21
Dept of the Premier and Cabinet Mining Regulation Branch HMCV Meeting – Air, Rain water tanks, Noise, Blasting June 2017 Andrew Querzoli – Deputy Director – Mining Assessments Nathan Zeman – Principal Mining Assessment Officer

HMCV Meeting –Air, Rain water tanks, Noise, Blasting …€¢ Tenement Holder must offer to test tanks ... DSD PPT_blue_16x9_master PowerPoint Presentation Author: Peter Davis Keywords:

  • Upload
    ngotu

  • View
    214

  • Download
    1

Embed Size (px)

Citation preview

Dept of the Premier and CabinetMining Regulation Branch

HMCV Meeting –Air, Rain water tanks, Noise, BlastingJune 2017

Andrew Querzoli – Deputy Director – Mining AssessmentsNathan Zeman – Principal Mining Assessment Officer

2Department of State Development

Presentation Overview

1. Background

2. Air Quality

3. Rainwater tank testing

4. Noise

5. Blasting

3Department of State Development

Relevant Government Reports and Presentations

PEPR presentation to HMCV - 11 April 2016

Available on DPC Website: http://www.minerals.statedevelopment.sa.gov.au/mining/mines_and_quarries/hillside_project

Mining Lease Assessment Report

Mining Tenement Documents

4Department of State Development

Two Stage Mining Assessment Process

Apply for Mining Lease by

submitting a Mining Proposal

(s34 / s35)

Public Statutory Consultation on Mining Proposal

(s35A)

DPC Assessment of Environmental Impacts from Mining Proposal

and Consultation(s34 / s35)

Lease granted with conditions and outcomes to be

achieved in PEPR or refused(s34 / s35)

Approval of Program for Environment

Protection and Rehabilitation

(PEPR)

Mining Operations

can commence

Stage 1 – Mining Lease – Completed Stage 2 - PEPR

Operations can commence subject to:1) Other permits and licences2) Access to Land3) Native Vegetation Legislation4) If required, payment of a Bond

Purpose:- Grant of mineral tenure and development approval

Purpose:- Operational approval

5Department of State Development

Stage 2 – The PEPROperational approvalThe purpose of the PEPR is to provide information demonstrating requirements of the lease can be met, and sets out the strategies to achieve the environmental outcomes determined through the lease application process.

PEPR must include:• Description of operations, mining, rehabilitation and closure plans• Environmental Outcomes (level of impact) including completion outcomes• Measures for achieving the Environmental Outcomes• Measurement Criteria (Operations & Completion) and Monitoring Plans• Leading Indicator criteria (where applicable)• Results of Consultation• Consideration of Lease conditions• Operator Capability• Calculation of the max. rehabilitation liability to inform the Bond

Key considerations in a PEPR assessment:• Does the evidence provided in the PEPR demonstrate the:

- Effectiveness of control measures for ensuring achievement of the approved outcomes (level of impact)- Effectiveness of criteria in measuring the approved outcomes (level of impact)?- Operator capability to implement the measures and management plans?

6Department of State Development

Government requirements for a PEPR

Government requirements for PEPR’s for Mining Metallic Minerals are set out through the Ministerial Determination (MD005) and Guideline (MG2b).

Available on DPC Website: http://minerals.statedevelopment.sa.gov.au/knowledge_centre

MD005 MG2b

7Department of State Development

Air Quality

Environmental Outcomes from Lease:

1) No impacts to public health and public nuisance2) No loss of abundance or diversity of native vegetation3) No impacts to agricultural productivity

8Department of State Development

Air Quality

Monitoring (Measurement Criteria) from Lease:1) Public health

a) PM 10 – dust in air that is less than 10 micrometres in sizeb) PM 2.5 – dust in air that is less than 2.5 micrometres in sizec) Chemical and Toxicological analysis of dust

2) Public nuisancea) Total Suspended Particulate Matter (TSP)b) Total Dust Deposition (TDD)c) Directional Dust Deposition (DDD)

3) Meteorological Monitoring

9Department of State Development

Air Quality

Monitoring (Measurement Criteria) from Lease:1) Public health

a) PM 10 < 50 ug/m3 as a 24 hour average (includes background)b) PM 2.5 < 25 ug/m3 as a 24 hour average (includes background)

2) Public nuisancea) Total Suspended Particulate Matter (TSP)

< 120 ug/m3 for all 24 hour periods< 90 ug/m3 for all 12 month periods

b) Total Dust Deposition (TDD)< 2 grams / m2 / month (mine contribution)< 4 grams / m2 / month for all 12 month periods (includes background)

10Department of State Development

Air Quality

Reporting requirements from Lease:

1) Real time monitoring data to be reported on the Internet for:a) PM 10b) PM 2.5c) Meteorological data

11Department of State Development

Air Quality

Strategies from Lease for Rex to Address in PEPR:1) “Undertake continuous dust and meteorological monitoring to inform decisions

for operational response and contingency measures to be implements to prevent exceedance of compliance criteria”

2) “Progressive rehabilitation and stabilisation of disturbed areas …”

Compliance from Lease:1) “In the event that monitoring shows …. a breach, the tenement holder must

immediately cease the activity which resulted in the breach”

12Department of State Development

Rainwater Tank Testing

• Tenement Holder must offer to test tanks

• Then test tanks for those who accept the offer

• Report results against Aust. Drinking Water Guidelines

• 4km based on location in relation to nearest communities

• Compliance with Lease condition is minimum legislation requirement

13Department of State Development

Rainwater Tank Testing

• March 2015 – Rex offered to undertake rainwater testing

• This satisfied Condition 8.1

• The PEPR must include details about how this condition has been or will be complied with

14Department of State Development

Noise

• EPA Environment Protection (Noise) Policy 2007 sets noise limits based on the land uses (zoning) in the relevant Development Plan

• Council zoning at the time of lease grant applies• Lease sets the noise criteria to be achieved at receptors

15Department of State Development

Noise Monitoring (Criteria)

• Noise measurements must follow procedures in the EPA Guidelineshttp://www.epa.sa.gov.au/data_and_publications/standards_and_laws/environment_protection_noise_policy

• Independent acoustic engineer report on annoying characteristics

• Adjust noise measurements if annoying characteristics are present

• Noise can be measured ‘for or at’ sensitive receptors

• Monitor noise on a continuous basis, and report noise and meteorological data in real time on a public website

16Department of State Development

Noise strategies – 6th Schedule – Condition #7

• Best practice is expected

• As a minimum, implement the mitigation strategies described in the Proposal and Response Document

• Investigate & implement additional design and engineering measures

• Proactive measures – continuous noise and met. monitoring to inform decisions for operational response and contingencies

17Department of State Development

Noise strategies – EML 6th Schedule – Condition #3

• “the Tenement Holder must ensure that separation distances between any extractive stockpiles and Pine Point ensure the achievement of the (noise) outcome”

• Ensures the handling of stockpiles will be undertaken away from sensitive receptors

• Location of stockpiles must be shown in the PEPR

18Department of State Development

Blasting

Environmental Outcomes and Conditions from Lease:1) No adverse impacts to:

a) Public Safetyb) Human comfortc) Third party property (including stock)d) Adjacent land usee) Aircraftf) Other receptorsfrom airblast, flyrock and vibration cause by blasting

2) No flyrock to encroach on third party property3) Notify property owners (subject to consent) no less than 48hrs prior

19Department of State Development

Blasting

Monitoring (Measurement Criteria) from Lease:1) Monitoring n accordance with Australian Standard AS 2187.2

Strategies from Lease for Rex to address in PEPR:1) In accordance with Australian Standard AS 2187.22) Blast exclusion zone3) Blast protocol and schedule to be developed in consultation with residents within lease and adjoining the lease.

20Department of State Development

Mining Regulation Web Links:

Regulatory Framework - https://sarigbasis.pir.sa.gov.au/WebtopEw/ws/samref/sarig1/image/DDD/BROCH005.pdf

Ministerial Determinations

http://minerals.statedevelopment.sa.gov.au/knowledge_centre/ministerial_determinations

Regulatory Guidelines:

http://minerals.statedevelopment.sa.gov.au/knowledge_centre/regulatory_guidelines

DPC SARIG Website – https://sarig.pir.sa.gov.au/Map

Contact

DPC Mining Regulation

Level 7, 101 Grenfell StreetAdelaide, South Australia 5000GPO Box 320Adelaide, South Australia 5001

Andrew Querzoli and Nathan Zeman