycle was improved, by controlling the inlet guide vane

    (IGV) and three-stage variable stator vanes.

    M501J cross-sectional view. The t#rbine section is an axial-flow$ fo#r-stage$ high-load$ high-

    performance t#rbine. The compressor is designed as an axial flow type with a press#re ratio of %&'(.

    The M501J combustor is based on the proven steam cooling system used in G-series

    gas turbines. MHPS implemented steam cooling mainly to enable operation at high

    temperatures with reasonable NOx emissions.

  • 7/24/2019 Himeji Number 2 Goes Commercial

    7/13

    While other manufacturers have largely abandoned steam cooling, MHPSs has

    extensive, positive experience with the technology. The company has millions of

    operating hours on the largest steam cooled fleet in the market with very good reliability.

    Third parties have validated MHPSs availability and reliability figures. Operational data

    from the M501G, which also uses steam cooling, has been collected by Strategic Power

    Systems Inc (SPS) since 2009 and reported through the Operational Reliability Analysis

    Program (ORAP) for verification. According to the data, the M501G fleet has

    demonstrated a five-year reliability average of 98.8 per cent.

    MHPSs steam cooling technology is different to other OEMs, where the GT is started up

    using air cooling and transferred to steam cooling under part-load conditions. In order to

    prevent the associated thermal shock, MHPS steam cooling is applied prior to firing the

    engine and the completion of a warm-up sequence is a requirement for start-up.

    M501J sinle-shaft confi!ration. Each block consists of one !)(* gas t#rbine rigidly co#pled to

    a +,T-) single reheat steam t#rbine. eca#se the gas and steam t#rbine are in a single shaft

    arrangement witho#t a cl#tch$ the gas t#rbine and steam t#rbine are ramped #p at the same time.

    This warm-up sequence is common with steam turbines to prevent condensate water

    ingestion. The warm-up sequence starts automatically and the plant can be started

    once all the condensate is removed from the line and the steam is

    superheated.

  • 7/24/2019 Himeji Number 2 Goes Commercial

    8/13

    Although this means it takes longer to start the gas turbine, there is less thermal shock,

    which improves reliability. While some argue the requirement for an auxiliary boiler

    MHPS does not see this as an issue, as an auxiliary boiler is usually needed in thesteam turbine seals of modern plants to start quickly.

    Compared with conventional air-cooling, this start-up sequence will add perhaps five

    minutes to start-up (time to gas turbine ignition) from a hot-start condition and around 30

    minutes from a warm start. If the machine is cold, it would add about 40 minutes.

    Although the turbine inlet temperature is increased from 1500C in the G-series to

    1600C in the J-series, the subsequent rise in nitrogen oxide (NOx) emissions are

    limited through the use of low-NOx technologies by improving the combustion nozzle for

    more homogeneous mixing of fuel and air and reducing the local flame temperature in

    the combustion area.

    Bottoming cycle

    While the efficiency of the gas turbine is important, it is also essential to optimize thebottoming cycle to achieve the high combined cycle efficiency that has been recorded at

    Himeji No.2.

    If the vacuum in the condenser is not efficient or the exhaust ducts from the gas turbine

    to the HRSG are not optimized etc., the end result is a relatively low combined cycle

    efficiency.

    Notably, the steam turbine is a big contributor to the overall combined cycle efficiency.

    The state-of-the-art SRT 50 steam turbine was designed to operate with a condenser

    vacuum of 96.3 kPa and features 50-inch last stage steel blades that result in large

    annular area for high efficiency and large capacity.

  • 7/24/2019 Himeji Number 2 Goes Commercial

    9/13

    This new large-capacity, single-casing reheat turbine features other advanced

    technologies such as high-efficiency reaction blade, welded rotor, advanced seals and

    high performance bearings developed to achieve higher efficiency, and more compactdesign.

    "inle-casin steam t!r#ine.The steam t#rbine is a big contrib#tor to the oerall combined cycle

    efficiency. The )-inch last stage steel blades res#lt in large ann#lar area for high efficiency and

    large capacity

    Construction

    The optimized bottoming cycle and high efficiency gas turbine has led to a plant that has

    the highest efficiency in Kansai Electrics fleet. Since startup, the units have recorded

    over 60% efficiency at ambient conditions, thus easing the tight energy situation.

  • 7/24/2019 Himeji Number 2 Goes Commercial

    10/13

    In order to help mitigate the current energy shortage, the construction and

    commissioning schedule of the new Himeji No.2 plant was carefully modified to expedite

    the Commercial Operation Date (COD) of each unit from its original schedule.

    The Table (see page 17) shows the contractual and actual COD dates of the first four

    and the subsequent two.

    First gas turbine shipment to Himeji No.2. The accumulated operating hours of Unit No.1 is over

    16 000 hours as of June 2015.

    The original plan contemplated the decommissioning of the existing Units 5 and 6 prior

    to the installation of the new Units 4 to 6. However, due to the critical electricity supply

    caused by the earthquake, the removal of the existing Units 5 and 6 was postponed.

    The new units were constructed in the area made available by the removal of Units 1

    through 3. This simultaneous removal and construction combined with the large-scale of

  • 7/24/2019 Himeji Number 2 Goes Commercial

    11/13

    the project in a fairly congested industrial area involved very complex planning and

    execution.

    Existing facilities, notably the water intake/discharge infrastructure, were used by both

    the existing and the newly erected units.

    Close communication and cooperation of several teams involving mechanical, electrical,

    I&C, and other departments prevented unintended interference connecting piping and

    many other major activities in the existing and new units. Careful attention was paid to

    avoid impacting on the operation of the existing units.

    The Himeji No.2 Power Station was conceived prior to the earthquake and tsunami that

    hit Japan in March 2011. In an effort to alleviate the difficult power supply situation in the

    Kansai area, Kansai Electric and its suppliers initiated an aggressive acceleration

    program that accelerated the COD of the first four units by two to four months and eight

    months for the last two remaining blocks. This was especially important to meet the high

    demand for electricity during the summer/winter peaks.

    The newly installed units have operated continuously at base load (approximately 486.5

    MW at site condition) with very good reliability since startup. The accumulated operating

    hours of Unit No.1 is over 16 000 hours as of June 2015.

  • 7/24/2019 Himeji Number 2 Goes Commercial

    12/13

    Internal view of the turbine hall.The newly installed combined cycle units have operated

    continuously at base load (approximately 486.5 MW at site conditions).

    Environment and economics

    The plants high efficiency has enabled about 30% CO2 and 85% NOx reduction

    compared with the original plant. In addition, the amount of warm water discharged is

    about 40% lower, thus reducing the ecological impact of the plant on the bay ecosystem.

    The vastly improved cycle efficiency results in substantial fuel cost savings. The new

    high efficiency combined cycle plant translates into savings in the order of $520 million

    per year compared with the old plant (42% efficiency).

  • 7/24/2019 Himeji Number 2 Goes Commercial

    13/13

    Even when compared with current technology, the savings are significant. Compared to

    combined cycle plants based on F-Class (54% efficiency) and assuming the same

    power output, the estimated saving is $253 million per year.

    Looking forward

    MHPS has sold 38 M501J turbines with 17 already in operation.

    In addition to those in Japan, it is operating units in Korea. The company has sold six in

    North America, with the first unit in Oklahoma scheduled to begin commercial operation

    in 2017.

    MHPS is confident of the M501Js performance and its place in the market based on the

    ability of T-Point plant to detect and correct typical prototype issues before a new

    machine goes to a client. The ability to do this is a big contributor to the high reliability of

    the fleet.