HiRadMat : report from WG2&3 – WANF dismantling. Agenda. Worksite: activities in progress TNC cleaning completed Beam line dismantling TCX block removal Cooling & Ventilation issues Cabling issues IEFC workshop talk. Worksite : activities in progress ( W3,4,5). - PowerPoint PPT Presentation
Citation preview
HiRadMat : report from WG2&3 – WANF dismantling
February 4, 2010S. Evrard
1
• Worksite: activities in progress– TNC cleaning completed– Beam line dismantling– TCX block removal
• Cooling & Ventilation issues• Cabling issues• IEFC workshop talk
Agenda
Worksite : activities in progress (W3,4,5)
February 4, 2010S. Evrard
2 TNC cleaning completed (ENDEL & DG/SCR)
Cleaning of good quality Smear tests taken where contamination was the highest: reduction by a 10 factor
(all smear tests < 1Bq/cm2 = contamination level)Dosimetry below estimates (collective dose 2.2 mSv where 2.8 was estimated)
0200400600800
10001200
day 1
day 2
day 3
day 4
day 5
Staff 1 (µSv)
Staff 2 (µSv)
staff 3 (µSv)
Estimate (µSv)
February 4, 2010S. Evrard
3
• 2 magnets, many beam monitors, He station, VAC pipes removed.
• DIMR level 2 written prior to intervention: EDMS 1058846
• Collective dose around 500 µSv (mechanics + transport)
• Magnets recuperated, remaining stuff as radioactive waste
Beam line dismantling (Michael Lazzaroni & DG/SCR)
Worksite : activities in progress (W3,4,5)
February 4, 2010S. Evrard
4
• Automatic hook available: movie• Shielded forklift ready (dose rate reduced
by a factor 5 !)• Blocks removed and stored in TT61• Next steps under study (TI2 line is a big
constraint on handling procedure)
TCX blocks removal (Serge Pelletier, DG/SCR)
Worksite : activities in progress (W3,4,5)
Cooling & Ventilation issues
• Cooling stationWater contaminated waste management to be defined by DG/SCR
• Ventilation unitUnit in TA7 definitely out of order dismantling
Smear tests taken in air ducts
Reinforce air tightness of two existing doors (no way to install a new one due to crane garland)
February 4, 2010
5
S. Evrard
February 4, 2010S. Evrard
6
• Remove old cables (DC + signal) from TNC cable trays up to patch panel in TA7
• Make room in cable trays from patch panel to BA7 for new routing of about 10 DC cables
• Work to be performed during LHC technical stops
Cabling issues
BA7TNC
IEFC workshop on Feb. 11
February 4, 2010S. Evrard
7
• Project overview (goals, location, Project organization)• Beam line (design, …)• WANF dismantling (RP survey, scanning, crane repair ,
cleaning, WANF & T1 dismantling,…)• Irradiation area (access, CV, RP monitoring, dump design)• Schedule (critical items, critical path)• Operation (beam time and user handling)• Conclusions
OUTLINE